Workforce planning in Projects

What are the different ways of assigning people to Work Centers?
My target is to get a worklist for CAT2 transaction from project internal activities.
1. I can assign people to Work Centers in workforce planning?
2. I can assign people to Work Centers with Organizational structure?
3. Is there any infotype in HR mini-master also to set such link?
What is the best practice to get that worklist updated?  I have it just empty and not sure why.
Also is it possible to do a workforce planning at the WBS-element level?  If so, how?
Thank you.

Best practice is based on requirement.
Please check  the customization of your data entry profile in  worklist area.
If you are using workfoce planning stricly for all the project then frist  is best approach. but that you have to update regularly the assignments.
2. I can assign people to Work Centers with Organizational structure?
Here you assign person, most probabaly permenanatly for long time to workcenter, so you need not to chagne.
3. Is there any infotype in HR mini-master also to set such link?
As per my knowledge  there is no such infotype to set up.
With regards
Nitin P.

Similar Messages

  • Workforce planning in maintenance orders

    Hello experts
    I did already a lot of research and I made also some tests in the SAP system but I didn't find any answer to my question.
    I have two work centers. Both should work for Projects and for maintenance orders or orders in general. The capacity planning and the workforce planning for projects (CMP1,3 e 9) is all clear. I have two work centers, assign them to a project and with the transactions mentioned before I can assign a person to the activity for the projects. But now I want to setup the maintenance order in a way that I'm able to make the workforce planning.
    I create a new order with IW31. There I'm going to maintain a work center for the first operation. In the operation itself I maintain the work load, the date and the assignment for the person. I release and schedule the order.
    Afterwards I'm able to see the requirement for this work center in the CM50.
    Now my question
    If I want to make the workforce planning report I can't see the assignment of the person I assigned before in the order. I can only see assignments of project activities. How can I handle this issue? Is there a change to be made on the work center or are setup some categories or profiles wrong?
    I'm looking forward to get a helpful answer and I'm thanking all of you who are going to reply to this thread
    Best regards
    Jimsonweet

    Hi,
    You can use CM51 for assignments of persons in operations. I am not sure this report combines these with assignments for networks.  Nevertheless, capacity evaluation can be configured in great detail in SAP. You may create your own profiles under customization for Capacity Requirements Planning and call your own evaluation profiles with CM07. Maybe you can create a report which better suits your requirement than standart reports in terms of selection and representation.
    Regards.

  • Workforce planning in maintenance order

    Hello experts
    I did already a lot of research and I made also some tests in the SAP system but I didn't find any answer to my question.
    I have two work centers. Both should work for Projects and for maintenance orders or orders in general. The capacity planning and the workforce planning for projects (CMP1,3 e 9) is all clear. I have two work centers, assign them to a project and with the transactions mentioned before I can assign a person to the activity for the projects. But now I want to setup the maintenance order in a way that I'm able to make the workforce planning.
    I create a new order with IW31. There I'm going to maintain a work center for the first operation. In the operation itself I maintain the work load, the date and the assignment for the person. I release and schedule the order.
    Afterwards I'm able to see the requirement for this work center in the CM50.
    Now my question
    If I want to make the workforce planning report I can't see the assignment of the person I assigned before in the order. I can only see assignments of project activities. How can I handle this issue? Is there a change to be made on the work center or are setup some categories or profiles wrong?
    I'm looking forward to get a helpful answer and I'm thanking all of you who are going to reply to this thread
    Best regards
    Jimsonweet
    Edited by: Jimsonweet on Nov 21, 2011 1:23 PM
    Edited by: Jimsonweet on Nov 21, 2011 1:24 PM

    Hi,
    Just check if you assigned the person responsible in Basic data tab of the work centre in u201CIR02u201D.Also check if you have maintained partner determination for the person
    In addition please check the following link if it may be of some use to you.
    http://help.sap.com/content/bobj/sbu/docu_epm_swp_design.htm
    Best regards
    DSR

  • Activity missing in Workforce planning:project view

    Dear experts,
               I an caught up with the following problem:
    1) I created a project with WBS and activities.
    2) Created relationship between activities.
    3) Created project team
    When I try to perform workforce planning (project view) using transaction CMP2, some of the activities are missing in the list.
    Please let me why this happens and also how to include the missing activities.
    Thanks and regards

    Hi
    Please check following prequisites-
    1.HR mini-master record (infotypes 0001and 0002).
    2.Assigned work centers to the internally processed activities.
    3.Entered  Formulas in the work center to determine capacity requirements.
    4.Scheduled the activities to generate capacity requirements.
    5.Assigned only one labor capacity to a work center. (that is catagory 002)
    6."Determine Cap. Check" indicator is ticked in the network header.
    Regards

  • PS Workforce planning, Person Assignment in internal activity.

