C-project costing

HI
      PLM GURUS,
        I am new to this forum and I am working in C-project ,C-folder.
Can anybody help me for
1) How to capture the cost of C- project and what are the configuration setting required for that.
2) Prerequisite for capture the cost.
I have create the project, BP partner , roles, resoures, resoures are assing to the roles in project.
thank you
sunil jawalkar
[email protected]

Hi Sunil,
The pre-condition is that you have a ERP system, where the controlling objects (internal order or WBS) can be created using the data from the cProjects.
The detailed settings for the customizing please see the attached configuration guide of note 979978. 
If you donot have access to the note, please let me know.
Kind regards,
Zhenbo

Similar Messages

  • Opening Balances for Project Costing in R12

    Hi All,
    What are the Open transactions should be migrated as Opening Balance in Project Costing (R12) for Projects and Tasks. Here at client place cost will come from Inv, PO, AP and OTL to Project costing (R12). Can you please explain in detail (Opening Balances & Historical Cost - How to Migrate)?
    Waiting for replies...

    Hi
    Usually on implementation of Projects, people are migrating total historical costs per project.
    Depend on your current system, you may convert the historical data summarized by project, task, expenditure organization and expenditure type. There is an option to summarize costs into the latest period, just before starting the future transactions import into Projects. Otherwise, consider summarizing cost data per period, per quarter or per year.
    The summarized data may be loaded as miscellaneous expenditures into Projects.
    Be aware that for converted expenditures you should setup a Transaction Source which is costed and accounted.
    Dina

  • Settlement of Project Cost and revenue to GL

    I am trying to Settle the project Cost and Revenue to GL account. For the same I have defined settlement profile maintaining GL as optional receiver and then I have maintained Source structure for cost and revenue as to separate them at the time of defining settlement rule, defined Allocation structure where in receiver against source, I have assigned GL as by cost element receiver. After that I have maintained settlement rule for WBS element, but when I am running a settlement is done to either of the GL for cost or Revenue which ever is defined first in settlement rule. It is not creating any settlement for second line item of the settlement rule and system is not giving any error message as well.
    Where as if I am trying individually only for cost or revenue , settlement is completed with all the values but with any accounting document generated, but if I see the entries to that GL, a settlement entry is created for that transaction.
    Can anyone please help in solving this issue ASAP.
    Thanks and Regards

    Hi,
        If it is posting to the first line means....
    Follow the steps below:
    First try to create a project and post the actuals and revenues.
    Go to cost element report pick up those cost elements both for costs and revenues.
    Go to Soruce Structure in the config, define the structure with name for Ex: 'Z1' and define two assignments, one is Costs and other Revenue, by selecting the costs go to Source mention the cost element where the actual costs are posted on (Mention only that cost element no other cost elements), next select the Revenue assignment and click on Source and mention the only cost element where the revenue wsa posted (Mention only that revenue cost element no other cost elements) and save the transaction.
    Come back to project builder, select the wbs and click on settlement rule, in the menu goto-->settlement parameters and check whether the source and settlement profiles are correct or not, incase source structure is not available mention the same.
    come back to settlement Rule overview and fill the fields as mentioned below:
    1st line:   Category: GL
                  GL Account: GL Account Number
                  Source Structure: COSTS
    2nd Line: Category: GL
                  GL Account: GL Account Number (Revenue Account)
                  Source Structure: REVENUE.
    Now Run the Settlement for the specific period costs posted, the costs will be posted seperately to the two different GL Accounts.
    I think this will resolve your problem.
    Rgds
    Sudhir Reddy

  • Project cost plan Header Data table ( PS module - T.code CJR2)

    Hi,
    I am working on PS module where we have to build a integration between PS Cost plan (At WBS Element level) to SD Quotation. I have to use transaction CJR2 for this. we will add the custom field 'Indicator' on the initial screen of transaction CJR2 for this. I want to know what is the HEADER DATA table for Project Cost Plan, so i can add this custom field in that table and letter on use in CJR2.
    If someone have done any kind of modification for work on CJR2 transaction, please provide me some information on this since i am first time working on PS module. I need some information on modifying the initial screen on transaction CJR2.
    Any inputs will be appreciated.
    Thanks,

    Hi,
    you'll find Project cost plan  in tables RPSCO / COSP
    regards Andreas

  • A Standard RRB report that shows actual project cost line items .... ?

