Availibility check "02" not generating a confirmed schedule line

Hey Gurus,
We can't figure out why when create a order using the availability check as "02" that the system will not create a confirmed quantity for the schedule line.  The material is available and we have also checked to see that the delivery time was reasonable for delivery of the product.  We run the availability check in the sales order and it still will not create a schedule line for us to create a delivery on. 
Do you all have any suggestions of master data and configuration that we should check in order to try to get this to work?
Sincerely,
Nina

Dear Nina,
I think in your case - the stock may be allocated to some other sale orders which are already created and not yet delivered.
Please check in CO09(Availability Overview) for that particular material.
Though you can see the stock in MMBE, it might be allocated to some other order..
Transaction:
First check the requirement type assigned to your sale order in Procurement Tab of a sale order.
OVZG(Req,. class) - Check Availablity Check indicator is checked
OVZH(Req. Type) - Check Req. type has assigned to Req. class.
In VOV6 - check Availability check indicator is checked for your schedule line category..
Check in Material master - general / plant view .. Availability check is assigned for that material..
If you have maintained all these settings properly, and still the order is not getting confirmed - then the stock might be assigned to some other sale order which is not delivered yet..
Thanks,
Venkatesh.S.P
Edited by: venkatesh paulraj on Mar 12, 2009 5:32 AM

Similar Messages

  • VL10G is not creating delivery for some of the confirmed scheduled lines

    Hi, I was trying to find the reason why we are getting a very generic error message (Message type V50R ID 036 - The document could not be delivered.) for some of the confirmed schedule lines when executing VL10G in batch and no delivery document is created. Those orders have confirmed scheduled lines and inventory has confirmed to have stock. However, when the VL10G is executed in background, the sales order line items will be captured into the list but when creating delivery, the systems is showing the above error message.
    From debug, found out the message is generated from LV50R_VIEW43.
    We went through lots of OSS notes but nothing seem to ring a bell here. We are using ECC6, list type = index list.
    The error message is very inconsistent. The same documents will be dropped for delivery after several days without any change to any of the sales document or inventory level.
    Some of the note mentioned the parallel processing lock on ATP check for the material may be the reason for the error however we are not using any parallel processing in VL10G. We also checked the index table VEPVG has all correct entries and all the entries are being selected into the delivery due list. Error happens when the delivery is trying to be created.
    Any advice is appreciated.
    Thanks.

    Hi ALL,
    Any suggessiton on the below issue.
    We have batch jobs to process the DDL for the STOs, but some of the line items of the same STO is not picked up by batch job, (VL10B is assigned in the batch job, i checked the variant and configuration, everything seems to be fine, when i try to process the DDL through VL10B manually by giving the STO number only, the VL10B program is not picking the STO, but the same STO can be processed through VL10D, what could be the problem and why the VL10B program is not recogonizing the STO for the delivery creation.
    We are using ECC 6.0
    Regards,
    Rajesh.R

  • How to delete confirmed schedule lines, without executing the ATP check?

    Sales and Distribution: Concerning ATP (product allocation)
    Situation:
    Step 1: An order is created with priority low. Quantities are confirmed for line items.
    Step 2: A second order is created with a higher priority. No confirmed quantities.
    Rescheduling program (SDV03V02) is then executed. This selects and sorts the orders in the correct order.
    The confirmed quantities for the first (low priority) order should now be freed up, to be able to allocate those quantities to the second (high priority) order.
    The problem I am facing is that the confirmed quantities are NOT released.
    We cannot use BAPI_SALESORDER_CHANGE or SD_SALESDOCUMENT_CHANGE to delete or modify the schedule lines, because these function modules execute the ATP check again. And when that happens, quantities are again confirmed and assigned.
    How can we get rid of the confirmed schedule lines, without executing the ATP check?
    Thanks,
    Edwin.

    Found a solution to the problem:
    In the Rescheduling program we export a parameter to the memory, to make it possible to delete schedule lines without executing the ATP check.
    Deleting of the schedule lines is done with a BAPI, which will call the ATP check automatically for ATP relevant materials. This we want to stop from happening (only when calling the BAPI).
    After the BAPI has been called we FREE the MEMORY ID.
    The parameter is imported again in Customer-Exit EXIT_SAPLATPC_001.
    Transaction.. SMOD
    Enhancement.. ATP00001
    Component.... EXIT_SAPLATPC_001,
    Include...... ZXATPU01.
    The customer exit is used in function AVAILABILITY_CHECK_CONTROLLER, just before calling function 'AVAILABILITY_CHECK'.
    Simply refreshing the ATP tables in the customer-exit, will prevent the ATP check from being executed (because we removed the list containing the materials for which the ATP check needs to be done). As a result, the function 'AVAILABILITY_CHECK' will not be processed.

