Change in Reorder Point

Hi,
How system changes reorder point after running forcasting (t code mp30) for any material?
What r those parameters?
I am using mrp type as vm
Correct answer will be appreciated and rewarded
regards,
Saleel

Hi
Can u send some example by taking some values, by doing so we will come to know how does the system calculate the reorder point?
-Saleel

Similar Messages

  • Mass change of Reorder point at MRP area level

    Hi,
    I have another constraint.
    MM17 will mass change the reorder point at plant level.
    Is there any process to do mass change of reorder point for a particular MRP area level.
    Please suggest.
    Thanks in advance.

    Hi,
    When I am doing mass change of reorder point through MM17 tcode selecting MARC table,it will chnage at plant level and getting reflected in material master once I save changes.
    But I need it at storage location level.I tried to do this through MM17 tcode selecting MARD table,which will ask for storage location data(i.e storage location level).But after I save the changes,changes are not getting reflected in Display material-MRP1 view.
    Can anyone pls suggest why this is happening.
    Thanks in advance.

  • Mass change of Reorder point on MRP areas for materials

    Hi,
    Is there any process to upload mass change of reorder point on MRP areas for materials.
    Please suggest.
    Thanks in advance.

    Hi Pavithra,
    I know this is an old thread and my answer may not be relevant to you anymore but maybe it will help others. Are you trying to do a mass change for the reorder points of the MRP Areas? If so, go to tcode SA38, then run program RMMDDIBE. Then go to create/change with Data tab. Select change MRP area and there you can change the reorder points for your MRP areas.
    Regards,
    Chester

  • Change the MRP run fro Reorder Point to Forecast Based.

    Dear Experts
    My client is a battery manufacturing company, its Semi Finished product is Make-to-Stock and Finished Product is Make-to-Order. Initially the MRP was configured as reorder based and in Material master it was set as VM     (Automatic reorder point plng ). But now we need to change the MRP form reorder point to Forecast Based. The rolling forecast of the coming 3 three months is given in Planned Independent requirement (MD61) as version u201800u2019 - REQUIREMENTS PLAN.
    We have changed the MRP procedure in Material Master form VM to VV Forecast-based planning of the finished product but unable to get any result means no Automatic PR is getting generated, the we have changed all the materialsu2019 MRP procedure of that Particular BOM to have the required MRP and Automatic PR raise but still no expected result is coming.
    I would request you to provide your expert opinion to execute the Forecast Based MRP, what else should I do achieve the Linking between the Rolling Forecast and MRP instead of Reorder point. Should I have to make changes in Material Master (Only on finished product, In house developed/manufactured Product, Raw material etc), any configuration change in MPR and PR . Looking forward for your specialist advice.
    Regards
    Sony

    I have provided the demand in MD61 and make stock level of the material in such a way that it should raise the PR for MRP run but it is not generating any PR. have checked that if I put value in the forecast tab of the material master manually then it is raising the PR but I need the system to pick the value form the demand that I provided in MD61. Is there any configuration related issue to get the values form the demand and generate PR accordingly. Please guide
    Should I have to provide 'VV' at the first level of the Material at its master data or at each component of the BOM irrespective of
    the components for Semi-Finished (In house production), Raw materials (Procure from the supplier). Please suggest...

  • Manual reorder point planning

    Hi Friends, Can anybody please convey complete procedure of manual Reorder pointplanning step by step including T codes. Full points will be awarded....
    Edited by: k prasanna on Aug 1, 2008 12:57 PM

    Hi,
    1. MM02 - MRP 1 view, here enter MRP Type - VB, Lot Size - EX and then enter Quantity for Reorder Point generation
    2. MD02 - MRP Run for Material with following Parameters
    Material
    Plant
    Processing key          NETCH               Net change for total horizon
    Create purchase req.    1                   Purchase requisitions
    Delivery schedules      3                   Schedule lines
    Create MRP list         1                   MRP list
    Planning mode           3                   Delete and recreate planning data
    Scheduling              1                   Basic dates will be determined for plann
    Activate all "Process Control Parameters"
    And then Press Enter.
    System will give Planned Order/Purchase Req. if Stock of Material falls below the Reorder Point.
    Also put some stock for the material so that you can analyze it in better way.

