Correct receipts for PO which is finally closed

Hi Sir,
What's the steps to correct receipts for POs having status of "Finally Closed"?
I look forward to hearing from you soon.
Kind regards,
James

James,
Once a PO is finally closed,Correction can not be done. If you really want to correct the PO in any way, then you need to reopen the PO using data base update script & then correct the PO.
Regards,
Jyoti

Similar Messages

  • Goods Receipt for Material which has no Standard Price in Process Order

    Hello everyone, is there a way by which we can prevent GR for process order which contains material that does not have standard price? And if ever we received material using process order how can we correct the process order right after we correct the standard price.

    Hi,
    i just don't know why you raised new thread as already ur previous thread is not closed
    Now just let us know whether system is throwing any error
    or what exactly happing in cofirmation screen
    Go to OPK4, here
    under goods movement there is option all components  just tick it
    then in second tab Gen individual entry tick Goods movement & termination for incorrect goods movement
    Coming to GR
    what is storage location ur giving
    just check in MMSC, whether this storage location is activated for the header material ( GR )
    Added
    Plz Go through all possible options
    [Auto GR is not happening.;
    Regards
    kumar
    Edited by: kumar kumar on Nov 10, 2009 2:25 PM

  • The receipt corrections form for PO does not recognize LPs

    Hi
    The receipt corrections form for PO does not recognize LPs to perform corrections. The LPs are currently in Subinventory, we have lpn numbers, through that i have found the on hand quantity and which are in Packed Condition ..What would be the reason ?

    Tim
    We created a new report that is XML-PDF. This was a copy of the seeded Oracle Purchasing report. This report uses a new XML document that generates a PDF. If I submit this new report the PDF document is created and viewable. In Purchasing I also set the default output to PDF using the same XML - PDF that we created. I have an open TAR with Purchasing (5553373.992) they support the seeded Template but want to wash their hands on the custom.
    I am not sure what your question is - "new PO process in 11.5.10". When I do a PO approval and generate an email - PO it kicks off automatically the PO Output Communication program based on the defaults I set in Purchasing it should be using the new tmeplate.
    Bob

  • I connect my ipad it shows in left side of itunes it is commencing sync then it freezes itunes  and i have to disconnct it  manually then  a error message telling me that there is not enough disc space for ipad which is not correct  any ideas folks

    i connect my ipad it shows in left side of itunes it is commencing sync then it freezes itunes  and i have to disconnct it  manually then  a error message telling me that there is not enough disc space for ipad which is not correct  any ideas folks

    i have reset the ipad and restored it to no avail

  • How do I get a receipt for final cut x

    How do I get a receipt for final cut x?  I paid for it to use at work and I cant claim the cost back unless I have a receipt.  Apple cant claim it is an app for personal use when they are pitching this software for professional editing

    Did you make the purchase? They should have sent you an email when you purchased it to confirm the transaction or something. That should include some sort of receipt.
    It is for personal use because not only businesses use it, individuals use it too for independent YouTube channels, etc.

  • HT201210 which version of ios 6 beta is the correct download for ipad3 wifi+celluar ... within the uk.

    hello, which version of ios 6 beta is the correct download for ipad3 wifi+celluar ... within the uk.
    many thanks
    stuart

    i do apologise - i am a developer an have succesffuly installed all beta on my current devices... but i live in the uk, and do not have the verizon or att network, so therefore could not find the correct download for my ipad3...
    i have emailed support but no response
    stuart

  • Which are the correct settings for gmail in MacBookPro

    I want to use mac mail to access my gmail. Can I  ? instead of going directly to web to access my gmail.? Which are the correct settings for the incoming and outgoing servers ?

    Hi,
    Yes. You can absolutely access your Gmail account from within either Mail or Microsoft Outlook for Mac. Make sure, that you have enabled POP/IMAP in your Gmail settings, then follow the instructions here: http://mail.google.com/support/bin/answer.py?hl=en&answer=180188 if you wish to access your account via POP3 instead of IMAP, change the incoming mail server to pop.gmail.com
    Regards,
    Gábor

  • [svn] 4241: A collection of minor fixes for FXG transcoding to SWF: matrix attribute name correction; allowing for 0x prefix for hexadecimal colors; allowing for an id attribute on FXG nodes; fixing blur filter quality encoding; fixing the order in which

