Why Do I get 0h hours for resources after using Resource Levelling in Project 2010?
Hi,
We are using MSProject 2010 and Project Server 2010 with Enterprise resources. All resources on all projects in the enterprise are shared resources. We are finding that after resource levelling is applied to the project some resources are only
being assigned a fraction of their total availability, and in some cases Project will assign 0 hours to a resource for several consecutive weeks even though the resource has capacity for the week the task is scheduled to start.
For example: Let's say we have a task that is scheduled to start on 1-20-14. The task is a 112 hours of effort with no constraints and one resource assigned to it. The resource is available 40 hours per week for the next 4 weeks. After resource
levelling I would expect Project to assign the resource as follows: 40 hours in week 1, 40 hours the next week and 32 hours the next week, for a total of 112 hours. Instead, Project does not assign the resource to the task until week 4 (even
though the resource has capacity on the start date of the task) and pushes the finish date out. In some weeks the resource has 0h hours showing in the timephased grid on the Resource Usage sheet. We have experimented with the levelling settings and it
does not seem to matter which boxes are checked, but following is our preferred settings:
1. Levelling Calculations set to Manual
2. Look for overallocations on a day by day basis
3. Clear levelling values before levelling is CHECKED
4. Level entire project is selected.
5. Levelling order is Priority,Standard
6. Level only within available slack is CHECKED
7. Levelling can adjust individual assignments on a task is CHECKED
8. Levelling can create splits in remaining work is UNCHECKED
9. Level resources with the proposed booking type is UNCHECKED
10. Level manually scheduled tasks is CHECKED.
Does anyone have any ideas about why Project is not using the resource's available capacity?
Thanks, Judy
Hi Judy,
Thanks to give us more detail. But actually if you need to level a resource, it means that this resource is overallocated. In your example, since it is not overallocated on the 12weeks task you mention, it means that it should be assigned on another task.
If not, there would be no need to perform any resource levelling.
Concerning the fact that levelling assign resource at 0hr per week, this can be absolutely normal.
Imagine that you have a resource working at 100% on 2 tasks on the same period. imagine also that there is actual work on one of the 2 tasks. Project will level the resource, meaning that it will move ahead the remaining work of one of the task (depending
on the levelling parameters). But the actual work will not move, thus between the actual work and the moved-foreward remaining work, the resource will be assign at 0hr by time period on the splitted task.
Please check all the task of the levelled resource and actual work.
See in my example below:
Hope this helps.
Guillaume Rouyre - MBA, MCP, MCTS
Similar Messages
-
How will get stoppage hours for PM02 orders
Hello Guru,
I want to find out stoppage hours for PM02 orders according to PM Act Type (eg. PM, predictive maint., TPM, etc). Background is that, our PM02 process schedules maint order as per maint plan & it wont triggers Notification in background so users are unable to enter work details ie. work start date/time & End date/time.
In this situation, how will get stoppage hours for PM02 orders?
<< Moderator message - Everyone's problem is important. But the answers in the forum are provided by volunteers. Please do not ask for help quickly. >>
Regards,
Amol
Edited by: Rob Burbank on Jan 17, 2011 4:25 PMHi PMAmol,
As Babu suggest, You can use Act Start and Act End date and time from Order Header for your requirement , Now how to use those ?
Once you do Order Confirmation via IW41 , for first operation mention date and time in Work Starts on date and time when you start your work,
Then this date and time will reflect in Act Start in Order Header, after that when you finish your work , then in IW41 along with final Confirmtn tick mention the date and time in Work Start on and Ends on field , when CNF status set on order you can check in order header , this date and time will reflect in Actual End date and time.
For report you can use Iw39.
Riyaj -
Why did I get charged again for items I have already purchased?
Why did I get charged again for items I have already purchased?
My theory is that because the original appleID wasn't an email, they're making you switch to it when you update to iOS5. So that creates essentially a new appleID and it isn't recognized as the one that originally made all your purchases. Sign out of the Store and then sign in using your old ID and it should do the trick.
The other alternative is to sync your apps rather than reinstalling them....if you can. Hope the phone service helps. -
HT201359 Why am I getting billed twice for a song download
Why am I getting billed twice for a song download
If you are being charged double the listed price then you can contact iTunes Support via this page : http://www.apple.com/support/itunes/contact/ - click on Contact iTunes Store Support on the right-hand side of the page, then Purchases, Billing & Redemption (if you are downloading the song twice then in some countries you will be charged again as redownloading is not currently possible in all countries).
Or are adding or changing credit card details on your iTunes account ? If you are then each time that you do so a small temporary store holding charge ($1 or the approximate local equivalent) may be applied to check that the card details are correct and valid and that it's registered to exactly the same name and address as on your iTunes account - it should disappear off your account within a few days or so.
