Customer Opening Hours Vs V_V2

Dear All,
We have special requirement, when a customer places order it has to take consideration in to the customer opening hours in to consideration, for example if the customer opens only on TUE and Thurs if he places order on Friday it has to give automatically TUE as delivered date, incase there is no stock we have standard 6 weeks date will be given by the system and this date also need to be the date of customer opening day.
This is all happing fine when we create the sales order with the fully stock, when there is no stock partial stock and when we have more than one schedule lien at sales order level it is working fine.
But when I Run the V_V2 for rescheduling the sales and stock transfer requirement transaction., that means in case if I have any stock coming in to my ware house before the date is given in the sales order schedule line, in the program it shows me confirmed date for the rest of the qty as goods received date + GR Processing Time From MRP1 from material master.
Here the problem is in this program it is not taking into consideration of customer opening hours from customer master.
This gives the new date just after the goods receive date, but I want customer opening hours to be considered that means if the customer is opened on TUE even though I receive the Goods on Friday I don’t want to deliver on Monday I want the deliver date to be Tue only.
Any Idea how can I achieve this???
V_V2 (Standard)
The 'Rescheduling' program (SDV03V02) processes sales document items that are contained in the item directory for the material. It takes into consideration open items and schedule lines from stock transfer items, stock transfer scheduling agreements and purchase order requests (items only), referred to hereafter as stock transfer documents, for the materials.
Thanks & Regards,
Sundu

hello, friend.
try this...
1.  first, define a customer specific calendar using t-code SCAL.  this calendar can include the days the customer is open.
2.  using XD02 or VD02, go to the Customer Master > General Data > Unloading points tab.  in here, specify the unloading point and the calendar.  (however, this may entail additional config on your part).
regards.
Edited by: jonathan yap on Feb 19, 2008 6:41 PM

Similar Messages

  • Customer opening hours not pulling...

    Hi All,
    Created purchase order & then delivery. But when I go in the delivery header-shipment tab - Ship to party and over there I can see
    Delivery date but not the opening hours.
    Its showing  00:00 - 00:00 and 00:00 - 00:00
    I looked into the PRD example provided by the user - uploading point and opening hours are maintained over there.
    I also tested in the same scenario in sandbox no openining hours pulling up.
    This is happening only for France customers.

    Hi,
    agree with Murali
    please go to shipping point and route to check whether 'time in hours/minutes' is maintained;
    - for shipping point, please firstly setup working times, and then maintain pick/pack and loading time in hours/minutes
    - for route, please maintain travel duration and transportation lead time in hours/minutes

  • Cutomer Oping Hours and V_V2

    Dear All,
    We have special requirement, when a customer places order it has to take consideration in to the customer opening hours in to consideration, for example if the customer opens only on TUE and Thurs if he places order on Friday it has to give automatically TUE as delivered date, incase there is no stock we have standard 6 weeks date will be given by the system and this date also need to be the date of customer opening day.
    This is all happing fine when we create the sales order with the fully stock, when there is no stock partial stock and when we have more than one schedule lien at sales order level it is working fine.
    But when I Run the V_V2 for rescheduling the sales and stock transfer requirement transaction., that means in case if I have any stock coming in to my ware house before the date is given in the sales order schedule line, in the program it shows me confirmed date for the rest of the qty as goods received date + GR Processing Time From MRP1 from material master.
    Here the problem is in this program it is not taking into consideration of customer opening hours from customer master.
    This gives the new date just after the goods receive date, but I want customer opening hours to be considered that means if the customer is opened on TUE even though I receive the Goods on Friday I don’t want to deliver on Monday I want  the deliver date to be Tue only.
    Any Idea how can I achieve this???
    V_V2 (Standard)
    The 'Rescheduling' program (SDV03V02) processes sales document items that are contained in the item directory for the material. It takes into consideration open items and schedule lines from stock transfer items, stock transfer scheduling agreements and purchase order requests (items only), referred to hereafter as stock transfer documents, for the materials.
    Thanks & Regards,
    Sundu

    hello, friend.
    try this...
    1.  first, define a customer specific calendar using t-code SCAL.  this calendar can include the days the customer is open.
    2.  using XD02 or VD02, go to the Customer Master > General Data > Unloading points tab.  in here, specify the unloading point and the calendar.  (however, this may entail additional config on your part).
    regards.
    Edited by: jonathan yap on Feb 19, 2008 6:41 PM

