Dear SAP experts,
In my company we have scenario for chemical procurement. Let's say that for a chemical process, we need either material A, material B, or material C.
If we procure material A we will need 5 liter, if we buy material B --> 3 liters, material C --> 2 liters. For our processing it can be either of them. So the point in here at the time of creating the PR, we actually dont know which materials we're ending up buying as we only know later when the bidding is finished.
Is there any way SAP can adopt this scenario?
Best regards,
John

Hi,
I don't think you can map this into SAP.  This decision is purely for business to decide which material to buy out of the requested ones after bidding, and reaching an agreement with the one of the supplier.
regards
alexandro

Similar Messages

  • April 30 Webcast: Ariba Network Enables MRO Procurement

    To find out how Ariba Network facilitates procurement of MRO parts and services, sign up for the ASUG webcast on April 30:
    Network Enabled Asset Integrity: SAP EAM Meets Ariba Network in a Chemical Plant
    Schedule
    Start: April 30, 2014 9:00 AM (CT), 10:00 AM (ET), 8:00 AM (MT), 7:00 AM (PT)
    End: April 30, 2014 10:00 AM (CT), 11:00 AM (ET), 9:00 AM (MT), 8:00 AM (PT)
    Description
    Hosted by: ASUG Chemical SIG
    http://www.asug.com/special-interest-groups/4197Learn how to improve asset maintenance processes, from ordering parts to managing contractors, by integrating SAP Enterprise Asset Management with Ariba Network. This session explains the functionality currently enabled by this integration and explores the MRO and labor management scenarios that will be available with the upcoming Ariba release.
    Speaker Name(s) and Company:
    Lauren McCallum, Solution Manager, Industry Business Solutions - Chemicals, SAP
    Monica Gassmann, Solution Manager, Industry Business Solutions - Chemicals, SAP

  • BI Best Practice for Chemical Industry

    Hello,
    I would like to know if anyone is aware of SAP BI  Best Practice for Chemicals.And if so can anyone please post a link aswell.
    Thanks