    Revision: 4241
    Author: [email protected]
    Date: 2008-12-05 11:00:45 -0800 (Fri, 05 Dec 2008)
    Log Message:
    A collection of minor fixes for FXG transcoding to SWF: matrix attribute name correction; allowing for 0x prefix for hexadecimal colors; allowing for an id attribute on FXG nodes; fixing blur filter quality encoding; fixing the order in which bevel filter colors are encoding - the SWF specification appears to have the wrong order specified; updating SwfxPrinter to display a linestyle's fillstyle (if present).
    Temporarily removing generated id attribute emitted in FXG to SWF optimization as this attribute is not present in the AS impl.
    Also updating compiler error base types to allow a rootcause to be specified for additional detail to a compiler message exception.
    QE: No
    Doc: No
    Checkintests: Pass
    Reviewer: Discussed compiler base error change with Paul.
    Modified Paths:
    flex/sdk/trunk/modules/compiler/src/java/flex2/compiler/CompilerException.java
    flex/sdk/trunk/modules/compiler/src/java/flex2/compiler/as3/EmbedEvaluator.java
    flex/sdk/trunk/modules/compiler/src/java/flex2/compiler/util/CompilerMessage.java
    flex/sdk/trunk/modules/swfutils/src/java/flash/fxg/FXGConstants.java
    flex/sdk/trunk/modules/swfutils/src/java/flash/fxg/dom/AbstractFXGNode.java
    flex/sdk/trunk/modules/swfutils/src/java/flash/fxg/dom/TextGraphicNode.java
    flex/sdk/trunk/modules/swfutils/src/java/flash/fxg/swf/AbstractFXGGraphics.java
    flex/sdk/trunk/modules/swfutils/src/java/flash/swf/TagDecoder.java
    flex/sdk/trunk/modules/swfutils/src/java/flash/swf/TagEncoder.java
    flex/sdk/trunk/modules/swfutils/src/java/flash/swf/tools/SwfxPrinter.java

  • [svn:fx-trunk] 11595: Checking in Sujata' s fix to FXGUtils for SDK which handles implicit close paths correctly.

    Revision: 11595
    Author:   [email protected]
    Date:     2009-11-09 16:34:49 -0800 (Mon, 09 Nov 2009)
    Log Message:
    Checking in Sujata's fix to FXGUtils for SDK which handles implicit close paths correctly.
    QE notes: Please retest bug test case.
    Doc notes: N/A
    Bugs:
    SDK-23093 - Unclosed path in static FXG displays with horizontal glitch
    Reviewer: Sujata
    Tests run: Checkintests, Bug test case
    Is noteworthy for integration: No
    Ticket Links:
        http://bugs.adobe.com/jira/browse/SDK-23093
    Modified Paths:
        flex/sdk/trunk/modules/fxgutils/src/java/com/adobe/fxg/swf/FXG2SWFTranscoder.java
        flex/sdk/trunk/modules/fxgutils/src/java/com/adobe/internal/fxg/dom/GraphicContentNode.ja va
        flex/sdk/trunk/modules/fxgutils/src/java/com/adobe/internal/fxg/swf/ShapeHelper.java

  • TS1424 I just received a receipt  for  Flo Rida whom which I never purchased.  How do I get this resolved? Please help...  Thanks

    I just got a receipt for some thing I have never purchased.  Please help.   It was for Flo Rida???  How do I fix this?  And can u tell me where and when it was purchased?  Thanks, Michael

    Hi,
    See Here to Contact iTunes Customer Service:
    iTunes Customer Service Contact
    http://www.apple.com/support/itunes/contact.html
    Support iTunes
    http://www.apple.com/support/itunes/

  • Finally Closed setup control in Purchasing

    Hi All,
    Is there a way to disable users from "FINALLY CLOSING" PO's. If so what is the procedure to do that? Is that something done in workfloww????
    Any Ideas?
    Thanks,
    Prathima

    For some reason I couldn't edit my first message which I sent out accidentally before it was complete.
    Here's the full version:
     Greetings,
    I use a stepper motor with timing belt to enable linear motion in an axis. I can get real time absolute linear position information with the help of linear sensors and convert them to actual step data using math operations. I was trying to find a way to feed this data back to the VI that moves the motor and create a closed control loop using LabView (not MAX). Overshoot and multiple pull in's are not a problem as long as the final position is correct (or within a certain tolerance). I was wondering if it was possible to feed the actual step data (which I received and calculated from linear sensors) to Movement VI's in LabView as "desired position" value? Is this possible? If not, does someone have another suggestion?
    Thank you. 
    My setup is as follows: PCIe 6321 and BNC 2110 for position measurement
    PCI7332 and UMI  7772 for motor control

  • OSS note 1044741 contains no correction instructions for 46C.

