Hello,
We are working on monitoring SAP systems of several customers. For every customer we have configured central monitoring on Solution Manager system of that customer. All satellite systems are added to RZ21 and CCMS agents are configured correctly. On the Solution Manager, in RZ20 we have created a rule based monitor specific to the needs of customer, and that monitor is used for the whole landscape of every customer.
But now I need to configure our central Solution Manager system which will collect CCMS data from all satellite systems of all customers on one place in RZ20. That central Solution Manager system should have direct connection only to customer Solution Manager systems and not to their satellite systems. Is this possible? If yes, can you please explain me how to do it or point me to documentation? I was unable to find solution.
To make this more clear I made a picture of desired configuration:
https://picasaweb.google.com/108686894540363563900/SAP#slideshow/5571983242527848482
Edited by: Dejan Terzic on Feb 10, 2011 10:04 AM

Hi Dejan,
as far as I know this is not possible.
we had similar issues, every time we migrated a new customer to or datacenter. Our solution was, to register the CCMS agents to two systems for a period of migration.
Sometime ago, I found a question for that an SDN:
Using another CEN for Solution Manager
I know, that this is not your question exactly, but it is the right direction...
Kind regards

Similar Messages

  • Integration of Seeburger Adapter in Solution Manager for Monitoring

    Hi Experts ,
    Can we Integrate the  monitoring of Seeburger adapter into the Solution Manager dashboard under central PI Monitoring ?
    We are using   AS2, FTP and sSFTP seeburger adapters here.
    Regards,
    Kamal
    Edited by: KAMAL KUMAR on Jan 11, 2012 2:33 PM

    Hi,
    check  [this.|http://www.sdn.sap.com/irj/scn/go/portal/prtroot/docs/library/uuid/408e1501-fb8c-2e10-edba-f51f13cde64e?QuickLink=index&overridelayout=true]
    Page 29 has useful information on adapter/channel monitoring.
    -santosh.

  • ISU BPM mapping in Solution Manager for monitoring

    Hi Experts
    I am trying to ISU BPM in Solution Manager so that I can monitor the system through SM,has anybody donethis before,if so please share the knowledge at earliest
    Thanks & Regards
    Amit

    Hi,
    check  [this.|http://www.sdn.sap.com/irj/scn/go/portal/prtroot/docs/library/uuid/408e1501-fb8c-2e10-edba-f51f13cde64e?QuickLink=index&overridelayout=true]
    Page 29 has useful information on adapter/channel monitoring.
    -santosh.

  • We have been having some issues with Email notifications not going out and getting hung up in SOST.  Can anyone please tell me whether we can use Solution Manager to monitor outbound emails?

    We have been having some issues with Email Notifications not going out and getting hung up in SOST. Can anyone please tell me whether we can use SAP Solution Manager to monitor outbound email?

    What version of Solman are you using ?  Check in t-code Rz20 >ccms monitor template of satelliate system , there would be option to monitor your outbound mails .You can sutomise your monitorig metrics in solman 7.1  else in 7.01 you use auto reaction methods to monitor .
    Regards
    Jay

  • Using more than one Solution Manager for different usages

    Dear all,
    we are using a solution manager system with >100 connected systems.
    The system should primarily be used as service desk system, but is also used for BC issues (e.g. MOPZ,...) at the moment.
    We have to implement a central monitoring system (CEN) using the CCMS infrastructure.
    It is recommended to use a seperate system for this issue, because of high performance requirement and the requirement to have the newest support packages for CEN+MOPZ.
    Because of that recommendation we are thinking about installation of a second solution manager system which should handle all BC and Monitoring (CEN+SolutionManager-Monitoring) issues.
    Do you have any experience with such a landscape? Are there known problems respectively is such a landscape possible/workable? How should the systems be connected? ( client system<=>solman / solman<=>solman )
    I regret that I could not find any official landscape recommendations from SAP for big landscapes (VAR environment)?
    If you know any applicable documents, please let me know.
    Thank you for your help.
    Best regards,
    Sascha

