Budgets in projects system

dear ps experts,
wud like to know in any report of S_ALR*
to know the budget updates in a project
1. first cj30 & cj32
2, later after some time cj36 & cj32
wud like to know which report shows that cj30 & cj32  history
and when cj36 & cj32 history.
because every update at cj30,cj32,cj36,cj37,cj34 there is document created in sap, how to view these details as &when required
thanx in advance
regards
srihari
ps : s_alr_87013560 is of now use for my requirement

Hi,
When you go into CJ3B, it asks you for the document number. Then press F4, this will take you to another screen. Here you have a facility of entering the WBS element. Enter the Top Level WBSE of the project for which you want to see the detail. Then it will show the list of documents generated for that project.
Hope this solves your issue.
regards
Pratap.V

Similar Messages

  • Urgent - Business Object for Original Budget in Project Systems

    Hi,
      I am working on a workflow for original budget release in Project Systems.The transactions used are CJ30 (Original budget creation) CJ32( Budget release).
      I have to send a workitem fo release the original budget for a user. But I am not able to find out any business object relevant to Budget.
    Can any one helo me in this...????
    Thanx,
    Sivagami.R

    Hi,
    I have tried that option already. But I could not find any.
    Any update????
    Thanx,
    Sivagami.R

  • Remove budget in Project System from prior fiscal years

    Hello,
    Budget control has been activated in PS.  In PS, it is on annual budget so there's budget and actuals in FY 2003, 2004, 2005, 2006, & 2007.  Is there a way to remove the annual budget in those Fiscal Years?  I've deactivated budget control using tcode CJBW.  Once budget control is deactivated, I tried removing the budget but it's giving an error "budget exceeded." 
    Is there a way to remove budget in PS for prior fiscal years?
    Thanks.

    hi,
    as per my knowledge, you had already de-activated the budget control.
    so, my Q is why do u have to remove/delet the budget, when the system has no control of budget on project.
    regards
    parikshit

  • Budgeting in project system

    Dear All
    Can anyone explain me about the allocating a budget from planned cost to a project ,I am understanding if i am allocated the 100% planned cost to a project,I am not understanding what is distributed,distributable,remainder.
    Regards&Thanks
    P.Srinivasan

    Hi srinivasan,
    The concept of Distribution comes when you either directly Budget your project Or when you have converted the planned total to the Budget. Both the operations can be done in CJ30.
    When you copy the planned amount to the Budgeted amount in CJ30, the Column “Planned total” is updated.
    When you prepare a Budget, it’s generally “Total up” from the lower level WBS element. Distribution of the Budget is generally Top down.
    Firstly when you allocate the budget in the “Budget” Column, then the same will immediately appear in the “Current Budget” and “Distributable”. This means that the “Distributable” amount is ready to be distributed to lower level WBS elements. You can enter the required amount directly under the Column “Budget” of the corresponding lower level WBS element. Once you do this, the Column “Distributed” of the higher WBS element is updated, by the amount which is “Distributed”.
    The column “Assigned” is updated once you have assigned any cost to the project. (Commitment plus Actual)
    If you are working with Release Function of the Budget ( CJ32), then the Column “ Release” will be updated ( which can be seen in CJ30). In this case, you will be able to use only the released budget and not the Current budget.
    Hope this explanation helps.
    Warm regards,
    Srinivas Potluri

  • Buget Exceed problem regarding material transfer in project system

    Hello Sir,
    I have a problem regarding budget in project system.
    when i do budget and release . and do any transaction
    with that budgeted wbs element in particular project.
    i get budget excced errors usally.
    however, budget remains more than exceeded buget.
    Let us touch with a example in brief, we have a buget for a L&T project 10 Lakh.
    Buget                                         Release                                          actual cost                                            total cost commitment
    10Lakh                                       10Lakh                                             8lakh                                                         1Lakh
    when i transfer a material from another project to this L&T project material worth is 50thousands.
    i get a errors for L&T project budget exceed with 40thousands.
    however in project budget remains 1Lakh remaining .
    why system shows errors for this material transfer worth rs 50thousands
    Please help me regarding this problem where is 1lakh budget
    with regards
    sanjay agrawal