    Hi Naser,
    Below information will helps you in detail explanation regarding Chemical industry....
    SAP Best Practices packages support best business practices that quickly turn your SAP ERP application into a valuable tool used by the entire business. You can evaluate and implement specific business processes quickly u2013 without extensive Customization of your SAP software. As a result, you realize the benefits with less Effort and at a lower cost than ever before. This helps you improve operational efficiency while providing the flexibility you need to be successful in highly demanding markets. SAP Best Practices packages can benefit companies of all sizes, including global enterprises creating a corporate template for their subsidiaries.
    Extending beyond the boundaries of conventional corporate divisions and functions, the SAP Best Practices for Chemicals package is based on SAP ERP; the SAP Environment, Health & Safety (SAP EH&S) application; and the SAP Recipe Management application. The business processes supported by SAP Best Practices for Chemicals encompass a wide range of activities typically found in a chemical industry
    Practice:
    u2022 Sales and marketing
    u2013 Sales order processing
    u2013 Presales and contracts
    u2013 Sales and distribution (including returns, returnables, and rebates, with quality management)
    u2013 Inter- and intracompany processes
    u2013 Cross-company sales
    u2013 Third-party processing
    u2013 Samples processing
    u2013 Foreign trade
    u2013 Active-ingredient processing
    u2013 Totes handling
    u2013 Tank-trailer processing
    u2013 Vendor-managed inventory
    u2013 Consignment processing
    u2013 Outbound logistics
    u2022 Supply chain planning and execution Supply and demand planning
    u2022 Manufacturing planning and execution
    u2013 Manufacturing execution (including quality management)
    u2013 Subcontracting
    u2013 Blending
    u2013 Repackaging
    u2013 Relabeling
    u2013 Samples processing
    u2022 Quality management and compliance
    u2013 EH&S dangerous goods management
    u2013 EH&S product safety
    u2013 EH&S business compliance services
    u2013 EH&S industrial hygiene and safety
    u2013 EH&S waste management
    u2022 Research and development Transformation of general recipes
    u2022 Supplier collaboration
    u2013 Procurement of materials and services (Including quality management)
    u2013 Storage tank management
    u2013 E-commerce (Chemical Industry Data Exchange)
    u2022 Enterprise management and support
    u2013 Plant maintenance
    u2013 Investment management
    u2013 Integration of the SAP NetWeaver Portal component
    u2022 Profitability analysis
    More Details
    This section details the most common business scenarios u2013 those that benefit most from the application of best practices.
    Sales and Marketing
    SAP Best Practices for Chemicals supports the following sales and marketingu2013related business processes:
    Sales order processing u2013 In this scenario, SAP Best Practices for Chemicals supports order entry, delivery, and billing. Chemical industry functions include the following:
    u2022 Triggering an available-to-promise (ATP) inventory check on bulk orders after sales order entry and automatically creating a filling order (Note: an ATP check is triggered for packaged material.)
    u2022 Selecting batches according to customer requirements:
    u2022 Processing internal sales activities that involve different organizational units
    Third-party and additional internal processing u2013 In this area, the SAP Best Practices for Chemicals package provides an additional batch production step that can be applied to products previously produced by either continuous or batch processing. The following example is based on further internal processing of plastic granules:
    u2022 Purchase order creation, staging, execution, and completion
    u2022 In-process and post process control
    u2022 Batch assignment from bulk to finished materials
    u2022 Repackaging of bulk material
    SAP Best Practices for Chemicals features several tools that help you take advantage of chemical industry best practices. For example, it provides a fully documented and reusable prototype that you can turn into a productive solution quickly. It also provides a variety of tools, descriptions of business scenarios, and proven configuration of SAP software based on more than 35 years of working with the
    Chemical industry.
    SAP Functions in Detail u2013 SAP Best Practices for Chemicals
    The package can also be used to support external toll processing such as that required for additional treatment or repackaging.
    Tank-trailer processing u2013 In this scenario, SAP Best Practices for Chemicals helps handle the selling of bulk material, liquid or granular. It covers the process that automatically adjusts the differences between the original order quantities and the actual quantities filled in the truck. To determine the quantity actually filled, the tank trailer is weighed before and after loading. The delta weight u2013 or quantity filled u2013 is transmitted to the SAP software via an order confirmation. When the delivery for the sales order is created, the software automatically adjusts the order quantity with the confirmed filling quantity.The customer is invoiced for the precise quantity filled and delivered.
    Supply Chain Planning and Execution
    SAP Best Practices for Chemicals supports supply chain planning as well as supply chain execution processes:
    Supply and demand planning u2013 Via the SAP Best Practices for Chemicals package, SAP enables complete support for commercial and supply-chain processes in the chemical industry, including support for integrated sales and operations planning, planning strategies for bulk material, and a variety of filling processes with corresponding packaging units. The package maps the entire supply chain u2013 from sales planning to material requirements planning to transportation procurement.
    Supplier Collaboration
    In the procurement arena, best practices are most important in the following
    Scenario:
    Procurement of materials and services:
    In this scenario, SAP Best Practices for Chemicals describes a range of purchasing processes, including the following:
    u2022 Selection of delivery schedules by vendor
    u2022 Interplant stock transfer orders
    u2022 Quality inspections for raw materials, including sampling requests triggered
    by goods receipt
    Manufacturing Scenarios
    SAP Best Practices for Chemicals supports the following sales and
    Manufacturingu2013related business processes:
    Continuous production u2013 In a continuous production scenario, SAP Best Practices for Chemicals typifies the practice used by basic or commodity chemical producers. For example, in the continuous production of plastic granules, production order processing is based on run-schedule headers. This best-practice package also describes batch and quality management in continuous production. Other processes it supports include handling of byproducts,co-products, and the blending process.
    Batch production u2013 For batch production,
    SAP Best Practices for Chemicals typifies the best practice used by specialty
    chemical producers. The following example demonstrates batch production
    of paint, which includes the following business processes:
    u2022 Process order creation, execution, and completion
    u2022 In-process and post process control
    u2022 Paperless manufacturing using XMLbased Process integration sheets
    u2022 Alerts and events
    u2022 Batch derivation from bulk to finished materials
    Enterprise Management and Support
    SAP Best Practices for Chemicals also supports a range of scenarios in this
    area:
    Plant maintenance u2013 SAP Best Practices for Chemicals allows for management
    of your technical systems. Once the assets are set up in the system, it focuses on preventive and emergency maintenance. Tools and information support the setup of a production plant with assets and buildings.Revenue and cost controlling u2013 The package supports the functions that help you meet product-costing requirements in the industry. It describes how cost centers can be defined, attached
    to activity types, and then linked to logistics. It also supports costing and settlement of production orders for batch and continuous production. And it includes information and tools that help you analyze sales and actual costs in a margin contribution report.
    The SAP Best Practices for Chemicals package supports numerous integrated
    business processes typical of the chemical industry, including the following:
    u2022 Quality management u2013 Supports integration of quality management concepts across the entire supplychain (procurement, production, and sales), including batch recall and complaint handling
    u2022 Batch management u2013 Helps generate batches based on deliveries from vendors or because of company production or filling, with information and tools for total management of batch production and associated processes including batch  derivation, batch information cockpit, and a batchwhere- used list
    u2022 Warehouse management u2013 Enables you to identify locations where materials
    or batch lots are stored, recording details such as bin location and other storage information on dangerous goods to help capture all information needed to show compliance with legal requirements
    Regards
    Sudheer