    Hello PS colleagues!
    I’m trying to use the workforce planning functions but I can not get the screen for person assignment in the internal activity.
    I have done this, IMG I go to this path:
    Project System -> Structures -> Operative Structures -> Network -> User Interface Settings -> Layout of Activity Detail Screens -> Define layout activity detail screens
    Then I create all tab, I copy the standard to my network profile and there is tab 8, in standard is call ”Admin.” then when I try it out it do not appear in the project, I use project builder.
    Does any one what more I need to do for this to work??
    Please help me out with this.
    Best Regards
    Jose Marin

    Check the consulting note 543362
    This note explains the steps/configuration node that needs to be in place for workforce planning
    Regards
    Sreenivas

  • Workforce Planning through Portal

    Hi All,
    Please help me out with the issue mentioned below,
    Users are accessing SAP through a portal and most of the project activities done by the Managers is through portal only. Managers are using the transaction CMP2 for workforce planning but off late we are facing a typical issue here. I would also  like to bring into light that this is happening only after application of some new HR module patches. Prior to this the system was working fine.
    When we try to assign a resource after selecting an activity in CMP2 transaction system pops up an information message in the portal as "First select an activity". We are not able to figure out as to why this information message is popping up even after selecting the activity. Request you to help out in this as this is hampering the process since managers are not able to assign the resources to the respective activities.

    No replies. So closing the thread.

  • Workforce planning data not getting copied into the CATs

    Dear all,
    I am doing the activity confirmation in the project by transferring the data from CATs. However in order to maintain the data in CAT2 we have to copy the data from workforce planning.
    currently it is not happening. The data is not getting copied in CAT2.
    regards,
    sudhir

    Hi,
       how about with worklist, these are the options required to transfer the data from PS to worklist.
    refer to the period which you have planned in CAT2?
    Rgds
    Sudhir reddy

  • Workforce Planning for Partially Confirmed Activities

    Hi All,
    I have recently configured Workforce planning for one of the clients, and it has been working as per the requirement. Here, I have configured Workforce Planning profile and Scheduling parameters of Network. So, once a Project and a Network is created, User plans Personnel for this Network's activity using CMP2. Also, CATS profile is maintained in such a way that Worklist shows the Planned hours and accordingly a person can book Time against it.
    Now, the problem arises after a Personnel assigned to an activity books the Timesheet. Once a Person books time against this particular Activity, it gets disappeared from CMP2 screen. Now, practical implications are that, suppose that person goes for a leave or leaves the organization and PM wants to assign another person for the same Activity (which is partially confirmed).
    How can we address this issue - to perform workforce planning for Partially Confirmed activities?
    Any pointers to User Exits, BADIs, BAPIs or SAP Notes are highly appreciated.

    Hi Sanjeev,
    Thanks for your feedback.
    In CMP2, we are already checking the activity work hours. According to that only we are adding resource, then checking that resource's availability and then assigning work.
    As an example, activity work duration is from 20.08.2014 to 30.09.2014. I assigned a resource A from 20.08.2014 to 30.09.2014 for 8 hours because he is available in that duration.
    Now, the real problem comes when this resource is suddenly unavailable (due to any reason) and PM comes to know about this on 07.09.2014. Resource A has already booked Timesheet for the duration he has worked (20.08 to 06.09). So activity is PCNF.
    So PM wants to reduce the Work assignment for Resource A from 30.09.2014 to 06.09.2014 and assign Resource B from 07.09.2014 to 30.09.2014, but he is unable to get this activity in CMP2 view because it is PCNF. Here PM can only see activities of same project which are in REL status.
    So how can I enable this PCNF activity in CMP2 view.
    If there is any IMG activity settings, then let me know.
    If this is standard behavior and can be done through User Exit/BADI/BAPI then also let me know.
    Message was edited by: Aditya Kotak

  • Workforce planning query

    Dear Experts,
             While trying to do workforce planning (Workforce planning:Project View), I get the following message: "No requirements were found for the selection criteria".
    Kindly let me know what may be the possible reasons for getting this message.
    Regards,
    Shynu John
    Edited by: Shynu John on Nov 7, 2009 8:14 AM
    Edited by: Shynu John on Nov 7, 2009 8:17 AM

