Changes in logical components of a project

Hi
I have the requirement to add another system to my maintenane project.  Having read Dolores Correa's Usual Questions and known errors blog I see that this is not s straight forward scenario.
The blog states that I should "Close the current project cycle", does this mean that I should "Complete the maintenance cycle"? in transaction /TMWFLOW/MAINTINST ??
If that is the case does that not mean that all of my transports will be imported into production?
I cannot find further information on consequenses of this requirement, so all help you can offer is welcome.
regards
marina

Hi,
When you close a maintenance project, TRs will not be automatically imported into PRD. You have to execute the task in your Tasklist to import into PRD.
While closing the the transport requests that are not yet imported into the production systems are also taken into account in the new task list for project imports (in technical terms, this means that the import project includes not only the current CTS project, but also the CTS project of the completed cycle).
If you create a new cycle, the system automatically assigns these processes and objects to the new cycle.
Refer Note: 1071412
Hope this helps.
Feel free to revert back.
-=-Ragu

Similar Messages

  • Meaning of defining multiple logical components in mainenance project?

    Dear friends of SolMan,
    I have a question regarding a possible functionality of ChaRM .
    In the maintenance project, defined in SOLAR_PROJECT_ADMIN, there is on the tab "system landscape" another tab "systems" where you define the logical component for which the maintenance belongs to.
    In the list for the logical components you have the possibility to define more than one logical component.
    Now my question is:
    - Why and for what am I able to define more than one logical components?
    Thanks for your help in advance.
    Best regards,
    Alex

    Alexander
    Yes it is very important part of CHARMS
    Because logical component tells you which client is dev or QA or Prd for any system
    When you activate CHARMS in your project where you have added the logical comp then system check for this logical comp ...the needed things ...like rfc or transport route etc
    You can have multiple logical comp for various systems in one project i& it s enough to support them with one maintenance cycle working ...........to support CHARMS functionality
    Hope it clarifies
    Regards
    Prakhar

  • Logical Components for a project

    Hi,
    We have ECC6.0 on which we have applied the Enhancement Package 2.0.
    While trying to create a project in solution manager for the Business Sceario we selected it is requiring Logical component for SAP ERP Enhance Package.
    While trying to create the SAP ERP Enhance Package logical component we are not able to find any systems to attach under that even though we have maintained installed product versions as both  SAP ECC / SAP ERP ENHANCE PACKAGE 2005.2. in the system defintion of our development system.
    We tried to put SAP ERP ENHANCE PACKAGE 2005.2 as leading product version even then we are not able to pickup that system under the SAP Enhance package Logical component.
    Please suggest.
    Thanks & Regards
    Mrutyunjay

    Hi,
    In SMSY under landscape components select your system and go to Header Data Tab. Click on Installed Product version. Then select the check box Free Product/Select product Version.
    Then you can find your product there. This will solve your problem.
    Feel free to revert back.
    --Ragu

  • ChaRM:Logical Components for Projects

    Hi Experts,
    I have done ChaRM config and i am about to create logical components for the project Project.
    I have below two questions please help.
    While creating a logical component when i have multiple clients in DEV, QAS and PRD how to proceed and second question is about RFC Users in satellite systems.
    1) My ECC landscape have DEV ->100, 200, 300, 400, QAS-> 100, 200, 300, PRD-> 100, 200 with multiple clients.
    So while creating logical component do i need mention all clients in the logical component or its enough if i mention DEV->100, QAS->100, PRD->100 ?
    If i mention only one client in logical component how transports will move to other clients in DEV, QAS and PRD. Please help.
    2) Second question is do we need to create READ, TMW, back rfc users in all clients for DEV, QAS and PRD for above ECC landscape ?
    Please help for above question.
    Regards
    Latha

    Hi,
    So while creating logical component do i need mention all clients in the logical component or its enough if i mention DEV->100, QAS->100, PRD->100 ?
    Yes, you can have this TMS track defined and use SCC1  for performing imports within the system (like QAS 100 to QAS 200 ). Or use the Tranport Target Group option so that your TR is visible in import queue of all system. More info Extended Transport Control (SAP Library - BC Change and Transport Organizer)
    2) Second question is do we need to create READ, TMW, back rfc users in all clients for DEV, QAS and PRD for above ECC landscape ?
    Yes, you need RFCs b/w your working client (100 ) and 000 client of domain controller. Not for all clients.
    Regards,
    Vivek

  • Problems with Logical Components

    Hi All,
    I am having problems with Logical Components with our project. We are implemeents SAP HCM and we have defined a logical component Z_ERP for the ECC server. now when you look at the transaction from SOLAR02 it seems they also have a logical Component SAP Learning Solution that is assigned to them. what could be the cause of this???