  • Procuring in barrells - after consumption v want to sell the empty barrel

    Dear all,
                   Here My client procuring chemical in barrels..After consuming the material  they wil sell the empty barrels. How to map this scenario.Pls help me

    Hi,
    Create 2 materials i.e 1 ) chemicals and 2) barrels...
    Now Do the Normal GR for chemicals which are coming in the barrels...
    At the same time do the GRN for Barrels also with 501 mvt type, so that stock of barrels will also go up..
    Now once conumption happens for checmicals....Do the normal sales cycle for Barrels..
    Hope it helps.
    Utsav

  • What are the settings required for QM in procurement

    Hi Team,
    What are the settings required for QM in procurement. I have  set indicator for QM in procurement in QM view in material master.
    I am not clear about  following fields to be maintained in QM view.
    QM Control Key
    Certificate type
    Target QM system
    Tech. delivery terms Indicator.
    Please suggest me in which case to be used this fiels. Is it relivant to Quality Certificates.
    Thanks

    Hi,
    All meaning are
    QM Control Key :
    If you activate the indicator for QM in procurement in the material master record at the client level, you must also store a control key at the plant level for quality management in procurement.
    Certificate type :
    Certificate types applies to the Certificate processing in procurement  &  Certificate creation
    Target QM system :
    whether the vendor's verified QM system, according to vendor master record or quality info-record (for a combination of vendor/material) meets the requirements for QM systems as specified in the material master
    -  If you activate the indicator for QM in procurement in the material master record at the client level, you must also store a control key at the plant level for quality management in procurement. If you want Procurment control then accordingly define Control Key.
    -  If you want Vendor's perticular certificate for Material then you have to define Certificate type.
    Also, you have to maintain Material, Vendor's Info record at plant level.
    Thanks,
    JM

  • Automatic PO from PR [free text base procurement ]

    Hi SAP gurus ,
    I have following question ,
    I am not using material master , it is a free text base procurement .
    even there are no contracts in place .
    Purchasing is only PR - PO w.r.t. & without respect to PR  - GR - IV . etc.
    How can I create a Automatic PO w.r.t. PR ?
    Can anybody please advice?
    Thanks ,
    Prasad

    Hello,
    1. Check auto PO tick in Vendor Master record.
    2. Create Info record for material group which you are going to use in PR. This is important for net price, purchasing group and tax code which will be mandatory in PO.
    3. Assign Source of supply as this info record in PR.
    4. Create auto PO in ME59N t- code.
    Regards,
    Shailesh Mackwan

