Hi Frnds,
  When  i go to CO11N -- Goods movement screen there i have a Lay out option where i can Hide the quantity , i want to do it user wise , now in the total system the Quantity coloumn has got hided , i have to do it user wise, is there option for that ?
Regard
Rajesh

Hi,
In user maintaince SU01
Parameter tab
enter parameter ID CORUPROF
Now enter the profile of co11n infront of it.
Nowthe user will see the layout which you have maintained in the profile
Regards,
Vishal

Similar Messages

  • Bapi goods movement Create (User Locking Error)

    HI all ,
             Please help me in the issue . I am doing Goods movement through BAPI(BAPI_GOODSMOVEMENT_CREATE) and i am scheduling this job in background . I am gettigng an Error of Plant data of Material locked by the user(myself) and for the next iteration its not  proceeded . Please help me how to get rid of the error .
    Thanks in advance,

    Hi Eric,
    Is the value get updated in the table?  After the Goods movement BAPI Just do wait up to 5 seconds and do the bapi commit.
    Other wise if it is possible just debug .
    With Regards,
    Sumodh.P

  • User exits when posting purchase document and goods movement (GR)

    I want to update some custom tables when posting PO and goods movement (GR) .
    Please suggest user exits for both posting.

    Check the below exists
    FOR PO
    LMEDR001            Enhancements to print program
    LMELA002            Adopt batch no. from shipping notification when posting a GR
    LMELA010            Inbound shipping notification: Transfer item data from IDOC
    LMEQR001            User exit for source determination
    LMEXF001            Conditions in Purchasing Documents Without Invoice Receipt
    LWSUS001            Customer-Specific Source Determination in Retail
    M06B0001            Role determination for purchase requisition release
    M06B0002            Changes to comm. structure for purchase requisition release
    M06B0003            Number range and document number
    M06B0004            Number range and document number
    M06B0005            Changes to comm. structure for overall release of requisn.
    M06E0004            Changes to communication structure for release purch. doc.
    M06E0005            Role determination for release of purchasing documents
    ME590001            Grouping of requsitions for PO split in ME59
    MEETA001            Define schedule line type (backlog, immed. req., preview)
    MEFLD004            Determine earliest delivery date f. check w. GR (only PO)
    MELAB001            Gen. forecast delivery schedules: Transfer schedule implem.
    MEQUERY1            Enhancement to Document Overview ME21N/ME51N
    MEVME001            WE default quantity calc. and over/ underdelivery tolerance
    MM06E001            User exits for EDI inbound and outbound purchasing documents
    MM06E003            Number range and document number
    MM06E004            Control import data screens in purchase order
    MM06E005            Customer fields in purchasing document
    MM06E007            Change document for requisitions upon conversion into PO
    MM06E008            Monitoring of contr. target value in case of release orders
    MM06E009            Relevant texts for "Texts exist" indicator
    MM06E010            Field selection for vendor address
    MMAL0001            ALE source list distribution: Outbound processing
    MMAL0002            ALE source list distribution: Inbound processing
    MMAL0003            ALE purcasing info record distribution: Outbound processing
    MMAL0004            ALE purchasing info record distribution: Inbound processing
    MMDA0001            Default delivery addresses
    MMFAB001            User exit for generation of release order
    MRFLB001            Control Items for Contract Release Order
    AMPL0001            User subscreen for additional data on AMPL
    For Goods Movement
    LMR1M001            User exits in Logistics Invoice Verification
    LMR1M002            Account grouping for GR/IR account maintenance
    LMR1M003            Number assignment in Logistics Invoice Verification
    LMR1M004            Logistics Invoice Verification: item text for follow-on docs
    LMR1M005            Logistics Inv. Verification: Release Parked Doc. for Posting
    LMR1M006            Logistics Invoice Verification: Process XML Invoice
    MRMH0001            Logistics Invoice Verification: ERS procedure
    MRMH0002            Logistics Invoice Verification: EDI inbound
    MRMH0003            Logistics Invoice Verification: Revaluation/RAP
    MRMN0001            Message output and creation: Logistics Invoice Verification

