WMS manufacturing component pick consolidation

Hello,
We are implementing WMS in our organization (EBS 11i).
We are using discrete jobs with supply type push for all components from inventory.
The request is to do component pick for the material but to consolidate the material first in a consolidation locator and only when we have a full kit to transfer it to the shop floor.
I know there is a king of solution using Pull instead of Push but we don't want to use this solution.
Is it possible to do it without customizations?
Thank you,
Chen

You can use WMS Rules to direct all your move orders to consolidation locator for discrete jobs picks.

Similar Messages

  • How to generate single move order for same components amongs different job using component pick release

    Hi all,
           I am new in manufacturing and we want to implement functionality of generating single move order for same component among different job using component pick release. Can any one help in this.
    we are using oracle R 12.1.3 version.
          For example. We create finish good XYZ which is build in WIP item. We create discrete jobs for XYZ suppose JOB1,JOB2,JOB3 multiple job we can create for XYZ item. in these JOB suppose component abc is similar with 5 quantity. so our goal is to generate 1 move order for all three JOBS with 15 quantity of abc component.
    please help me to achieve this goal. Immediate  Reply will be appreciated.
    Thanks & Regards
    user11152750

    PranitSaha
            Thanks For your reply. Can you please tell me in detail how can I group as I am new. How using MRP we can group same component from different job in single move order for delivering that component to shop floor.
    Thank you..

  • How to create a manufactured component in a production order network

    Hi,
    I've been facing problems to create a subnetwork in a production order. I want to add a manufactured component at a production order network.
    Does anyone know any BAPI or FM to solve this problem?
    Thks,

    I tried to use the below FM sequence, but I just create no-manufactured compenents. However this tried was failed too, becaus a couple of fields was missing when I go to CO02 transaction.
    CO_XT_COMPONENT_ADD
    CO_XT_ORDER_PREPARE_COMMIT

  • Urgent: Component Pick releases - Shortages

    Hi Gurus,
    I need help.
    I am planning to implement work order process in our site. I think I finished all required setups like items, BoMs (say 100 lines of BoM components). All components on BoM are operation pull.
    Now I created a job and went into component pick release form. The move order is generated for 60 components, and no on hand is available for other 40 components.
    But what I want to see is if on hand is not available for one of the component, I should not be able to create move order. Because I am not sure when I get delivery for other 40 components in above example, until that my move order will be picked and staged.
    Please help me how can I avoid releasiong the move order for a work order that has shortages?
    Thanks
    Veerakumar
    Edited by: Veerakumar Tikka on Jun 13, 2012 5:42 PM

    Hi PS,
    In genergal, if I have shortage, component pick release is not creating the move order.
    I want to control few items to not to release, I changed the item's supply type as push and tried to release the move order for all lines on the BoM, but as expected for push type componet's transaction type is wip component issue and pull type are backflush transfer on move order. Assuming all material available
    Then I went into BoM setup, unchecked the "auto request material", then tried the component pick release. Now also it created the move order for all lines on the BoM.
    I did not understand what is the significance of "auto request material", or any other setting causing this attribute does not work?
    Just let you know, inventory org setup, I checked "release backflush components".
    Thanks in advance.
    Best regards,
    Veerakumar

  • How is the storage type for a component picked automatically in PO staging

    Hi
    The Process cycle is :
    Sales Order created MRP-Planned Order ---Production Order
    Problem : Transfer Requirement not created for Picking
    Now if I go to Co03--GOTOWM Pick list , For the component the storage type is notr updated automatically
    I compared with Materials for a TR was created & found that Storage type 100 was updated automatically
    Q:How is the storage type for a component picked automatically in PO staging (WM activated )

    Hi Rajesh
    Thanks for your inputs . Actually I forgot to mention that the client is not using Storage type in any of the material master data
    The problem was because the control cycle was not maintained for the combination of material /Plant & Supply Area
    Anyway thanks for your info .Appreciate your cooperation
    Arindam

  • Usage of Component Pick Release

    Hi,
    I want to know the usage of Component Pick Release.
    Regards,
    Arun

    To add to Karthik's response:
    CPR also lets you create allocations on the material needed for a job.
    This way, even if you have a job that starts in a couple of days, you can be sure that in the meantime some other transaction didn't steal the material that was scheduled to be used on your job.

  • Component Pick Release - Source Subinventory, Move Order

    I am using component pick release screen for push components.. Is there any possible way to select source subinventory prior to creation of move order ?

    Hi,
    Yes, please enter the Sub inventory & locator at BOM level.
    So it will be available in WIP Job & Job mover order.
    Thanks
    ND

  • Component pick release for partial quantity

    Hi All,
    For R12 environment , customer needs move order to be created for partial quantity using component pick release.
    As far as I know component pick release cannot be done for partial pick release and only possible when onhand qty is not available.
    Can any one pleas elet us know if we can have any alternate solution or easy customization so that client can edit the quantities before going to move order creation?
    Thanks
    Vasudha

    when the move order is created..update the allocation and then perform transact move order
    ex if for 10 qty move order is created..but if u wish to issue 5 qty to the job..then update the allocation..for the remaining u can just backorder the move order
    HTH
    Mahendra

