Adjusting Values in an Asset

Hi experts
I'm trying to change the asset values it is not working as I planned.
I have created Z transactions Types with copy from TT. 200 and 250 to retire the acquisition value.
However I didn't find a transaction type to correct my depreciation values.
Would someone knows how to correct the depreciation amount ?
Thanks in advance
Deocleciano

Hi,
From which T-code you are making posting and which error is coming.
Regards
Shayam

Similar Messages

  • APC Value and Plan Value for an Asset.

    HI Gurus,
                      I am developing a report where I have to display the APC value and Plan value of an Asset.Can anyone pls give an insight how to find this for the Asset.

    Hi,
    why don´t you use the logical database ADA which most of the FI-AA standard reports do? The logical database is a service to get this information without developing all the READ information and translation by yourself, especially when talking about mid-year-reporting, consistence checks, etc..
    If you decide to use ADA, then the events GET ANLA0, GET ANLAV and GET ANLCV are from interest for you for information about APC and planned/posted depreciation value.
    Regards,
    Markus

  • How to clear asset scrap value from the asset

    Hi,
    An asset has been partially retired in 2007 and transfered the balance to other asset. There is a scrap value in the same asset and still appearing in scrap value field of asset explorer. This is giving an error in asset year end closing. Please give a solution to solve this issue. The scrap value is visible in the asset under Planned values tab and there is zero net book value.
    Regards
    Paroy

    Dear Markus,
    I dont mean somebody would search for me. I replied to your query to get inputs from various people. Someone might have faced a similar issue, they may have a solution or someone might have known and implemented a Note.
    I think the main purpose of these forums is knowledge sharing and quick solution to an issue which a person in question could not figure out.
    Regards
    Paroy

  • Adjustment of advance payment after adjusting AUC with Main Asset

    HI,
    My client is running KO88 without adjusting advance payment for Asset Purchase (AUC). Now this has led to accumulated advance payment with a huge amount. The purchase has taken place for more than 3 years.
    Kindly suggest, what is the correct step for adjusting down payment when we do purchase of assets through MM route.
    example: Please correct me if I am wrong.
    Step 1: Asset PO- ME21N with Internal Order and Acct Assignment category as A
    Step 2: Advance Payment- F-47, F-48
    Step 2: GRN- MIGO
    Step 3: MIRO
    Step 4: F-54
    Step 5: KO88
    Finally, how do we correct these old advance payments which are not adjusted yet and the KO88 is run. Ajay Maheshwari SAP Trainer

    So, what u r suggesting is, no need to reverse the Old AUC settlement in KO88. We can clear the old advances in F-54 and then execute KO88 which means- Re-execute KO88 after advance clearance.
    The issue here is, all the old advances have accumulated since, 2011. Now, how to work?
    Please advice Ajay Maheshwari SAP Trainer, Mukthar Ali Ahamed N.

  • Mouse wheel to adjust values of colors/ font size etc

    Hello,
    Is that possible to make FW CS5 use mouse wheel to adjust values (hue, saturation, font size etc.) similarly to PS?
    It's a bit of a drag to have to click the slider and each time I want to fine tune the tone.
    Rgs
    Joey

    You can set the pref mousewheel.withcontrolkey.numlines to -1 on the about:config page.
    The pref mousewheel.withcontrolkey.action must be 3 (default)
    To open the <i>about:config</i> page, type <b>about:config</b> in the location (address) bar and press the "<i>Enter</i>" key, just like you type the url of a website to open a website.<br />
    If you see a warning then you can confirm that you want to access that page.<br />
    * http://kb.mozillazine.org/about%3Aconfig

  • Memo Value for Main Asset and Sub Asset

    Dear Experts,
    I am having the requirement that, all the main asset should have the memo value Rs 1.
    For this I have specified the memo value in OAYI. But system is taking the memo value for Main asset as well as Sub asset.
    But we don't want to keep the memo value for sub asset.
    I hope, I am missing some settings. Could anyone please help me to solve this.
    Regards,
    Aswin

    Hi:
           You need to review your copy settings for sub assets for your relevant class's screen layout in  SPRO...Financial Accounting,,,,Asset Accounting....Master data....Define Screen Layout for Asset Master Data....Select the screen layout which has been assigned to your asset class in OAOA. You will not find any field for value copied. So it is not possible to avoid this happening becuase it is done a t CO code level.
    Regards