  • During conf-plant field in goods movement screen - to be didplay

    During Confirmation of a process order, in the goods movement screen, user can change the plant for a component...As a default it is copying the order header plant.
    Since it is a changeable field i.e. value can be changed , user is changing the filed value and system is issuing the material from that plant.
    Since the user has authorization in many both plant, hence I cannot restrict by authorization.
    I tried in CO86 to change field status, but I am not in the position to get the plant filed in goods movement screen.
    I am changing the screen with transaction variant, but I need to change all the training documents which  is very big job and train many people.
    Is there any other way out?

    Hi Rajesha
    Not fully sure but i think you can use the BADi ( WORKORDER_CONFIRM) to acheive this.
    BADI Details-
    Definition - WORKORDER_CONFIRM
    Interface - IF_EX_WORKORDER_CONFIRM
    Methods = AT_SAVE, BEFORE_UPDATE, IN_UPDATE, AT_CANCEL_CHECK
    Within this  a system message may be issued only in in these conditions, while saving the confirmation ERROR_WITH_MESSAGE (for AT_SAVE method) or NOT_ALLOWED (for AT_CANCEL_CHECK method) at the same time
    Just try this with your ABAP consultant  ...
    IT'll not make the plant field in display mode..but send an error if doesn't match with the plant in order header
    Best Regards
    Sumit Sharma
    Message was edited by:
            Sumit Sharma

  • New Goods Movement Type for Inventory Manager

    Hi Guys,
    I need to change a goods movement code used on Mobile App Inventory Manager 4.0 to a custom (Z) goods movement code, the fileds are the same so I thought changing the constant will work for this as we do a GoodReceipt with no reference to Purchase nor Production order (gmCode = 501) with a custom, copied from standard, Movement type gmCode = 950 (this is a well known practice on ERP). I have changed only the global constant on my copied IM application, for testing purpose and the local GR was created with gmCode = 950 instead of gmCode = 501, but when I was transmiting in order to create goods movement document on SAP, the application throws an error like: "PostReceiptsSteplet - Goods Movement Impossible with good movement type 950 - Server error". So I would like to know first:
    If is it possible to include or change the standard gmCode for custom gmCode on mobile app Inventory Manager 4.0?
    What would it be the Best Practice to do this? The steps to include a custom movement type, now I know is not only changes on global constants
    I have checked the java doc for this method "PostReceiptsSteplet", and it did not say anything about the constructor .... or how is used... what has inside... what is the condition of execution.... nothing ...
    Please Help... Mark Pe Stephen Streeter Jason Latko Omar Candelaria Manju Venkatesha
    BR,
    Mariana
    Tags edited by: Michael Appleby

    Jason Latko
    If those java source code are so troublesome to request... why should I request them if I won't change the app's base functionality??. Instead of requesting those java source code, the documentation of the java doc should improve, well the documentation in general for this app should improve ... Is only a suggestion ... I'm trying very hard not to ask for those source code, because what Mark Pe  answer me on another post: If I ask for them, a disclamer must be signed because I could change a base functionality... and that's perfectly fine. But if I need to extend a class and add a few field: why do I need to ask for the code instead of checking the documentation and apply the customization needed?
    Now I have some trouble extending a SAPOBJECT, because I don't quite understand the design of how you manage MaterialDocument / MaterialDocumentItem on the app. But I will post this question on another thread
    BR & Always Thankful
    Mariana

  • User exit in CO11N ,goods movement specific component  can split for batch

    Hi experts
    When  system going to production confirmation by CO11N . now user go to goods movement button , here i want to know user exit,here component line item is batch active or not so i can allow or validate . at that time  if component is batch active then user can split qty batch wise else validate (you can not change & exit).
    Much regards .
    Anup shukla