  • Availability check should not be carried out in Quotation VA21

    Hi,
      While creating the quotation we want that availibility check should not be carried out when user enter the material code on VA21 screen, as per the material lead time system should directly set the delivery schdule date, as in many cases if some other user is working on the same material then system save the quotation with confiirm quanity as zero in the schdule line, thsi we want for only one lant.  what setting can be made for this.
    regards,
    zafar

    how to know all the categoru which are applicable in quotation
    For this, first you need to identify what item categories are assigned to quotation which you can find in VOV4.  Next for these item categories, you need to list the relevant schedule line categories from VOV6
    G. Lakshmipathi

  • Payment doc is not reflecting in Payment summary & check is not generated

    Hi Expert,
    I have run f110, in proposal run 37 item reflecting  but in paymment summary (i doc) only 34 items are picked, but FI documnet is created for all 37 items same is checked in BKPF table, but check is created for only 34 items. ( i am making vendor paymemt)
    My query is below?
    y check is not generated for remaning 3 items?
    how come FI document is created for all 37 items? if in paymnet summary only 34 items are picked
    As i am new to SAP, i am very much confused.
    waiting for reply
    Regards
    Pankaj

    Check those missed and cleared documents may be MIRO and MIRO reversal documents.

  • Check number not generating

    Hi Team,
    Please can you suggest me.
    While execute the F110 check number not generated.
    I given correct payment method and i checked varient,accont id, check lot is it correct
    Posting orders: 3 generated, 3 completed
    Program RFFOUS_C: No records selected
    The following documents were not processed since they will be sent by EDI
        CoCd Payment document/Payment order
        MASN XXXXXXXX
        MASN XXXXXXXX
        MASN XXXXXXXX

    Hi,
    I think this error of "The following documents were not processed since they will be sent by EDI" is coming because your payment method is assigned for EDI Compatible Payment Method.
    To check this, Go to TCode FBZP and select Config Button House Bank. Then in the House Bank Config screen, click on the tab
    EDI Partner Profiles - and then click on EDI comp. pyt mthds.
    Although your field in EDI Partner Profile could be blank but still you need to click EDI comp. pyt mthds button. Here check if Payment Method C is assigned. If so then delete the line and regenrate the Check Number through SE38-RFFOUS_C
    Regards,
    Sanjay

  • Confirmed Schedule Lines in Sales order on a Holiday

    HI Experts,
    I am seeing that I have a confirmed schedule lines on a Holiday though the Calender assigned to Shipping Point and Plant has been marked as holiday. I have not maintained any unloading point calender in Customer master and I do not think it is mandatory. However, ECC is connected to APO/GATP. Since The availability check is happening from GATP, Will it consider the factory calender in ECC or Should a Time series be maintained in Location Master so that The confirmed delivery date will not be on a holiday.
    Any inputs will be appreciated.

    Dear Prady Reddy,
    unloading point calendar is not mandantory.
    The ECC factory calendar will be transfered and considered in APO scheduling but you can also define other calendars in APO with time streams and you can assign it to locations.
    Hope this helps.
    Regards,
    Tibor

  • Delivery group 001: Item 000020 contains no confirmed schedule lines

    Hi,
    I am getting following error message when i try to save sale order
    "Delivery group 001: Item 000020 contains no confirmed schedule lines"
    The item is a BOM itam and when i checked Deliverygroup for all items in BOM, it is the same for all.
    Pls let me know how can i save sale order??
    Thanks in Advance
    Srikky

    hi srikky,
    delivery group stands for:
    for example you have entered a BOM item in line item 20.
    and it contains plenty of components in that BOM
    then if you assign these delivery group at transaction level then it will combine all the components material available dates and gives one single Material availability date basing on the components feasibility.
    so coming to your issue, here that delivery group's 001 is not having confirmed material availabilit date so it is throwing an error on schedule lines.
    i think you should go to OVZJ and check FIXED DATE AND QUANTITY against the salesarea.
    test and confirm the forum
    balajia

  • Date flexability while confirming schedule lines

    Hi Freiends,
    In MTS situation (Make to staock) the system confirms the schedule line date immediately since the material is available in stock and also there is no availablility check done.
    Now, I have a requirement where we want to have a flexability of confirming schedule line as per our dates.
    Note that since there is no availablity check hence we cannot put some time (dummy time) in Pick Pack in order that the confirm delivery date could be postponded.
    Is there any means to confirm schedule line data as per our requirments.
    Thanks & Regards in advance
    Nayan Shah