  • Value addition on asset

    Hi,
    Please let me know how SAP would calculate depreciation in the following business scenario.
    Jan 1st 2004: An Asset is aquired for $1000.
    Life time: 3 years
    Depreciation on Dec 2004: $300
    Depreciation on Dec 2005: $300
    Value left on asset: $400
    On Jan 1st 2006 or some time during the 3rd year, the asset got re-furbished and now the value of the asset after refurbishment is $600 and with an additional life time of 2 years.
    By accounting principles, I would expect the asset to depreciate
    Depreciation on Dec 2006: $300
    Depreciation on Dec 2007: $300
    Retirement.
    What would SAP do in this context?
    Thanks,
    Sivaram

    Once the depreciation start date is set, the subsequent acquisitions will take this depreciation start date as reference, and not the date of the subsequent acquistion, as you are assuming.
    Please read SAP note 46456, which explains this issue more in detail.
    The 'Calculate according to asset value date' indicator in the calculation key for the depreciation cannot be maintained as of maintenance level 3.0E. As SAP note 53166 describes this indicator frequently caused misunderstandings. And that is why this function has been "removed".
    But, you can still configure this behaviour with a modification, in table T090NP, field XBZDAT at your own risk. Please beware that with such a modification, there is no support in case of future incidences. In note 814004 you will find a short report which enables you to change the parameter.
    I hope this will help you.
    Kind Regards,
    Pankaj

  • Value date for Asset

    Hi,
    My question is how system picks value date for asset acquistion. I mean an asset is bought and is capitalized at 7 June, how wil system determine which date to use for capitalization. A detailed help would be of great value.

    Hi,
    Please refer to the below link:
    http://help.sap.com/saphelp_erp60_sp/helpdata/en/4f/71e122448011d189f00000e81ddfac/frameset.htm
    Regards,
    Kiron Kumar T.

  • NET BOOK VALUE OF THE ASSETS NOT APPEARING IN THE BALANCE SHEET

    Hi,
        I have uploaded the old assets by using the T.code As91, but the values of the assets are not appearing in the Balance Sheet.Please help in solving this issue
    Ramaswamy

    Hi
    After loading the asset thro AS91, there is a transaction OASV thro which you need to update the GL accounts. 
    Thanks
    Ashok
    Assign points to say thanks

  • No effect on the revaluation value of the asset after write-off

    My user have written off Some of the Assets from  Transaction ABAV; only  Book value of the Assets is effecting in Balance Sheet; but there is no effect in the Revaluation value.
    When the user is doing the  REPEAT depreciation run in AFAB, it is not happening.
    Can anybody suggest what could be the reason.
    Regards,
    Sudish

    solved.

  • How to Settleing SIngle CIP Order value into Different Assets (%age wise)..

    Hi Friends.
    I am very new to AA.
    I have a scenarios where we have created a Internal order having some limit for Asset purchase. for e.g. USD:1,00,000/-
    Currently we have bought some USD: 55,000/- worth of assets and debited to this order.
    Now we want settle USD:45,000/- to  4 assets (in differenet %age ratio), Rs.10,000/- will remain in Order and will be settled to some new assets in future.
    So the point is we want to settle Part of IO value to 4 assets and want to continue the Order with balance Rs.10000/- value in it.
    Can you explain me with T.codes what's the procedure to do this?
    Regards
    Ashok Prabhu K

    Hi Ram
    Thanks for reply.
    Currently I have below rcvr in settlement rule, Should I remove this..? Below AUC  already has some values.
    Cat Settlement ReceiveReceiver-short text %     Equivalence nSettNo.StrFrom From fTo peTo fisFirst usLast use         
    FXA 20000050-0        China Strategic Expa100.000            AUC 1     0          0          009.2008009.2008         
    Secondly, I understood about %age, asI need to reatain some value, if total of 4 assets do not total to 100% will that run..?

  • Transfer partial asset values from completed asset to AUC/other asset

    Hi All
    Is it possible to transfer partial asset values from completed asset to AUC/other asset.
    if yes please let me know how to do that?