    Check these BADIs:
    MB_RESERVATION_BADI                     MB21/MB22: Check and Complete Dialog Data              
    MB_QUAN_CHECK_BADI                      BAdI: Item Data at Time of Quantity Check              
    MB_PHYSINV_INTERNAL                     Connection: Core Inventory and Retail AddOn            
    MB_MIGO_ITEM_BADI                       BAdI in MIGO for Changing Item Data                    
    MB_MIGO_BADI                            BAdI in MIGO for External Detail Subscreens            
    MB_DOC_BADI_INTERNAL                    BAdIs when Creating a Material Document (SAP Internal) 
    MB_DOCUMENT_UPDATE                      BADI when updating material document: MSEG and MKPF    
    MB_DOCUMENT_BADI                        BAdIs when Creating a Material Document                
    MB_CIN_MM07MFB7_QTY                     Proposal of quantity from Excise invoice in GR         
    MB_CIN_MM07MFB7                         BAdI for India Version exit in include MM07MFB7        
    MB_CIN_LMBMBU04                         posting of gr                                          
    MB_CHECK_LINE_BADI                      BAdI: Check Line Before Copying to the Blocking Tables 
    ARC_MM_MATBEL_WRITE                     Archive AddOn-Specific Data for MM_MATBEL              
    ARC_MM_MATBEL_CHECK                     Check AddOn-Specific Criteria for MM_MATBEL            
    Rob

  • How to undo changes in Delivery after goods movement happened

    Dear All,
    I need to undo the manual changes done in delivery note but the goods movement and billing document has been created.
    Advise me regarding this.
    Thanks in advance
    Raghu

    Agreed with Amit. It doesnt make a sense that after doing PGI and billing user can change delivery document. This is standard functionality of SAP to avoid missuses of Sales documents. Like Delivery document you also can't change billing document or delivered items in sales order. For this you need to go reverse your whole sale process e.g Reverse billing VF11 > Reverse PGI VL09 change or delete delivery document VL02N and change or delete sale order VA02

  • Restrict user to delete item in good movement at the time of confirmation

    Hi ,
    I have one requirement i.e. When user confirming the partial confirmation and if he selected the goods movement button i have to restrict the user not to change the material quantities in the goodsmovement screen.How i can do it .Is there any user-exits to do so, if any plz give me more info .
    Regards,
    Anand

    Hi
    Try any of the below enhancements
    CONFPP01
    With this customer enhancement you can determine your own default values
    (ones that deviate from SAP logic) for a confirmation. The confirmation
    can be changed in the customer enhancement.
    The following are copied to the interface: the operation in the order
    (AFVGD), the order header (CAUFVD) and the confirmation (AFRUD) as well
    as the confirmation parameters (TCORU). The confirmation is copied back
    from the customer enhancement to the SAP standard program.
    CONFPP02
    With this customer enhancement you can make your own checks of the
    confirmation after the SAP checks have taken place. The confirmation
    cannot be changed.
    The following are copied to the interface: the operation in the order
    (AFVGD), the complete order header (CAUFVD) and the confirmation
    (AFRUD).
    CONFPP03
      With this customer enhancement you can make your own checks once an
      operation has been selected for confirmation. The data cannot be
      changed.
      The following are copied to the interface: the operation in the order
      (AFVGD) and the complete order header (CAUFVD).
    CONFPP04
    With this customer enhancement you can carry out your own checks on the
    confirmation. The confirmation can for example be changed depending on
    the user's entries.
    The following are copied to the interface: the operation in the order
    (AFVGD), the complete order header (CAUFVD) and the confirmation
    (AFRUD). The confirmation is copied back from the customer enhancement
    to the SAP standard program.
    CONFPP05
    With this customer enhancement you can update your own data once you
    have saved the confirmation. You cannot change the confirmations.
    In this customer enhancement it is strictly FORBIDDEN to send error
    messages or other messages because otherwise there is the danger that
    data will be inconsistent. SAP takes no responsibility for this !!!
    The following are copied to the interface: a table with all the
    confirmations (AFRUD) created in this transaction and a table with the
    order headers (CAUFVD) that belong to it.
    CONFPP06
    With this enhancement you can determine which data from a manually
    entered confirmation is transferred to the automatically created
    confirmations, for example, when a confirmation is entered for a
    milestone operation.
    In addition to the order data (IS_CAUFVD) and operation data (IS_AFVGD),
    the confirmation type (I_CONF_TYPE) is also transferred. The data from
    the manually entered confirmation is imported via the structure
    IS_AFRUD_MAIN and the data determined by the system for the
    automatically created confirmation is imported via the structure
    IS_ACT_DATA.
    The data from the automatically created confirmation can then be
    modified and exported via the structure ES_ACT_DATA.
    CONFPP07
    With this enhancement you can define your own detail areas (screens)
    that can be issued for the single screen entry of time ticket
    confirmations.
    Two function modules are available to implement the flow control for the
    customer-defined screens. While the function module EXIT_SAPLCORU_S_100
    transmits the data from the confirmation, order, operation and work
    center, the entered confirmation data can be exported using the function
    module EXIT_SAPLCORU_S_101 and the structure ES_AFRUD.