    Hi Sascha
    Technically Solution Manager is being billed as the Central system for everything Service Desk, MOPZ and CCMS - one central location for all scenarios
    One of the reasons for this is lifecycle management -- monitoring or EWA scenario finds a problem, service desk raises the issue, charm or mopz implements the solution and it is tested and distributed and the whole lifecycle is documented one system. Indeed I am aware of no functionality to integrate scenarios between Solution Manager systems - each Solution Manager system in your proposal will be standalone for each scenario
    I can't provide guarantees because SAP recommend 1 Solman PRD only, but it might be possible to use another PRD Solution Manager system (or client) for scenarios that not already setup in the existing Solution Manager system - this certainly is the most possible way to have 2 PRD Solution Manager systems (or clients) running in parallel.
    The key thing to be aware of is RFC conflicts - as each scenario usually has its own RFC this might be avoided - however
    do watch out for situations where scenarios share RFCs or you if find RFCs existing with the same name OR client and SID in any systems in the following landscape
    Landscape 1 - Satellite System 1 to Solman System 1 Service Desk, MOPZ
    Landscape 2 - Satellite System 1 to Solman System 2 CCMS, EWA
    Best wishes
    Stuart

  • One Solution Manager for different customers

    Hi Guys!!
    I am configuring a Solution Manager for different customers wich have a different S-users and different users to manage the solution manager system.
    My problem is that there is only one SAP-OSS RFC destination where I can fill the data only for one of the S-users. From "solution_manager" transaction you can indicate the S-user too (Edit - Global Settings) but the same problem occurs, I can fill the gap only with one S-user and I have to change this one when I want to work with different S-user.
    Can i configure the system to indicate different S-users depens on the user who I use to logon to solution manager system?
    Thank you very much in advanced,
    Edorta.

    Hi Edorta,
    you did not mention, which scenarios do you plan to use.
    Functionality to use the SolMan for many customer numbers is already available or will be added in future Support Package Stacks.
    It has been already added for
    - Maintenance Optimizer
    Note 1021275 - Maintenance Optimizer: RFC Destinations for Partners
    - Forwarding SAP Messages (with different S-Users resp. customers)
    IMG: Solution Manager -> Scenario-Specific Settings -> Service Desk -> Value Added Reseller
    Check for SAP Notes on component SV-SMG* with key word "VAR" (as Valued Added Reseller), "Service Provider"
    Best regards,
    Ruediger Stoecker
    SAP Notes added
    Message was edited by: Ruediger Stoecker

  • Communication Channel Monitoring using CCMS/Solution manager

    Hi ,
            I have configured everything in solution manager for message monitoirng of PI system, but my requirement is to monitor communication channel error in ccms.
    Is there any possibilty to trigger alerts for communication channel errors ??
    Regards
    Veeramalla

    Hi,
    Please refer following threads
    SAP Solution Manager and PI
    In addition you can refer solution manager wiki:
    http://wiki.sdn.sap.com/wiki/display/SM/WeblogsrelatedtoSolutionManager
    Regards,
    Deepak
    Edited by: Deepak  Shah on Feb 23, 2011 11:15 AM

  • Is it a must to use Solution manager for ECC 6.0 upgrade

    Is it a must to use Solution Manager for ECC 6.0 (FICO & HR) upgrade? I am told Solution Manager is required only if it has ABAP and JAVA stacks, or involves Enhancement Packages; and could be optional if it is only ECC 6.0 with ABAP stacks.

    Hi,
    I'm having a difficult time finding some guidance for setting up our R/3 Enterprise system in solman properly, so that I can create the upgrade XML file required to go directly to ERP 6.0 EHP4. 
    I've set up the R/3 system fine, but when i create a maintenance transaction i cannot for the life of me figure out how to tell it I want to go from r/3 to ERP6 ehp4.
    Any docs out there for this?
    Thanks!
    I figured it out... i had to add the R/3 Enterprise logical components to my system landscape.  After that I was able to select R/3 as the initial data in the maintenance transaction and then the system i wanted to upgrade, and then the option to upgrade.
    Never mind!
    Edited by: Tom Janes on Sep 9, 2009 12:52 AM

  • Questions on "FAQ - SAP Solution Manager for VARs"

    Hi,
    I just got through the FAQ - SAP Solution Manager for VARs, but have some further questions:
    For me it is not quite clear which connections are necessary for which VAR scenrio.. currently we have setup the service desk in our solman. Customer's aren't linked to the solman yet - we have saprouter-saprouter connections. Connecting them via SAP support backbone is an interesting option, especially for incident management. To get this working we should follow note 1124718 right?
    But what about the other scenarios like maintenance optimizer and ewa monitoring? I guess for that we definitly need to build up RFC connections to each relevant customer system (~300+x)?! I think it will be hard to handle so many connections - just consider if a customer is cancalling the maintenance contract, everything needs to be removed again... best would be to have a central communication point...
    For MOPZ we need up-to-date system information. So everyone is talking about SLD. Do you also recommend this option? There we need again a connection (direct to SolMan SLD or via external SLD on customer side).
    According to the FAQ there is a workaround for ewa monitoring for customers with security doubts.. is this also working for non-ABAP components? We need SMD and WI for generating ewas for JAVA systems...
    With regards to Enterprise Support contract: ewa only need to be monitored for productive systems? Can a customer be charged if they want to have ewas monitored for other sytems too? How long do we need to keep the ewas (1 month, 3 months, half year) before they are deleted? Are there any specific requirements?
    All the work to get these scenarios working.. is this covered within the Enterprise Support contract? Can the customer be charged for work thats done by the VAR in their system (e.g. RFC connections, SDCCN, SLD,...)?
    Sorry for this long text.. hope you have some helpful ideas!
    Regards,
    Richard