    I am trying to apply OSS note 1044741 to fix BC Set creation for deleted table entries. However OSS note 1044741 contains no correction instructions for 46C. Please provide assistance.
    Bruce Reeves

    Dear Bruce,
    How to raise an OSS note:
    In service.sap.com, choose Keys and Requests -> Development Requests -> Create Development Request
    The Create development request form appears. It is divided into the sections described below:
    Classification
    In the 'Classification' section of the form, you can classify your request by selecting various criteria from the listboxes. This information is used for reporting purposes and to assign your request to a processor at SAP.
    Reporting unit is only displayed for information. It defines if you enter the request for yourself, on behalf of a Customer Competence Center (CCC), of a customer, or of a user group. Which entries are available depends on the organization you are working for.
    Priority defines the priority this request has for you.
    Industry is only displayed for information. This is the industry of your company.
    Other Industry allows you to select further industries if the request refers not only to your industry. To select more than one industry, hold down the <Ctrl> key and select the desired items by clicking on them.
    Component defines the application component to which your request applies.
    Core release defines the R/3 release you are currently working with.
    Add-on defines, in case the request applies to an industry solution, the specific add-on release you are currently working with.
    General provides generic features for a better classification of your request. If you wish to define more than one category, hold down the <Ctrl> key and select the desired items by clicking on them.
    Cross-component provides cross-component features for a better classification of your request. If you wish to define more than one application, hold down the <Ctrl> key and select the desired items by clicking on them.
    Only relevant for country allows you to specify that your request is only relevant for the selected country.
    Personal classification by requestor
    In the 'Personal classification by requestor' section, you can add your own classification criteria to the request:
    Classification 1 - 3: allows you to specify your own features, e.g., "Project xyz". You can enter any text up to 30 characters in these fields.
    Description
    In the Description section of the form, you can describe in detail the feature you request for the SAP software.
    In the Language field, select the language in which you are describing your request. For processing at SAP, all non-English requests will be translated into English.
    In the Short text field, enter a meaningful title for your request.
    The Long text field is mandatory. Use it to describe your request in detail. Even if you attach external description files, please enter a detailed description here.
    The Business need field is mandatory. Please use it to explain why the requested feature is needed for your business.
    The Example field is collapsed by default. Click on the plus symbol to the left of the field to expand the entry field, and enter an example for the requested feature.
    The Current workaround field is collapsed by default. Click on the plus symbol to the left of the field to expand the entry field, and describe which procedure you currently use instead of the requested feature.
    The Proposed solution field is collapsed by default. Click on the plus symbol to the left of the field to expand the entry field, and describe how you propose to solve the issue related to your request.
    Attaching documents
    You can also attach files that further describe your request, for example, documents or presentations. All file types supported by this site can be attached, this includes all popular Office formats.
    To be able to attach files to your request, you must have the Check In Wizard program installed on your computer. Otherwise, an error message will be displayed. If you do not have the Check In Wizard installed, click here to start the installation
    NOTE:
    This will automatically save your request with the status New. The request will, however, not yet be sent to SAP. If you have not yet filled in all required fields, the system will prompt you to do so before you can add an attachment. The attachments will be listed only after you have saved or sent the request.
    To attach a file, choose Add attachment.
    The Check in Files dialog box appears.
    Select the file you want to attach, and choose Open.
    A status dialog box appears. When the status The check in process has completed successfully is displayed, confirm with OK.
    The file is now attached to the development request.
    Repeat the above steps for any additional files, if required.
    Saving the development request
    When you have entered all required data you can save your request. To do this, choose Save. You can then edit the request and send it to SAP later. This allows a company or user group to internally manage, discuss and consolidate its development requests before it decides which development requests will be sent to SAP in the next step. (Development requests that are no longer relevant can be set to status Closed by author).
    Sending the development request to SAP
    When you have entered all required data, you can alternatively send the request to SAP immediately. To do this, choose Sent to SAP. You need a special authorization to use this function. If you had saved a request before but not yet sent it to SAP, you can send it to SAP later using this function.
    Resetting the request form
    If you make a mistake during data entry and want to reset all entries to the values they had when you opened the form, choose the Reset button.
    Closing the request
    If you find that you no longer need the request, you can close it. In this way, you specify that no further processing of the request is necessary.
    To close the request, choose Closed by author.
    (After closing, confirm the request to remove it from your inbox.)
    Confirming the request
    Confirm the request if you have received SAP's final decision. The development request will no longer be shown in your Inbox.
    To confirm the request, choose Confirm.
    You will find the answers in your SAP inbox.
    Visit the following link for information regarding SAP Notes:
    http://help.sap.com/saphelp_nw04/helpdata/en/b8/3cf839fd35384de10000000a11402f/frameset.htm
    Hope this will help.
    Regards,
    Naveen.