Store holding charge : http://support.apple.com/kb/HT3702 -
Why am I getting billed twice for the same thing
I ordered 9 songs off of Itunes on 12/29/12 and my visa was billed $10.50 an email was sent to me confirming this.
today (1/2/13) I was sent another email billing my visa for $7.32 for 6 of the same songs I ordered on 12/29/12.
Why am I getting billed twice for these songs.This a user to user forum. We don't know why you where billed twice. Please navigate to the Contact Us link at the bottom of this page and contact Apple. They will be better suited to answer your question.
Regards -
Why do I get a "call ended" alert after voice directions, when using Googles Maps App with my iPhone 5s paired to Bluetooth service in my GM auto
Hello Snosilla! I'm so sorry for all the confusion and for all the time taken to activate service with us! I do see that the iPhone 5c is $99.99 right now. The iPhone 5s is actually $199.99. There's no need to call Pam anymore, we can take over from here.
I've followed you in the forums. Please accept me, and follow me back. Then, send me a Direct Message and I can look into this for you. If you do not have an active line yet, I may need to get you through to our activations department, but I will do all I can!
Thank you!
ChristinaB_VZW
VZW Support
Follow us on Twitter @VZWSupport
VZW Support -
Why do I get this error when trying to use my bluetooth headset as a listening device? There was an error connecting to your audio device. Make sure it is turned on and in range. The audio portion of the program you were using may have to be restarted.
I may have already resolved this issue buy removing the device from my computer and re-pairing it. It is currently working just fine.
-
How do i get a colormap for intens graph using basic imaq
This is a follow up to
http://exchange.ni.com/servlet/ProcessRequest?RHIVEID=101&RPAGEID=135&HOID=506500000008000000B58D0000&UCATEGORY_0=_49_%24_6_&UCATEGORY_S=0&USEARCHCONTEXT_TIER_0=0&USEARCHCONTEXT_TIER_S=0&USEARCHCONTEXT_QUESTION_0=how+do+i+get+a+colormap+for+intens+graph+using+basic+imaq&USEARCHCONTEXT_QUESTION_S=0
where I asked for help getting a colormap for saving an image as a jpeg. Now, I have decided that I would like to use an intensity graph for my display of the RGB image that I have captured using my pci-1411 frame grabber board. How do I get the right colormap for the intensity graph display? I do not have vision and do not intend to purchase it. I am using the basic IMAQ package.
jc
Mac 10.4
LV7.1
CLDDear Sir, usually the intensity graph will help you with monochrome images, since they have a one color intensity. If you want more colors you will be able to get up to 256, and not true color (24 bit). You might want to use the Picture Control instead or a Child Window approach, please look in your Help menu, 'Search IMAQ Examples...' and then browse for IMAQ examples and choose the ones that are for Picture Control. For the Child Window look in our website for an example called 'IMAQ Display Without IMAQ Vision'.
Good luck!
Nestor.
Nestor
National Instruments -
Why do I get Publish Failed Error Message when trying to publish a project to SWF. I am using Captivate 6 (32 Bit) Version 6.0.1.240. I have tried clearing the Cache and renaming my Preferences folder
Try the troubleshooting tips here:
http://www.infosemantics.com.au/adobe-captivate-troubleshooting/basic-troubleshooting-tech niques
You may have something in your project on one of the slides that is tripping up the publishing process. -
Why do i get quicktime error -50 everytime i try to export a project?
why do i get quicktime error -50 everytime i try to export a project?
I had this -50 error when exporting my movie. I tried multiple things to fix that, when I discovered the solution.
When you insert/add/overwrite a clip into the timeline, sometimes FCPX does not generate the vignettes associated to the video (only the audio waveforms are correctly displayed). You can read the clip successfully, apply effects and do everything with it in the timeline, but when exporting this corrupted clip, the -50 error will occur. The solution is then to remove this clip and add it again (it should not bug twice on the same clip!).
So I do not know whether you are in the same situation, but I hope this could help. -
Why does itunes get locked with last update after clicking on search button ?
Why does itunes get locked with last update after clicking on search button ?
Why does itunes get locked with last update after clicking on search button ?
-
I want to get desktop path for client user using webutil
oracle database 11g
oracle forms 10 g
client windows
i want to get desktop path for client user using webutil
as i want to save file in this pathTo get the user's path to their Desktop is a two step process. First, you have to echo the %USERPROFILE% to a output file and secondly, read the directory from the output file in to Forms. The code would look similar to the following:
/* When-Button-Pressed trigger */
DECLARE
v_temp_path VARCHAR2(250);
v_temp_file VARCHAR2(12) := 'webutil.log';
f_file Client_Text_IO.File_Type;
BEGIN
Client_Host('cmd /c echo %USERPROFILE%\Desktop > c:\'||v_temp_file);
f_file := Client_Text_Io.FOpen('c:\'||v_temp_file, 'R');
Client_Text_Io.Get_Line(f_file,v_temp_path);
Client_Text_Io.FClose(f_file);
b_dummy := WebUtil_File.Delete_File('C:\'||v_temp_file);
--At this point, you have the path stored in the v_temp_path variable.
