Cost problem in PS

Hi,
Regarding cost in the projects, here i am getting two different cost in kp26 and kp06, the cost shown in kp06 is correct but in kp26 it is showing by dividing the amount with 12 months. can any one give me the reason to that ?
Regards
Karunakaran
Edited by: Philip Eller on Jun 5, 2008 3:32 PM
Edited by: Philip Eller on Jun 19, 2008 9:53 AM*

Hi,
KP26 - is being used to maintain the labour hour / activitiy rate in combination with work center and cost center yearly as per the decision of the management. and it is distributed according to the distributtion key maintained(0, 1, 2, 3 etc)
KP06 - is being used for planning the activity on cost element and the same is also a combination of activity type, cost center and cost element.
In both the cases the distribution key is used and if distribution key 1 is used the system will divide the cost according to the the period which you have maintained on the selection screen.
Regards
KK

Similar Messages

  • Reg.Negative delivery cost problem in PO release

    Dear Friends
    '' PO cannot be released due to negative delivery costs" this is my client requirement, I am unable to understand this. Please explain and give the solution.
    Thanks
    Rajakumar.K

    how can you have negative delivery costs?
    that means you order material, get it delivered by a carrier, and then the carrier pays you (instead of you pay carrier)?
    Please explain your PO process in a bit more detail.
    maybe this thread with a similar problem can help you:
    http://forums.sdn.sap.com/thread.jspa?threadID=1516469

  • Costing problem while running Process order

    Hi,
    This is a  problem relating to costing of HALB material.. While doing process order for a fert material (BOM of FERT material contains a HALB and two ROH materials) a window occurs while saving ' Error when calculating costs, see log'. Why is this happening? I have checked the BOM , all components are subjected to cost relevancy (X). For HALB material no values are manually maintained in planned price 1,2,3 fields in Costing 2 view of material master. Do we have to manually maintain or will it be taken from the ROH materials in HALB BOM. For ROH materials values are comin in planned price 1,2,3 fields in Costing 2 view . If this has to be done what is the configuration. The ultimate issue is while running process order for FERT material no costing is happening for HALB material.Pls share your suggestions. Rewards assured.
    regards
    Ashok

    Hi,
    when you have raw semifinish and finish material as in sequence then first order of semifinish has to be created and it will capture raw material cost and other expences if incurred after confirmation of semifinish material you will be able to create a finish material production order b' cause that semi- finish material yo have to consume for finsh order.
    if at all first sfg order has updated the price of sfg (after settlement of order) then it will take correct price for finish material
    reward points if you find it useful.

  • Material costing problem in import to arrive at batch profitability?

    Dear all,
    Here my client requirement is to arrive at a material profitability with respect to that batch(shipment), but some times in import procurement exact profitability will not be arrive due to practical problems, which are
    1. freight & demurrage paid to shipper is not the exact cost which need to be incurred on to material because the freight is imaginary (20%) in order to have assessable value at the time of PO, however this can be adjusted at the time invoice but what about the demurrage demurrage paid by company to shipper will be in turn collected from handling agent, and hence net demurrage will not be known at the time of PO.
    Kindly suggest me on this to arrive at batchwise profitability with respect tom material?
    regards,
    Sanjana....

    Batch management is used to safe gaurd the homogenity fo material.
    Batches also maintained if you want to split value of the material
    Batched are identified with batch numbers. These numbers are created manually or dynamically while entering goods receipt.
    *One batch can be posted once.
    Batch will have two statuses Un-restricted and Batch restricted.*
    Batches can be maintained with classification with which we can assign some characteristics like quality related for shelf life related.
    To activate the batchmanagement for a material you must select the batch management check box in material master purchasing view or in general plant storage.
    Manual creation:
    Create Batch -> MSC1N
    Enter material
    Batch number (Unique for material)
    Create PO -> Click on batch tab -> Assign batch number (created) and Post.
    Batch with Classification:
    Create Characteristics : CT04
    Create Class: CL02 -> Click or char tab -> Enter Characteristics.
    Create Material with Classification View -> Select Class type.
    Just try like this you will get it and create PO and check the posting with Movement 341 & 342 for Batch restricted and un-restricted stocks.
    Regards
    Ravi