  • Value of inventory after Goods Issue, before Goods Receipt for open order

    Dear Experts,
    Raw materials R72 and R82 are required to produce Semifinished Product S10.
    Semifinished product S10 is required to produce Fnished product F20
    On 10th August 2011, I created and release a Process Order for material S10 copying component materials R72 and R82.. Goods issue for component materials R72 and R82 were done for this process order using tcode MIGO (mvt type 261).
    It  takes four to five days to properly blend components R72 and R82 to obtain S10.
    It means Goods Receipt for this process order will be done on 14th or 15th August when this blending has been completed.
    Management suddenly issues a directive that stock take should be carried out in the plant on the 12th August 2011, and my process order is still open and cannot be closed ( or goods receipt cannot be done)  because blending is yet to be completed.
    Please how do I take care of this scenario/situation since Goods Issue has been done already?
    How will the Accountants see or get the correct value of inventory?

    When I run WIP Calculation for my Process Order, what will be the effect ? I mean what accouts are updated by WIP Calculation within a period (not across a perion or  at period end)?
    GI values issued to the Process order will come into WIP GL .( Since your client want to know the stock take should be carried out in the plant on the 12th August 2011- we are doing WIP calculation)
    > After  this WIP Calculation is run,  and say about 2days later, Goods Receipt for this process order is to be posted, what steps am I suppose to carry out?
    After GR Made, Run a WIP calculation again for the order so that The WIP from the GL account will get reduced ,now WIP= (GI value + confirmation ) -(GR Value),
    Check in DEV system before doing in PRD,
    On Month end, do the variance calculation and do the settlement

  • Message no. RU 195:Automatic goods receipt for order 619271463 is not possi

    dear expert:
    when i confirm the production order via co15  ,sytstm prompt :
    Automatic goods receipt for order 619271463 is not possible
    Message no. RU 195
    Diagnosis
    Order 619271463 contains several operations, which have a control key which indicates "automatic goods receipt".
    However, an automatic goods receipt is only allowed once per order for the following reason:
    If the automatic goods receipt is posted more than once, this would lead to incorrect stock quantities.
    Procedure
    Check the control keys of the operations in order 619271463. Change the control keys in such a way, that an automatic goods receipt occurs for one operation only.
    production order is confirmed  but it cann't be delivered automatically.
    help me analyse it .
    best reagards.

    Hi,
    In normal scenario in a production order each routing operation will consist a control key with settings for automatic goods reciept.
    So in a production order you can use only one control key with automatyic goods recipt. This will be the last operation of the order. From message mentioned by you it is showing as may u have mentioned auto goods reciept for more than one operation.
    PP01 is normal confirmation control key & PP99 is for milestone with auto goods reciept. PP95 - w/o milestone with auto GR.
    Please check control key & correct it.
    Hope this will help you.
    Regards,
    Ashish

  • Goods receipt for subcontract does not erase requirement in MD04

    Hi,
    I have a subcontract material for example X which is built of 3 components - A,B & C.
    Initially the BOM in the Purchase Order of X did not have any component. I mistakenly posted a goods receipt and realized that the requirement were not getting deleted from MD04 of the components. There after to correct this, I reversed the goods receipt and populated the BOM with components A, B & C and again posted goods receipt for the subcontract material X.
    When I receive material X, the requirement still exists in the stock requirement list (MD04) of A, B & C.  I also went to Transaction ME2O and saw that the stock at the vendor did not get reduced.
    I have checked the Goods Receipt material document and the components A, B & C have a movement type of 543 O. In MB51 Goods movement for the components, I can see the deduction from the vendor.
    Why are the requirements not getting deleted from MD04 of A, B & C and why is not  the component stock at the vendor getting reduced?
    For all other orders, the requirements get erased in MD04 of A, B & C when I receive X
    Please help me out with this issue.
    Sincerely,
    Ketan

    thread closed

Maybe you are looking for