Cost in Material Master

Dear all
I have created a material master. Material type is HAWA.
this is accounting one view.
Price Control      V              Price Unit        -       1
Moving Price      75             Standard Price       100
Total stock         10            Total value              750
Now i need to change moving price field as 100,  because we have wrongly entered the value. Now the stock is already .
posted how can i solve this problem?
regards
Reddy

if you want to change the moving average price you need to run an trax MR21 for that
but at the year end you will have to knock offf the values for the audit purpose
Regards
Sujoy

Similar Messages

  • PGI Should get block - without material cost in material master

    Hi All,
    The scenario is we want to show error message while doing PGI if the material does not have any material cost in material master. How it is possible? Will we able to do with standards?
    Scenario: Material cost is nil in the material master, system should through error message if it do PGI for that material.
    Please let us know to solve it out.
    Thanks and Regards
    Lakshmikanth

    Dear friend
    According to me this should not be SD consultants worry at all
    1.The moving ave price or standard price needs to be mentioned in MMR by MM people depending on the material type and valuation class choosen and whether you are choosing accounting view
    2.Most of the material types which comes for sales like FERT i dont think you can save their Material master records without mentioning either standard price or moving ave price in the accounting view
    (It really surprises me that there is a material available for sale without mentioning either standard price or moving ave price in the accounting view of its master record) ( What i mean is it is already mandatory )
    If not made then in OMS9 you can make it as mandatory
    All these should solve your purpose
    From SD side you can include VPRS condition type in the pricing procedure which will be statistical
    Try changing  that to mandatory and see what is the impact
    I think now at sales order level itself you can control
    Regards
    Raja

  • Update of Price in Material Master  when standard costing is released.

    Hello SAP gurus,
    When we created standard cost estimate, various cost estimate is created in various views Cost of good sold, cost of good manufactured and Inventory ( commercial ). Different view have different cost estimate.
    But we I release costing , the material master is updated by cost estimate of Inventory ( commercial). The cost estimate from Cost of good manufactured should be update?
    I am not able to solve the above issue , please help with customizing link
    Regards,
    Anand Agrawal

    Hi Anand,
    While you configure the Cost Componenet structure you define the attributes of cost Components in OKTZ.
    When defining the cost components, you must specify whether the cost component plays a role in the creation of the different prices that are transferred into the material master record. You have the following options:
    Standard price
    Costs that are flagged as relevant for stock valuation form part of the standard price if the results of the standard cost estimate are marked and released. These costs also serve as a basis for the following:
    The calculation of target costs in variance calculation
    The valuation of scrap in variance calculation
    The valuation of work in process for the confirmed yield for the operation (order-related production, process manufacturing) or at the reporting point (repetitive manufacturing)
    Commercial price
    Costs that are flagged as relevant for inventory valulation for the purposes of commercial law form part of the commercial price. This price is calculated in an inventory cost estimate and can be written to the material master record.
    Tax price
    Costs that are flagged as relevant for inventory valuation for the purposes of tax law form part of the tax price. This price is calculated in an inventory cost estimate and written to the material master record.
    The above information will prove helpful.
    Regards,
    amol

  • Cost of Material Component

    Hi experts,
    I am not able to view the cost of material component in Structure overview report...but i am able to see the cost of the activity , WBS element...I wanted to see the cost of material component also..pls tell me what is to be done?

    Hi ,
    Go to the network header select Control tab , In selection tab Costing put following parameters,
    Costing sheet PP-PC1,Costing varian plan PS02 costing variant act. PS03,Plan cost calc 2.determine plan cost.
    save the project and reopen and check for planned cost.System will get material cost from material master.
    Rgds

  • How to reset planned price in material master

    Hi Gurus,
    Can anyone tell me how to reset planned price in material master.
    my user has run ck40n with wrong values, but i am not able to reverse costing run by using ckr1 or ck44. what could be the reason behind this.
    even after executing tcode ckr1, i can still see the standard cost in material master.
    how to reverse the costing run.
    Thanks in advance
    Suresh

    Hi,
    If you want reset you can delete the cuurent planned price in the material master for the cuurent period,
    Use t.code CKR1,  you have to enter comapny code, plant,material
    In control parameters you have to choose radio button Current Standard Cost Estimates
    Current Standard Cost Estimates
    If you set this indicator, the system will select the current standard cost estimates for deletion.
    If you also set the Additive cost estimates indicator, then additive cost estimates will be selected for deletion.
    Regards,
    Rama Mohan Bangaru