    Hello sir,
    there is no any problem regarding budget supplement but if project sometimes
    remains 20lakh buget price remaining out of 50lakh.
    and need 1 lakh material price for transfer in project
    then why need to do budget supplement for 1 lakh if project
    remains 20lakh price rest.
    please guide me for above problems
    with regards
    sanjay agrawal

  • Project system Budget Needs to be Doubled

    Hi All,
    I am facing a issue in project system where we have to double our budget, if we need to run a settlement in the system.
    For a example, if we have a budget of 100,000 and that is allocated to TWO sub WBS Elements as 50,000 each and when we want to run the settlement run it informs us that the budget is exceeded. So if we need to get the settlement run we have to allocate additional budget to the main WBS Element. But when we checked all the Purchases for the respective WBS, we find that the budget is not exceeded, but the settlement is checking for budget again in the main WBS Element.
    This is the way our consultants have configured this and now they are no more in the company. Can any one ex-plane how we can fix this so that we don't need to allocate more budget to the main WBS Element.
    Regards
    Ruchendra

    Hi Ruchendra,
    Have you checked the settlement rule ..It might be receiver as higher level wbs-element in lower level wbs-element.
    For example:-
    You maintained two 2nd level wbs-element below 1st level wbs with 50000 budget each.
    Now you consumed budget and cost inc rued.
    Now while settlement this cost moves to higher level wbs-elemnt bcoz of settlement rule.
    Thats why it needs budget to cover up that cost.
    Check this ..It might help you.
    Thanks
    Rahul

  • Project system - Budget

    Hi
    We have activated Project system at our end.
    We are maintaining Budget at cost element level in project system.
    we required to maintained in at both cost element and material level which we have given with example wise
    Can any body help in the same -- Please guide us
    Example
    If initial we procure Material A - in 2005 at the rate of Rs.500/-
    per kg and quantity required for the project is 200 KG
    Accordingly we maintained the budget for the same for Cost element for Rs. 100000/-.
    If during the execution stage the cost went up to Rs. 700/- Per kg. say in year 2006.  and we raise a purchase order for 142 KG where the budget will get  exhusted. but we can not able to put the trace on quantity wise budget tracking.
    I Do agree that value wise we can put the track but i required it to maintained t quantity wise also.
    Please guide us in the same issue.
    Points will be awarded.
    Thanks & Regards
    Mahesh

    Hi,
    Good afternoon and greetings,
    Wishing you a very Happy New Year 2007
    Please go through the following OSS Note
    Note 167405 - Totaling up zero values not possible
    Please reward points if found useful
    Thanking you
    With kindest regards
    Ramesh Padmanabhan

  • Project system budget error.

    hi all,
    this my query against budget error in project system in tcode sap_alr_87013558 i am finding that my budget is for 11100000, actual is 8116942,commitment is 511355,remord plan is 9597403,and available is 1502597 .
    please note that even i am having the budget i could not make a requistion for 44000. plase help me out.
    Regards ,
    Abraham

    hi Paul,
    My overall budget is 100000 the project is been  planned  on the overall basis and not on annual basis
    my assigned value in tcode Cj30 is 98000 so i have only 2000 remaining But in information system tcode s_alr_87013558 it is showing me that mine assigned value is only 70000 and remaining is 30000 but however  i  could not make any purchase req or any services activity even though i have 30000.
    What is this Assigned Values is there any report for me to see this assigned values.
    The solution which i did is in tcode cjbw i have deactivated the availability control for the project. Now the 30000 which was available it is absorbing and my problem is now solved but now this available budget is also going in minus values how can i stop this.
    How Again can i Reactivate the availability control. In my budget profile (OPS9) i have put availability control status as 1 (activate at the time of budget allocation)
    And also can u give me the ps community name.
    Regards,
    Abraham