    Hi Trevor,
    If you brought them in from the Business Process Repository, the logical component is going to be the default one. If you want to use your own, you need to replace the default one with yours.
    You can do this in SOLAR_PROJECT_ADMIN by going to the System Landscape tab > Systems tab > highlight the SAP Learning Solution logical component row > press F4 > replace it with Z_ERP.
    If for some reason SAP Learning Solution isn't listed as a logical component you may have to add it, you can also just go to SOLAR02 > Edit > Replace Log. Comp > Enter SAP Learning Solution in the top box and Z_ERP in the bottom one > click Save.
    regards,
    Jason

  • Logical components problem when checking project

    Hello,
    I have searched in the forum for a solution, but the people who had the same kind of problem managed to solve it with means that do not work for me.
    Here is the situation :
    - We have a three tier landscape, DEV-QAS-PRD, in transport domain DOMAIN_A, with domain controller DCA
    - We have our Solution Manager system, DCB, which is part of (and domain controller of) transport domain DOMAIN_B
    - The two transport domains are linked, as specified in SolMan prerequisites for managing systems from other transport domains. This has been tested, and transports can be forwarded and imported freely from one domain to another.
    - I have created the systems, RFC destinations, and logical component for the three tier landscape in SolMan system DCB. The RFCs are all OK.
    - I have created the domain controller DCA system in SolMan DCB, with RFC destination to client 0, as defined in the prerequisite for Change Request Management.
    - Finally, I have created a project in SolMan system DCB, with this logical component.
    When I try to do a Check on this project, in the Change Request management tab, I have green lights everywhere, except for the following :
    - In "Check logical components" : No consolidation system found for DEV-040 (our development system)
    - In "Check consistency of project" : Message from function module /TMWFLOW/CHECK_PRJ_CONS: No export system for PRD-020 (our production system)
    We have checked the TMS settings and transport routes, and everything looks OK.
    Any ideas on what to check/try would be welcome.
    Thanks,
    Thomas

    Hi,
    Check the status of the DC's in the track created in CBS.
    at following location.
    http://url:port/webdynpro/dispatcher/sap.com/tc.CBS.WebUI/WebUI
    There should be no Broken DC's in the track.
    If every thing is fine here and you still have problems then check by repairing the class path of the component.
    Hope this helps you.
    Regards,
    Nagaraju Donikena
    Regards,
    Nagaraju Donikena

  • 2 Logical Components in 1 Maintenance Project

    Dear all,
    We have two system system landscapes / logical components (Dev -> Tst -> Prd) in parallel; Finance and Logistics.
    Is it possible, to have them both in one Maintenance project?
    And more important, to have them both available in the project logistics task list (/TMWFLOW/PROJ).
    How do I arrange the parallel transporting eg. for Dev_FI -> Tst_FI and Dev_LO -> Tst_LO?
    Thanks for the answers,
    jan

    Hi Jan,
    Yes it is possible to have both parallel landscapes in same maintenance tasklist. Just create 2 separate logical components with the appropriate system role assignment in SMSY transaction.
    Now assign them in the Systems Landscapes Tab in the Project. When you create the maintenance cycle for this project it will automatically generate a tasklist with these 2 landscapes.
    It will show total six systems in your tasklist. DEV1>QAS1>PRD1 and DEV2>QAS2>PRD2. Now when you assign this IBase Component in your change request, it gets linked to this maintenance cycle.
    When in Normal Correction, you will get pop-up for actions like 'Logon to System' and "create transport Request' asking which Development system you want to logon to or create transport request in.
    Hope this helps...
    Thanks,
    Kriti Bhalla

  • 2 Logical Components for 1 Business Process Step

    Hello All,
    I'm looking for a way to assign in SolMan --> transaction Solar01 - Tab Structure - Business Process Step, 2 logical components for 1 business step. When creating the business step I have to assign 1 specific logical component to this step. Once I have done this I can only select  the chosen logical component ffor SAP Transactions, configuration object etc.. As my business step is running on 2 different systems I need to find a way to link transactions etc. in the step to the different systems. Is there any way to change this for the Level 3 elements, like it is for level 2 (business processes) where I can choose in the different tabs between all the logical components?
    Thanks in advance
    Ramó