  • Costing of Material without BOM & its Impact in COPA

    Hello,
    I have a scenario wherein Few Finished materials does not have BOM and Routing. However client is aware of Standard Price for these Materials. These materials are lying in stock since long but may get sold. Client is ready to update standard price by MR21 and would not mind to exclude these materials from costing run. However We have profitability analysis active, so as per my understanding while selling such parts for which system does not have costing run, it will give cost estimate error since no costing variant was used for price calculation of these materials.
    Need your suggestions.
    Regards,
    Rahul

    Hi….
    You don’t use MR21 because SAP don’t create CO-PA
    document without standard cost estimate of material which have
    price control “S” when you create billing document  .
    To change material current stock’s amount, you can use MR21.
    MR21 don’t have a role to release standard cost to material master.
    For material which don’t have BOM and routing but have price control “S”
    , you should calculate standard cost using t-code KKPAN to create billing
    document without error related to standard cost.

  • Adding fields in costing view of material master

    Hi gurus,
    I need to add 4 fields in costing view of material master. I have followed the steps in SPRO, for configuring customized screen in material master.
    1) Created a function group YMMCO and copied the screen 2904 from program SAPLMGD1.
    2) Added 4 fields in my customized screen.
    3) Created copy of 01 ( Screen reference ) to z1 in OMT3B.
    Since 2904 is not there in the sequence . I changed one 0001 sequence at the end to 2904 . I also assigned my program
    SAPLYMMCO to it. I can see the changed fields in data screen and subscreen.
    4) Then I assigned the SSq to z1 in transaction OMT3E.
    But unfortunately, when I go to MM01 to create a material , I am not able to view the fields I added in costing view.
    I have checked the screen for the previous field, it shows 2904 only.
    Two days back, I did the same thing in basic data view 1 , it was working properly. As per client's suggestion I put it in
    costing view, it is not working . Please give me suitable suggestions.
    Thanks in advance.
    D. Mallick

    Hi,
    I also need to add custom fields to Basic data view. After copying & changing the screen sequence in Config, I could able to see the custom fields in Basic Data view.
    I have appended structure with custom fields to MARA table.
    But the values I enter in the screen is not getting updated to the table MARA.
    Can you please let me know the code, I should have have in PAI (Process After Input) module in the Sub Screen to update the values?
    Thanks,
    Dasa

  • Open field for cost center on the material master

    We have a unique requirement in a facility we intend to implement plant maintenance in to track a cost center to a material by including the cost center on the material master somewhere.  Cost center is not a field on any of the material tabs we use for maintenance materials, but the requirement is just that it is tracked in a field, even if it's just an open field like a "user defined field" or another field not used often.  We realize there are disadvantages such as the field not being checked against active cost centers, but we are looking at options short of adding cost center as a field manually to a tab (which I believe would require ABAP assistance).  I don't think there are any other fields/tabs we are currently not utilizing but I could be wrong... The best option we can think of is adding it in a material characteristic so it shows on the classifications tab, but I thought I would see if anyone has any other ideas.
    Thanks

    Not sure what is the need of cost center on material master when you want to implement Plant maintenance module. Do you have any specific requirement for this?
    Ideally cost center will be derived from either functional location/ equipment (equivalent of material master) on to PM work order or notification.
    Can you elaborate the requirement?
    After all if you wish to go with cost center, then I suggest it should be at plant level as PM requires plant level distribution. You can add up a custom field and give the reference of cost center data element with help of developer.

  • Costing error while change mrp data in material master

    Hi dears,
    This is Rem process. when i try to change the material master MRP data ex. ( mrp type M1 to M0)
    system not allow to change and show the error as
    Product cost collector 000000750122 is still active (assigned to PrCtr 50601-025)
    i need to change the mrp data in mm02 and i donot want to do delete the pcc .
    any process to carryover
    thanks
    Edited by: raj on May 24, 2010 12:22 PM

    Hi,
    MRP is mainly configured for a material so that tere would not be any need for manual checking of the stock so as to create a PR. 
    The parameters which you have specified for a particular material like reorder point and lot size will help in planning for a particular material.
    If you need only Qty of two (Less) then  there s no need of configuring a MRP for that material
    And lot size is also decided basing on certain other factors like
    1) Lead time
    2) Transportation costs involved in procuring the material etc
    So ifyou want to generate PR for a qty of 100 then you need ot change the lot size
    I hope this gives you clarity
    Thanks & Regards
    Pavan

  • In costing view in material master

    we are running some customized report
    The values are from costing view2
    at the time of running the customized report ,some value is zero for some material
    because at the time of running the report,there is no costing for that material
    after running the costing the values are updated in material master
    once again we run the customized report
    the values are not picking in our report

