Change in Reorder Point
Hi,
How system changes reorder point after running forcasting (t code mp30) for any material?
What r those parameters?
I am using mrp type as vm
Correct answer will be appreciated and rewarded
regards,
Saleel
Hi
Can u send some example by taking some values, by doing so we will come to know how does the system calculate the reorder point?
-Saleel
Similar Messages
-
Mass change of Reorder point at MRP area level
Hi,
I have another constraint.
MM17 will mass change the reorder point at plant level.
Is there any process to do mass change of reorder point for a particular MRP area level.
Please suggest.
Thanks in advance.Hi,
When I am doing mass change of reorder point through MM17 tcode selecting MARC table,it will chnage at plant level and getting reflected in material master once I save changes.
But I need it at storage location level.I tried to do this through MM17 tcode selecting MARD table,which will ask for storage location data(i.e storage location level).But after I save the changes,changes are not getting reflected in Display material-MRP1 view.
Can anyone pls suggest why this is happening.
Thanks in advance. -
Mass change of Reorder point on MRP areas for materials
Hi,
Is there any process to upload mass change of reorder point on MRP areas for materials.
Please suggest.
Thanks in advance.Hi Pavithra,
I know this is an old thread and my answer may not be relevant to you anymore but maybe it will help others. Are you trying to do a mass change for the reorder points of the MRP Areas? If so, go to tcode SA38, then run program RMMDDIBE. Then go to create/change with Data tab. Select change MRP area and there you can change the reorder points for your MRP areas.
Regards,
Chester -
Change the MRP run fro Reorder Point to Forecast Based.
Dear Experts
My client is a battery manufacturing company, its Semi Finished product is Make-to-Stock and Finished Product is Make-to-Order. Initially the MRP was configured as reorder based and in Material master it was set as VM (Automatic reorder point plng ). But now we need to change the MRP form reorder point to Forecast Based. The rolling forecast of the coming 3 three months is given in Planned Independent requirement (MD61) as version u201800u2019 - REQUIREMENTS PLAN.
We have changed the MRP procedure in Material Master form VM to VV Forecast-based planning of the finished product but unable to get any result means no Automatic PR is getting generated, the we have changed all the materialsu2019 MRP procedure of that Particular BOM to have the required MRP and Automatic PR raise but still no expected result is coming.
I would request you to provide your expert opinion to execute the Forecast Based MRP, what else should I do achieve the Linking between the Rolling Forecast and MRP instead of Reorder point. Should I have to make changes in Material Master (Only on finished product, In house developed/manufactured Product, Raw material etc), any configuration change in MPR and PR . Looking forward for your specialist advice.
Regards
SonyI have provided the demand in MD61 and make stock level of the material in such a way that it should raise the PR for MRP run but it is not generating any PR. have checked that if I put value in the forecast tab of the material master manually then it is raising the PR but I need the system to pick the value form the demand that I provided in MD61. Is there any configuration related issue to get the values form the demand and generate PR accordingly. Please guide
Should I have to provide 'VV' at the first level of the Material at its master data or at each component of the BOM irrespective of
the components for Semi-Finished (In house production), Raw materials (Procure from the supplier). Please suggest... -
Hi Friends, Can anybody please convey complete procedure of manual Reorder pointplanning step by step including T codes. Full points will be awarded....
Edited by: k prasanna on Aug 1, 2008 12:57 PMHi,
1. MM02 - MRP 1 view, here enter MRP Type - VB, Lot Size - EX and then enter Quantity for Reorder Point generation
2. MD02 - MRP Run for Material with following Parameters
Material
Plant
Processing key NETCH Net change for total horizon
Create purchase req. 1 Purchase requisitions
Delivery schedules 3 Schedule lines
Create MRP list 1 MRP list
Planning mode 3 Delete and recreate planning data
Scheduling 1 Basic dates will be determined for plann
Activate all "Process Control Parameters"
And then Press Enter.
System will give Planned Order/Purchase Req. if Stock of Material falls below the Reorder Point.
Also put some stock for the material so that you can analyze it in better way. -
BAPI_MATERIAL_MAINTAINDATA_RT reorder point & Forecast parameters
Hi
I use BAPI_MATERIAL_MAINTAINDATA_RT for change reorder point and only this, but after run i see that the forecast parameters changed too.
example code
head-material = matnr.
head-logst_view = 'X'.
plant-material = matnr.
plant-plant = werks.
plant-reorder_pt = value.
plantx-material = matnr.
plantx-plant = werks.
plantx-reorder_pt = 'X'.