    A Standard RRB report that shows actual project cost line items but that also shows amount/qty by rejected, billed, to be billed, postponed?
    I'm looking for something that will allow project managers to reconciile with the RRB totals and be able to dril in a see a level detail not available in RRB to decide what should be billed, what should should be deferred (postponed) and what should be rejected out of hand.
    Thanks.

    Thanks Virendra Pal but the VAx5 reports are not really the answer - maybe a custom report will be required right enough.

  • Creating Master Project - Child Projects Hierarchy in Project Costing

    Hello,
    Is it possible to create a Master Project (for example, for a division) and one or many Child projects for that divisions as the projects get rolled out?
    A division is given a budget which can be assigned to the Master Project and as the divisional Projects are rolled out with a specific budgeted $s, the Master Budget would be reduced with a new version, so the total budget amount at Master Project Level remains the same.
    Just like each sub-task roll up to a Top task and top-task make up the total Project, is it possible to create hierarchical Master-child project relationship with up roll up capability.
    Thanks for sharing your thoughts. Note: The client @ 11.5.10 does not have License to use Project Contracts, and uses only the Project Costing module.
    Regards.

    Hey, those ain't "newbie" questions. The first one gets posted to the Forum Comments forum weekly. The second one, well I should have posted my normal detail, but got lazy - mea culpa, mea culpa.
    1.) This ARTICLE should step you through the processes with the e-mails. If you have any questions, let us know. There are several places, where e-mail notification can be turned ON and OFF. Some are global, and some are specific to threads.*
    2.) Ah, the ImgBurn site. The top 2/3 are all ads. Hey, it's great free software, so who can blame 'em? Scroll down to where the page has the various versions and what they addressed. There is a Download button there (well below those ads). That is what you want. Normally, I mention the scrolling way down page, but you caught me here.
    Good luck,
    Hunt
    * Going back a few months, while trying to help another user on the Forum Comments forum, I got hit with a global change in my e-mail settings. I got about 1,000/day, for every forum that I participate in - think 1,000 x PS, PrPRo, Encore, InDesign, Illustrator, Audition, PrE and all of their sub-fora! Fortunately, it only took about 3 days for Adobe to get that fixed.

  • What kind of component to use as CI if I want to add a project costing rec

    Seems like the Project_Express and Intfc_Proj_Express components do not allow, by default, for a creation of new records. When I tried to enable the creation by allowing for Adds in the component properties, and then create CIs from these components, it still will not allow me to create a record (the create in the CI tester is disabled). Any ideas on how to create a project costing transaction record via a CI?

    Allright I found an answer myself. What we call Cinch-cabel in German is a common phono-cable in English...
    so in order to extend the speakercables just use male to female phono-cable!
    my bad guys!

  • Allowed GR reversal affecting the project costs

    Hi,
    We have just performed our month-end settlement but when we are tallying our project costs and project costs clearing accounts, we have noted discrepancies. The discrepancies were from the reversals of GR for projects costs that were already settled. Is this really the standard of the system? To allow reversal of GR even if project costs were already settled to AUC?

    Hi,
    Suppose take a material A for which in month Jan you created a requirement PR-PO for the same, after that you did GR for the same in same month of Jan. Then you perform period end process for Jan., so your jan month will have actual of that material with respect to that CO object which will have actual posting in GL for that month. Now, in Feb general procees after period end process of jan, you reverse the GR with respect the present period that Feb. and and now you compare the value of settlement and present Account's value which would not match, so it will match once you settle this present updates with respet that material for the same CO object, then it will match with account's values
    Best Regards
    Vicky

  • How to find the difference between Project costs & Cost center costs?