    I've seen people use some absolute craziness to get more than three levels. The most extreme being using multiple projects at the highest level (i.e. a project for PTP Accounts Payable). Don't go there.
    I personally like to have 1 transaction per process step. Don't use the transaction tab as another process level, use it to better describe the process step (like all the other tabs are uses). It results in a better understanding of the system as you go forward. To do that I make teams break up things they think are one step (this can take some arm twisting, so hit the gym and maybe take a few judo classes).
    This allows you to use SolMan in more powerful ways. For instance, if you attach development objects to a step with 5 transactions, you cannot tell which transaction is modified by the development object. However, one transaction per node provides you this link. There are other examples, but basically the "where used" button becomes very useful when you have 1 transaction per node.
    Maybe you could provide a specific example of your process and we can think of a better way to collapse it.
    Such as:
    - PTP Non-Merchandise Purchasing
    -- Expense Purchasing
    --- Create Purchase Requisition
    --- Create Purchase Order (Assign Vendor & Price)
    --- Send to Vendor
    --- Post Goods Receipt
    --- Perform LIV
    --- Process Payment
    Some companies have 6 level processes already defined in models and putting it into SolMan can be a pain for sure. Your naming convention is usually the best route.
    regards,
    Jason
    The system role and template work around doesn't apply to your situation.

  • [svn:fx-trunk] 11810: Fixing up some logic around pauseWhenHidden ( there were some bugs) and also changing some logic around enabling/ disabling.

    Revision: 11810
    Revision: 11810
    Author:   [email protected]
    Date:     2009-11-13 17:07:56 -0800 (Fri, 13 Nov 2009)
    Log Message:
    Fixing up some logic around pauseWhenHidden (there were some bugs) and also changing some logic around enabling/disabling.  Also fixing a small documentation bug on VideoPlayer2.scaleMode.
    When a video component (or one of its ancestors) becomes disabled, the video pauses.  When it becomes re-enabled, we do not play the video.  This behavior is baked in to VideoDisplay and does not depend on the pauseWhenHidden flag.
    QE notes: -
    Doc notes: -
    Bugs: SDK-24182, SDK-24181, SDK-24193
    Reviewer: Kevin
    Tests run: checkintests
    Is noteworthy for integration: No
    Ticket Links:
        http://bugs.adobe.com/jira/browse/SDK-24182
        http://bugs.adobe.com/jira/browse/SDK-24181
        http://bugs.adobe.com/jira/browse/SDK-24193
    Modified Paths:
        flex/sdk/trunk/frameworks/projects/spark/src/spark/components/VideoDisplay.as
        flex/sdk/trunk/frameworks/projects/spark/src/spark/components/VideoPlayer2.as

    Thanks Erik,
    If nothing else, this huge list of updates and fixes, shows clearly that the Logic Dev team is working hard on fixing and improving LPX to a major degree.... and from the list of fixes done.. show they do read the bug reports submitted!
    As an aside....
    I recall how all the 'naysayers' prior to LPX (and in some cases, since...)  were proclaiming how Logic was dead, the team was being disbanded, we won't see any further development, the Dev team doesn't listen or care... and so on....... I wonder where those people are now?

  • SOLAR_MIGRATION and logical components: what's the behaviour

    Hi All,
    We have a Solution Manager Dev box and want to transport the contents of our project to Prod using Solar_Migration.
    In dev we had created logical components. However, Basis team has already created same logical components in Prod it now seems with proper systems linked to these.
    Will SOLAR_MIGRATION transport overwrite the logical components in PROD?
    Will it just transport the logical components, or alse the linked systems defined in SMSY?
    If SOLAR_MIGRATION also transports the systems defined in SMSY, will it overwrite similarly named systems in PROD?
    If we have differently named logical components in DEV, will they simply get added to the list of logical components in PROD.
    Thanks gurus,
    Jurjen

    Will SOLAR_MIGRATION transport overwrite the logical components in PROD?
    ...Change the names just to be sure.
    Will it just transport the logical components, or also the linked systems defined in SMSY?
    ...Yes also the linked systems
    If SOLAR_MIGRATION also transports the systems defined in SMSY, will it overwrite similarly named systems in PROD?
    ...NO, they get appended to the list
    If we have differently named logical components in DEV, will they simply get added to the list of logical components in PROD.
    ...Yes, they get appended.
    Jurjen