  • User Exit   in  MB11  /  GOODS  MOVEMENT +_+_+

    Hi experts,
    I have a requirement where I need to know the User exit in MB11.
    My requirement is such that when a goods mvmt 261 is done using MB11,  It should call a special function (custom program) using a Userexit.
    Or a general user exit in goods movement if not (MB11 specifically), so that I can trigger this call for special function.
    Any info is greatly appreciated.
    Thanks
    Preeti
    MB1C, MB11, Goods movement.

    Check these BADIs:
    MB_RESERVATION_BADI                     MB21/MB22: Check and Complete Dialog Data              
    MB_QUAN_CHECK_BADI                      BAdI: Item Data at Time of Quantity Check              
    MB_PHYSINV_INTERNAL                     Connection: Core Inventory and Retail AddOn            
    MB_MIGO_ITEM_BADI                       BAdI in MIGO for Changing Item Data                    
    MB_MIGO_BADI                            BAdI in MIGO for External Detail Subscreens            
    MB_DOC_BADI_INTERNAL                    BAdIs when Creating a Material Document (SAP Internal) 
    MB_DOCUMENT_UPDATE                      BADI when updating material document: MSEG and MKPF    
    MB_DOCUMENT_BADI                        BAdIs when Creating a Material Document                
    MB_CIN_MM07MFB7_QTY                     Proposal of quantity from Excise invoice in GR         
    MB_CIN_MM07MFB7                         BAdI for India Version exit in include MM07MFB7        
    MB_CIN_LMBMBU04                         posting of gr                                          
    MB_CHECK_LINE_BADI                      BAdI: Check Line Before Copying to the Blocking Tables 
    ARC_MM_MATBEL_WRITE                     Archive AddOn-Specific Data for MM_MATBEL              
    ARC_MM_MATBEL_CHECK                     Check AddOn-Specific Criteria for MM_MATBEL            
    Rob

  • Change Moveing average price in MIGO Goods Reciept through user exit

    Hi,
    i need to change the moving average price in the MIGO transaction  (Goods Issue) through user exit can any one help me with user exit.

    Hi,
    Check these Enhancemnts...
    Exit Name           Description
    V02V0001            Sales area determination for stock transport order
    V02V0002            User exit for storage location determination
    V02V0003            User exit for gate + matl staging area determination (headr)
    V02V0004            User Exit for Staging Area Determination (Item)
    V50PSTAT            Delivery: Item Status Calculation
    V50Q0001            Delivery Monitor: User Exits for Filling Display Fields
    V50R0001            Collective processing for delivery creation
    V50R0002            Collective processing for delivery creation
    V50R0004            Calculation of Stock for POs for Shipping Due Date List
    V50S0001            User Exits for Delivery Processing
    V53C0001            Rough workload calculation in time per item
    V53C0002            W&S: RWE enhancement - shipping material type/time slot
    V53W0001            User exits for creating picking waves
    VMDE0001            Shipping Interface: Error Handling - Inbound IDoc
    VMDE0002            Shipping Interface: Message PICKSD (Picking, Outbound)
    VMDE0003            Shipping Interface: Message SDPICK (Picking, Inbound)
    VMDE0004            Shipping Interface: Message SDPACK (Packing, Inbound)
    Badi Name            Description
    DELIVERY_ADDR_SAP    Determine Time-Dependent Delivery Address in Delivery
    DELIVERY_PUBLISH     Returns BAdI Implementation: Automatic GR Posting T 2
    DELIVERY_PUBLISH     Updating of Delivery in Purchase Order
    DELIVERY_PUBLISH     AIP: Delivery Confirmation for Sales Order
    Regards
    Raghu

