Assigning Sales Revenue cost element to various Profit centres

Hi
I have one controlling area and three company codes assigned to it. 
I have around seven profit centres under each company code.
How can I assign the sales account (revenue cost element) to different profit centres.  No cost centre assignment will be given in the posting. 
I am unable to find a solutions to this.  Kindly offer your views on how can we assign the same sales revenue element to different profit centres under various company codes.
Regards

check this path'
Controlling>Profitcentre accounting>Assignment of account assignment object to prfit centre>assign cost object
Define the cost element in it
Edited by: shibu john on Oct 28, 2008 12:31 PM

Similar Messages

  • Profit center in New GL-Revenue Cost Element

    Do we need to make revenue cost elements for the revenue GL Accounts in New GL,since now the profit center would be mandatory itself by document splitting functionality..
    Awaiting response..
    regards,

    Hi
    In New GL as the PC is a part of FI there is no need to create revenue cost elemnts for revenue GL accounts to make the values from these revenue GL accounts to flow to PC.
    Thanks
    Sandy

  • How & Where can we do Revenue Cost Element Planning

    HI,
    We need to do planning for Revenue cost elements. How & Where can we do Revenue Cost Element Planning.
    Generally we will do excel planning upload for Cost Elements in KP06. But where can we do Excel plannin for Revenue Cost Elements in the system?
    Kindly provie me the transaction code and some inputs on how can i proceed.
    It would be a great help if any one can respond on this.
    Thanks
    Kishore

    Hi Kishore,
    We can plan Sales Revenue through T-code KEPM-Edit Planning Data or through T-code KE13N by Uploading CO-PA-Sales Plan in Quantity and Revenue terms. Here we have to set  different Plan Layouts for Quantities and Revenues. After successfully uploading the data file,  we have to transfer the Sales Plan data to SOP in T-code-KE1E.  Then We can check the values by Co Code, Plant, Product-wise and Customer  in T-code KE25-Display Plan line items.
    Regards
    appalas

  • Report Writer Issue - Revenue Cost Element - After Upgrade.

    Hello ,
       After upgrade some of the report writers are not pulling up all the plan data.
       I found out that the revenue cost elements (cost element category - 11) are not being pulled by
       report writer in ECC 6.00, where it used to pull them in 4.6C. These postings were done to
       our budget version using KP06.
       These revenue cost elements postings are not stored in COSP. I dont have any idea in which tables
       they are stored.
       Does anyone have any clue about this.
    Thanks,
    Sandeep

    Its a report writer report developed here..(not standard one)
    The cost center is a revenue cost center. So when we post our revenues we post it to this revenue cost center.
    The issue is in 4.6C env it used to pull this data, but in 6.00 it is not pulling.....
    Thx,
    Sandeep

  • How to get the member of cost element group from Profit center group

    Hi Guys,
                  I need to get the member of cost element group from Profit center group like in Tcode KCH3 and the same from Account Group like in Tcode KDH3.
    Any Function Module available to get this data.
    Thank U for Ur time.
    Cheers
    Senthil

    I am closing this thread.

  • Requires an assignment to a CO object for revenue cost element

    Hi All,
    I am posting directly in FI revenue entry through FB70. For that I am using the revenue GL Code 62200030 and same has been created as a cost element using cost element category 11 Revenue under controlling area...
    Now when I am posting the transaction I have already given profit center at line item level (& not a cost center as it will never takes credit entries). But after giving all the data at line item level system is giving me the following error "Account 62200030 requires an assignment to a CO object-Message no. KI235". I am using SAP ECC 6.0
    I can not use cost center in revenue entry as my cost center has been blocked for revenue posting.
    Kindly help to resolve this issue.
    For helpful answer points will be surely assign & thanks in advance.
    Regards,
    Sandeep

    Hi Sandeep
    First of all, do not offer points.. Edit your post and remove those words.. Else, your thread might get locked....You can give points for helpful answers as per your discretion, but pls do not offer them in your thread
    You need to enter an Internal Order or a Prof Segment to a revenue line item...
    If you do not want to do this, then convert this message into Warning message in OBA5
    Regards
    Ajay M
    Edited by: Ajay Maheshwari on Jan 17, 2011 10:01 AM

  • COPA cost base same cond. map to NET Sales different cost elements problem

    Hi Guru,
    I have the following issue:
    I mapped ONE billing condition type assigned to ONE value field.  ZPCD is assigned to value field VV110 (net sales)
    That one condition type can post to 2 different cost element based on the account assignment group of the item
    One cost element is set up and revenue type 11 and the value is posted to COPA value field NET SALES
    The other cost element is set up as cost type 1 and the posting to COPA is blank i.e. no posting to value field NET SALES
    In both cases a COPA document is created i.e. total 2 COPA documents one for each posting.
    What is the problem??
    Thanks
    Linda

    For the purchased products, you may perhaps use the condition type VPRS to bring in the  material price from the material master.

  • Assign center to cost element

    Hi Guys,
    Where can we assign the cost center to the cost element or the other way around.
    Pls suggest.
    Thanks
    Srikanth.

