Hello all SAP Controlling Expert,
I would like to know, is there some configuration of CO module that related to PP order completion status process?
Such as  if PP order status is ...... CO Process can be continued or can not continued.
Thanks in advance for your help.
Kon

Hi,
   Please read notes 530563 and 743766 for information on this issue.
regards
Waman

Similar Messages

  • Serial number related sales orders???

    Hi everyone,
    i got this problem when i try to use serial number of an equipment to search all related sales orders.
    in our company it is defined that serial number would be created in the first sales order, when the customer purchase the configurable products at the first time.--- we call that initial sales.
    then after months or year, customer could come again and buy upgrades or addtional options on that products(we can select serial number to locate that machine in the configurator in sales order)--- we call that following up sales.
    so, now the situation is, i can call TA IQ03 to see the equipment and through reference to find the initial sales order, HOWEVER... if i want to have an overview of all Equipments related following up sales, Is that possible ??? or at least the last following up sales which determine the configuration status in the service equipment.
    i dont see any info about that in IE03 or IQ03, is that to be found in any tables, if i would rather write a small report to do that?
    the only way i can figure out now is to check the configuration of sales orders, maybe through VBAP-CUOBJ then call function to get the serial number... is there any other way?
    thanks a lot !!!
    yunfan
    Edited by: yunfan Wang on Feb 11, 2012 5:02 PM

    hi, Ncvajja:
    First thanx for ur instant reply.
    i would try ur way on monday, but as i assumed,
    the method u mentioned may be correct in those companies where the serial number is automatically created by delivery. (as i remembered, the table SER01 is for delivery)
    however in our company the serial number is saved in SER02, which are order related, that means the serial number is automatically created after the sales order is created.
    so in this way, i only find the first order through SER01 or 02, no matter it is delivery or sales order, but what i want is the sales order after that. in the following sales process, the serial number is already there for selection...
    anyway, those above is only based on my knowledge, iif i was wrong about this, hehe, please tell me, i am quite junior in this area...
    thanx

  • DONE button is not working in Oracle Configuration page in Order Management

    Hi,
    We are in 11.5.10.2 application, In order managemnt DONE button is not working. Once we choose all the options and click on DONE button the configuration page is not closed.
    Please help us to come out ot this problem.
    Thanks
    Krishna

    Hi,
    We are in 11.5.10.2 application, In order managemnt DONE button is not working. Once we choose all the options and click on DONE button the configuration page is not closed.
    Please help us to come out ot this problem.
    Thanks
    Krishna

  • How to configure third party order ?

    how to configure third party order ? and how the business know that the customer has received the goods so that invoice to be raised?

    hi shoban,
    Third party order processing is as follows:
    Assume three companies X, Y and Z
    X - The company,
    y - The customer
    Z - Vendor
    When ever X gets a PO from Y to supply some goods, X has an option of either manufacturing those goods or procuring those goods.
    If he is procuring the goods, there are two methods that are generally followed:
    Method 1) After receiving the PO from Y, X creates a sales order against Y.
    Now at the same time he also creates a PO to a vendor Z to produce the goods
    Z produces the goods and supplies to X
    X receives the goods from Z
    Then X delivers the same goods to Y.
    After that X invoices Y and Z invoices X.
    Note : Here there is no direct/ Indirect relation between Z and Y.
    This process is known as Trading Process. and the Material here is created  with Material type HAWA.
    The other method is a Third party order processing method:
    Here the glaring difference is that instead of Z supplying the material to X and X in turn supplying the same material to Y.
    X authorizes Z to supply the material to Y on his behalf and notify him once the delivery is complete.
    Now Z supplies the material to Y and acknowledges the same to X.
    Z  will send a copy of delivery acknowledgement and invoice to X.
    After receiving the delivery confirmation and invoice from Z, X has to verify the invoice and this process is known as invoice verification and is done in SAP through Tcode MIRO.
    The next step for X  is to create an invoice and submit to Y
    Only after the invoice verification document is posted  then only X can create an invoice for Y.
    This is the business flow that is followed for third party order configuration.
    There are few steps that have to be configured to enable the system to function as mentioned above.
    Step1)
    If you are always followwing a third party process for a material then you have to create the material using item category group BANS.
    The procument type should be marked as External procurement (F) in MRP 2 view of the material master record.
    if you are not always allowing third party order processing then u can create a material master record with item category group as NORM and the procurement type should be marked as ( X) meaning both types of procurment ( in house manufacturing and external procurement).
    step 2)
    the item category in the order should be manually changed as TAS.
    For that you need to confugure the item category determination
    ord type + item cat grp + usge + Hiv level = Item cat + Manual item cat
    OR + NORM +      +       = TAN . + TAS
    OR + BANS +       +       = TAS
    Step 3)
    make sure that during the item category configuration for TAS  you need to mark relevnat for billing indicator as F
    step 4)
    The schedule line cateogry for this type should be CS.
    make sure that you mark  subsequent type as NB - purchase requisition  in this schedule line category as this will trigger the purchase requision order immediately after the creation of the sales order and the PO to vendor is created against this purchase requiesion.
    Hope it helps
    Mastan