CALL function 'BAPI_MATERIAL_MAINTAINDATA_RT'
EXPORTING
headdata = head
Importing
return = return
TABLES
plantdata = plant
plantdatax = plantx.
I try to select/deselect auto_reset (reset forecast model automatically) but nothing was changed.
Do you know what is wrong whit this??
Best Regards
Szymon Glapiak
Edited by: Szymon Glapiak on Nov 4, 2008 6:20 PMHi,
You might need to check for an OSS Note for this BAPI.
For detailed Desc of BAPI, Refer to http://abap.wikiprog.com/wiki/BAPI_MATERIAL_MAINTAINDATA_RT
Or you can also use WE60 for IDOC ARTMAS01, the segment definition will help you to understand the BAPI parameters. -
Automatic reorder point planning -forecast view
Hi
Our client want to implement automatic reorder point Planning.
Reorder point quantity was maitained from last 3 years but MRP type is 'ND' as they are not using MRP.
Now i am changing MRP type to:VM and in forecastting view: i maintained model as:D constant model period indicator:M
His periods:60 , forecast periods:12 initialization:X tracking limit:4000 selection procedure:2 reset automatically
Is it ok ? than can i run MP30. and the client wants to run for many materils(2000).
How can be run for many materials.?
Regards,
srihari.MDear,
In automatic re-order oint planning , system uses past consumption data (historical data) to forecast future requirements. The system then uses these forecast values to calculate the reorder level and the safety stock level, taking the service level, which is specified in MRP2 view, and the material's replenishment lead time into account, and transfers them to the material master.
Since the forecast is carried out at regular intervals, the reorder level and the safety stock level are continually adapted to the current consumption and delivery situation. This means that a contribution is made towards keeping stock levels low.
From MP30 you have to executed forecast and system has generated forecast values and updated safety stock and reorder point also. Only thing to remember is you have to maintain service level in MRP 2 view of material master when you use VM- MRP type to calculate safety stock and reorder point
Find bleow the set up following set up for automatic re-order point planning :
1.Material Master Set up : Maintain all the relevent parameters from MRP1 to MRP4 view , Forecasting View
1.MRP Type -VM , Lot Size -EX
2.Procurement Type -E for FG and F for ROH
3.Planning Startegy -10 or 40 in FG/SFG and 20 for componenet
4.Planned Delivery Time in MRP2 VIEW
5.Indiviaul/Collective Indicator - 1/2 based on your requirement in MRP4 View
6.BOM Explosion -Keep it blank
7.Service level percentage -MRP2 view
8.Maintain Forecastin view data like model selection , Histry period , period indicator , Forecast control pramaters ,
10.Make sure that you have min 12-8 monhts total consumption update in Forecasting view .
Configuration : InSPRO -MRP -Check MRP Type -VM-check the details like Re-Orde point .Safety Stock both the automatic calcvualtion box are marked .
Finally as a sample test , select any material -mm02-execute forecast in mm02-forecasting view -exectute forecast -then save .Run MRP in MD03-1,1,3,3,1.NETCH indicator and check the result in MD04
HOPE IT WILL HELP. PLEASE REVERT BACK.
Regards,
Alok Tiwari -
Automatic reorder point and safety stock caluclation- MRP type:V2
Hi,
I want the system to calculate reorder point and safety stock. To simulate this i created one material with
MRP type:V2, service level as 97%, Forecast model:D,Hist. period:12,Forecast periods:12, and I entered
the historical value for past 12 months as 100 nos in material master.
04.2009 100
03.2009 100
02.2009 100
01.2009 100
12.2008 100
11.2008 100
10.2008 100
09.2008 100
08.2008 100
07.2008 100
06.2008 100
05.2008 100
Then I went to MP30 and executed the forcase.When I checkd the material master the system has calculated the reorder point as 14 nos. But there is no value updated in safety stock field.
Now I have two questions.
1) How the system has arrived the reorder point value as 14 nos.
2) Why there is no safety stock updated in material master.
Could u please clarify this.
Thanks and Regards
PurushothamanHi,
This is further to my preivous mail. I have changed the consumption values and now i am getting the safety stock.
MRP type:V2, service level as 97%, Forecast model:D,Hist. period:12,Forecast periods:12, and I entered
the historical value for past 12 months as.
04.2009 100
03.2009 80
02.2009 110
01.2009 85
12.2008 90
11.2008 95
10.2008 125
09.2008 90
08.2008 90
07.2008 92
06.2008 101
05.2008 100
After executing the forecase the sytem has calculated the below parameter.
Basic value:95.759
MAD:11.448
Safety stock:10.252
Reorder point:23.658.