    Issue Resolved

  • Change shipping dates/times for confirmed schedule line

    Hi,
    I am having a problem changing the confirmed schedule line in a Sales Order VA01.
    I have added my code into the user-exit
    *       FORM USEREXIT_MOVE_FIELD_TO_VBEP                              *
    *       This userexit can be used to move some fields into the sales  *
    *       dokument schedule line workaerea VBEP                         *
    *       SVBEP-TABIX = 0:  Create schedule line                        *
    *       SVBEP-TABIX > 0:  Change schedule line                        *
    *       This form is called at the end of form VBEP_FUELLEN.          *
    FORM userexit_move_field_to_vbep.
          vbep-ezeit  = '235900'.
          vbep-wauhr  = '235900'.
          vbep-lduhr  = '235900'.
          vbep-mbuhr  = '235900'.
          vbep-tduhr  = '235900'.
    However, in the above code I manage to only change the first schedule line in case I choose a delivery proposal. I need to change the line with a confirmed quantity. Instead I change only the first shedule line without a confirmed quantity.
    Question: Which user-exit can i use to change shipping times dates for all schedule lines or just confirmed schedule lines?
    Thanx

    Hi,
    Use form routine "USEREXIT_SAVE_DOCUMENT_PREPARE" in MV45AFZZ.  Update VBEP as well as XVBEP Structures.
    Regards
    Vinod

  • Rush order :-Even though stock available  Sytem is not ablet   to confirm

    Hi all,
    In case of Rush order- insipite of  stock available in the system  its not able to confirm the quantities .
    Immediate delivery is not happening because of this
    Please let me what might be the reason?
    Regards
    Anil

    Hi anil maripady
    As you are doing rush order , first of all go to VOV8 and check the following things in  rush order document type :
    1) Shipping Conditions - immediate
    2) Immediate Delivery - [X}
    3) Lead time in days - NIL
    Now go to  MD03 and check how much  stock is available of that material and how many open orders are also there with that material in that plant
    Another option go to MMBE and check how much stock is there for that material in that plant and storage location
    Regards
    Srinath

  • Customer refund paid using F110 for which check is not generated

    Hi,
    A customer refund is paid using the transaction F110. Payment document got generated and successfully posted. But the check number is not allotted for that document and checks are not printed. In the same payment run payment is made to the vendors for which checks got generated. I had checked customer master data and payment method settings and not able to figure out what is the exact reason.
    Please respond
    Regards
    Srinivas

    Hi,
    System thinks Check should be issued to vendors and collected from customer so check creation refer to the field LFA1-LIFNR, name written here is used for Check creation. Does customer name lie in to LFA1-LIFNR. This is the reason check issued for customer is not created. If you want then get the check printing form analyzed by an ABAPer to modify, if any.
    Regards,
    Chintan Joshi.

  • Check No not generated

    i am faceing problem when clear payment throught T-code F-58. Clearing document no is assigned but check no is not generated.
    thanks
    Guro

    Hi ,
    In T code FBZP kindly ensure that you have entered the form in the selection option :
    - Payment methods in CO code , select the payment method and view the Forms section and ensure you have enterd the payment medium form in that .
    Hope this helps .
    Regards ,
    Dewang T.

  • Materials in stock at u loc consider for Availability check but not for MRP

    Dear ALL,
    Please solved the problem by settings in the customizing  we are able to set the materials  at stock U location (serviceable )should not be considered in Mat Availability  for PM orders
    Settings we have made for all storage locations in U * By excluding storage location stock from MRP
    If storage location stock is excluded from MRP at plant level, no receipts for this storage location will be created in the planning run.
    so we are able to run the availability check perfectly
    But now MM dept.is not accepting this as they want this stock to be considered for MRP
    Has anybody done this scenrio successfully please reply the solution
    Regards
    Pratap

    A way that I think of, is to set the ATP at SL level, so in PM order you check only in a specific location, not in all the plant.
    Of course that you need to let all SLs to be relevant for MRP, otherwise this stock is not considered for planning.

  • Checks are not generated after Automatic payment run

    Hello,
    I have a strange issue. Payment has been executed normally through APP. However some of the checks are not printed and it is not gone to PAYR table as well. I can see the payment documents in REGUH table and the documents have been cleared. This is not a new vendor and the check payments have been made to this vendor through this process.
    Could you please suggest what could have gone wrong as PAYR & REGUH table and payment list from ZF110 must match. Here it matches only REGUH & Payment list from ZF110. The vendor has been asking for the payment and we realized this issue
    Thanks
    Ivan

    Please check if relevant print variants have been assigned in the relevant check print program (RFFOUS_C for e.g.). If you have posted in 3 company codes and assigned check print variant in only 2 company codes, then some of the checks will not be printed even if the payment document has been posted.
    As part of business process, it is always useful to print the payment list and reconcile atleast if the number of expected checks have been created.
    Ron

Maybe you are looking for