  • Shipment cost problem

    Hi sap Gurus,
    i defined scales for shipment costs (VS01) :
    1) scale basis L4 (transportation zone of departure point)
    2) scale basis L5 (transportation zone of destination point)
    3) scale basis D (gross weight)
    Then i defined a condition TYPE "ZB02" that has tridimensional scales (1-2-3) and i insert it in pricing procedure SDFC00 after FB00.
    I defined a condition record, but when i do shipment cost the condition record is found by the system (in pricing procedure i see it) but it's red.
    ---> the system calculates only condition TYPE ZB01 that has bidimensional scales (gross weight & distances).
    I think that the problem is that the system don't found the right value of transportation zone of departure & destination.
    But i checked that transportation zone was defined for customer (ship to party) & for shipping point..
    any solution?
    thanks a lot
    Alba

    Dear Alba,
    This is due to not maintaining the condition record for that "ZB02" shipment cost condition type in TK11 transaction.
    After assigning the scales to ZB02 you maintain the condition record for that condition type in TK11 transaction.
    Before going to maintain the conditionrecord you make sure that you maintained access sequence to that condition type.
    As per my advaice you no need to maintain scale basis for transaportation zones.
    You can consider these scale basis
    Gross weight
    Net weight
    Volume
    Distance
    Number of different means of transportation
    Time (travel time or wait time)
    Tariff zone (destination)
    Destination region
    If you want to maintain cost Transportation zone wise you can keep these fields in the condition table based on that you can create condition record.
    For more clearence please go through this SAP help link it will help you about Shipment cost scales and condition record maintenance.
    http://help.sap.com/saphelp_47x200/helpdata/en/28/53584348be11d385ed0000e81ddea0/frameset.htm
    I hope this will help you,
    Regards,
    Murali.
    Edited by: Murali Mohan.Tallapaneni on Oct 24, 2008 11:34 AM

  • Cost Problem in DIAPI

    Hi, everybody, I have a trouble when make a transaction by SDK DIAPI way, the Problem is about a cost assign, every time, when I make a Transaction, I send values, that add is grater that one, but, when I look the item in SAP, this Item have 1 in his cost.
    I’m using This Objects:
    - SAPbobsCOM.StockTransfer
    - SAPbobsCOM.BoObjectTypes.oStockTransfer
    - SAPbobsCOM.BoObjectTypes.oInventoryGenEntry
    Somebody knows what I’m doing wrong

    can you post some sample code of what you are doing?
    This could give me a better idea to help you...
    Regards,
    WB

  • Can you help me with a Cost problem in an Order?

    Hello SAP experts, i have a question regarding orders and their costs if i go inside an order and i go to the menu then ->Goto->Costs->Analisys-> and then choose the layout ->Target/Actual Comparison, in this layout there is a column that says
    Total Target Cost and Total actual cost, i would like to know is what data does the system use to calcule those values, i know that one value is the amount of material that was charged to the order, but i would like to know from where does it take the other value the cost value so it can reach that number, thank you in advance

    Hi,
    In simple words:
    Target cost = Plan price * Actual qty
    Actual cost = Actual price * Actual qty
    Now where does the price come from... it depends on the valuation variant which is used for the order type. Normally it is the standard price from the material master which you can see in Accounting - 1 view or Costing - 2 view.
    The actual quantity is the qty of a component which has been issued to that order.
    So to get a clear picture, take a material which you see in the cost analysis view of that order & open the material master. Check the price for that part, multiply it with the qty issued & your query should be clarified.
    Revert if you face any issues.
    Regards,
    Vivek

  • Freight Costing - Problem of G/L account with Cost Center

    Dear Gurus,
    In VI02, I have the following u201CAccount Assignmentu201D message of error:
    u201CG/L account 60900000 cannot be used (please correct)u201D
    u201CComparison of the field selection strings from the G/L account 60900000 and the account assignment category K reveals that there is an incompatible combination of field selections for the field selection group 'Earmarked Funds'.u201D
    Questions:
    Bearing in mind that I am in the Shipment Cost cockpit, I need to mention that the system directly allocated me the following Account Assignment Category: u201CKu201D for u201CCost Centeru201D.
    1-     I could there either way create another Account Assignment Category for Shipping instead of Cost Center
    2-     The system tells me about an incompatible combination of field selection, how can I change that field selection to make it compatible? There are so many possibilities that I get bogged down in choosing the right combination.
    I have been to OME9 and OB14 to try to maintain fields, however those fields have different values or names.
    My aim here is to coordinate a G/L account group with a Cost Center for Freight Costing
    Can anyone help?
    Thanks
    Chris

