if your TMS has the tranport routes: Dev to QA to Staging to Prod, how do you set up your system landscape for the ChaRM maintenance project?
Specifically, where does staging go?
thanks,
Jason

it's something like R3D:10 to R3Q:60 to R3S:80 to R3P:100
there isn't a system role for Staging in the projects system landscape. I was told by SAP that your landscape should match your TMS client specific transport routes.

Similar Messages

  • Low SP level in backend,CHARM system is on SP18,no transports /TMWFLOW/REPO

    Hello All ,
    Currently we are in process of Applying SP18 in SAP Solution Manager 4.0. Our APO is connected to solution manager ( CHARM ) for transports related activities. However APO's has SP14
    So when i try to trace APO transports in CHARM system in tcode : /TMWFLOW/REPORTING , i am not able to trace them becuase of low level SP in APO.
    Is there any way out where in i should not update the SP level in APO , but apply some notes or patches
    in APO or solution manager to manage the tracing of transports in solution manager.
    Thanks in advance.

    Hello Timo
    Did you find any error in the JSPM logs? If you faced no errors, then SAP note 910073 my help to synch the versions. Please check in the "information system" page if the old versions are still listed.
    Regards,
    Désiré

  • SolMan ChaRM - System landscape not ready yet

    Hi all,
    We are configuring ChaRM for an implementation use, therefore all the systems are not set up yet.
    Is it possible in SolMan to define logical component without "real" systems ?
    We saw that in STMS it was possible to create virtual systems, but how do we link these virtual systems to SolMan ChaRM ?
    Is it possible to define a virtual system landscape and to build and configure ChaRM scenario with this ?
    Thanks a lot for all your help,
    Regards.

    Yes, it is possible to define a development system and virtual systems (Q- and P-System).
    Via transaction SMSY you can describe the planned Q- and P-System at first as 'virtual'.
    Create transport routes with transport buffers as you would do for existing systems.
    Define the buffers as they should be named in future.
    For experimental purposes we connected our IDES-System to our development SolMan system.
    In this environment we could map such a ChaRM-configuration.
    In the meantime we practiced it in our production SolMan system, too.
    Best regards
    Horst

  • ChaRM:System Change Option

    Hi Team,
    I have activated CHaRM BC sets and created maintenace project. The mainteanace cycle also created successfully. But in the t.code /tmwflow/cmsconf, in the "System Change Option" tab, no systems are displayed. How to bring the ChaRM client, DEV,QA &PRD systems (satellite systems) in this tab.
    Note; I am working in SAP EHP 1 for SAP Solution Manager 7.0, ST: SAPKITL433
    Thanks.
    PSK
    Edited by: psk.psg on Oct 6, 2010 7:46 AM

    Hello,
    Have you completed the following steps in SOLMAN
    1) In SMSY creation of RFC connection to the required systems like for CHARM consider you have 3 systems , Customizingg, testing and prod then you have to create the RFC connection to all the 3 systems for particular client.
    2) In SPRO in SOLMAN have you Activate Integration with change request mgt
    3) Also I hope you have configured STMS properly and distributed the STMS.
    Best Regards
    Shishir H D

  • NWDI in three system landsacpe

    Hi
    1. I had Portal Dev system where central NWDI & central SLD was configured with template installer, developers were doing initial developements
    2. Now I have installed the Portal Quality system, I Just registered with the central SLD of Portal Dev
    3. Now How to do the NWDI config of the Portal quality system?. Do I need to do fresh NWDI with template installer or Register this quality with Dev system?
    How to register the Quality with central NWDI DEV system?. anyone help me?
    Thanks in Advance...
    AJ

    HI,
    You already have a NWDI, so just mention your portal quality server in runtime system.
    you can mention it in CMS.