  • Project system budget erro

    hi all,
    this my query against budget error in project system in tcode sap_alr_87013558 i am finding that my budget is for 11100000, actual is 8116942,commitment is 511355,remord plan is 9597403,and available is 1502597 .
    please note that even i am having the budget i could not make a requistion for 44000. plase help me out.
    Regards ,
    Abraham

    Hi,
    Good afternoon and greetings,
    Wishing you a very Happy New Year 2007
    Please go through the following OSS Note
    Note 167405 - Totaling up zero values not possible
    Please reward points if found useful
    Thanking you
    With kindest regards
    Ramesh Padmanabhan

  • Table for budget distribution undet project system.

    hi,
    do any one know the table for budget distribution under a project system?
    i need to get the data of budget assigned to a WBS level with the position ID, for a project. the transaction code to distribute the budget is by using transaction code - IM52.
    i posted this question in here before, but the answer i get is incorrect, as i need the table for budget under porject system. thanks

    Check these tables:
    PRPS  WBS (Work Breakdown Structure) Element Master Data
    IMPR  Investment Program Positions
    IMPS  Assignable Operative Objs for Capital Investment Positions
    IMAK  Appropriation requests - general data

  • Project system: Budget exceeded issue.

    Dear Sir or Madam,
    This issue is related to project system.  We have overall budget and annual budget.  If annual budget in a year is exhausted is it possible to make the system look at overall budget since there are sufficient funds in overall budget. 
    Thanks
    Joseph

    Hello Joseph,
    Unfortunately not. You may however change the assigned budget profile so that the overall budget is
    checked (transaction OPS9->tab "Availability Control->flag the field "overall") and rebuild availability control of the project in transaction CJBN afterwards.
    But there is definitely no "combination" of both possible.
    Greetings
    Florian

  • Project System Budget Control against Material Reservation

    hi all
    I need to control project system budget to stop/control creation of material reservation if budget is exceeded. I know that standard SAP PS budget availability control configuration could not handle material reservation.
    Will SAP Funds Management do the trick? any insight is greatly appreciated.
    Thansk,
    Tony

    Hi,
    Good afternoon and greetings,
    Wishing you a very Happy New Year 2007
    Please go through the following OSS Note
    Note 167405 - Totaling up zero values not possible
    Please reward points if found useful
    Thanking you
    With kindest regards
    Ramesh Padmanabhan

  • Technical spec for Project systems report

    Hi all,
    My requirement is to create technical spec's on this Project Systems monthly and yearly budget and actual tracking with drill down capability
    And the char and KF are:-
    Char
    Project Definition
    WBS Element
    Cost Element
    Vendor
    Purchase Order No.
    Purchase Order Item
    Requester
    Created On
    PO Description
    Final Delivery
    KF
    PO Value
    Value - Quantity Delivered
    Amount Invoiced
    To be invoiced - Value
    To be Delivered - Value
    Can anyone help me that which standard query is suitable for this requirement.

    Hi,
    Check the below business content queries:
    0PM_MC01_Q0001     Budget Comparison (Actual Costs) 
    0PM_MC01_Q0002     Budget Comparison (Planned Costs)
    0PM_C06_Q0002       Budget Proposal (Periodic)
    0PM_C06_Q0003       Budget Proposal (Objects)
    Check this might be useful:
    http://help.sap.com/saphelp_nw2004s/helpdata/en/e8/858f40f5767d17e10000000a1550b0/frameset.htm
    Hope this helps.......
    Rgs,
    Ravikanth

  • Budgeting and control system

    friends,
    we implemented fi, co, mm, sd, pp and project systems. we want to implement budgeting and control system. what is the exact flow of BCS in between these modules,
    regards,