  • Logical Components and Solution Landscapes - 2 PRD ECC Servers

    When I assign my PRD ECC5 server to Logical Components > SAP ECC > SAP ECC Server > SAP ECC, I select the Product Version as SAP ECC5.
    From the drop down list on Production System, I can see both my ECC 5 PRD's clients listed. I select one client, all OK. Problem is I have 2 Production ECC5's, both to be used in seperate solutions. So I can only select ONE of these,
    How can I use 2 ECC5 Production systems in Logical Components, or does it need to be configured differently?
    Thanks,
    Derek

    hi Derek,
    you can create more than one logical component under ECC. Just name it something like ZECC2 and the define the systems for this logical component. You can then use the logical component in your project system landscapes.
    To add a new one just right click on the text SAP ECC Server and select Create Logical Component.
    regards,
    Jason

  • Understanding and using Logical Components for Managed System configuration

    Experts.....
    I am embarking on a fresh installation of SolMan 7 EhP1 SPS25 and after a few bugs along the way, I am finally nearing the end of including the first Managed System.  Somewhat related to {forum:id=10293771] I am hoping I can get some advice, but specifically with regards to Logical Components.
    General question - I have a slide from SAP that shows a picture from Product->System->Instance->Logical System (client)->Logical Component.  I am confused because it shows that Client 100 of a given ABAP system could be assigned to Logical Component A, whereas Client 200 of the same system could be assigned to Logical Component B.  This seems wrong to me?
    I am at the last step of the managed systems configuration wizard : "create logical components" and only want to ensure that I set things up to hopefully ensure that later usages (Maintenance Optimizer, etc) will handle things correctly!!!
    - Our SAP landscape is not very complex
    1. only ERP and EP (Dev/Test/Prod). 
    2. We are utilizing HR Self Service (XSS).
    3. The ERP ABAP systems are on Netweaver 7.01. 
    4. EhP4 has been installed, however we only activated the HCM business functions.  Therefore SAP_HR is on 604 whereas SAP_APPL is on 600.  I think this might be driving some of the confusion in SMSY
    For the DEV ABAP system I am trying to configure:
    1. The system is showing up in two products : "SAP ERP" and "SAP ERP Enhancement Package" with the header data for both showing "EHP4 FOR SAP ERP 6.0 / NW7.01" and "SAP ERP 6.0"
    2. Under "SAP ERP" the "product instance selection" shows only "SAP NW - Adobe Docu. Service" and "SAP ECC Server" as relevant
    3. Under ""SAP ERP Enhancement Package" the "product instance selection" shows only "Human Capital Mgmt" as relevant by default.  I manually flagged the development portal system as "relevant" for "SAP XSS (Self Services)"
    4. The RCA DBA Cockpit system is complaining "No data available for extractor activation. Please check product mapping and Software Components in SMSY"
    5. In the Managed System wizard, there is no logical component for any of the "EHP4 FOR SAP ERP 6.0 / NW7.01" selections
    From what I can tell, I think this is correct:
    1. Create a Z_EHP4 logical component and assign the DEV/QAS/PRD systems to them
    2. Also assign the DEV/QAS/PRD to the existing SAP logical component "SAP ERP ECC SERVER"???
    3. For the Solutions, my plan is to create
    a. Non-Production ERP : with the dev/test erp/ep systems, but test system as the leading system
    b. Production ERP with the prod erp/ep systems only
    Thanks for any advice/guidance to help me avoid future problems!!
    Edited by: Eric Poellinger on Jun 15, 2011 6:32 PM

    General question - I have a slide from SAP that shows a picture from Product->System->Instance->Logical System (client)->Logical Component. I am confused because it shows that Client 100 of a given ABAP system could be assigned to Logical Component A, whereas Client 200 of the same system could be assigned to Logical Component B. This seems wrong to me?
    Client 100 could be assigned to any number of logical components, client 200 could be assigned to those same ones or none of them. A logical component is just a grouping of systems used to accomplish some task in SolMan.
    For example with ChaRM you could have 2 logical components.
    ZCHARM_DEV development (100) -> QA (200) -> prod (300)
    ZCHARM_SEC security (900) -> QA (200) -> prod(300)
    One is used to show the path for moving development changes to prod, the other for security changes. 200 belongs to both, but 100 only to one.
    Set them up in whatever way meets you needs. It looks like for you, you could just use the default one and assign your clients to the various system roles. Not all functionality in SolMan uses the logical components though.