  • Unicode Conversion in a system landsacpe

    Hello,
    we are planning a unicode conversion of our productive system.
    Our productive system is the source system of several systems like BI, mobile engine, webshop and so on.
    About the problems of unicode conversion within the productive system I have found a lot of information.
    But what about the scenario: If our productive system is unicode based and the satellite system do not have unicode, is that a problem.
    Do we have to keep in mind to convert also the target/satellite system ?
    And futher more do we have to analyse the program codes in the satellite system for BI (transfer structure,infoobject and so) ?
    Do anybody have expierience with his system landscape ?
    Thanks so far,
    Komin

    hello henning,
    are you connected with the other systems via RFC?
    if yes it should be no problem, because you can different in you rfc settings, between incoming non-unicode lettes and outging unicode
    regards
    stefan

  • System LAndsacpe

    Hi experts,
    (Q1). I’m new to SAP XI and recently I’ve attended an interview with an MNC. There the interviewer asked to draw complete system landscape (all systems which are integrated with XI). I told him that I’ve configured JDBC, File (with content conversions), IDOC, RFC and SOAP adapters. I need a sample system landscape wherein I can show all the systems involved in configurations and it shud cover all the above mention adapters. In which scenario we use JDBC adapter……I
    (Q2). In a system landscape do we maintain a single File server or every system will have there own file servers. If only a single file server exists then how we can configure file2file scenario using RFC?
    (Q3). In which scenario we use JDBC adapter….I mean can we send the data directly to DB lets say SQL Server without using any front-end applications.
    Thanks in advance
    Faisal
    Points will be given to the correct answers.

    Hi Abdul,
    Abdul, first you have to know what is sld, how many sld's can be configured, it purely depends on the client's requirement, they may maintaing single SLD for DEV, QUA & Production, or they may maintain individually. and if we deploy the .tpz file of adapters all the adapter which are present with the XI will be deployed and can be viewed and according to the requirement we choose the adapter.
    If u deal with the DATABASE then u have to go with the corresponding JDBC adapter, else if u want to work with CSV or XML files then u will be going for the file adapter, it purely depends on the requirement of your scenario.
    SLD contains
    1>SW catalog, which contains
    SW product: is any application. Ex: MS office.
    SW Component: is any new funcationality that is added to the product.
    SW Component version: version of the new functionality.
    2>System Catalog, which contains
    Tech systems: SW products are installed on the tech systems.
    Busines Systems: are Logical systems that take part in the actual message exchange.
    for further clarification refer this links...
    http://help.sap.com/saphelp_nw2004s/helpdata/en/31/f0ff69551e4f259fdad799a229363e/frameset.htm
    http://help.sap.com/saphelp_nw70/helpdata/en/24/8fa93e08503614e10000000a114084/frameset.htm
    regards,
    Kishore kumar

  • ChaRM System Logon

    hi all,
    After assigning status to "Being developer" Developer would have to logon to the satellite system from solution manager. This is not working for me , for my clarrification what configuration i have to verify??
    can u any one explain in detail ?

    Hi prakash,
    Can you please let us know how is the landscape setup.
    Is the system connected by the SLD in solman or is the data extracted from an external SLD via RFC connections.
    Please check it via SMSY_SETUP where any updates of your satellite systems are visible via a Exclamation mark ..
    Let me know if this input is helpful.
    Br,
    Sri
    (Your points drive us)

  • 3 system and 4 system landscape - Charm

    Dear All,
    We have 3 system landsacpe for ECC and 4 System Landscape for BI?
    Is it possible to configure CHaRM for these landscape?
    If yes, please give me step by step guidelines.
    How to create Maintenance Cycle?
    Raj

    Hi Raj,
    This is possible. The three system landscape is the usual scenario. In four system landscap, you just need to add a pre-production system in your landscape.
    Go to the Wiki http://wiki.sdn.sap.com/wiki/display/SM/Weblogs%20related%20to%20Solution%20Manager and search for Change Request Management. There are some 10 docs available there. Specifically have a look on
    First steps to work with Change Request Management scenario
    /people/dolores.correa/blog/2008/07/26/first-steps-to-work-with-change-request-management-scenario
    Call service.sap.com/rkt-solman. You can find the materials for project prepration, corrections etc.
    Call SPRO in your solman system and go through the documentation provided there.
    This will give you adequate information for configuring ChaRM.
    Rajeev

  • Full production refresh to development systems and Charm?