  • BAPI_MATERIAL_MAINTAINDATA_RT reorder point & Forecast parameters

    Hi
    I use  BAPI_MATERIAL_MAINTAINDATA_RT for change reorder point and only this, but after run i see that the forecast parameters changed too.
    example code
    head-material = matnr.
    head-logst_view = 'X'.
    plant-material = matnr.
    plant-plant = werks.
    plant-reorder_pt = value.
    plantx-material = matnr.
    plantx-plant = werks.
    plantx-reorder_pt = 'X'.
    CALL function 'BAPI_MATERIAL_MAINTAINDATA_RT'
      EXPORTING
         headdata = head
      Importing
         return = return
    TABLES
       plantdata = plant
       plantdatax = plantx.
    I try to select/deselect auto_reset (reset forecast model automatically) but nothing was changed.
    Do you know what is wrong whit this??
    Best Regards
    Szymon Glapiak
    Edited by: Szymon Glapiak on Nov 4, 2008 6:20 PM

    Hi,
    You might need to check for an OSS Note for this BAPI.
    For detailed Desc of BAPI, Refer to http://abap.wikiprog.com/wiki/BAPI_MATERIAL_MAINTAINDATA_RT
    Or you can also use WE60 for IDOC ARTMAS01, the segment definition will help you to understand the BAPI parameters.

  • Automatic reorder point planning -forecast view

    Hi
    Our client want to implement automatic reorder point Planning.
    Reorder point quantity was maitained from last 3 years  but MRP type is 'ND' as they are not using MRP.
    Now i am changing MRP type to:VM  and in forecastting view: i maintained model as:D constant model period indicator:M
    His periods:60 , forecast periods:12 initialization:X tracking limit:4000 selection procedure:2 reset automatically
    Is it ok ? than can i run MP30.  and  the client wants to run for many materils(2000).
    How can be run for many materials.?
    Regards,
    srihari.M

    Dear,
    In automatic re-order oint planning , system uses past consumption data (historical data) to forecast future requirements. The system then uses these forecast values to calculate the reorder level and the safety stock level, taking the service level, which is specified in MRP2 view, and the material's replenishment lead time into account, and transfers them to the material master.
    Since the forecast is carried out at regular intervals, the reorder level and the safety stock level are continually adapted to the current consumption and delivery situation. This means that a contribution is made towards keeping stock levels low.
    From MP30 you have to executed forecast and system has generated forecast values and updated safety stock and reorder point also. Only thing to remember is you have to maintain service level in MRP 2 view of material master when you use VM- MRP type to calculate safety stock and reorder point
    Find bleow the set up following set up for automatic re-order point planning :
    1.Material Master Set up : Maintain all the relevent parameters from MRP1 to MRP4 view , Forecasting View
    1.MRP Type -VM , Lot Size -EX
    2.Procurement Type -E for FG and F for ROH
    3.Planning Startegy -10 or 40 in FG/SFG and 20 for componenet
    4.Planned Delivery Time in MRP2 VIEW
    5.Indiviaul/Collective Indicator - 1/2 based on your requirement in MRP4 View
    6.BOM Explosion -Keep it blank
    7.Service level percentage -MRP2 view
    8.Maintain Forecastin view data like model selection , Histry period , period indicator , Forecast control pramaters ,
    10.Make sure that you have min 12-8 monhts total consumption update in Forecasting view .
    Configuration : InSPRO -MRP -Check MRP Type -VM-check the details like Re-Orde point .Safety Stock both the automatic calcvualtion box are marked .
    Finally as a sample test , select any material -mm02-execute forecast in mm02-forecasting view -exectute forecast -then save .Run MRP in MD03-1,1,3,3,1.NETCH indicator and check the result in MD04
    HOPE IT WILL HELP. PLEASE REVERT BACK.
    Regards,
    Alok Tiwari