  • Shop Floor Statuses - Assign Shop Floor Statuses - Component Pick Release

    Hi,
    is there someone who knows the use of the following forms in WIP module:
    - Shop Floor Statuses
    - Assign Shop Floor Statuses
    - Component Pick Release
    We are in 11.5.10
    Please provide also an example of a business scenario where this functionality could be used.
    Thanks in advance
    Regards
    Riccardo

    hi,
    shop floor statuses are created which will allow/disallow moves and assigned to particular operations in the job.
    they are normally used in OSP operations to control the movement of material thru intraoperation by the users when the material is gone for OSP.
    and they can also be used to hold the job when its moving in operations (may be due to quality problems etc..)
    Component pick release is used to issue the required components to a particular job based on pick slip report.
    its another way of issueing material to wip apart from backflushing thru wip material transaction form.
    hope that u can hav idea abt these.
    if u need any clarifications, ols reply

  • Discrete Job Component Pick Release (SRS)

    Hi All ,
    For Push - Supply type , we can issue items to the job manually . Could any one brief purpose of Discrete Job Component Pick Release (SRS) in WIP
    Thanks
    Kiran

    Hi,
    Pls check if below MOS(metalink) note helps you:-
    Move Order FAQ #2: Quantity Delivered vs Detailed in Move Order Lines (MTL_TXN_REQUEST_LINES) [ID 431479.1]
    11i Move Order Transaction - FAQ [ID 114156.1]
    Oracle Work in Process Product Documentation [ID 67009.1]
    Also below discussion:-
    http://kr.forums.oracle.com/forums/thread.jspa?threadID=951381&tstart=0
    http://www.oracleug.com/user-guide/work-process/component-pick-release
    Thanks,
    JD

  • Q: Component Pick Release

    Hi all,
    quick question regarding component pick release. I have a WIP job that needs 5 components. 3 are available and 2 are not. I release the available components to the warehouse. Now the warehouse is not supplying them all together. They are supplying one each day. I don't want to use Pick Set functionality because this will only create the move order if all components are available.
    What I need is to receive all the available components together (in my example the 3). Can this be achieved by the Pick Slip Grouping rules?

    Hi,
    Yes, please enter the Sub inventory & locator at BOM level.
    So it will be available in WIP Job & Job mover order.
    Thanks
    ND

  • WIP MFG Component pick release

    Unable to do component pick release for all discrete jobs. It was creating as backordered by default and immediately gets closed.
    Note: sufficient stock is available, supply subinventory defined as non reservable. This problem is occuring only for last two days.
    regards
    Ravi

    Hi, Ravi, are you using Move Order for components? Any messages?
    Regards,
    Ricardo Cabral

  • Component Pick Release - Personalization

    Hi,
    I have a scenario that, I want to run request for custom document from Component Pick Release Form in Work in Process Responsibility after click on "*RELEASE*" button.
    Please guide me how could I do this?
    Regards
    waqas hassan

    Hi,
    Yes, please enter the Sub inventory & locator at BOM level.
    So it will be available in WIP Job & Job mover order.
    Thanks
    ND

  • Component Pick Release for Partial Discrete Job Quantity

    I'm on 12.0.6 and we currently do not use component pick release, but we are considering doing so.
    My employer currently creates a single discrete job (say 120 items) and then completes that discrete job over several days.  Say they plan to produce 30 a day over 4 days.  Is there a way to use component pick release to release that partial quantity?
    So if we have three shifts running and we want to produce 30 a day, 10 each shift.  We want to run component pick release 3 times a day for four days, only releasing the components needed for 10 assemblies each time? Possible?
    Is the only alternative to create 12 different Work Orders?

    when the move order is created..update the allocation and then perform transact move order
    ex if for 10 qty move order is created..but if u wish to issue 5 qty to the job..then update the allocation..for the remaining u can just backorder the move order
    HTH
    Mahendra

  • Component Pick Release

    Hello,
    Is ther a API available to perform a WIP Component Pick release. I know there is a FORM and SRS available thru the application, but is there a public API available?
    TIA
    Amit

    Pl refer the MFG guide . I guess wip_picking_pub package should provide some details .

Maybe you are looking for

  • Getting multiple error while refreshing or scheduling WebI report

    Hi BO Admin Experts , Feacing  multiple errors  while refreshing or scheduling webi reports in BI4.0 CMC , Please find the below errors : 1)report schedule status failed 2)Parameters : xxxcorp-franklinee; ATOu supply unv Error Message : An internal e

  • When I open Safari a web site appears saying I have a virus

    The message is as follows: System has Detected Security Error, Due to Suspicious Activity and Network Firewall seems to be Turned Off. System Might be infected with Trojan BackDoor.Flashback. Please Contact Support - Certified Live Technicians For He

  • Horizontal layout for images or video

    Hi, Sir May Check with you how coldfusion can layout for images or video in horizontal way? the default is vertical when we use cfoutput. what founction and tag support, or we had to design a horizontal looper for the purpose? The example web page ho

  • [SOLVED]Applications left after uninstalling wine

    I've completely uninstalled wine without uninstalling the applications I was running through it. Now their entries were left in the Activities menu (gnome shell). How do I remove them? Last edited by bogdan2011 (2012-02-04 09:00:04)

  • Want to know abt standard functionality

    hey guys Can you tell me if there is some standard functionality avialable in R12 to achieve below functionality 1)Shows the detail for the Sub-Lease contracts and 3rd parties. PN module 2)To show Future open balances by Store PN module