  • How to set up logical components for ChaRM?

    Hi,
    we do have the following system landscape. One DEV and two separate QA and PROD systems.
    DEV->
    >QA1  -> PROD1
    >QA2  -> PROD2
    For these we want to transport parallel from DEV to QA1/QA2 and then parallel to PROD1/PROD2 via ChaRM.
    My questions are:
    1) Do I have to set up one or two logical components?
    2) How do I have to set up the logical component exactly?
    Thanks.
    Regards,
    Alex
    Edited by: Alexander Barth on Jul 20, 2009 4:02 PM
    Layout changed
    Edited by: Alexander Barth on Jul 20, 2009 4:03 PM

    Hi,
    Chk the below link .
    https://websmp202.sap-ag.de/~sapdownload/011000358700000657692007E/ECTS_CHARM_SP12.PDF
    Thx,
    Waseem.

  • Logical components for ERP and ERP EnhP 3

    Hello,
    We have a landscape or ECC 6.0 Systems created in the SMSY.  Those systems were linked to a new logical component Z_ERP60 under product ERP 6.0.  Then  we used that logical component in all the projects.
    Later on, we upgrade ECC 6.0 to EnhP 3.  So, we went to the SMSY transaction, to the infrastructure components--systems and add new product versions to the existent system.
    However, the logical component is defined as valid only for the original product ERP 6.0, and not to the new ERP 6.0 EhP3.  When we go to SOLAR01 transaction we still see that processes from BPR that belongs to EhP3 are greyed. 
    We want to know which is the best practice to handle this request, whether we create a new logical component associated to the product ehp3, Z_ERP60_EHP and then replace all the projects with the new component, or is there any other alternative.
    I appreciate your inputs.
    Regards
    Esteban Hartzstein

    Many thanks for your answer.  The attachment is related to whether ERP EhP is available as a product in Solution Manager.  We are in SolMan EhP1 (SP 18), so we already have the product available.  However my concern is that we need to redefine the logical component.  Logical component belongs to one single product, being ERP 6.0 or ERP 6.0 EhP.   So, in our case we need to create a new logical component with the new ERP 6.0 EhP and then re-atach all the individual systems to the new logical compoent.  Then we need to replace in all the projects withe the new logical component.  Is there any alternative to deal with this problem of redefintion of logical components??
    Regards
    ESteban Hartzstein

  • What do you mean by changing a Function Group in upgradation projects

    Hi ABAPers,
    I am new to upgradation project will any one help me in understanding the concepts like.
    1) what do you mean by changing a Function Group in upgradation projects
    2) what is the relation b/w the Maintenance view and function group
    3) what happens when we regenerate the table maintenance in se11
    4) how can i restore the changes that have done to FG after regenerating
    5) Suggest me is there any Tcode or procedure to see the code in Remote system (like how we compare the versions of remote system)
    Could you please help me ..
    Any relevant docs you can send it to  [email protected]
    Thanks in advance..

    Hello Smriti,
              Exploding a BOM means to display all the components and sub-components for a BOM in a particular transaction (eg) VA01,CO01,ME22N etc..
    You can use the SAP FM's depend on the Functionality:
    CS_BOM_EXPLOSION               General BOM explosion
    CS_BOM_EXPLOSION_EQUI          BOM explosion - initial screen: equipment
    CS_BOM_EXPLOSION_MAT           BOM explosion (old version); as of 3.0, use CS_BOM_EXPL_MAT_V2
    CS_BOM_EXPL_EQU_V2             BOM explosion for equipment
    CS_BOM_EXPL_KND_V1             BOM explosion for material
    CS_BOM_EXPL_MAT_V2             BOM explosion for material
    CS_BOM_EXPL_PSP_V1
    CS_BOM_EXPL_TPL_V1             BOM explosion for functional location
    CSS7                           Explode BOM (Document)
    CS_BOM_EXPL_DOC_V1             BOM explosion: document sub-assemblies
    CS_BOM_EXPL_GNRL2_V1           General BOM explosion: document sub-assemblies
    CSSO
    CS_SO_MODE_BOM_EXPLOSION
    As per Garet in response to your question better talk to the Functional team to get the better underatanding for your requirement.
    Check the below link for more details on BOM:
    http://sap-img.com/sap-sd/what-is-bom-referring-to-sap-sd.htm
    Thanks,
    Greetson

Maybe you are looking for