  • Automatic reorder point and safety stock caluclation- MRP type:V2

    Hi,
    I want the system to calculate reorder point and safety stock. To simulate this i created one material with
    MRP type:V2, service level as 97%, Forecast model:D,Hist. period:12,Forecast periods:12, and I entered
    the historical value for past 12 months as 100 nos in material master.
    04.2009     100
    03.2009     100
    02.2009     100
    01.2009     100
    12.2008     100
    11.2008     100
    10.2008     100
    09.2008     100
    08.2008     100
    07.2008     100
    06.2008     100                 
    05.2008      100                
    Then I went to MP30 and executed the forcase.When I checkd the material master the system has calculated the reorder point as 14 nos. But there is no value updated in safety stock field.
    Now I have two questions.
    1) How the system has arrived the reorder point value as 14 nos.
    2) Why there is no safety stock updated in material master.
    Could u please clarify this.
    Thanks and Regards
    Purushothaman

    Hi,
    This is further to my preivous mail. I have changed the consumption values and now i am getting the safety stock.
    MRP type:V2, service level as 97%, Forecast model:D,Hist. period:12,Forecast periods:12, and I entered
    the historical value for past 12 months as.
    04.2009     100
    03.2009     80
    02.2009     110
    01.2009     85
    12.2008     90
    11.2008     95
    10.2008     125
    09.2008     90
    08.2008     90
    07.2008     92
    06.2008     101
    05.2008     100
    After executing the forecase the sytem has calculated the below parameter.
    Basic value:95.759
    MAD:11.448
    Safety stock:10.252
    Reorder point:23.658.
    Can anyone explain me how these calculation arrived.
    Thanks and regards
    Purushothaman

  • MASS Article Master reorder point update thru program

    Hi Gurus,
    The BAPI to change Article Master is BAPI_MATERIAL_MAINTAINDATA_RT.  Can you please let me know if there is any BAPI which i can use for MASS update of articles instead of calling the above BAPI in a Loop. My purpose is to mass udpate reorder point for articles.
    Your help would be highly appreciated.
    -David.

    Hi David,
    You can use the transaction MASS_MARC to do this.
    Remember you can only change reorder point of the articles already on replenishment using this transaction.
    Regards,
    Naveen

  • Can use Scheduling agreements using VB/V1 reorder point MRP?

    Hi,
    Curretly client is using MRP PD with forward scheduling of 120 days and total horizon of 240 days (it is scheduling 6 months back and 6 months forward from current date) so that Vendor will always have at least 6 months of forecast requirement and client wants to use Min/Max and Reorder point as the key fields for inventory? will this is possible by changing MRP type VB or V1 or R1?
    I have a taken a test material and changed MRP to VB and it did not ran for forward dates as the stock was not below reoder point? what are the points i'm missing here?
    Appreciates everyone time and help.
    Thanks
    Siva

    VB is consumption based planning and Scheduling agreements can be used only with PD MRP

  • MRP with reorder point and safety stock and planning calender issue

    Hi,
    We are using currently MRP type PD and using Scheduling agreements and after the demand management changes when ran MRP the delivery quantities are fluctating in higher range and vendor complains about it so to avoid this we are constantly changing GR Processing days in material master? how can we avoid the drastic changes on the order quantites on scheduling agreements with out changing GR processing days.
    For example : we constantly manufacter 480 vehciles per week and some time because of holidays it will be 320 or 560 per week then the forward scheduling agreement quantites instead of 480 parts week(twice a week delivery) goes up and down and vendor needs a at least a range for his prodcution?
    I was thinking to use Reorder point but when i changed the MRP type VB then i cannot see forward scheduling agreements at MD04? does MRP type VB or V1 will allow forward scheduling also like 120 days ahead of planning?
    Appreciates everyone time and help.
    Thanks and Regards,
    Siva

    you can use MRP time fence to restrict the changes in planning data for specified horizon. For example If MRP time fence = 30 days, no changes in planning data will be allowed for coming 3o days unless you manually intervene.if any new requirements came in this period , they will be planned automatically at the end of this period only.