  • Regarding production order closing and demand closing

    Hi Gurus,
    I am new to pp module..
    I have the requirement on production order closing and demand order closing.
    The requirement needs plant,reuirement plan no ,basic finish date and percentage in selection screen.
    In the output display plant,requirement plan no,PIR No,order,order finish dat ,***.order qty,***.delivered qty,qty difference,percentage%,order status as in alv grid display.
    And in the output it has 2 buttons named technically complete and demend close .whener user click on first button system should take all the orders which r selected to the program with the same reuirement plan as for the selected order and then technically close all the orders with the same reuirement plan number.
    when user clicks on demand close button,system should take the respetcive requirement plan number,order finish date and material and it has to take the pir no which match the above and deactivate the pir and save.
    I need the help about this.
    Thankx in advance.

    Dear Chandu,
    First settle the production order using the T Code CO88,and then close the production order.
    Prerequisites
    Prerequisites for setting the CLSD status are:
    The order must have the status Released (REL) or Technically completed (TECO)
    The order balance must be 0
    There can be no open purchase requisitions, purchase orders or commitments
    There can be no future change records from confirmation processes
    Regards
    Mangalraj.S

  • Configuration related to PO colabration in ECC and SNC

    Hi
    Can anybody throw light configuration related to PO colabration in ECC and SNC.
    Regards
    Raj

    Hi Raj,
    Below link provide you SNC information about Integration ECCPISNC and functionality of SNC
    link http://help.sap.com/saphelp_snc70/helpdata/EN/b4/f20483605b0d4fa856354a986e900d/frameset.htm but if you want configuration document then Click on below link
    http://help.sap.com/bp_bblibrary/500/BBlibrary_start.htm
    A07_BB_ConfigGuide_EN_DE.doc (Kanban processing)
    S32_BB_ConfigGuide_EN_DE.doc (SCM setting)
    S34_BB_ConfigGuide_EN_DE.doc (Supplier)
    S55_BB_ConfigGuide_EN_DE.doc (Contract Manufacturing Procurement)
    hope this documents are useful.
    Thanks,
    Nikhil

  • IDoc Configuration for Production Order Creation and Change

    Hi All,
    Please Help me out for IDoc Configuration for Production Order Creation and Change
    I have found the IDoc for Production Order
    Messgae Type : LOIPRO and IDoc type : LOIPRO01
    Actually my requirment is to send the (LOIPRO01 )IDoc from SAP R/3 to XI system ,when ever the Production Order Created and Changed,
    I have done following Configurations:
    1. RFC Destination created for XI system
    2. PORT was created for XI
    3. Partner profile created WE20 and LOIPRO01 IDoc is added in OutBound Perameter.
    I need to know how to do the followning.
    1. How do i configure the outbound Production order idocs when Production Order is created or changed.
    2. in NACE (Output control) which is the Application for Production Order.
    3. How can I set IDoc as output Type for Production Order Creation.
    Thanks in advance
    Dhanabal T

    Hi Michal,
    I know that it is the old thread but still want to get clarified from you out of curiosity.
    Unlike other IDOC, i actiavated change pointers for LOIPRO
    1.message and idoc type is linked
    2.function module , message type , idoc type is linked
    function module used is CLOI_MASTERIDOC_CREATE_LOIPRO
    3.BD64, distribution model is created and distributed
    4. port and partner profile is in place.
    5. IDOC is not getting generated after creating the process order.
    do we need to activate the change documents for the message type in BD52,
    if yes can you please provide the object types for the same.
    or i am missing something else. please guide me in this regards.
    Thanks in advance for your time.
    S.Janagar

