Changes in Material Master leading to issues in MRP

Hi,
For a particular material a user changed a lot of material master data (MRP1 and MRP2 view) within a couple of hours.
As a result MRP is not working as we would expect:
- some orders have no quantity in the "Available quantity" column in MD04 and as a result do not trigger any PO (Received/Required quantity = -1, but Av qty = blank)
- whenever a shipment is foreseen it is consumed/reserved by/for the order which requested delivery date is closest after that shipment date
These are the changes made to the master data in November 2009:
Planning Strategy Group: from Make-To-Stock Production to No Planning to Strategy Group for Spares & Consumables to No Planning to Strategy Group for Spares & Consumables
MRP Group: from Client Specific MRP Group for Period Mgmt to General to External Procurement to Client Specific MRP Group for Period Mgmt to General to Client Specific MRP Group for Period Mgmt
Availabilty Check: from Indiv. Req. to Indiv. Req w/o PO. to Indiv. Req.
Unplanned Consumption in period: from blank to 11.2009
Fwd Consumption Period: from 0 to 999 to 0
Consumption Mode: from blank to Forward Consumption Only to blank
Unchanged MRP material master data:
Bwd Consumption Period: 0
MRP type: MRP
Planning Time Fence: 1
Lot size: WB (weekly lot size)
Procurement type: External Procurement
Backflush: always backflush
What should we do to have MRP work correctly again for this material?
Changes to material master MRP? Delete all schedule lines and start from scratch in SOs?
All help is much appreciated!
Best regards,
Geert
Edited by: Geert P on Dec 10, 2009 6:08 PM
Edited by: Geert P on Dec 14, 2009 4:04 PM

Solved internally by adjusting Strategy Group

Similar Messages

  • Not able to transfer changes in material master (periodic)

    Hi Friends,
    Got an issue here. I am not able to transfer the changes I made in material master. I want this as periodic, Made the specific setting in CFC9. And for your information 'Activate ALE Change Pointers Generally' and for massege type are activated.
    But when I execute CFP1 I got massege: 'No appropriate master data changes: Transfer has not happen'.
    I made changes in material master (global level),..like gross weight changed. Material is in active IM, no duplication.
    Any help Please? We are on SCM 7.0.
    Thanks,
    Satyajit
    Edited by: Satyajit Patra on Mar 20, 2010 9:12 PM
    OK, Guys I think I need to raise an OOS... It was for SCM 7.0, but was basic config....thts why I edited the thread so many times expecting some responce.
    Edited by: Satyajit Patra on Mar 22, 2010 7:41 AM

    Hi Satyajit,
    Please look at OSS  Note 1069560 - Data inconsistencies: Activating integration. models in parallel, if this helps you.
    Since  Gross data of material is in the basic view, it is common across plants , whereas, IMs are normally designed to have material masters at plant level.
    We may have same material in different IMs with different  plants. Therefore changes of the basic view fields are then contained in multiple IMs.  SAP advises to have a larger IM or sequential activation of IMs.
    I hope this will  help you .
    Regards
    Datta

  • RMDATIND program - used for change the Material Master

    Hi Experts,
      Could please confirm whether using RMDATIND program can we change the Material master data?...
    Thanks
    R P R kumaar

    Execute this program and you can find an information icon in the toolbar. press that icon. you will complete documentation regarding this program

  • PuP price not changed in Material master

    Hello All experts
    I have one question about the material ledger related transaciton, I have a Material with 2+V (price deter. and price control) setting in Material master data in Accounting 1 TAB. And material ledger is active for this material, the Periodic Unit price is 1 USD in current period and stock is 0.
    One PO posted for this Material for purchase with actual price 100 USD, and 101 movement type with special stock indicator E was used in Goods receipt posting. I think these stock will be treated as valuated sales order stock. But GR posting didn't trigger any PuP price change in Material master. Is that situation normal? Pls kindly help.

    With price control V in activity-based material price determination (indicator2 in the material master), the moving average price is calculated. With price control S, the material is valuated with the standard price and the moving average price is calculated for information purposes.
    In single-/multi-level material price determination(indicator 3 in the material master), the valuation price (standard price) remains unchanged and a periodic unit price is calculated for the closed period.
    This option is only for materials with price control indicator S,and is only recommended if in addition to multiple currencies and/or valuations, you use single-/multi-level material price determination.
    In single-/multi-level material price determination, a periodic unit price is updated for information, but it can only be used for material valuation in the closed period.