--You can assign this variable to a block item or reference it directly in your code.
END;
When you reference the value of the v_temp_path, don't forget to wrap the value in double-quotes (" ") becuase the path will have spaces. Since your plan is to write a file to the user's desktop, your call to FOPEN will look like this:
f_file := Client_Text_Io.FOpen('"'||v_temp_file||'"','W');
Hope this helps,
Craig... -
Why the App Store ask for sq.after using it for years and how do find the answers
Why the App Store ask for sq.after using it for years and how do find the answers
Reset security questions
http://support.apple.com/kb/HT5312
If you do not have a Rescue email, you need to contact apple support, they will guide you through the process of resetting your security questions.
https://ssl.apple.com/emea/support/itunes/contact.html -
Is there a way for me to use airplay on my mid 2010 MacBook Pro ?
Is there a way for me to use airplay on my mid 2010 MacBook Pro ?
http://support.apple.com/kb/ht5404
-
WHY CANT APPLE GET CAR CONNECTORS FOR AMERICAN CARS
I WAS WONDERING IF ANYONE KNOWS WHAT APPLE HAS AGAINST AMERICAN CAR MAKERS????? ONLY CAR ADAPTERS YOU CAN BUY IS FOR GERMAN AND JAPANESE CRAP. I JUST BOUGHT THE IPOD NANO, AND I CANT CONECT IT TO MY CADILLAC WITHOUT ELIMINATING MY CD CHANGER, OR HAVING TO PUT UP WITH CHANGING RADIO STATIONS ON THOSE FM TRANSMITTERS.... APPLE, HELP US AMERICANS OUT!!!! WE ARE PROBABLY 75% OF YOUR BUSINESS
Ok, so the subject of your post is the question, "why can't Apple get car connectors for American cars?".
I think the answer is simply that Apple doesn't control GM, Ford or Chrysler. As a matter of fact these companies make a TON more money than Apple and have a lot more power than Apple about what goes into their products.
It isn't fair to say it's Apple's responsibility to make cars compatible with the iPod. It's Apple's responsibility to make the iPod compatible with cars. And Apple HAS done that. Thats why several car companies are including a way to control the iPod off of THEIR factories.
The more forward thinking car companies with the most recent designs have been doing this. Even if Cadillac came out with a CTS that works with your iPod tomorrow would you go out and buy that new CTS just so you could work your iPod off the steering wheel or whatever? OR, would you rather go get a great aftermarket Alpine or Kenwood? Both of which have decided it would be in their best to make devices which are compatible with the iPod.
Chevy recently came out with a new car design - the HHR - which does this. I seriously, seriously doubt Steve Jobs called Bob Lutz (the CEO of Chevy) and said "Hey Bob, you'd better start making cars that work with the iPod because it's our responsibility to force you to do that. And if you don't you're gonna be in big trouble mister".
What leverage does Apple have to force GM to do anything?
More than likely, the engineers at Chevy (being bright individuals) said, "hey, lets make this really cool hip car work with a really cool hip mp3 player so we can sell more of these cars". It's in Chevy's best interest to do that.
My turn to ask you a question.
How should Apple go about forcing GM, Chevy and Ford to build in iPod controls?
Remember, the iPod already has this funcionality as evidence by the new HHR, Nissans, BMWs, Ferraris and others at this site:
http://www.apple.com/ipod/ipodyourcar/
Again, I recommend that if you want CADILLAC to change their cars, ask CADILLAC - not Apple. Apple did it's part with the iPod (as evidenced at the above link).
Think about it.
Maybe you are looking for
-
Hi, i have an editable instance of cl_gui_alv_grid. Is there an easy way of getting out the data or do i really need to implement an event handler catching handle_data_changed? I'm not interested in the event itself, and cause the column is a kind of
-
Adobe Reader 10.1.7 I cannot " register(record) under " the modifications brought to a document PDF ( rotation). When I open the new document the modifications were not registered(recorded).
-
Opening FLV files using Adobe Flash Player 10.3.181.23
Hello I have with me a few FLV files from YouTube - so i had searched that Flash Players could open such files. I'd like to enquire if this version of Flash Player 10.3.181.23 does work? Are there other steps i have to undertake before opening these
-
Ugldapusessl option in Messaging server
I'm trying to configure an iPlanet Message store to do secure LDAP searches by setting the 'local.ugldapusessl' to 'YES' and ugldapport to 636. I have installed certs on both the directory server (iplanet DS5.1SP1) and the message store (iMS5.2). I a
-
How to store notes using GOS functionality
hi expert urgent things can u help me in this issue how to store note or text in repository using GOS generic object services ??? as soon as possible . thank you