    I already checked T code ABUMN
    But by using this code whole asset value is transferred ; I want to transfer only partial value.
    eg. If i postasset value of Rs. 1000 to a machine & capitalise it. But after posting i found that actual asset value is only Rs. 600 and balance is of another asset.
    then how can i transfer balance asset value of Rs. 400 to another asset card.

  • Amortize Adjustment Flag in Fixed Assets

    Hi,
    We have a requirement where we need to get all the assets for which the Amortize adjustment Flag is set. When we query a asset from Asset Workbench and then click on Books to see Cost, NBV etc. details,there is an option to make check mark against Amortize Adjustment. I want know which table hold value for this update.I see from the front end form that FA_BOOKS_V is being used but am not able to find this field in the table.
    Regards
    Aman

    Hi,
    You isolate assets where an amortized adjustment is made by checking fa_transactions_headers where (transaction_subtype = 'AMORTIZED' OR transaction_key = 'UA'). Any asset/book combination that meets that has an amortized adjustment. Since one can't make any expensed adjustments after an amortized adjustment, you don't have to check for a specific transaction. Just check where the condition exists.
    Regards.
    Ata ur Reman
    Thanks for Halim (My Oracle Support Community)

  • Sale value of group asset- sub asset more than wdv less than group total

    Hi,
    I am maintaining group asset for Income Tax Depreciation. All the asset under the same class is consider single asset for Income tax purpose. For eg value of Plant and machinery under Income tax is derived for all asset totaled together after depreciation for the year. Thus P&M is considered single asset for calculating I.T. Depreciation, even though it may contain 100 assets.
    For Income tax, for P & M class of asset depreciation for first year is with different rate and for rest years with different rate. Hence I have maintained sub asset for this group asset. Whenever a new asset is purchase, for income tax purpose it is recorded in the newly created sub asset number.
    The problem arises in sale of asset. When I am selling any machinery the sale value is deducted from the group value for IT purpose. In this case even though the value of sale is higher than the WDV of the individual asset it is adjusted in total. While configuring this in SAP I am facing following difficulties-
    1.     As the rate of depreciation is different for different years I am not able to maintain a single group asset. I have to create a sub asset. This facilitate the right depreciation calculation by different dep rate for purchases in diff year.
    2.     But as I am maintaining different Sub asset the sale value cannot exceed the balance of that particular asset, even though the total value in SAP for all the group assets is higher.
    3.     I can not allow having negative values. Negative values are not allowed to maintain in IT Records.
    Please help to resolve the issue.

    Hi,
    I am maintaining group asset for Income Tax Depreciation. All the asset under the same class is consider single asset for Income tax purpose. For eg value of Plant and machinery under Income tax is derived for all asset totaled together after depreciation for the year. Thus P&M is considered single asset for calculating I.T. Depreciation, even though it may contain 100 assets.
    For Income tax, for P & M class of asset depreciation for first year is with different rate and for rest years with different rate. Hence I have maintained sub asset for this group asset. Whenever a new asset is purchase, for income tax purpose it is recorded in the newly created sub asset number.
    The problem arises in sale of asset. When I am selling any machinery the sale value is deducted from the group value for IT purpose. In this case even though the value of sale is higher than the WDV of the individual asset it is adjusted in total. While configuring this in SAP I am facing following difficulties-
    1.     As the rate of depreciation is different for different years I am not able to maintain a single group asset. I have to create a sub asset. This facilitate the right depreciation calculation by different dep rate for purchases in diff year.
    2.     But as I am maintaining different Sub asset the sale value cannot exceed the balance of that particular asset, even though the total value in SAP for all the group assets is higher.
    3.     I can not allow having negative values. Negative values are not allowed to maintain in IT Records.
    Please help to resolve the issue.

  • Settlement of negative value to an asset in WBS (CJ88)

    Hello,
    I have a negative value for a cost element in a WBS which I want to settle it to an asset.
    Settlement rule is maintained.
    There is no error while executing CJ88.
    But it does not settle the negative values of that Cost elements.
    Please suggest how to settle this negative values.
    Regards
    Tushar

    Hello,
    There is no error message.
    Regards
    Tushar
    Edited by: Vijay Kumar Singh on May 31, 2010 1:57 PM

Maybe you are looking for