  • Goods Movement user-exit - message capable

    I am searching for a user-exit during goods movement. I have found several enhancements (MCBF*) but none of them allow me to set an error message if a specific condition exists.  None of the enhancements contain a message-id statement. 
    I want to test the goods movement before it is posted for a condition and if true, display an error message and thereby prevent the goods movement from happening. 
    Thanks for the help.
    Maggie

    <i>None of the enhancements contain a message-id statement.</i>
    Remember, you need not have the message class defined using the message-id statement.  You can write the message as.....
    MESSAGE E001<b>(00)</b> with 'The message Text'.
    Here you are specifying the message class 00 in parenthesis.
    Regards,
    Rich Heilman

  • The total goods movement status not changed after goods receipt using MIGO

    Dear gurus:
    when i use T-code MIGO doing goods-receipt against Inbound delivery, the total goods movement status don't changed. i tryed VL32N to do goods receipt, and the status changed.
    how can i do to make the status change when i receive goods in MIGO against inbound delivery?
    best wishes,
    David

    Hi,
    If your MM is integrated with WM (SU mgt or HUM) you have to post the GR with Inbound delivery.
    Amit

  • LAST GOODS MOVEMENT DATE wise report

    Hi MM Experts
    Is there any report through which we can find LAST GOODS MOVEMENT DATE ( goods receipt , issue date ).
    i have tried MC.2 but in this report material , plant and sloc description is coming , i want code so that we can understand easily.
    regards
    anubhav

    Hi,
    To get the plant, material code with description in MC.2 transaction.
    Please following below steps:
    on output screen >>>
    settings >> Characteriastics display >>> select key and description or only Key.
    Regards,
    Shailesh Mackwan

  • User wise change of sensitive fields

    Hi guys,
    We are having trouble with fields like payment term, payment block and baseline date. All user can change them as and when they want. Is there any possiblity of restricting of the change of these fields to users. I mean here,some users should be able to do the change and other can not.
    Br
    Samiti Chakri

    Dear Samiti Chakri ,
    You could create a profile by transaction PFCG to link to Your user, where You give them only the option to see the fields but not to change them. Please run SU24 and insert the transaction (fd02/fk02) to check the authorization objects linked to them.
    Or:
    you can go to SPRO > Financial Accounting(New) > Accounts Receivable and
    Accounts payable > Customer Accounts > Master Data > Preparations for
    creating Customer Master Data > Define sensitive fields for Dual Control
    You can see all the fields that are available for Sensitive Fields here in order to build up a dual cotrol.
    I hope this can help.
    Mauri

  • Lock a certain day from posting goods movements

    Hi, is it possible to lock a certain calendar day so that no goods movement can be posted on that day? Thanks in advance for any input.
    yu

    In that case you want to use auth group that I mentioned earlier. From Jan 20 through Jan 31 when you want to lock MM transactions but leave it open for COGS or other adjustment /correction postings, then you should define which group of people should have that access and assign auth group to inventory accounts as well as these users. You should activate auth group control only for such period. But remember such group of people will be able to do any inventory transaction. If you know they will be posting only to COGS then bring COGS account as well under same auth group and let them not post to any other GL accounts. You can still automate these changes using the program and batch job. Obviously OB52 will look complicated.
    There is no way to establish date wise control if you are looking for it. You will have to work around one of these ways.
    Regards
    Subodh