BOM Prices for production...

Hi Experts,
My client activated the ML, They are following Actual costing...no Standard cost estimation...
Now the reqirement is ..for one product they are having the multiple BOMs(With different combination of Raw materials), at the time of production the production people taking bom based on the availability of materials....
Now the requirement is he wants to now what is the present cost of the BOms(all BOMs) of that particular product on that date.
Based on this he can select which bom we can take for production.
How can we get the price of all BOMs for the particular product same time.....any standard report is there to achive this..
Please give your inputs..
Thanks
Chandu

Hi Chandy
Well if you want to check price for a BOM you have to run a cost anyway. (CK11N)
You can set a costing variant (OKKN) to work on standard costs (plan activity price) or you can set to take actual prices (actual activity price + last reg info purchase).
Anyway you will have to run and you can run reports to check it.
One problem would be compare the the BOM´s because you would have to run many costing versions and compare them.
Well I hope I have gave some scenarios to check.
Regards
Fred

Similar Messages

  • How to set the price for product in service channel site

    Hi
    In R12 I had registered the Partner using Register as a partner link.After registration I saw the site selection page i clicked the "Channel services" site. And i click the "Products" tab i see the product only i does not see any price for it. and only one product has the price i clicked the "Add to cart" button and i had seen the error      
    Error           
    The column(s), PRICE_LIST_ID, has an invalid value(s), 11833 .
    The column(s), PRICE_LIST_ID, has an invalid value(s).
    what i want to do solve this error.
    And also i was trying to enroll in the partner program by clicking the "VisionOne authorized partner program" from the Available programs bin i saw the error message when i click the "Enroll now" button
    " The following input contained illegal input value, please re-enter your input or contact the system administrator: "
    Thanks

    Hi;
    Please make a search at metalinks as "The following input contained illegal input value, please re-enter your input or contact the system administrator", There are more than 6 notes mention this error message
    Regard
    Helios

  • List price for Products

    Hi All,
    is anyone aware of the List price table which is maintained for products?
    Regards
    Sidd

    Sidd:
    Pricing data is spread over all sorts of condition & supplemental tables; there is no single table holding a standard price list.
    To get you started, the following is an overview of the CRM table naming convention:
    PRICE table names are named CNC*;
    Associated SUPPLEMENTAL tables are named CNS*;
    Pricing SCALE tables are named CNL*.
    Regards,
    D.

  • Price for JRE 5.0 for PowerPC?

    Hi,
    Now JRE 5.0 for PowerPC is available for evaluation.
    What is the price for production version?
    Thanks
    Eugene

    If you're talking about the download page, I've
    noticed it does go down from time to time. Usually
    trying again a bit later resolves it.ya, today can download already... i think is the page down that day...
    thank a lot!~

  • Last Purchase Price for a product

    Hi,
    I need some here.
    Item A is made up of Item B and C (in production BOM)
    Item B is in production BOM as well and is made up of Item D, E and F.
    I need to calculate the Last Purchase Price of Item A, which is:
    Item C (LPP $10)
    Item D (LPP $12)
    Item E (LPP $20)
    Item F (LPP $30)
    Total Item A LPP = $72
    Any suggestion of what the best approach of doing a query/ a XL report for this?

    Hi!
    1. Define BOM for Item A
    2. Link a Price List for tht.
    3. Update your child items and child price's in a price List.
    4. Click the orange Drop Down Arrow in BOM window.
    5. This will automatically calculate the Item Price for Item A and update the Price List tht linked in it's BOM
    Hope Help u !!

  • Unit Price in Issue for Production for Item with wrong UoM

    Dear All,
                In issue for production the item cost being picked does not match either our Last Purchase Price or Price List1. In some cases the price considered is an average:
    Eg:- For Item A with Purchase UoM in Nos. and Inventroy UoM in Gms, we had not enetred the conversion factor i.e 1 No=100g. Thus GRN was made for 25 Nos. @ Rs.450/Unit. But actual stock was 2500g. Hence to rectify the stock we made an OB entry for 2475 as on GRN date with zero Price. Thus total stock was 2500 and Value 25*450=RS.11250
    When we did an Issue for Production for this item: Qty:400g, the unit price considered was Rs.28.125 when the actual price to be considered is Rs.450[Unit Cost]/100 [UoM Conversion]=Rs4.5. We had entered Rs.4.5 in Price List1 and had selected this price list in the BoM as we had not entered a conversion factor in the Item Master Data and SAP does not allow alterations to this tab once the Item is involved in transactions.
    I think the system calculated the price as follows: (25450+14750)/400=Rs.28.175
    How do we avoid/correct this in the future?