    Hello Richard,
    (1) regarding network connections see document [Draft:Technical Support Network Connections for VAR Scenario|http://service.sap.com/~form/sapnet?_SHORTKEY=00200797470000089947&_OBJECT=011000358700000880802009E] as overview and with a lot of detailed information. 
    (2) yes, you have to setup once all your customer connections at the beginning but then only add/remove with customer contract changes
    (3) the workaround by sending by email can handled a anexception. EWA has to be done for productive systems like nowadays done by SAP. Additional EWA services could meas additional business case for a VAR - that's contract between VAR and customer.
    (4) whatever you think may be a business to sell - do it ! (and get a monetary bonus from your boss
    Kind regards
    Heinrich

  • Preparing Solution Manager for SMD Agents Installation

    Hello everyone
    I have to configure the Solution Manager of QAS to receive new SMD Agents, I looking at the transaction SOLMAN_SETUP.
    Does anybdoy know what do I have to do to prepare the environment for the installation of SMD agents?
    Thank

    Hi Marcelo,
    Check note 1365123 - Installation of Diagnostics Agents, this note shows the agent installation strategy. You must install one SMD agent per host (physical or virtual) . The SMD agent should be installed in all host you want to monitor.
    In order to connect the SMD agent into your Solution check the following WIKI:
    http://wiki.sdn.sap.com/wiki/display/SMSETUP/Diagnostics+Agents#DiagnosticsAgents-Connectionoptions
    Also, you can managed the SMD agent in the "Agent Administration", it can be found at:
    - SOLMAN_WORKCENTER
    - Tab Root Cause Analysis
    - "Agent Administration"
    I recommend you to use the "Direct connection to solution manager" for your agents. It is easier than the SLD registration.
    Regards,
    Allam

  • Solution Manager for Implementation project

    Hello,
    I want to know how we should use solution manager for an implementation project. I am aware about the ASAP methods and the transactions in solman system for each phase. I have starting trouble like how to and where to start with? My ECC systems are not yet installed. Still we can go ahead with Blueprint creation and definition of roadmaps etc. Currently, it is done on paper.  If anybody has done an implementation project through solution manager, could you please give me some hints how to start ? I repeat I am aware of the transactions but dont know what to add there in solar01/02 when the process are not defined/system not installed. Please guide me.
    Rajeev

    Hi Rajeev,
    You're correct; you can start building the Business Blueprint without SMSY having all the systems that are 'to-be'. As long as you enter logical components in the project landscape with the correct product versions, you can replace those with the actual components once they have been installed. The BPR needs those product versions in the blueprint when you load the relevant scenario's. Once loaded, you can start documenting the scenario's, place the processes and process steps not used out of scope or delete them entirely and define custom scenario's, processes and process steps.
    When the Blueprint has been completed with relevant design documentation, the Configuration transaction can be used to document how you actually configure the systems and, of course, to configure them from Solution Manager. The system landscape officially has to be definitive at the end of the Blueprint phase, unless you won't be configuring the systems centrally from Solution Manager.
    The Solution is actually not necessary for a clean implementation; the Project will eventually lead to the solution. Once the systems are all configured and documented in SSM, you create the Solution and upload the project documentation into it in the Solution Directory.
    Let us know how you get on!
    Kind regards,
    Patrick

  • How to configure CTS+ for Solution Manager for XI 3.0

    Hi ,
    We are working on XI 3.0 SP 20 and Doing a file system based transport of .TPZ files. We observed that there is a possibilit of misssing the objects while tranporting. So we are planning to set CTS+ with our Solution Manager.
    Question:
    1. Can we configure CTS+ through the latest version of Solution Manager for XI 3.0 landscape?
    If Yes .. How?   If No... Why?
    2. Is there any way to make the the transport automated like ABAP tranports.
    If there is.... Please send the link or documents..
    Thanks
    Manoj