  • Issue with OOTB Procurement and Spend report on top of W_AP_INV_DIST_F

    We are implementing OBIEE 11g on top of EBS R12. Observed today that AP_INVOICE_DISTRIBURIONS_ALL has a lot of records with PO_DISTRIBUTION_ID as NULL (This is expected as this table holds not only PO but also Expense tyoe invoices). The mapping used to populate W_AP_INV_DIST_F (SDE_ORA_APInvoiceDistributionFact) uses the PO_Distribution_ID to derive Product_ID. Thus, in W_AP_INV_DIST_F a lot of lines exist with PRODUCT_WID of NULL (which is also understable).
    My question is - In Procurement and Spend OOTB reports (for ex - Spend by Top Categories) , it is showing all records from W_AP_INV_DIST (and not filtering to Spend_Type of "PO Matched"). Thus, most of the records is going into the "Unspecified" bucket.
    Any thoughts on why the OOTB report would work like that (This is affecting any OOTB report that is built on top of W_AP_INV_DIST_F and involves products or product categories)?

    Out of curiosity, why do you only maintain 13 months of history in PeopleSoft? I have never heard of this. Dont the business users want to track PeopleSoft before 13 months? With regard to your question, given you are only able to load 13 months on a full load and this is impacting the links to the correct suppliers, you can consider keeping a refresh date on the tasks that load the W_SUPPLIER_D tables. This can prevent reload for the supplier dimension. However, I am not sure how you intend to handle the other dimensions as I assume you will have the same issue. If you only have 13 months of history, BI Apps will only load 13 months of history on a full load. Also for the SCD dimensions, there should be a CURRENT_FLAG that is set to Y only for the current record and there should still be a link to the previous records where CURRENT_FLG = N. As long as your SCD is working fine, and you can prevent the reload of supplier dimension via the refresh date changes, it may work. I would advise your PeopleSoft team to maintain history..esp if they want to take advantage of Analytics and trend analysis.

  • How to create Protein or Chemical structures in .pdb or .mol format for use with iBooks Author. Please help.

    Dear Community,
           There are a large variety of software packages used by Chemists and Biologists to view and manipulate Protein and Chemical structures in 3D. They typically have formats such as .pdb, or .mol. I have looked around and none of the software packages that I currently use allow me to export to the COLLADA (.dae) format.
            Does anyone have any idea where to begin to allow me to do this. I would like to try and put in some of the 3D objects into the iBook Author program.
    Thank you. Chase

    I believe that Apple should have provided an easily way to get Pymol images into iBooks Author as VRML has been the de facto standard.  After a number of days, I have a method which works, but this much effort should not be necessary.  Anyway here it is.
    1)  Set the viewport in Pymol to 512,384 to do this in the command window type
    viewport 512,384
    Note, I'm not totally sure you need to do this.
    2) Draw you image in Pymol and output the image in VRML format, to do that
    File -> Save Image As -> VRML 2 ...
    I'll assume that you have given the file the name "pymol_output", you actual get pymol_output.wrl
    3) In a terminal window go to the folder where the above file is located and issue the following command.  This removes some stuff that messes up the lightening
    sed '9,15d' pymol_output.wrl > bender_in.wrl
    4) Next you need blender.  You can download it from
    http://www.blender.org/download/get-blender/
    5)  Open Blender.  In the upper right corner in the Scene section
    right click on Lamp and delete it
    right click on Cube and delete it
    right click on Camera and delete it
    Save this file so you don't have to do this every time.  I called mine empty_blender_file.blend
    6) Either open empty_blender_file.blend or continue from #5 and read in the file from #3
    File -> import->X3D Extensible 3D (.x3d/.wrl)
    this reads in the file
    7) Write out the file in collada .dae format
    File->export->collada (.dae)
    Done.  This file will read into iBooks Author and have somewhat uniform lighting.  By the way, .dae files can be opened an checked in Preview.  Its easier than going back and forth into the iPad, since you can rotate the image in Preview.
    Hope this helps, let me know if it works for you and if you have any suggestions.
    Finally someone needs to write a one step VRML and X3D to collada converter that will work with PyMol and Chimera etc.
    Have fun!