  • Profit center change is  material master issue in EHP7

    Hi,
    we are facing issue in materail master  profit center  change .recently upgared with ehp7 after this upgarde its not allowing to change in materail master.
    i have alternative solution for this is t code OMT4 i can change message type E to W .
    But my old version its allowing even though OMT4 having Message E
    Please anybody help on  this
    Regards
    Vinod

    Hi Vinod,
    Did you find any solution for your issue?
    We need to do some mass update of profit center for a big chunk of our materials by this Dec.
    Last time we tried changing the profit center we faced error MM326.
    Is there an SAP note or some other solution that can be used for this case?
    Thanks
    Akash

  • Mass change of material master

    Hi Experts,
    I have a query regarding mass change to be done in material master. I need to update one value in the Material group 4 field in sales org view 2 in MM02 transaction for nearly 300000 materials. One option i find is LSMW and the other i saw is transaction MM17. Please let me know how feasible is this MM17 transaction? Is it possible to upload all the 30000 materials through MM17 transaction in one go and update the field? Will there be any performance issue if MM17 transaction is used?
    Please give your suggestion.
    Thanks
    Dinakar

    Hi,
    Use MM17,
    Goto the Transaction code MM17 and in the table check the MVKE- sales org data for material
    and select the Fields tab and choose the field MVKE-MVGR4 and  execute
    Now enter all the materials in the next screen  for which you want to change  and execute
    In the next screen you can maintain the new values for the old
    Please check and revert
    thanks,
    santosh

  • Change in material master

    Dear all,
    I am trying to change the Price control of a material from V to S.
    It is showing me a system message as follows:
    Price control cannot be changed (cost component split exists)
    Message no. M3160
    Diagnosis
    Costing is active and has already been carried out for the current period. You can only change the price control to "Standard" if the moving average price and the standard price are identical
    Now when i am trying to make the standard and moving average price identical,system is throwing an error as follows:
    Standard cost estimate exists in period 04 2009
    Message no. M8155
    Diagnosis
    A standard cost estimate has been entered in the material master record for the specified period. This can be a current or future estimate.
    Note: This message category can be changed in Customizing for Invoice Verification. This means that you can receive an error message even though the message is defined in the standard system as a warning message.
    The following documentation only deals with the standard case.
    System response
    You cannot manually change prices.
    Procedure
    1. To update the price determined using a standard cost estimate in the material master and activate the price for material valuation, you have to mark and release the standard cost estimate.
    Mark and release standard cost estimate
    Procedure for System Administration
    2. If you have authorization for Customizing, in Customizing for Product Cost Planning, you can define this message as only a warning or information message for certain users. These users can then change the price manually.
    Pls try to throw some light in this issue about how to process the price control change?????????
    also pls let me know the spro path for message type M8 155??????
    also what is the menu path for M8 155 in product cost planning?
    regards,
    indranil

    http://help.sap.com/erp2005_ehp_03/helpdata/EN/47/60ff6249f011d1894c0000e829fbbd/frameset.htm
    For System path of M8 155 go to SPRO - MM - Purchasing - Logistic Invoice Verification - Define Attribute for System Message / OMRM
    Regards,
    Ashok

  • Changes in Material Master: Track by user

    Hi All
    I have an urgent issue...I want to track the changes done by a user in the material master.  Is there any standard way of doing it.  I want to know what the old values were also for the fields changed by the user.
    Tom

    Hello,
      You can use MM04 to get a drill report showing the user name,date, time stamp. Once you dril down into this, you will get the details of change.
    Thanks,
    Venu

  • SAP SCM Upgrade to 5.0, Material Master Initial Transfer Issue

    Dear Folks,
    We are doing an upgrade to SCM 5.0 for a client and are facing the issue of material master initial transfer. The changes to exising material like Proc type etc. travel seamlessly but while we try to create a new material in R/3 and transfer it to APO or if we delete an existing product in APO and re-transfer the material from R/3, it simply doesn't happen. We donot get any kind of errors also. We have tried various suggestions and solutions but all have failed. To summarize the activites that we have done to check the issue, please see the track below.
    Action                                                              Observation
    1. Observed queue blocks on R/3 and APO sides:            No blocks.
    2. “Important” logs on R/3 as well as APO side:                No error logs on CIF observed.
    3. Check material master data fields in R/3 relevant and necessary for APO: Done
    4. Check the APOKZ flag in MARC Table:                        Done
    5. Check OSS relevant notes for the issue:                      Done
    6. Check CIFMAT and MATLOC tables in APO:                Done
    7. Check the TRFCQIN and TRFCQOUT tables in APO     Done; nothing relevant to CIF observed.
    8. Debug CIF and find the issue                                       No breakthrough.
    9. Check location and location pre-requisites for CIF         Done
    Now we have raised OSS notes to SAP and are awaiting a solution.
    I request all Gurus to pitch-in and suggest possible issue here and perhaps a solution too. I am very hopeful that some one might have faced similar issue and have found a solution to the same.
    Warm Regards,
    Chandra

    This required packaging materials to be CIFed first before transferring the other materials. Issue resolved, SAP issues a note on this.