    Hi
    You may assign default cost center to a cost element at Controlling area level in KA01/02
    or you may assign a default cost center to a cost element at company code/valuation area/ business area /profit center lever in OKB9
    Regards
    Sach!n

  • Cost elements for account Profit or loss on exchange rate valuation

    I am running transaction F110 and among the invoices to be paid there are foreign denominated invoices. I have 4 business areas set up and have one GL account where all the gains and losses arising from the exchange rate fluctuation are posted (this account has been assigned a cost element).
    When I run F110 i get error that the gain/loss on valuation account requires a CO object. I thot the system would be able to determine all the CO objects from the invoices selected for payment. In a payment run, there are a number of invoices belonging to different CO objects.
    Is there a way i can get around this. If i delete the cost element will i be able to draw up financial satements per business area.

    Hi,
    You can set up in OKB9 for Co Object determination.
    You can set Business Area as mandatory in OKB9 and then click on Detail per business Area and another screen will open up, there you can enter, Cost center against Business Areas.
    This will resolve your issue.
    Regards,
    SAPFICO

  • Allocation of cost  from one profit center group to various profit centr gr

    Hi Experts,
    Here we  created one profit center as group function having various cost centers like common function Admin,Accounts,Legal,HR etc. Now we want to allocate the the cost from group function to various profit center group.
    Kindly give your valuable solution.
    J.Francis

    Hi,
    The allocation can be done through Distribution either in a fixed value or in percentages.  You can define a planning
    cycle for a sender profit center group and define the amount to be allocated to receiver profit center group.
    Define Actual cycle in the same way.  In periodic processing which may be every month/quarterly/half yearly,
    you can distribute the values from one group to the other.
    Best Regards,
    Sadashivan

  • Assign Plant to a GL Account and Profit Centre

    Where do I assign a plant to a GL account and Profit Centre.

    Hi,
    a plant is not direct assigned to a profit-center and not to a G/L account.
    A plant is assigned to a company code (in customizing), a GL account can be created (account master data) within a company code (if its used in this CC), a profit-center is assigned to one/more company codes (profit-center master data).
    In material master / costing 1 view (which is plant related) you can assign a material to a profit center, thus all postings in one plant related to this material belong to this profit center.
    Best regards, Christian

  • Settlment Cost element determined from work centre

    Hi
    I want to settle costs on plant maintenance orders to different type 21 cost elements depending on the main work centre on the order.
    I understand that the ORDER TYPE can have different SETTLEMENT PROFILES and that these can determine the cost element to post to. HOWEVER the problem I have is I can not create new order types for this purpose (to much re-work).
    any help would be appreciated
    phil

    Hi,
    I dont think so that in Standard setting you can assign Settlement profile by work center. Automatic assignment of settlement profile is possible by Order type . Manual assignment of settlement profile will also not work as in one PM order you may have mutiple operation which belongs to different work center.
    So this looks very unique requirement and you will have to go for some development or user exit which can make you able to post the settlement based on Work center.
    regards
    Ranjan

  • Using SKF to do allocation for Profit Centre

    Dear All,
    I am in the process of setting up the distributing the cost from 1 cost element to several profit centre base on SKF, which requires ratio of number of employee.
    The requirement of SKF is basically to capture the number of employee of one PC / total of employee of Profit centre group. Distribute the cost of cost element of ONE profit centre to a several profit centre (defined in PC group) base on SKF.
    I have created the SKF via KK01 and creating Profit centre group.
    Change the SKF via 9KE5.  Now, i am stuck of ensuring the ratio is created properly, which i think should be defined in 9KE5?
    I have tried to define the distribution rules via 4KE2 by choosing variable portion with actual value / SKF. However, the receiver of the profit centers which i defined the PC group was zero after i executed the cycle via 4KE5.
    Could you please shed some light what i have gone wrong or missed anything, as i have been trying to google and forum on the steps of setting up the distribution.
    Thank you so much and very much appreciated.

    Hello,
    Thanks for the reply. The concept should be the same for the distribution and assessment. I may adopt the cost allocation instead.
    However, may i know using SKF, are we able to compute the ratio :
    the number of employee of one PC / total of employee of Cost centre group?
    Could you shed some light on that? I understand we need to manually enter the number of employee, but using formulae for the SKF?
    Thanks

  • Cost elements Assign to different profit center

    Hi All,
    I have 3 costelements are, these cost elements i have to assign to profit center.
    Where i have to assign these things, i mean which transaction code i have to use.
    Thanks
    Rams
    09833624515

    Dear,
    Use transaction OKB9 to assgin cost elements to a profit center.
    One cost element can be assgined to one profit center only.
    Regards,
    Chintan Joshi

  • CO assignment object for sales revenue account

    while doing the intercompany billing after PGI, system is throwing an error 'account assignment object is required for sales revenue account xxxxxx'.  However, the sales revenue account is created as a revenue element and the profit centre accounting is active.  How can I solve this issue ?
    Regards

    Hi,
    The account assignments flow from the sales order into the billing document.  If you update the profit center in the sales order in the profi center field of the item detail view - > account assignment tab, it will be captured in the billing document.
    Also if you want this to happen automatically, this can be maintained in the material master.  Or you may need to define a substitution using 0KEM.
    Cheers.

Maybe you are looking for