  • FI configuration related to HR

    Hi All,
    What's the FI configuration related to HR? Really appreciate your help.
    Thanks

    Hi,
    You create wage types. How do you understand wage type For example your basic pay is a wage type in this way you created all the wage types in the salary structure. Then you create symbolic accounts they are nothing but type of accounts whether it is an expense account,receivable or payable. You assign wage types to symbolice accounts and inturn symbolic accounts are assigned to FI GL accounts. This is FI - HR integration.
    Thanks,
    Giridhar

  • ATP,confirm quantity for Purchase Order related Sales Order

    Hi everybody,
    I have purchase requisition related sales order item. I created purchase order with this PR.
    I entry confirmation date and quantity on the PO.
    Sales order item's delivery date equal to purchase order item's confirmation date.
    Sales order item's confirmed quantity eq purchase order item's confirmed quantity. It is ok for me.
    But, goods receipt not do yet for this purchase order and sales order stock = 0.
    If I run VL10N for this sales order, I can create delivery.
    I wants to see availilable sales order stock item on the VL10N items. How can I see?
    or
    If no goods receipt for sales order items then sales order item confirmed quantity can equal 0. How can I do?
    Best regards
    Gulay Celik

    Hi
    You can meet your requirement in multiple ways
    1) Modify the requirement routine for copy control from Sales order to Delivery  that DO not create the delivery for third party orders unless the GR is posted for the respective sales order.
    2) IF you have implementded Inbound Delivey functionality in your system, You can change the availabiltity situation every time you modify the GR dates and times. Modify the PO user exit that when ever a new confirmation Key LA is entered in the purchase order it goes and updates the schdule line dates and quantities in the order based on the dates entered in the LA confirmation key.
    and even if delivey gets created also what is the problem ? The GI cannot be posted though unlsess there is sufficient stock.

  • ECC Report showing Outline Agreements WITH related Release Orders

    Does anyone know of a report in ECC which will display all Outline Agreements together with all the Related Release Orders associated with each Agreement Number?
    I have trawled through hundreds of SAP transaction codes and cannot find something that will give this information - I can use ME3N of course, but ideally my Users want to be able to search on ALL Outline Agreements and see the associated release orders
    If anyone is able to help it would save me a headache!
    Many thanks
    Jane

    You can get Goods Movement from MSEG Tables. Why do you need Goods Movement in Sales Flow?
    While Creating Every Document in SAP R/3, we will put reference Document and Item.
    While Creating Sales Document, Customer PO is reference Document.
    For Delivery, we can create againest Sales Document or Invoice etc.
    For Invoice, either Delivery or Sales Document.
    Pull all the Data Sales, Delivery, Billing and Shipping with Reference Documents into ODS.
    You need to create a Infoset on these ODS.
    Let me know if you still have any Questions.
    Nagesh Ganisetti.
    Assign points if it helps.

  • How to report Invoice details and also the related Purchase order details

    Hello,
    Any suggestions on How to Report both Invoice details and the related Purchase Order details.
    Ex:
    INvoice Line items Amounts /Qty
    PO Line Items Amounts /Qty
    Thanks in advance
    Jagadish

    Hello,
    Any suggestions on How to Report both Invoice details and the related Purchase Order details.
    Ex:
    INvoice Line items Amounts /Qty
    PO Line Items Amounts /Qty
    Thanks in advance
    Jagadish

  • Want to display no. of ser. orders closed with in 1 day and outside 1 day

    Hi Experts,
    Im displaying a summary report for Closed call.
    I want to display the Number of Service Orders Closed With in 1 day and Out side 1 day.
    For example:
    Brand......ASP...................With in 1day...............................Outside 1 day
    ABC1........ALPHA Tec...........24................................................5
    BCD2..........BETA Tec.............76................................................7
    The difference of days I have brought using 2 variables (1. is for closed date and 2. is for service order created date)
    In the Formula Variable I have (Subscrated Closed date - Created Date)
    I'm not very sure how to bring the count of the service order that are closed with in 1 day and outside 1day.
    Please help.
    Thanks

    Hi,
    This could be achieved through Data model level as well:
    1. By assuming you have two date char Created date and closing date.
    2. Create a char (On-time) flag and populate flag by ABAP coding if Closing - Created = 1 then field should be Check ("X").
    3. Restrict your report with this Flag to find out number of Service orders on-time.
    4. Define a counter KYF in your data model and maintain fixed value = 1 in your cube / ODS.
    This is one approach let me know if any further information is required.
    Regards,
    Venkat