    If you need the stock price correct, the only option might be creating a new item with correct information in the first place.  Once you have error data to start with, there is no way to corrected as you wish.
    Thanks,
    Gordon

  • Adding a goods reciept for production sets no unit price

    Hey All,
    We are performing a goods reciept for production using DI API.
    We use a non continuous stock system
    On the Bom we have set te price to 5 EUR.   When we report a completion using the Business one client the unit price of the goods issue has a value of 5.
    When we add the goods receipt using DI API the price is not set.  After some investigaton we have seen that the DI API automatically uses the last purchase price of the Parent item.  According to me, this means that DI API is using the same logic as the SAP Business one Client
    This is a code example of how we are adding the goods receipt:
    SAPbobsCOM.Company m_company = new SAPbobsCOM.Company();
                    //Set the company properties
                    m_company.Server = "Server";
                    m_company.CompanyDB = "TEST";
                    m_company.UseTrusted = false;
                    m_company.DbUserName = "sa";
                    m_company.DbPassword = "******";
                    m_company.UserName = "manager";
                    m_company.Password = "manager";
                    m_company.DbServerType = BoDataServerTypes.dst_MSSQL2005;
                    //Connect
                    m_company.Connect();
                    Documents doc = (Documents)m_company.GetBusinessObject(BoObjectTypes.oInventoryGenEntry);
                    //doc.Lines.ItemCode = "383100";
                    doc.Lines.BaseType = (int)BoObjectTypes.oProductionOrders;
                    doc.Lines.BaseEntry = 20035;
                    doc.Lines.Quantity = 1;
                    doc.Lines.BatchNumbers.BatchNumber = "TEST";
                    doc.Lines.BatchNumbers.Quantity = 1;
                    doc.Lines.WarehouseCode = "01";
                    int error = doc.Add();
                    if (error != 0)
                        //Error
                        MessageBox.Show("Error occured with code: " + m_company.GetLastErrorCode() + " " + m_company.GetLastErrorDescription());
    Kind regards
    Tom Baeyens
    Produmex

    no replay, clossing threat.

  • Determine price for minimum qty of mix of products

    Hi all,
    Is there the possibility to fix a price for a minimum quantity of a mix of product ?
    Mix are not identified as a material code but we have only single material codes.
    Do I need to create sales bom?
    An answer is appreciated
    Thanks
    Vir

    Hi Hari -
        Sorry for the delay, I was playing around in my system to see if my approach would work. Basically I created a new restricted key figure (RKF) which is defined as Price restricted to 0CALMONTH value 01/2007.
    Now I have created two new calcualted keyfigures which are defined as
    CKF1 ='RKF'.
    CKF2 ='RKF'.
    The description of RKF will be 'Price for Calmonth 01/2007' and that of CKF's will be 'Price for Calmonth 02/2007' & 'Price for Calmonth 03/2007'.
    With this approach you cannot display Calmonth in the report (be it in rows or columns).
    This approach may not be pratical for your report requirement but thats the best I can think of :-).
    FYI, you can extend this approach to further calmonths and run the report by Calendar year instead of Calquater.
    Good luck!

  • Bom for production order and subcontracting

    Dear guru ,
    I have a finished material that can be use both produced in-house and procured externally with subcontracting.
    Now i use one only bom with usage 1 (production ) for the two process.
    I have a problem for one component.
    For subcontracting i must consider this component as a phantom (with explosion of its components) , instead for the in-house production I must consider this component as a normal stock item.
    Can I use only one bom or I must create an alternative bom for manage the two cases ?
    Thanks for your help.

    Dear CRIS,
    In my understanding this may create discrepancies during the material transfer from own stock to the vendor and also during
    month end checking process.
    What's the problem of maintaining that component as a stock item?why it should be treated as a phantom only for sub-
    contracting?
    Even if you are maintaining 2 different alternative BOM's for the final product one with the component as a normal assembly and
    the next one as a phantom,you will be facing issues during costing purpose and material inventory also.
    Come back with your further questions.
    Regards
    Mangalraj.S