    Hi,
    Prepare Funds Management Installation
    When implementing the Funds Management Government component, you should take care to carry out the individual steps in a particular order. You enter the required preconfigurations and functions at different points in the SAP System.
    So when implementing Funds Management, you should observe the following sequence:
    1. You use the "Enterprise Structure" to create company codes, FM areas, and controlling areas. For more information, see the Enterprise structure IMG in sections:
    a) "Define, Copy, Delete, Check Company Code"
    b) "Maintain FM Area"
    c) "Define, Copy, Delete, Check Controlling Area"
    2. You then assign an FM area to each company code and controlling area relevant to Funds Management.
    For more information, see sections:
    a) Assign company code to FM area
    b) Assign controlling area to FM area
    3. You create your G/L accounts in the General Ledger Accounting menu. For more information, read the chapter: Create G/L accounts in the G/L accounting IMG (FI-GL) under G/L account master records.
    4. Use Financial Accounting customizing to maintain the field status definition groups. These determine which fields in the account can accept input, must be maintained, or are hidden, when you are entering business transactions. For more information, read: "Maintain field status variants" in the Financial Accounting Basic Settings.
    Note that the additional account assignments "Commitment item", "Funds center" and "Fund" will only accept input if you mark the relevant fields as required or optional entries. This applies, however, only to G/L accounts whose commitment items are assigned with the 30 such as a revenue account. G/L accounts whose commitment items are assigned with a transaction other than 30 should have the error hidden.
    If you want to reference earmarked funds when posting a payment, you must define the additional account assignment "Earmarked funds" as a required or optional entry.
    5. Likewise, for Materials Management purchase requisition and purchase order postings which do not go into stock, you must flag the "Commitment item", "Funds center" and "Fund" fields as required or optional entries in order to be able to make entries in them. You can find more information in the Purchasing IMG in section "Maintain account assignment types" .
    6. If you want to integrate inventory management with Funds Management, there are different ways of controlling this, depending on the warehouse concept you chose. For more information, go to the Funds Management IMG and read sections Make Other Settings and Integration with Inventory Management.
    7. If you want to integrate Assets Accounting, you must go to the Funds Management implementation guide and flag as budget relevant the transaction types for the individual transactions (acquisitions and retirements). You can find more information in the IMG Funds Management Government in the section Flag Transaction Types as Budget Relevant.
    8. If you want to integrate Payroll Accounting with Funds Management, you must define funds centers and funds for the individual Infotypes. For more information, see the Funds Management IMG Funds Management Government in the section "Define Start Date for HR Integration (Without HR Commitments Scenario 2)".
    9. If you want to integrate Travel Management with Funds Management, the "funds center", "commitment item" and "fund" fields must be ready to accept input when you post in Travel Expense Accounting. You enter these settings in the Travel Management IMG Dialogue and settlement control -> Screen layout for trip data input -> Set up variable construction for account assignment objects.
    10. You switch to the Funds Management application menu, create your master data (commitment items, funds centers and funds) and then define your account assignment derivation.
    For more information on account assignment derivation in Funds Management, see component Funds Management (PSM-FM) under Account Assignment Derivation as well as section Define Account Assignment Derivation.
    For more information on creating master data, see the component Master data in the componentFunds Management (PSM-FM).
    11. You can then subsequently make the remaining settings via the Funds Management implementation guide. For more information, read the following chapters.
    Further notes
    The Funds Management application component can not be used simultaneously with the components Cash Budget Management and/or Project Cash Management if you use year-dependent master data in Funds Management.
    If you want to use Funds Management with Cash Budget Management and/or Project Cash Management you must note that Cash Budget Management and Project Cash Management only process 10 character commitment items.
    Regards,
    Eli

  • Project system Report Developement

    To,
    Dear Colleagues,
    I have a requriement to develop a new report for Project system. Apart from Table PRPS,BSEG,MSEG Please let me know the table and logic to pick up the fileds and displayed in the report
    The requirement is as follows
    Month   WBS Element no  Budget uploaded   Budget utilized  Balance  G/L Code   Vendor code   Amount
    These are the coloum heading, out of this  Balance= Budget uploaded-Budget utilized.
    I need table name, process logic, and some helpful hint so that the performance will be optimum.
    Thanks and Regards
    yogi

    It is possible to write such a report.
    Get a good ABAPer to fulfill your requirements.
    There is a very good article in the SCN Sheetal Deshmukh which gives all the table details. Look that up