  • Report for Reorder point, safety stock, current stock and fixed lot size

    Hi,
    Purchasing Dept. is looking for a report which can give list of materials falling below the reorder point, so that they can go ahead and create procurement proposals for those materials.
    They also want to see the Reorder Point, Safety Stock, current stock and fixed lot size in the same report.
    Let me know if there ia any standard report availbale which displays the same or any approach to get the same.
    Thanks in Advance.
    Regards,
    Shankar Goud.

    Hi,
    There is no standard report because this is meant to be managed by the MRP run.
    The MRP lists show all materials that have a problem (such as stock below reorderpoint) but MRP generates requirements for these anyway and so all you need to do is to look for the MRP generated requirements (requisitions?) and you have your list?
    Are you using MRP?
    If so then please use the standard functions in MRP to get this.
    If not, then WHY NOT?
    Steve B

  • Calculation of Safety Stock and Reorder Point under Forecast Model T

    Hi Gurus!
    Happy Holiday!
    I would like to ask for your assistance on how the the safety stock and reorder point was calculated with the following values available. I would really appreciate it if you could give me details on the calculation.
    Below are the values:
    Basic data
    Forecast date        01.12.2009        Unit                  CTN
    Forecast model       T                 Service level         0.0
    Period indicator     M                 Paramtr profile
    Control data
    Initialization                                Tracking limit        4.000
    Model selection      A                 Procedure selection   2
    Parameter optimizatio                Optimization level    F
    Alpha factor         0,10               Beta factor           0,10
    Gamma factor       0,00              Delta factor          0,30
    Basic value           5.464-           Trend value          5.603-
    MAD                      4.758            Error total              4.722
    Safety stock         1                   Reorder pnt.          1
    No. of values
    Consumption           6                Forecast periods       1
    Initial. periods      0                Fixed periods          0
    Periods per season   12
    Historical data
    Period                Original     Corrected value
    11.2009                3.000              3.000
    10.2009                0.000              0.000
    09.2009                0.000              0.000
    08.2009                9.000              9.000
    07.2009               21.000             21.000
    06.2009               20.300             20.300
    Forecast results
    Period                Original     Corrected value
    12.2009                0.000              0.000
    Appreciate your assistance!
    Thank you and Happy Holidays!
    Ji

    Sweth, you are asking for consulting, and in my opinion it is way beyond what can or should be reasonable to achieve in such a forum. You are asking complex questions, that most probable have more than one possible answer.
    I suggest that you get on-site help from a knowledgeable and experienced consultant. These are crucial business issues, and should be dealt seriously.

  • Safety stock and Reorder point calculation in inventory planning

    Hi,
    How System does  the calculation of own safety stock, and Reorder point, maximum safety stock level at parent and child location while running inventory planning services in SAP APO SPP. does anyone about the calculation  please let me know
    Regards
    Puneet

    Hi,
    How System does  the calculation of own safety stock, and Reorder point, maximum safety stock level at parent and child location while running inventory planning services in SAP APO SPP. does anyone about the calculation  please let me know
    Regards
    Puneet