    Hi SDN Community,
      Where I work we have a policy of refreshing the development systems (ECC, CRM, APO, BI, SRM) on an annual basis with full production system data, HR data is subsequently wiped clean from the development system. 
    For each of our systems we have a development system, a QA system and a production system.
    The decision to do these full refreshes was taken to ensure that developers and configurers can do decent testing in the Dev environments - prior to transporting to our QA system - to ensure that we have a reasonably stable QA system. Prior to the refreshes - QA was considered too unstable by our business to be used as a good test platform - the full D refreshes solved this problem.
    We have recently installed SAP Charm (Change request management) which is a solution manager based product that manages the transportation of objects in change requests - attached to maintenance cycles.
    During our first development system refresh we discovered that all open Charm projects (maintenance cycles) were placed into an unuseable status due to the refresh. This means we had to rebuild all of the Charm projects after the refresh - which took a considerable amount of time + resources and delayed project work. We don't want to be in this situation again for our next refresh.
    SAPs response to us has been that they have no other customer that does full Development system refreshes - and also has Charm. I wonder if this is accurate, I think what SAP are saying is that they don't have many Charm customers... Is refreshing Development so uncommon?
    We are considering products like SAPs TDMS - and alternatives (eg gold client) - but most of these appear a little immature - for refreshing complex system landscapes - such as ours and keeping everything in synch after the refresh.
    My questions to SDN -
    What do you do - do you do full refreshes to your D systems?
    If not - what are the arguments against refreshing D systems (is this considered bad practice)?
    Are there any other Charm customers out there in a similar situation to us?
    How do you manage the stability of your QA environments and stop the transport into QA systems of untested changes - if your D systems are not similar to you production system
    (note we have some 300 active users in just our ECC development system)?
    Any suggestions / recommendations as to how to best proceed would be greatly appreciated.
    many thanks in advance,
    Julian Phillips
    Edited by: Julian Phillips on Nov 11, 2008 2:33 PM

    Thanks Naushad for your reply,
      I wonder if D refreshes are less common - more due to the additional hardware costs incurred (disk space needed to store full production data is usually pretty large) to do them - than due to avoiding disrupting development - probably a bit of both.
      I did not mention this - but in our refresh we do reimport all transports that we open prior to the refresh - which used to solve our problems - in terms of restoring active changes - but with SAPs Charm system - this approach does not work as the Charm projects are left in an inconsistent status.
    We are now leaning towards introducing a 4th set of systems into our landscape - so that we have the following platforms:
    Development --->  Pre QA  ---> QA  ---> Production
    This approach will allow us to keep both the Pre QA and QA systems refreshed every 6 months or so - and our new Dev system - we will refresh very infrequently (every 5 years perhaps) if at all. We will tie the Charm system to our new development - and this system will then not be impacted by refreshes. This approach means additional hardware cost - but as it happens we have a few spare boxes - so this maybe our best bet.
    The core reason for our refresh is so that we will be able to preserve the stability of our QA test platform - which for us is the critical factor here. If QA has poorly tested work in it - we run a higher risk of disrupting other testing and also of this poorly tested work reaching production.
    When we used to have a development system as you described and just the single QA box - we experienced frequent instability in our QA box - due to poorly tested working reaching it - and this delayed numerous projects.
    Does anyone else have a 4 box setup like this? Anyone else encountered this on an SAP project anywhere? Pros / Cons of this approach?
    //Julian
    Edited by: Julian Phillips on Nov 12, 2008 8:08 AM
    Edited by: Julian Phillips on Nov 12, 2008 8:18 AM