    Hi,
    Use SAP008. And under the scheduling tab in the Other formula field maintain SAP004 and under the costing tab besides the activity tab there is a field without a label. Maintain the formula SAP008 there.
    Hope this helps.
    Regards,
    Gokul
    Edited by: Gokul on Nov 11, 2009 11:40 AM

  • Workforce Planning in Planning and Budgeting Cloud Servie

    Hi Experts,
    Does Oracle Planning and Budgeting Cloud Service (PBCS) have Pre-build modules Workforce Planning, Capital Asset Planning and Project Finance Planning.
    According to my understanding PBCS doesn't have any pre-build modules. I am not sure whether recently it has been added or not, so I wanted to double check.
    Thanks in Advance.
    Regards
    SKH

    PBCS still does not offer other planning modules like Workforce plnning/Capex etc.
    you can see more info at https://docs.oracle.com/cloud/latest/pbcs_common/CSPGS/apes02.html
    Regards,
    Sunil

  • Need Guideline in Workforce Planning

    Hello All,
    I am working on project, where I have to create data forms in workforce planning. I also am reading Oracle Hyperion workforce planning Administrator Guide. My question is can some one help or guide me to create my plan types?
    I can create dimensions by Navigating > Administration > Dimensions > Add Dimensions
    I can create Data Forms by Navigating > Administration > Managing Data Forms > Create
    I have confusion about under given questions....
    1- As I know there are pre-build data forms ..so how can we modify and use them for loading data? I can understand we can load data by DIM or Outline load Utility but how can we load data manually?
    2- What is relationship between Dimension and Data Forms which I have mentioned up there? If I create Dimensions then we can work or Data Forms or is there any other philosophy?
    3- How to increase rows, and columns in those data forms and what will be the Fields for HR?
    I have been told to create two dimensions i.e. Employees and Positions. I can create those Dimensions as I mentioned above steps but what kind of parents and child i need to put and how can i load those dimensions in to Workforce Data Forms.
    I hope to hear positive reply..
    Thank you very much in Advance for helping me to understand this workforce.....I am really new in to workforce please help...
    Thanks,

    Hi Alp Burak,
    Thanks for great guide line....I have already worked with essbase but i dont have enough exp. but i am more positive to learn every day new stuffs...and thanks for nice comments i will look through your suggested points then will get back to you....
    But today i facing new error...if you any great views about then please pass to me
    I have created new planning application at work since they asked me to develop workforce application for their business needs. I have created planning application and then I initialized to workforce.
    Now as soon as I click on any of those Data Forms I am getting this error ( The data form Begin vs End is invalid. Check log for details. ) ...............> Moreover, I have checked error.log file too and it was saying that there is no any application.
    I went back to Essbase system to create Essbase server and put same name as my application has then tried to REFRESH but as soon as i click on refreshed I have not get any message or any changes....other than that I went back to my workforce planning application even i am not able to see REFRESH button Visible....
    Please guide me and let me know that where i am laging...and what should i have to do....since I have already ready Planning admin and workforce admin guide too but just do not get why i am getting this error...
    I will appreciate you if you guide me from you precious time.....This my work project so hop to hear from you...
    Thank you very much in advance...and prompt reply will be appreciated

  • Issues in Workforce Planning

    Dear Friends,
    I am facing following isues in workforce planning.
    1) I am not able to assign team maintained at WBSE level in assigned activities.Though the manpower maintained at Work Center is easily asigned.
    2) The capacity requirement for activity as well as resource in not getting distributed, though I am using Distribution key to distribute work equally both at activity & work center level.
    3) Last, once a resource has been assigned to a particular activity for a particular period, the system is still allowing allotment of same resorces to other activities during same period.
    Please provide your valuable inputs.
    Regards,
    Seemant

    Thanks for response.
    We are maintaining WBSE team for the same WB SE to which network activity is assigned. The requirement for having a team at WBSE as well as Work Centre arises because, as per the business scenario the project may utilize resources other than that on Work Centre.
    I have done all required settings & marked all relevant indicators.
    Yes in I am using SAP020 Distribution Key.
    For the third point that I mentioned (that you say to be standard system behaviour) I would explain again.
    Once I have loaded a particular resource with work form a particular project, logically the system shall block that resource for that particular time frame (within which it is loaded). Are you saying this is standard system behaviour?
    Thanks,
    Seemant