  • Reorder Point Planning

    Hi all,
    Business Process is:
    1. I am having 6 plants assigned to a single company code.
    2. I had created material "A" and assinged to all 6 plants with
    different manual reorder points, selected MRP type VB,.
    Plants:                    1000      1010    1020    1030    1040    1050
    Sloc                        A100     B100    C100       D100   E100   F100
    reorder point      100         20        30       25        18       32
    i have defined all MRP plant parameters for individual plants:
    From my central stores A100 at Plant 1000 the stock will be issued to remaining all Plants, so central stores-in-charge will run an MRP daily or weekly, as we have set different reorder points for the same material at receiving plants
    (1010, 1020,1030,1040,1050) so system first triggers the shortfall at all receiving plants and later triggers the Supplying Plant 1000.
    Requirements:
    1. If the avaialability stock at sloc B100 at Plant 1010 is 15, after running MRP the system is able to create an Auto PR for 5 quantity,. so its working fine,,,,
    but my client requirement is:
    if the avaialability stock at various plants are:
    Plants:         1000      1010   1020   1030   1040   1050
    Sloc        A100     B100   C100  D100   E100   F100
    reorder point   100         20       30      25      18        32
    avail stock          250         15       40      32      29        35
    diff stock      +150          -5     +10      +7    +11       +3
    so if we observe the above table,,, we can see the difference stock (Avail stock - reorder point) now if my stores-in-charge runs an MRP, a PR for 5 quantity at Plant 1010 is generated, however we are having excess stock at different plants.
    what we want is, if my stores-in-charge runs an MRP, no PR should be generated to any Plant except a message saying that at particualr Plants(1020,1030,1040,1050) there are excess quantity of (10,7,11,3) at their individual storage locations.
    i am not having much idea about MRP run,,,  
    1. how to map the above business process in system?
    2. if i use planned order concept, ie. during MRP run a Planned Order for a Plant will be generated later my stores in charge will convert this planned order to purchase requisition based on the stock availabile at different plants? so how to work with planned orders/
    3. Can i do total mrp run for all plants (1000,1010,1020,1030,1040) at a time?
    can any one please help me out,,, its urgent.
    regards,
    urendra

    Hi all,
    1.  In OM0E i have defined planning scope and assigned 6 plants as sequence.
    2.  In MD01, i have selected the same planning scope, create purchase requisitions - planned orders,  i have'nt selected any Plants.
    3. system has given a msg that planning run scope is only possible through parellel mode,  now i have selected the parallel processing check box.
    4. after pressing enter,, system gvs me the following msg,,,
    Please check the destinations for parallel MRP
    Message no. MD251
    Diagnosis
    No destinations have been entered in Customizing or none of the the destinations (application server) entered are active.
    In Customizing for MRP, you define the logical destinations (servers) to be used for parallel processing.
    how to overcome this,,,
    regards,
    urendra

Maybe you are looking for

  • How to use JDK 1.5 in WSAD 5.1.2 to complie the code

    Hi, We have currently deployed our code on JDK 1.4 in WSAD 5.1.2. How to run wsad 5.1.2 with jdk 1.5, this is just for compiling the code and not for deployment as we will be tieing up with RAD 7.0 on a future date after the migration of our Webspehe

  • EBP without XI

    Hi all, Is it necessary to implement an SAP XI to send/receive XML Invoice or Purchase Order in EBP 4.0? Is it necessary to configure the Integration Engine in EBP with the role of Business System as Application System. Thank you

  • Syncing devises on iCloud??

    Howdy all, I had set up icloud on my old email ID on my macbook and iphone since then I have changed my email. I then set up my new ipad with the new apple ID/icloud ID. I need to change/edit my icloud account to get rid of the old email ID as my dev

  • PLEASE HELP!!! Ical is BLANK!

    Think I did something very stupid and managed to delete some important files which really messed up my Mac, but I have managed to import most of the files from my back-up external hard drive and things are back to normal... almost! Problem is my ical

  • Can i get a new ipod touch battery for free?

    My battery life is horrible and i dont know why... i let it die and charge everynight....... i hope that makes sense to you. Is there a way i could figure out if my ipod is being defectiveor not..thanks.