  • Evaluation System

    Hi All ,
    I have created project and assigned the logical component which includes  3 systems with DEV, Test and Prod roles .
    When I define a Business  Blueprint in SOLAR01 it opens  by default a project with an "evaluation system"  role.
    My question is which one of the systems in my system landscape supposed to be an evaluation system, Dev , Test or Prod ?  
    What is the best practice ?
    I know that is Evaluation system is designed for Business Blueprint phase , but what is really meaning ?
    Cheers ,
    Evgeny

    Hi all,
    I've had the same issue with regards to getting the error below when assigning transactions to a Blueprint business process.
    "No system found for component and Evaluation system in the Project"
    But I think I have solved it and seems pretty simple to change the system role from Evaluation System to any other that is relevant in your landscape.
    Go to transaction SOLAR01 > Click on the first level of the Project Name (Under Business Blueprint Structure) to select the Project.
    Click Business Blueprint in the Menu > System Role > Choose the relevant System Role (in my case Development)
    Click Copy
    This should replicate to all nodes and then you should be able to assign transaction to the business processes.
    Quite strange and seems simple, I checked the Solution Directory, Solar Project Admin etc etc but couldn't find the solution until this which should work.
    If not, there is a similar work around which also works.
    Go to transaction SOLAR_PROJECT_ADMIN
    System Landsacpe Tab
    Systems subtab
    Click System Role Assignment
    Remove the Evaluation System (or all those not relevant to your Project and Logical Components)
    Save Project
    Go to SOLAR01 and it should reflect it in the Blueprint.
    You can always go back to this and add the System Roles you removed and the Blueprint will reference the correct Role.
    Hope this helps everyone,
    -Rohan

  • Error in Solar02 " Error - No system found for component SAP LEARNING.....

    Hi,
    I have selected the Business repository from the Tcode Solar01c, and i can see the list of configuration under Business Scenario,
    when i am trying to execute any Tcode,(My understanding is that this Tcode must execute in Development system) it gives the following Error,
    " No system Found for Component SAP Learning Solution and Role Evaluation system in project ZPROJ.
    In SMSY i have created Two systems Dev :100 and Qas:300  Which are assigned to one logical component whose producted Version in SAP ERP.
    Please advise by reviewing above scenario.
    Regards,
    SM

    Hi Irfanl,
    I've had the same issue with regards to getting the error below when assigning transactions to a Blueprint business process.
    "No system found for component and Evaluation system in the Project"
    But I think I have solved it and seems pretty simple to change the system role from Evaluation System to any other that is relevant in your landscape.
    Go to transaction SOLAR01 > Click on the first level of the Project Name (Under Business Blueprint Structure) to select the Project.
    Click Business Blueprint in the Menu > System Role > Choose the relevant System Role (in my case Development)
    Click Copy
    This should replicate to all nodes and then you should be able to assign transaction to the business processes.
    Quite strange and seems simple, I checked the Solution Directory, Solar Project Admin etc etc but couldn't find the solution until this which should work.
    If not, there is a similar work around which also works.
    Go to transaction SOLAR_PROJECT_ADMIN
    System Landsacpe Tab
    Systems subtab
    Click System Role Assignment
    Remove the Evaluation System (or all those not relevant to your Project and Logical Components)
    Save Project
    Go to SOLAR01 and it should reflect it in the Blueprint.
    You can always go back to this and add the System Roles you removed and the Blueprint will reference the correct Role.
    Hope this helps,
    -Rohan

  • No system found for component and Evaluation system in the Project

    Hi Folks ,
    Im facing this problem when im trying to Execute the T-codes from Solar01 of the Transactins Tab by Selecting the Line item and clicking on Execute button. Following is the Error and there no logs for it.
    No system found for component and Evaluation system in the Project
    Even i have checked with the RFC settings and Logical components are right
    Please do suggest me - This is PRD issue . Try to do the needful .
    Thanks in Advance
    Amrita
    Edited by: Amrita Amrita on Dec 3, 2009 12:53 AM