    Hi all,
    Can you please explain me ? What is project Cost & Cost center cost and which are the tables having those fields of project cost & cost center Costs? And how to find the difference between their costs ? And please give me the functional Idea about it?
    Thanking you all in Advance...
    Regards,
    Chandru

    Hi,
    goto table COSP:
    1) object-no. beginning with 'KS' refer to cost-centre
       example: 'KSKOKA4711'
       with KS, KOKA = controlling area and 4711 = cost centre
    2) OBJNR beginning with 'PR' refer to projects / WBS-element
       example PR00001234
    Message was edited by: Andreas Mann

  • How to settle project costs to AUC

    Dear Experts,
    Please teach us how to settle project costs to AUC.
    Your response is very much appreciated.

    Refer below link
    http://help.sap.com/saphelp_erp60_sp/helpdata/en/2a/f9f56e493111d182b70000e829fbfe/frameset.htm
    Venkat

  • Bapi for Open Projects Cost in PS

    HI,
    I need a bapi or funcation module for Open Projects Cost in PS .
    thanks.

    Hi,
    Refer this :
    http://www.sapbapi.com/bapi-list/

  • Can Oracle Project costing drive the depreciation expense amount from FA

    -Does Oracle project have direct integration with Oracle FA for deriving the Depreciation amount to oracle project costing and same as sallary in oracle payroll ?
    Answer:
    1) No, there is no integration as such with Payroll
    --- Second Q If Yes ;
    If i have Machine X it depreciates 100 USD per month , so i have assigned this machine for 15 days in project 1 and the other 15 days to project 2 did the system will allocate 50 USD to project 1 and 50 USD to project 2?
    Can someone answer this - my thoughts are ...
    2)Yes, ideally it should allocate amount to multiple projects, not sure whether it is done automatically or we need to run any process ... is there any documentation on this as I was unable to find it.
    Please if the Q1 have answer yes i need document how to do this integration , and if Q2 answer is yes also i need who to or what is the condition to reach this point?
    Thanks, Ferhiz DInshaw

    per our pidgin conversation:
    first of all, you are right - there is no such integration with Payroll or FA. depreciation is calculated in FA only. in Projects we do not derive it or control it in any way.
    all we do in PA is we collect costs as they occur, generate asset lines and advise FA that an asset is subject to depreciation
    regarding multiple projects - that is not how it works right now. a project can have as many assets as needed. However these assets are bound to a single project and do not exist as organization wide transactions.
    when you interface your asset lines to FA, you can merge them to existing assets. This again is standard FA functionality. If there is a requirement to have cross project assets in PA, it is an enhancement request.
    hope it helps
    thanks
    gene

  • How to derive/generate Revenue only wth Project costing?Burdening possible?

    Hello Experts / Dina,
    I am doing a implementation to customer where only Project costing is in scope and customer wanted to derive / generate revenue for few of the revenue generated project using oracle project costing. Currently this customer is using legacy external application to enter manual journal for revenue.
    So can you please provide me workaround to achieve only revenue generation using oracle project costing?
    I have one workaround but wanted to validate from you all experts. Plz help me...
    1. Enabling budening on same expenditure item I can generate revenue using burden schedule and setup total burden cost db and cost cr account in auto accounting so that burdent Cost Crd account will be a reveue account and burden Cost dbt account will be UBR a/c. and then transfer the burden cost to GL as revenue vs UBR.
    This work around is thorotical and dont know what is implication of burden mulitpliers. If I used this workaorund then revenue (burden cost) amount is depend upon the expenditure orgnization multiplier and not on job based or employee based. How to solve this problem?
    I think there is possibility to drive the burden multiplier based on expenditure types..if taken that approch then end up in creating lot of expenditure type for each multiplier.
    So please help with workaround or someother method.
    Thanks