Can anyone explain me how these calculation arrived.
Thanks and regards
Purushothaman -
MASS Article Master reorder point update thru program
Hi Gurus,
The BAPI to change Article Master is BAPI_MATERIAL_MAINTAINDATA_RT. Can you please let me know if there is any BAPI which i can use for MASS update of articles instead of calling the above BAPI in a Loop. My purpose is to mass udpate reorder point for articles.
Your help would be highly appreciated.
-David.Hi David,
You can use the transaction MASS_MARC to do this.
Remember you can only change reorder point of the articles already on replenishment using this transaction.
Regards,
Naveen -
Can use Scheduling agreements using VB/V1 reorder point MRP?
Hi,
Curretly client is using MRP PD with forward scheduling of 120 days and total horizon of 240 days (it is scheduling 6 months back and 6 months forward from current date) so that Vendor will always have at least 6 months of forecast requirement and client wants to use Min/Max and Reorder point as the key fields for inventory? will this is possible by changing MRP type VB or V1 or R1?
I have a taken a test material and changed MRP to VB and it did not ran for forward dates as the stock was not below reoder point? what are the points i'm missing here?
Appreciates everyone time and help.
Thanks
SivaVB is consumption based planning and Scheduling agreements can be used only with PD MRP
-
MRP with reorder point and safety stock and planning calender issue
Hi,
We are using currently MRP type PD and using Scheduling agreements and after the demand management changes when ran MRP the delivery quantities are fluctating in higher range and vendor complains about it so to avoid this we are constantly changing GR Processing days in material master? how can we avoid the drastic changes on the order quantites on scheduling agreements with out changing GR processing days.
For example : we constantly manufacter 480 vehciles per week and some time because of holidays it will be 320 or 560 per week then the forward scheduling agreement quantites instead of 480 parts week(twice a week delivery) goes up and down and vendor needs a at least a range for his prodcution?
I was thinking to use Reorder point but when i changed the MRP type VB then i cannot see forward scheduling agreements at MD04? does MRP type VB or V1 will allow forward scheduling also like 120 days ahead of planning?
Appreciates everyone time and help.
Thanks and Regards,
Sivayou can use MRP time fence to restrict the changes in planning data for specified horizon. For example If MRP time fence = 30 days, no changes in planning data will be allowed for coming 3o days unless you manually intervene.if any new requirements came in this period , they will be planned automatically at the end of this period only.
-
Report for Reorder point, safety stock, current stock and fixed lot size
Hi,
Purchasing Dept. is looking for a report which can give list of materials falling below the reorder point, so that they can go ahead and create procurement proposals for those materials.
They also want to see the Reorder Point, Safety Stock, current stock and fixed lot size in the same report.
Let me know if there ia any standard report availbale which displays the same or any approach to get the same.
Thanks in Advance.
Regards,
Shankar Goud.Hi,
There is no standard report because this is meant to be managed by the MRP run.
The MRP lists show all materials that have a problem (such as stock below reorderpoint) but MRP generates requirements for these anyway and so all you need to do is to look for the MRP generated requirements (requisitions?) and you have your list?
Are you using MRP?
If so then please use the standard functions in MRP to get this.
If not, then WHY NOT?
Steve B -
Calculation of Safety Stock and Reorder Point under Forecast Model T
Hi Gurus!
Happy Holiday!
I would like to ask for your assistance on how the the safety stock and reorder point was calculated with the following values available. I would really appreciate it if you could give me details on the calculation.
Below are the values:
Basic data
Forecast date 01.12.2009 Unit CTN
Forecast model T Service level 0.0
Period indicator M Paramtr profile
Control data
Initialization Tracking limit 4.000
Model selection A Procedure selection 2
Parameter optimizatio Optimization level F
Alpha factor 0,10 Beta factor 0,10
Gamma factor 0,00 Delta factor 0,30
Basic value 5.464- Trend value 5.603-
MAD 4.758 Error total 4.722
Safety stock 1 Reorder pnt. 1
No. of values
Consumption 6 Forecast periods 1
Initial. periods 0 Fixed periods 0
Periods per season 12
Historical data
Period Original Corrected value
11.2009 3.000 3.000
10.2009 0.000 0.000
09.2009 0.000 0.000
08.2009 9.000 9.000
07.2009 21.000 21.000
06.2009 20.300 20.300
Forecast results
Period Original Corrected value
12.2009 0.000 0.000
Appreciate your assistance!
Thank you and Happy Holidays!
JiSweth, you are asking for consulting, and in my opinion it is way beyond what can or should be reasonable to achieve in such a forum. You are asking complex questions, that most probable have more than one possible answer.