  • I have a problem with Java and an e-procurement system integrating

    I use an e-procurement system at work and yesterday I could not get my parts list from the suppliers web site to display in our in-house eprocurment finance package.
    There is not a problem with the finance package. There is not a problem with the suppliers web site. I have verified both of these by other colleagues being able to complete what I am trying to do.
    The difference between my version of Firefox and my colleagues' is that I am on version 6.0.1 and they are on 6.0.
    I have had problems with Java not displaying certain animations on the suppliers web site but, my colleague does not and I am suspicious that this is the problem. Can anyone verify this please and what can I do about it. My Java updates are up-to-date as of yesterday and are automatic.
    Thanks.

    I was quite amazed I never got a reply to this, in the past people here have been helpful. In any case I was finally able to enter this website on the exceptions list in the Java panel, and I believe it is okay  now.

  • How can I firce procurement Card settlement in SRM 7.0?

    Hello,
    We are moving from SRM 5.0 to SRM 7.0, and I would like to understand if there is a way to force items to be settled to a procurement card in 7.0 (using an external cataog aggregator). Currently, in 5.0, we have a "P" appended to the end of a product category when they come from the catalog if they are forced to be settled to a procurement card. This means we also have to maintain all product categories twice (once with a P and once without) in COMM_HIERARCHY. we have a BADI in place to force the pro card selection if the product category ends with a "P".
    Is there an easier way in SRM 7.0? We want to replice PO's back to ECC but do not want to have to maintain all product categories twice in both environments!
    Thanks in advance for any help!
    -Eric

    Masa,
    Can you please provide more details on this for me? Is the "Customer Field" the supplier, because we would like to be able to have different settlement methods for each supplier in some cases, because it will be possible to procure items from a supplier for MRO items and settle them to a work order and cost center, while still procuring from that same supplier for non maintenance items that will be paid for with a procurement card.
    Thanks - Eric

  • Service procurement & implementation scenario in SRM 7.0

    Hi Guys,
    I would like to know if in SRM 7.0 the new Service Procurement External Staffing scenario would work in the Extended classic scenario implementation? Or is this only supported in standalone?
    Do we have to custom build the document exchange between ECC - SRM - SUS for confirmation and invoice documents like in SRM 5.0. I am searching for a possibilty to let the service agents themselfs fill in the confirmation with the service entry sheet.
    If the extended classic scenario is supported then we are quickly done. Other possibility is to let an existing web application (to capture time sheets) generate a XML confirmation message and send this message to EBP via XI. This way the hours can also be captured. Invoicing can then by handled e.g. by ERS. What do you think?
    Thx.
    Skander

    Hi Muthu,
    Thx for your response, but these blogs do not provide an anwser to my question. I have read the release documentation of SRM 7.0, but even then I still have the above question.
    Will this business scenario work in combination witht the extended classsic scenario (and how does SUS fits in this picture)?
    Kind Regards,
    Skander
    Edited by: Skander Essaim on Jul 7, 2009 2:12 AM

  • Sales forecasting scenario for production and procurement

    Hello Gurus
    We have currently one scenario  need your inputs and expertise
    We have a requirement for the Sales forecast for the production and procurement planning. More over its like demand planning but sales needs to have a 6 months or yearly sales forecast in the system.
    Is there any option or functionality available for the same.in  SAP-SD
    Thanks inadvance
    Regards
    Venkat

    Hi KV chalapathi
    check this link
    How to maintain Sales forecast or projection in SAP
    hope clear your issue
    Regards,
    Krishna

  • Sale order wise stock and Issuance of external procurement material.

    Transaction : ME21N and MIGO                                           
    Dear SDNites,                                             
    When i make a account assigned PO(with ref to sale order), then material comes and goes directly for consumption.                              
    I want that when the material comes after 105 movt., it should go to un-restricted stock and i can see in mmbe(or any other transaction) how much qty. has come against 
    which sale order, so that i can issue material also sale order wise by movement 231                                                                  
    Pls. help as to how to go about it.                                    
    Rgds.,                                                    Parag                                                     09815999582.