    Hi Dina,
    First of all many many thanks for posting your answer on this question.
    1. > I tried using total burden schedule approch to generate revenue but I think there is problem to restrict the accounting for the expenditur items which should not be burden ( need not to be generate revenue). As Total burdening approch creates burden accounting as raw cost though burden mulitplier is not specified ( system takes as value 0) :(
    2.> Then I tried a approch of using create & distribute burdening method ( burdening on separate expenditure item) - This works fine and generate burden accounting ( revenue a/c -& UBR). And provides a restriction of generating revenue on selected expenditure items based on burden schedule schedule (multiplier as 0 not specified). On Expenditre Inquiry also can reports a revenue after querying on Expenditure Type Class as "Burden Transactions". You can also reverse items and reverse costing / burdening ( reveneu ) with normal standard process.
    3.> If I wanted to use borrowed and Lent processing then I guess it will be easy. But only problem is I can't keep Project Org as Resource Org. Then there is pain in defining lot of resource organization and project organization ( I m not sure customer will agree :() . Also after referring the Project API guide I am still confuse about 2 diff extention doing same thing.
    a.> Transfer Price Determination Extension b.> Transfer Price Override Extension . Can you please explain what is difference between both of them and wat is purpose for both of them?
    Also In case i don't used the extension then I will be left only using Transfer price % ( 100% + ) to derive my revenue price? rght? Also I am not sure how can customer will have restrictions on the expenditure items which should not generate revenue? ( By defining another transfer price schedule on the selected TASKS with rule as transfer price % 0? )
    and I hope by using borrowed and lent processing I can do adjustments ( like reversing of revenue ) as standard way?
    Please guide.
    Thanks a ton !!!
    Cheers,
    :-)

  • Looking for the New Upgradations in Project Costing from 11.5.3 to 11.5.10

    Hi All,
    Iam looking at the New Features added in Project Costing as we need to give a demo for the client on the advantages of Upgrading from 11.5.3 to 11.5.10. any record on these lines would be of great help to us.Appreciate your kind suggestions in this regard.
    Thanks in Advance,
    Satyam Team

    Hi, a basic brief of the upgrade the principal steps are:
    1.- Cloning your 11.5.3 OEBS to a new server (IBM AIX 5.2), with similar characteristics to the final server in Production.
    2.- To continue with the steps described in the note of metalink 316365.1 - Oracle Applications Release 11.5.10.2 Maintenance Pack Installation Instructions.
    3.- To do a set of tests that include cycles of revenue and expenditures, this way as technical tests, and review all customizations.
    This basic step must be led to end in an environment of test, and when all the tests certified the environment , to do it in production server.
    Good Luck

  • I in need of oracle project costing,project billing and project management setup documents? can you please help me.

    I am in need of project costing and project billing and project management setup documents with screen shoot? Can anyone help me?

    I have no clue about recovering the info, but when you say you save you should always use Save As. That clears unneeded info from the file. With the file size you have, that may be an important need.

  • Retirement Cost in Project Costing

    Hi,
    Can anyone help me out the steps to capture the retirement costs in Project costing for Capital Projects.
    Regards,
    Murthy

    Well, in a capital project, you collect the CIP and expense costs for each asset you are building. The same applies to retirement costs. You use a capital project to accumulate/capture costs associated with the retirement of a group asset. Oracle manuals do specifcally use the term "retirement of group assets" when capturing retirement work in process (RWIP). You would then interface the RWIP costs to Oracle Assets (the same Mass Additions process as setting up a new asset). Why they say group asset, that I do not understand? Why should it matter if it is a group asset or not, when it comes to retirement? I personally have never done this though. If we have any retirement costs, we just record directly to the general ledger - don't record any Oracle project cost. But then we don't have a lot of assets and don't retire many assets as a result. Will be interesting to see if any Oracle customer out there is actually doing this. You may have to end up going to Oracle Support to get this information. The user guide is not very information about exactly how this RWIP thing works. Make any sense?
    John Dickey