  • Production Order   : OUTPUT Type Configuration for Production Order  as EDI

    Dear SDN All ,
      OUTPUT Type Configuration for Production Order.
    <b>Doubt in third Point</b>
    We have found the IDoc " LOIPRO01 " for Production Order
    (Please confirm that this IDoc can be used for outbound IDoc for Production Order)
    And foloowing
    <b>1. Defining the Output Type for Particular Application.
       T-Code: “NACE”</b>
      A. Output type have created upder application "ME" description : "Inventory Management"
      B.  " ZEDI "  created for getting output as EDI type
         ZEDI is copied from "WF01" output type. and
         Transmision mediam as "EDI"          
         Program : RSNASTED
         Form Routine :  EDI_PROCESSING
              (Please confirm is this for IDoc creation)
    <b>2. Partner profile creation:</b>
      A. Partner profile created under logical system and
      B. and In outbound parameter declared as "LOIPRO"(This is for sending the IDoc "LOIPRO01" to XI system).
    <b>3. Customization for output type for Proction Order -- (For CO02,CO08)</b>   ---
       A. But only one functional customization is remaining to do, for getting the IDoc while saving the Production Order in T-Code "CO02" and "CO08"
            <i>For Example:
                in sales order transaction va02 (in DBI 450 client) and select any Sales order.
                & select following menu path.
                 Extras --- > Output -
    > Header -
    > output
               Here we can set our output type "that U defined in NACE Transaction-Code"</i>
    <b> Like the same way I want to set output type  for CO02, CO08 transaction.</b>
    But I couldn't find the menu Item in Co02 and Co08 for setting the output.(like VA03)
    Please help me out for setting the output type for Production Order Creation.
    Thanks in advance,
    Dhanabal T
    Message was edited by: Dhanabal T

    Hello.
    I have a similar requirement. Did you guys find the solution?

  • Order Management Implementation - Configurator and Move Orders

    We are in the process of implementing Order Management (11i) version. We have been facing the following issues:
    a. Configurator button on order lines form does not open for PTO models - we are not using the Oracle configurator, but are interested in manually choosing the options during Order entry - the form does not open, despite the fact that we have set up the profile,BOM:Configurator URL of UI Manager, as per the suggestions of Oracle.
    b. Issues around using Workflow for Move orders - basically, suggested set ups in Organization parameters have been done, but do not see specifically that the workflow process has been started, when saving a move order.
    Does any one been successful in getting through either of the issues - any input is highly appreciated.
    null

    we did face the same problem whes the configurator button was pressed nothing opened up. We applied patch set B and that took care of the problem.We are going to use Oracle Configurator and not BOM bit do have configurator developer installed yet, so are creatinf bills in BOM and selecting the model to order through the sales order screen and choosing the options etc by clicking on the configurator button.The order gets saved but does not gets over to receivables as the workflow process that needs to be run(as per oracle) does not seem to be doing anything at all. There are so many bugs especially in OM that it would take sometime for it to stablize.
    Let me know if you need to the specific things that we did to make the configurator screen to appear.

  • Material Variant configuration in sales order line item from Ztable

    Hello Experts,
    we have configurable material and and creating sales order. from sales order line item if we goto configuration we can maintain variant configurations. My requirement is that when i click on configuration after selecting a line item i need to check ztable where i have material no and and relable text. if an entry exists i have to populate this relable text in one of the configuration filed. Can any one help how can i read and update configuration in sales order level and where to do this coding so that when i click on configuration the value from ztable populated in a field.
    Many thanks in advance.

    Hi Senthil,
    It is simple.
    When you create a characteristic which should have the value maintained in the Z table, go to the tab values. Here you have a push button called "Other Value check". Here you click this button and select the function module option. Now, in the window, you will have a place where you can mention the name of teh function module.
    You create a function module with the help of your developer to find out the text maintained in the Z table using teh rules you have in your mind and update that logic in the characteristic. In the earlier screen, you just have to mention the name of the function module, thats all, your work is done.
    Now when you configure, for this characteristic, the value will be automatically determined using teh function module. You have to create such characteristics as "Not ready for input" ones in additional data for which you cannot enter values manually.
    Hope this helps.

Maybe you are looking for