    Hi,
    When you are trying to create PO with reference to SO what is the item category used in SO, Use item category as "TAB" then SO will generate a Purchase Requisition. Convert this Purchase requisition in to Purchase Order, account assignment will be copied as "E Individual Customer stock" Sales order and Cost element will populate from PR.
    When you post the GR for above PO, the stock is managed as Special Stock indicator "E" sales order stock, in MMBE also it displays as SO stock.At the time of GR value is booked to SO and stock will be shown in MMBE.
    This stock is reserve for particular SO against which you have procured, but you can transfer post the same from SO stock to your OWN stock
    Hope this clarifies,
    Thanks & Regards,
    Sridhar

  • Advance Procurement through Sale Order

    Dear All,
    I required detail infromation pertaining to advance procurement of ROH items against sale order. If manual Purchase requisitions are being created by assigning sale order as account assignment, exception-20 is coming. I also like to inform project system is n't used. Your earliest reply is highly appreciable.
    Thank you in advance.
    Best Regards,
    Ranjan

    Dear Biplap,
    Exception Message 20 is Cancel process, meaning the system is directing the relevant person to delete the requirement in order to avoid excess inventory. 
    This is bound to come, since u have not run MRP but you are manually procuring the material.  This need not be a point of concern as long as u are aware that the material and qty in consideration is what u require.  Once u run the mrp at a later date, the exception message will change based on the planning results.
    The exceptional messages will not stop you in any of your transaction but it is only a message for the MRP controller to take corrective action, if need be.
    reg
    Kiki
    Award points if this helps.

  • How do the Procurement of materials from projects?

    Hi Friends'
    How do the Procurement of materials from project s, here our Process is:
    Whenever our engineers on site see any shortages he will send a report thro our customized InfoPath request form. Then we decide depending on the material whether to order to USA or Procure locally. Some mechanical parts we procure locally. For this in PR we give reference of WBS element. Purchase department raise PO, we receive material, sent to site And finally we charge USA(parent Company)  for this amount against this project.
    For the items like electronic cards, Critical mechanical parts to be ordered to USA we send the InfoPath form to USA. We get weekly shipments from USA. We create PR and also PO. No action by our purchase dept. The FREE OF CHARGE (FOC) material is received to us. Stores will do MIGO and then we dispatch to Site.
    Friends please suggest how to do this Process through project systems. I need the entire configuration setting that we need to do and the process also, plz friends... I need these settings step by step.
    Regards,
    Hari
    Edited by: Hari  Krishna on Jan 3, 2009 12:39 PM

    suggest attend course PLM220
    If using only WBS then you have to raise PR from MM module and the material demand will not be driven from PS (except Easy Cost Planning)
    If using networks then assign material component to network activity and set the item category as non stock item - this will trigger PR from activity

Maybe you are looking for

  • Help needed Regarding a business logic

    Hi all, My business requirement is requires to get a checksum from the KIOSK field. This would be something like a rule that for a given KIOSK generates a number from 0 to 9. The Field value contains alphanumerical Can any of guys help me in this log

  • Missing sender information in message from BPM send step

    Hi All, I am testing a scenario uses Integration Process. This Integration process sends out a async message from deadline branch, but this message has empty sender service. Am I missing something in configuration? Please let me know how can i config

  • How do I text on my ipad mini with data

    How do I text with an ipad mini.  I have a data plan and want to text other platforms as well as iPhones.

  • Clearing out my MacBook

    Hello, I am getting a PC TEMPORILY... OMG I KNOW!!! I would like to know the procedure on how to get all of my files off of my Mac and onto a DVD so that I can transport the data to the new computer. Thanks in advance.

  • All Templates in Spanish!?

    I just got my Macbook... when i started playing with iWeb I realized that all the Templates are in (what appears to be) Spanish. I then checked my Pages trial and the temps are also in Spanish. Why? I'm assuming I clicked somewhere and made it spanis