  • Maintaining Price for BOM / Bom item with customer

    Hi,
    We are using BOM concept for SO, and price we are maintaining at item level  like we have a FG material  9910    and it has BOM componenet  as , A,B,C  and we are maitaining price at item level for A,B, and C   now I want to maitain price at with  BOM  and customer
    BOM :  9910
    Item A,B,C
    BOM : 9911
    ITEM: A,B,C,D
    Now our requirement is to maiatin price as   CUSTOMER / BOM Header material  / BOM ITEM
    sohow to make the condition table for my requirement,  as MATNR field we can select only one time in table  how to take MATNR of Header and MATNR for item.
    regards,
    zafar

    Hi Prakash,
          Thanks for your reply it is a good link which u have send,  but my requirement is not solve with the given link I want to maiatin price at item level  for this in Main item item category I have maiatin LUMF  and alll price at item level  but  my requirement is I want to maiatin price at item level only but refeence to Main Item
    MEANS  :  I Hva emain item 9910.  with item  , 1.2.3  and i have another main item 9911  with sub items ,1,2,3,4  in such cases I want to maiatin price for sub items 1,2,3,4  but ref. to customer and Main item
    CUSTOMER / MAIN ITEM / SUB ITEM
    how to mainatin price in VK11  as per above requirement.
      regards,
       zafar

  • Patch 7303030  FAILED: file cst4274743.sql on worker  1 for product bom use

    Hello
    I'm a noob to the Oracle world, and are trying to update our system from 12.0.4 to 12.1.3 I got to the point of installing patch 7303030 and I keep get this FAILED: file cst4274743.sql on worker 1 for product bom username BOM. I have looked in the threads but have not found anything that has helped so far. I have tried restarting the worker but got the same result. can any one point me in some direct so i can complete my update in my test environment.
    Thanks

    Hello
    I'm a noob to the Oracle world, and are trying to update our system from 12.0.4 to 12.1.3 I got to the point of installing patch 7303030 and I keep get this FAILED: file cst4274743.sql on worker 1 for product bom username BOM. I have looked in the threads but have not found anything that has helped so far. I have tried restarting the worker but got the same result. can any one point me in some direct so i can complete my update in my test environment.
    Thanks

  • How to make Different Price for same product in one Sale Order

    How can i customizing my system?
    I need to sale for different price same product A in one sale order. And price condition type cant be manually. i can separate them by position. for ex. in first position: product A is one price and in 2nd product A with discount. i tried to do it by changing a price group for 2nd position to determinate a discount condition but it generates invoice split.
    Someone have any suggestions?

    Hi
    you can have it automatically determined after some custo and using userexit_pricing_prepare_tkomp in MV45AFZZ and RV60AFZZ.
    The idea is to use ítem category field (PSTYV) as a part of pricing data to determine different prices for same material by changing manually ítem category when creating a sales order
    - you'll need to create a new ítem category copied from the one you´re using and do all assignments
    - add field PSTYV, if not there, to pricing field catalog. This thread has an example on how to and coding required for userexits
    http://scn.sap.com/thread/1693234
    - Adjust your pricing sequence as per new table
    - Maintain specific prices in new table for materials with this new ítem category
    Finally, when creating a sales order change, when required, default ítem category by new one to get specific price for material.
    Regards,
    JM

  • Actual activity price calculation for production order

    Hi
    Can any one guide me in how many ways we can assign actual activity price calculation for production order?
    I knew only one way by assigning PPP2 costing variant?
    I have another doubt is: if we don't mention any material valuation indicator (moving average, standard) in valuation variant, how system will calculate material prices? is there any other way, to recognize the prices by system?
    regards,
    Ramesh B