    Hi all,
    I've had the same issue with regards to getting the error below when assigning transactions to a Blueprint business process.
    "No system found for component and Evaluation system in the Project"
    But I think I have solved it and seems pretty simple to change the system role from Evaluation System to any other that is relevant in your landscape.
    Go to transaction SOLAR01 > Click on the first level of the Project Name (Under Business Blueprint Structure) to select the Project.
    Click Business Blueprint in the Menu > System Role > Choose the relevant System Role (in my case Development)
    Click Copy
    This should replicate to all nodes and then you should be able to assign transaction to the business processes.
    Quite strange and seems simple, I checked the Solution Directory, Solar Project Admin etc etc but couldn't find the solution until this which should work.
    If not, there is a similar work around which also works.
    Go to transaction SOLAR_PROJECT_ADMIN
    System Landsacpe Tab
    Systems subtab
    Click System Role Assignment
    Remove the Evaluation System (or all those not relevant to your Project and Logical Components)
    Save Project
    Go to SOLAR01 and it should reflect it in the Blueprint.
    You can always go back to this and add the System Roles you removed and the Blueprint will reference the correct Role.
    Hope this helps everyone,
    -Rohan

  • Timeout parameter in SolMan-ChaRM

    Hi,
    I need to know the parameter which decides the timeout for tcode SM_CRM in SolMan 7.1
    the ABAP gui closes after about 5 mins of inactivity whereas the web browser of tcode SM_CRM remains open for long time(about 1 hour)
    What are the parameters which decide these timeouts for both ABAP gui as well as web browser in SolMan Charm System.
    The reason behind the need to know this is the java threads in our systems are all getting consumed resulting in JAVA stack getting crashed.
    We suspect the SM_CRM is the culprit as it remains open for long time and this tcode is being used widely in our project.
    OS : AIX
    DB : oracle
    -Ujjwal

    Assuming you are talking about the timeout value for the web interface, it is in the {installdir}/ocas/conf/ocwc.conf file. The parameter you want to change is ssn_timeout. I believe you will need to restart ocas to make it effective.

  • Event due to the System or SystemLandscape creation

    Hi
    Does portal runtime generates any kind of event,for any System or System landsacpe get created in PCD?
    Thanks
    arati

    Hi Gurucharan,
    Do you have any networks attached to the WBS?
    Do they have any activities with planned costs?
    Check report S_ALR_87013533 - Plan/Actual/Commitment/Rem.Plan/Assigned.
    If you see values in the 'RemOrdPlan' column, then your networks are being treated as commitments.
    Regards,
    Kent Bettisworth

Maybe you are looking for

  • MAPPING CHALLANGE.....POINTS WILL BE GIVEN!!

    Hi i am doing a File2Idoc scenario, i am stuck in the mapping ... the file is something like this...its only a part of payload C1TN4028260000PP345700210 2620582 005 0000000000000072020061802 000000000000000000 C2TN402826000000001037331742557076 00000

  • Data Conversion rules for EDI processing (same client IDOC processing)

    Hi, I am trying to post IDOCS in same client.Its a PO->SO process. ie. there will be 1 outbound and inbound idoc in same client using EDI processing. I am using Data Conversion using Rulesfor converting sender fields. The LIFNR and PAORG od segment E

  • How do I get my Yahoo homepage when I click on Firefox?

    I want to KEEP my Yahoo homepage, can I do this when I log on with Firefox?

  • Can I use verizon iphone5 in china ?

    We are about to purchase an Iphone 5 and will be spending 4 months in Shanghai, can we use the Iphone 5 in China ? If 'yes' , what do we need to do to enable use in Shanghai.

  • Installation error: Full Java Edition2004s-Trial

    I’m trying to install “Full Java Edition2004s-Trial” and I got the below errors. Please help <b>FJS-00003</b>: TypeError: dir_profile has no properties (in script NW_Java_OneHost|ind|ind|ind|ind, line 39637: ???) <b>MUT-03025</b>: Caught ESAPinstExce