    Hi Venkat,
    Thank you for the Demo. The Demo gives me information about the CTS+ setup. I am looking for the compatability of CTS+ for XI 3.0.
    We have Solution Manager 7.1 setup in place.
    Please let us know if we can setup CTS+ on solution Manager (7.01 EHP1) and use it to transport XI 3.0 SP20 IR/ID objects  across  the XI landscape.
    Regards,
    Manoj

  • FAQ - SAP Solution Manager for VARs

    You can find further technical questions around configuration & functionalities in a comprehensive
    FAQ to SAP Solution Manager for VARs.
    This FAQ covers questions and answers around:
        > SAP Solution Manager, enterprise edition
        > SAP Solution Manager VAR setup: configuration of Service Desk
        > Work Center Service Desk: functions & configuration
        > Work Center System Monitoring: setup of SAP EarlyWatch Alert
    You can access the FAQ directly thru the following link [FAQ - SAP Solution Manager for VARs|http://service.sap.com/~form/sapnet?_SHORTKEY=01100035870000722612&_OBJECT=011000358700000490172009E].
    Navigation path: SAP Service Marketplace > SAP Support Portal > SAP Support Infrastructure > SAP Solution Manager > SAP Solution Manager for Partners > Information for Service Provider > Training and HowTo Documents > Administrator
    Please notice: The FAQ will be updated from time to time.
    Edited by: Susanne Schlehf on May 4, 2009 2:48 PM
    Edited by: Susanne Schlehf on May 18, 2009 12:56 PM

    Hello Richard,
    (1) regarding network connections see document [Draft:Technical Support Network Connections for VAR Scenario|http://service.sap.com/~form/sapnet?_SHORTKEY=00200797470000089947&_OBJECT=011000358700000880802009E] as overview and with a lot of detailed information. 
    (2) yes, you have to setup once all your customer connections at the beginning but then only add/remove with customer contract changes
    (3) the workaround by sending by email can handled a anexception. EWA has to be done for productive systems like nowadays done by SAP. Additional EWA services could meas additional business case for a VAR - that's contract between VAR and customer.
    (4) whatever you think may be a business to sell - do it ! (and get a monetary bonus from your boss
    Kind regards
    Heinrich

  • Solution Manager for SAP BI

    I have to use solution manager for an SAP BI/BW implementation. The BW client is currently in SAPERP 2005 (ECC 6.0). Is is possible to use solution manager in the same system or should the BI/BW be implemented in NetWeaver for implementing solution manager.
    Thanks,
    Neha.

    Hi Neha,
    I am not sure, whether I understand your question correctly.
    - SAP ERP 2005 (ECC 6.0) and SAP Solution Manager 4.0 are separate installations, each will get their own system id.
    They might share the same hardware, depending on your hardware capacity.
    Best regards,
    Ruediger

  • Solution Manager for SAP BI/BW

    I have to use solution manager for an SAP BI/BW implementation. The BW client is currently in SAPERP 2005 (ECC 6.0). Is is possible to use solution manager in the same system or should the BI/BW be implemented in NetWeaver for implementing solution manager.
    Thanks,
    Neha.

    Hi Neha,
    I am not sure, whether I understand your question correctly.
    - SAP ERP 2005 (ECC 6.0) and SAP Solution Manager 4.0 are separate installations, each will get their own system id.
    They might share the same hardware, depending on your hardware capacity.
    Best regards,
    Ruediger

Maybe you are looking for

  • Three of us ail fail to connect at the same time?

    Something is really wonky with iChat. There are three of us that video chat almost daily. All of a sudden none of us can connect! I mean literally overnight! No one has made changes to their system. These are three G5 macs in three separate locations

  • After burned to dvd the edge are cut off in my tv screen. looks like zoomed

    hi i am FCPX user. i create my project using format (resolution )as showed on the pic below after burned to dvd the edge are cut off on my tv screen. looks like zoomed as showed in  the pic below. thanks for taking ur time to help me!! then i export

  • Safari not rendering Verdana

    I cleaned up my fonts today when Font Book flagged several fonts were duplicates or had other problems. I removed the fonts as suggested by FB and there were no immediate problems anywhere, not even Safari. This morning, without having logged out or

  • Move position of label item on canvas

    Hello, i want to reset the position of a label item which is created under a canvas. Example: Canvas: CS_Main --> Tab Page: ROOT --> Graphics: T_Star (Graphics Type: Text) With which function can i do that during the run in a trigger or is it possibl

  • Portal Personalize problems.

    Dear experts I want Personalize link in my masthead. For that I have done the below steps. 1) Created a role. 2) Assigned portal personalization workset to that role. 3) Assigned the role to user. 4) In masthead iview I have changed the property "Sho