    Hi,
    Have u marked and released the std prices. check at table level which fields are upated and compare with the fields you use in the customized report.
    Regards
    Raghu

  • Not Getting Costing View in Material master

    Dear All
    In OMS2 i have selected Costing View for Raw Material type. But Still i am not getting Costing1 and Costing2  View while creating material master for Raw material Type.
    Kindly Suggest Me.
    Thanks
    Shobana

    hi,
    Normally this shd not happen...
    but let me know whether you are creating a new material type or making changes in the old one ROH only...
    If we see the std sap provided ROH settings in OMS2, then Costing shd be already provided..and if you are making the new material type, use the sref as ROH and then also, the costing will come automatically...
    Regards
    Priyanka.P

  • Accounting & costing view in the material master

    hi
    my client wanted to block the accounting & costing view in the material master for the end users
    what i need to do

    Hi,
    You can (Authorization material master by views of accounting & costing ) achieve this by way of authorization control. In transaction PFCG, select your role for creating / changing the material master. Select option Maintenance statuses. Then at change status option select views that you want to give the authorization to the users. Create profile & save the role. Now assign the role to the users. They will get only those views you have selected. You have to select those views in all the roles related to material master (create, change, display).Better Consult Basis Consultant,
    Regards,
    Biju K

  • Costing Issue-Previous Price changes in Accounting 1 tab in Material Master

    Hi SAP Experts,
    Our Client has an issue with "previous price" field under the "Accounting 1" tab in Mateial master .The issue is that client never did costing to this material XXXXXXwith plant XXXX. But system is showing value in the "previous price" field. We have checked whether previious cost estimate exists. There was no previous cost estimate and still the system updated "previous price" field.
    Can anyone let me know in which cases the system updates "Previous Price" field in Material Master ?
    Your help is highly appreciated.
    Kind Regards,
    K.S.K

    Hi
    May be this material was created with reference to the same material in other plant or with ref to some other material or may be costing run was deleted from CKR1
    br, Ajay M

  • Cost center assignment based on material master

    Hi Experts:
    My client wants cost center assignment to be based on material master, for example, SAP system should be configured in a way that when costs arise due to a product price variance, then SAP should automatically post to the cost center for the specific brand instead of posting to only one default cost center. Is this really possible? In OKB9, I am only able to assign only one cost center to the GL account. Because of this, at the end of each month, the accountant manually allocates the costs from the overhead cost center to the respective cost centers for the brands which incurred this cost.
    Is it possible to configure SAP to detect that the cost belongs to product A therefore post this cost to Cost center for product A; or this cost belongs to product B therefore post this cost to cost center for product B?
    Your feedback is greatly appreciated.
    Thanks,
    Mariam.

    Hi,
    For your scenerio, try Derivative rule of Profit center. If you maintain Derivative rule for Profit center with product which is indirectly assigned to cost center.
    For example :
    Product A - Profit center1-cost center1
    productB- Profit center2- Cost center2
    Regards,
    Sreekanth

  • Update of cost in the material master

    Hi all,
    From the purchasing point of view,In the normal process Cost in the Material master gets updated from purchasing documnents automatically.In this case,manually if the cost is changed in the purchase order affects the cost in the material master.My requirement is this should be done automatically after receiving the vendors confirmation of list of material costs.There may be chance of change in the cost of the materials.so the costs of the materials which were changed should get updated in the material master automatically(VPRS).
    Ie changing of the costs of the materials in the purchase order should be reduced .How this will done??
    If we have more than 2000 line items in the purchase order,it will be quite little bit difficult to update each material cost in the purchase order .
    Thanks in advance..
    Regards...VM

    Hi,
    Normally material will be valuated with two types of price controls S -standard price and V-moving avaerage price.
    A std price as its name indicated it is std and will not chnage.
    A moving average price will chnage accordingly with the change in the material price.
    Normally it will be better create a info record for the material and vendor combination for the plant or purchase organisation with a info update indicator in the purchase order will serve your pupose .
    With the proper settings at SPRO system creates info record during creation of PO if it does not exist or updates the existing record if it has one with the latest price details in the form of last purchasing document so that these details get defaulted during creation of PO.
    However you can create a outline aggrement so that a PO can be created with reference to that.
    Or you can create a condition record for the price for your combination so that it can get defaulted.
    The price which is there in PO will not be defaulted to material master.
    Or time to time you can review the prices and maintain via MR21.