I suggest that you get on-site help from a knowledgeable and experienced consultant. These are crucial business issues, and should be dealt seriously. -
Safety stock and Reorder point calculation in inventory planning
Hi,
How System does the calculation of own safety stock, and Reorder point, maximum safety stock level at parent and child location while running inventory planning services in SAP APO SPP. does anyone about the calculation please let me know
Regards
PuneetHi,
How System does the calculation of own safety stock, and Reorder point, maximum safety stock level at parent and child location while running inventory planning services in SAP APO SPP. does anyone about the calculation please let me know
Regards
Puneet -
Hi all,
Business Process is:
1. I am having 6 plants assigned to a single company code.
2. I had created material "A" and assinged to all 6 plants with
different manual reorder points, selected MRP type VB,.
Plants: 1000 1010 1020 1030 1040 1050
Sloc A100 B100 C100 D100 E100 F100
reorder point 100 20 30 25 18 32
i have defined all MRP plant parameters for individual plants:
From my central stores A100 at Plant 1000 the stock will be issued to remaining all Plants, so central stores-in-charge will run an MRP daily or weekly, as we have set different reorder points for the same material at receiving plants
(1010, 1020,1030,1040,1050) so system first triggers the shortfall at all receiving plants and later triggers the Supplying Plant 1000.
Requirements:
1. If the avaialability stock at sloc B100 at Plant 1010 is 15, after running MRP the system is able to create an Auto PR for 5 quantity,. so its working fine,,,,
but my client requirement is:
if the avaialability stock at various plants are:
Plants: 1000 1010 1020 1030 1040 1050
Sloc A100 B100 C100 D100 E100 F100
reorder point 100 20 30 25 18 32
avail stock 250 15 40 32 29 35
diff stock +150 -5 +10 +7 +11 +3
so if we observe the above table,,, we can see the difference stock (Avail stock - reorder point) now if my stores-in-charge runs an MRP, a PR for 5 quantity at Plant 1010 is generated, however we are having excess stock at different plants.
what we want is, if my stores-in-charge runs an MRP, no PR should be generated to any Plant except a message saying that at particualr Plants(1020,1030,1040,1050) there are excess quantity of (10,7,11,3) at their individual storage locations.
i am not having much idea about MRP run,,,
1. how to map the above business process in system?
2. if i use planned order concept, ie. during MRP run a Planned Order for a Plant will be generated later my stores in charge will convert this planned order to purchase requisition based on the stock availabile at different plants? so how to work with planned orders/
3. Can i do total mrp run for all plants (1000,1010,1020,1030,1040) at a time?
can any one please help me out,,, its urgent.
regards,
urendraHi all,
1. In OM0E i have defined planning scope and assigned 6 plants as sequence.
2. In MD01, i have selected the same planning scope, create purchase requisitions - planned orders, i have'nt selected any Plants.
3. system has given a msg that planning run scope is only possible through parellel mode, now i have selected the parallel processing check box.
4. after pressing enter,, system gvs me the following msg,,,
Please check the destinations for parallel MRP
Message no. MD251
Diagnosis
No destinations have been entered in Customizing or none of the the destinations (application server) entered are active.
In Customizing for MRP, you define the logical destinations (servers) to be used for parallel processing.
how to overcome this,,,
regards,
urendra
Maybe you are looking for
-
How to use JDK 1.5 in WSAD 5.1.2 to complie the code
Hi, We have currently deployed our code on JDK 1.4 in WSAD 5.1.2. How to run wsad 5.1.2 with jdk 1.5, this is just for compiling the code and not for deployment as we will be tieing up with RAD 7.0 on a future date after the migration of our Webspehe
-
Hi all, Is it necessary to implement an SAP XI to send/receive XML Invoice or Purchase Order in EBP 4.0? Is it necessary to configure the Integration Engine in EBP with the role of Business System as Application System. Thank you
-
Syncing devises on iCloud??
Howdy all, I had set up icloud on my old email ID on my macbook and iphone since then I have changed my email. I then set up my new ipad with the new apple ID/icloud ID. I need to change/edit my icloud account to get rid of the old email ID as my dev
-
PLEASE HELP!!! Ical is BLANK!
Think I did something very stupid and managed to delete some important files which really messed up my Mac, but I have managed to import most of the files from my back-up external hard drive and things are back to normal... almost! Problem is my ical
-
Can i get a new ipod touch battery for free?
My battery life is horrible and i dont know why... i let it die and charge everynight....... i hope that makes sense to you. Is there a way i could figure out if my ipod is being defectiveor not..thanks.