    Dear Zafar,
    If you desire you maintain two different cost centers for the two company and you need to have both of them posted on the same G/L account and Cost element, I would advice you to:
    - create a Z table where by controlling area you define where the specific cost center need to get posted
    - include this validation check in the exit for validation for controlling
    - include this validation check in the exit for validation for finance
    - include this validation check also in the sales order user exit
    Standard SAP seems do not have direct link between cost centers & cost elements. For this reason ideal solution is to generate a table where you may define you needed structure.
    E.g.: some ideas on the table you may create
    Controlling area
    Cost element from
    Cost element to
    Cost center from
    Cost center to
    I hope this suggestion may answer to your need.
    Regards,
    Viviana A.

  • TARGET COST PROBLEM

    Dear Gurus,
    In a process order when i click on cost analysis i do not see target cost.the target cost column is empty .
    Actual cost column is ok and there are values it and same is with Target/actual variances column.
    What is the reason the target cost column is empty.
    Thanks in advance
    Regards
    Ram

    Hi
    Target costs are populated when you do the goods receipt. System will search for the released standard cost estimate and then apply that for each material component. If these 2 conditions are passed, then you will get  target cost in order.
    Plan cost = Plan qty * std cost estimate
    Target Cost = Actual qty * std cost estimate
    Actual cost = Actual qty * actual costs
    Eg:
    A production order is planned for producing 10 units of a material
    Then plan cost on the order = 10 units * std cost
    Target costs are calculated once production is confirmed.
    Suppose only 9 units were produced out of 10 planned
    Then target cost = 9 units * std. costs
    Edited by: Ganesh M on Feb 26, 2010 10:15 AM

  • Transport costs problem

    Hello, i have a condition ZT which is the condition for transport costs.It appears / does not appear in the condition schema in my purchase order.
    When i create my billing document , can i insert and additional line for the transport(even if there is no transport cost in PO condition schema)?

    1. U can always add condition type in PO manually
    2. I assume u r talking about MIRO. U can add Unplanned delivery cost in MIRO.
    Regards,
    NNK

  • Landed cost problem

    Sir it is ok that by t-code MIRO we can mention freight details but how to get LANDED cost .
                                               I am on-line .

    Hai,
    Create one condition type for Landed cost - freight and assigned to your pricing procedure.So that it will flow.

  • Internet Data Cost Problem

    I am using blackberry airtel.Whenever i access internet there will be some amount reduced from my main balance eventhough i put blackberry internet tariff plan.After using internet my balance will reduced to zero balance.What is the solution for it.Please help me.For this only i didnt put internet paln in blackberry.

    Try asking them what apn to put on your phone. Then check your apn if it's correct http://btsc.webapps.blackberry.com/btsc/viewdocume​nt.do?externalId=KB05327&sliceId=1&cmd=displayKC&d​...
    Good luck!!!
    Click " Like " if you want to Thank someone. If Problem is resolved accept it as a "Solution ", so that others can make use of it.
    Click if you want to Thank someone. If Problem is resolved, so that others can make use of it.

  • Costing problem

    {"W803649790212 the standard cost is 45.67 but actual purchase price is 3.12 Euro Per 100 PCE that is 1.75 Rupees and landed price is 2.09 RS. Even after re costing system is picking the cost as 45.67 RS only because of which the Inevntory valuation for the stocks available is very high in IN10."}

    Hi
    Change the standard price using T.code MR21.
    Regards
    Dev

  • Distribution of cost problem

    hi,
    i am getting a  message like Customizing error: Business transaction groups are not current, when i am trying to use the t.code: ksv5 (Distribution). Please help me to solve this issue

    Check note 101206
    thanks
    G. Lakshmipathi

  • Distribution of costs problem

    hi,
    i am getting a message like Customizing error: Business transaction groups are not current, when i am trying to use the t.code: ksv5 (Distribution). Please help me to solve this issue

    Hi,
    Please use the Business Transaction RKIV ( Actual Over Head Distribution ) At T Code KANK
    Bya....