  • Weight change in material master, update all open PO's

    Hello
    IS there any standard way for mass update open purchase orders, when weights and volumen in material master change ?
    example:
    there is a change in neto weight for material AAAA, which is inserted into mm02, basic data for his material. This change doesn't effect already created  open orders with this material. Is there any standard way to update them in sap 4.7 ?

    Changes will get reflected for new docs only. This is standard.
    Now other question comes, why you want to change in PO. I am sure PO are already sent to vendor. Then ideally it is not advisable to change in those PO.
    If you haven't sent those PO to vendor, open those PO do some minor corrections SAP will populate the change information in PO documents.
    Also changed information will get effective later at GR stage also.
    So no question to worry.
    Check and revert

  • Mass Change in Material Master

    How to do mass Change of material group (say from 1HA TO 1HB) in material master in basic data 1 tab.
    Plz explain steps.

    Hi Rohit,
    Follow the Steps  SPRO - SAP Reference IMG - Production - Material
    Requirement Planning - Planning - Define Storage location MRP per plant - Enter
    the plant - Check for which Storage locations has got the indicator 1 - Storage
    Location stock excluded from MRP - Now remove that or choose the values.
    if you give me brief i can help you out more.
    Thank you .
    Regards
    Ram

  • Mass changes of Material Master field with different values

    Hi,
    How to change a field in Material Master for more than thousand materials. I think MM17 can only be used for mass changes of materials with same values. I need to upload different values for different materials. Is there any other way to do this.
    Thanks,
    K R Vishnu Kumar

    Hi Kumar.
    I think you have to use LSMW for mass updation for Material Master fields with different values.
    Regards,
    Rahul.

  • Price change in material master

    Hi,
    When does the moving average price change, if the PO price or the invoice price is different from the one in material master. Is it after the creation of PO, GR or invoice?
    Thanks and regards
    Aparna

    Hi,
    Moving Average price = Total Value
                                       Total Stock
    Moving average price updates once you make GR and IV
    If you are making GR & IV for new po , then new moving average price of that material will be :
    Total stock = stock already present in plant + GR made stock of that new po
    Total Value = Total Value of the material in plant + Invoice amount for that new po
    Thanks & Regards
    Prashanth.venkategowda

  • HOW TO TRACK CHANGES IN MATERIAL MASTER

    Dear All,
        I have changed material master with change number.
    Now i want to see both old and new material master.
    how to do this?

    Dear
    Goto MM03/MM02-Enter material code -hit Enviornement  at the header -Display Changes -It will display the list of changes WITH DATE TIME -Double Click on the Chekc box  to know the details of changes .
    Regards
    JH

  • Change of material master during transfer between SRM and R/3

    Hi,
    I have a question for modifying material master data between R/3 and SRM.
    I would like to know if it is possible to change the material number during the transfer. The reason is:
    I have 2 R/3 backends and 1 SRM system. The material codes in the 2 R/3 systems are different but some materials having different numbers in R/3 are referring to the same material. I want to see such materials with the same material number. Is it possible to do this with Middleware plus some interruption in between? The "translation" should be bi-directional.
    Thanks

    Hi,
      No probs if the field is not replicated.No idea how to bring that through replication though.
      Coming to the Product Search...Although the number of such materials is less...You will have to modify the Product search which will take care of the  display of other products as well.
      The Std product search(<b>bbph_product</b>) uses the the search help exit "<b>BBP_F4IF_SHLP_EXIT_PRODUCT_GEN</b>".So you need to replace this one with your custom FM.
      In your custom FM,you will have to check for the HARMINIZED code field for all such materials and accordingly while selecting the Material select the HARMONIZED code as the Material number and in the Product search display that HARMONIZED code as the "PRODUCT ID". Also,you  will have to develop RFC enabled FM which will actually fetch all the Materials from the BAckend at runtime. Also are you displaying the Product List Plantwise?
      Pls give me ur mail ID where i can mail you the  sample code.
    BR,
    Disha.
    Pls reward points for helpful answers.