    Dear,
    Costing variant PPP2 is linked to some valuation variant inn OPL1
    System will check the valuation of material and activity according to this valuation variant
    For material valuation there are many stg acceding to which system will take the price the raw material,
    Valuation strategy for material component
    Strategy sequence that determines the valuation of the materials used in the cost estimate.
    Use
    The materials are valuated using the price in the material master record or the values calculated in a material cost estimate.
    Procedure
    You can enter a single strategy, or you can enter multiple strategies in the form of a strategy sequence. If you enter multiple strategies, the priority of the strategy determines what price or what values are selected.
    Examples
    Assume that the following strategy sequence is entered for material valuation:
    1. Planned price 1
    2. Standard price
    3. Moving average price
    If the system finds a value in the Planned price 1 field (costing view), this value is taken as the value for valuating the material.
    If the system does not find a value, the value in the Standard price field (accounting view) is used.
    If the material does not have a standard price, the system uses the value from the Moving average price field.
    if you have not mentioned, then system will give error that "valuation stg not found"
    Valuation strategy for internal activities and processes-
    Strategy sequence that determines how internal activities and processes are valuated in costing.
    Use
    The activities and business processes used are valuated with the prices from Cost Center Accounting or Activity-Based Costing to determine the production costs or process costs. The prices can either be calculated iteratively through price calculation, or entered manually by the user.
    Procedure
    You can enter either a single strategy or more than one strategy in the form of a strategy sequence. If you enter more than one strategy, the priority of the strategy determines which price is selected.
    Examples
    The following strategy sequence is entered:
    1. Actual price of the previous period
    2. Plan price of the previous period
    3. The most current plan price
    If the system finds a price for the activity type, this price is used for valuating the internal activities. If no price was calculated for the previous period, the plan price from the previous period is used to valuate the activity type.
    If the system cannot find a plan price for the previous period, it looks for a future plan price, using the next price in the posting period to valuate the internal activities. For example, if plan prices have been entered for periods 2 and 3, and a plan price is calculated in period 1 for period 4, the system uses the price from period 3 in accordance with the valuation strategy Most up-to-date plan price.
    Again if you have not mentioned, then system will give error that "valuation stg not found".
    You can use any costing variant for actual (PPP2)and planned(PPP1) according to your requirement.. check in OPL1

  • Moving average price for semi finished products

    Hi
    Could anyone light on this issue,
    Our client maintain moving average price for the semi finished material, need clarification on below points
    1)  What is the advantages and disadvantages due moving average price,
    2) Which price in the material master after the production order settlement,
    3) Is there any impact of this on WIP calcaultions
    Thanks in advance
    Mohan M

    Hi
    there are no advantages of it, ONLY Dis Advantages!!!
    That will ruin your inventory valuation forever.. Consider the eg below if your price control is V
    1. Your moving price in mat master is 100 USD
    2. You Mfr on Jan 1 @ Actual cost = 110 in Prod order and Qty = 1.
    Upon GR, GR will happen @ 100 and at period end if Qty is lying in stock, 10 variance will also be inventorized
    BUT, now consider this
    1. 1. Your moving price in mat master is 100 USD
    2. You Mfr on Jan 1 @ Actual cost = 110 in Prod order and Qty = 1.
    Upon GR, GR will happen @ 100 and variance lying is 10 in prod order
    3. You Mfr on Jan 10 @ Actual cost = 110 in Prod order and Qty = 1.
    Upon GR, GR will happen @ 100 and variance lying is 10 in prod order
    4. On jan 15, you consume Qty 1 and qty lying in stock is 1
    5. In period end, when you do settlement, following will happen
    a. For prod order 1: Qty Mfd 1 and Qty lying in stock 1 - Result: variance 10 will be inventorized.
    Mvg Avg price will shoot upto 110
    b. For prod order 2: Qty Mfd 1 and Qty lying in stock 1 - Result: variance 10 will be inventorized.
    Mvg Avg price (MAP) will shoot upto 120
    System wont check whether the qty lying in stock pertains to prod order 1 or 2... It will simply check if the Qty of prod order matches with qty lying in stock. hence, it will keep on inventorizing variance in this case.... and your MAP will touch the sky
    Regards
    Ajay M

  • Bom for production order - Function module

    Hi
    I'm looking for a function module or bapi which can provide me with the BOM for a specific production order.
    The FM should also handle changes to the BOM and just show me the updated BOM on the production order.
    KR
    Jesper Dueholm

    Dear JDU,
    You can use this FM BAPI_PRODORD_GET_DETAIL if you want to get the BOM components related to the production order or
    use FM,CS_BOM_EXPL_MAT_V2 for getting BOM multi-level display.
    There is no functional Module through which you can do BOM changes in the production order or in the BOM and it has to
    reflect the changes in the order immediately.
    Check these functional modules for BOM change,
    S_BI_BOM_CHANGE_BATCH_INPUT   Change bill of material via batch input
    S_BI_CHG_CHANGE_BATCH_INPUT
    S_CL_P_ITM_MASS_CHANGE
    S_CL_S_ITM_CHANGE
    S_CL_S_ITM_CHANGE_COMPLETE
    S_CL_S_ITM_ODP_CHANGE
    S_CL_S_SUI_CHANGE
    S_CL_P_BOM_MASS_CHANGE
    S_CL_S_BGR_CHANGE
    Regards
    Mangalraj.S