  • Person assignment with workforce planning

    Dear All,
    I plan activity for one day 8 hours & assigned person to activity in CMP2 & distribute work for same day & for same hours,
    when i assign same person with diffrent activity with diffrent project with in CMP2 system not showing any message with same person is assigned same day with diffrent project.
    How same person can work two project with same time,
    Kindly share yours experiance.
    Regards
    Gajjen

    Hi,
    I tested with without person assignment in work center, yes you can assign any person to any project if have capacity but when we distribute work in workforce planning by assignment of person with day & time then same person how can assign to other activity ,because his working hours are fixed,if working time is 8.5 hours & person assign for 8 HR to activity then same person should not work to another activity more than 0.5 hrs,system should not allow.
    May i know Standard SAP allow it or not?
    Regards
    Gajjen

  • Table for Workforce planning

    Hi Friends,
            I am working with cmp3 transaction (Workforce Planning). Once we give the Work center and Profile, it takes to the screen, where we can see the personnel resources. Can anyone please tell me in which table these are getting stored. I checked the table PROJ. But, it gives the name of the persons who created a project. I need the planned resources name for a work. Can anyone pls help me with this.
    Thanks,
    Sharmila

    HI
    GOOD
    go through this links
    http://www.sap.com/solutions/business-suite/erp/pdf/BWP_SID_Workforce_Cost_Planning.pdf
    thanks
    mrutyun

  • Error Message when opening Project Plan on Project Professional from PWA 2013 using either Google Chrome or Firefox

    Dears,,
    One of our clients uses Google Chrome
    as their standard navigator to open PWA 2013 that we have deployed for them.
    Every thing went fine until we tried to open a project plan using Project Professional 2013 from PWA using the Edit in Project Professional option, we had the below error:
    "Project Web App was unable to find the specified Project.
    the project was not found on Project Web App. some possible reasons include:
    The Project has not yet been saved successfully to the server.
    The Project has been deleted on the server.
    you don’t have adequate permissions to open this project.
    if the project is available in the local cache, you can click the globe in the status bar and select "Work offline", and then open the project, if the problem continues, contact
    your administrator."
    Please note that IE is working fine with this scenario,
    the belwo screenshot shows the error that appears to the users.
    Ibrahim Al-Masri Technology Manager at MethodCorp

    Hi All,
    As Gary and Guillaume suggested, have you tried to install IE tab extension for chrome?
    See the link below:
    http://www.ietab.net/
    and also im with what Dale has posted
    (why don't you just tell the PM to use Internet Explorer instead of Google Chrome? 
    I suspect that this problem reveals that PWA does not work perfectly in browsers other than the Internet
    Explorer,
    so I would simply mandate that all PMs and TMs need to use Internet Explorer for Project Server. 
    Just a thought.  Hope this helps.)
    from my side , i have tested it and it works perfect. 
    Karim El Zarka, MCTS Sharepoint 2010 , MCITP SharePoint Administrator 2010 Whenever you see a reply and if you think is helpful, click "Vote As Helpful"! And whenever you see a reply being an answer to the question of the thread, click "Mark
    As Answer

Maybe you are looking for

  • Error  while create payment in UI   F-53

    Hi Gurus, while creating payment in UI F-53   i got an Error. vendor:3730,plant:3000,company code:3000 invoice document number:5105608648. what is problem for this... ERROR: The difference is too large for clearing Message no. F5263 Diagnosis A non-a

  • Page select table at top

    Does anyone know how to add one of those links at the top of every page that takes you to another page? Bascially I want to add one that when you select it, it takes you to another website. Ex, I have a message board with proboards. On my site I woul

  • Disable Vertex Tax Jurisdiction Code Validation & RFC Call

    We want to disable calling vertex for tax jurisdiction code in some cases based on sales org & division.  For a small business unit we are using SAP ECC 5.0 SD module to create customers & sales orders.  These orders are placed via a external non-SAP

  • Connecting to irc servers

    No can do: ... for any main channel on all three servers I want, gets me nowhere but ... Setup: ... courtesy of a discussion over here, plus I did enable this account's IRC service. Info is scarce otherwise, no matter what source. Can someone point m

  • EzDrummer in garageband 2.0

    will dfh ezDrummer work with garageband 2.0? i listened to the toontracks demos, and they are nice, but i don't want to spend $100.00 if the program isn't compatible. thanks iBook G4   Mac OS X (10.4.10)   garageband 2.0, eMU 0404 usb