  • EIM/WIM: Displaying open hours

    Hi,
    We have just installed EIM/WIM and try to check a situation where there are no agents available to respond to cusomer's request for a chat. When a customer clicks on the Chat button in a Web browser he/she gets the following message:
    Thank you for your inquiry. Our service hours are 9am-5pm PST, Monday-Friday. If you are trying within the service hours and still getting this message, please try after some time, as all our agents might be busy or unavailable at this time.
    Then we have created a calendar with open hours from 01:00 AM to 11:00 PM, but again customers get the same message, i.e. the part of this message indicating open hours does not correspond the open hours in the calendar. We have restarted the EIM/WIM server but again no luck.
    What's the cause of it? How can we workaround this problem?
    Thanks.
    Igor

    Igor,
    This is a static message (not a macro based message) that why it keeps showing the same message
    This can be changed in the Chat Template (Department > Your Department > Chat > Templates) in the Options->Off Hours tab. Kindly refer to the EIM/WIM Administration Console User Guide (page 177 - 181). I think it should be the same for both v4.2(x) and v4.3(1).
    Thanks!
    -JT-

  • Lync Response Group Manager - cannot change opening hours

    Hi all
    I've run into an odd problem with Lync Response Groups with Lync 2013 Server. Just wondering if anyone has seen this before or knows of a solution. I've searched around but can't find any reference to this particular problem.
    Response supervisors who are defined in the workflow and are a member of the AD group CSResponseGroupManager cannot change working hours for their response group from a custom schedule to a preset in the web interface.
    If the workflow is already set to preset they can switch between existing presets, and they can switch from preset to custom. But once it has been set to custom they cannot change it back to preset.
    They can select to do so but when they click Save they receive an error on the page saying "The term 'Remove-CsRgsHoursOfBusiness' is not recognized as the name of a cmdlet, function, script file, or operable program. Check the spelling of the name,
    or if a path was included, verify that the path is correct and try again."
    I don't believe this is by design, why would you want a workflow manager to be able to switch between presets or to custom but not back again?
    If they are a member of CSResponseGroupAdministrator this works, however this is not really a solution as members of this group can edit all workflows and we don't want the managers of a workflow for one department able to access the workflows of another.
    Any information greatly appreciated.

    Hi
    I had to abondon working on this for a while as we only had 1 Response Group in place, it wasn't too much hassle for me to do these changes myself.
    However we now have about 6 Response Groups. All are managed and have a user listed as manager in the workflow, that user is also in the CSResponseGroupManager AD user group.
    As previously described they can change the opening hours from between existing presets, and from preset to custom, but attempting to change back to preset from custom causes the error given previously.
    This does not occur if the user is a member of CSResponseGroupAdministrator, however putting our Response Group managers in this group is not appropriate as it gives them access to all Response Groups not just their own.
    Is it possible the error is due to the fact that the CSResponseGroupManager group is not giving them permission to the Remove-CSRGSHoursofBusiness cmdlet, I think PowerShell tells you a cmdlet doesn't exist if you don't have permissions to use it?

  • How to clear vendor open items with customer open items in APP?

    Hi Experts,
    Our vendor is our customer - in this scenario how to clear vedor open items against customer open items. I have defined vedor is customer means I have given customer number in vendor master record, selected chek box 'clear with customer'.  Still problem is not solved, hence I am requesting you to help me in this regard.
    Thank you very much,
    Regards,
    Ganesh.

    Hi
    In FBCJ after payment you have clear manually vendor balance in F-44.
    If you want SPL GL in FBCJ then write a Substitution .
    1. step 001 - Special G/L Substitution
    2. Prerequisite - Transaction code = 'FBCJ'
    3. Substitution posting key -- Exit (need help from abap) exit name
                                              G/L Exit (need help from abap) exit name
                                              Special G/L Ind Exit (need help from abap) exit name
    you can't do this without ABAP help
    Best Of Luck
    Tanmoy

  • Customer open item line wise details

    Hi ,
    I have customer open item for 240 days. Now he has made payment today for part amount only. I have cleared this amount against the outstanding amount. Now in FBL5N open item is only for balance amount. BUt when I  CHECK REPORT- S_ALR_87012178 days for the open item is between 31 to 60.
    How this dates are calculated.I have posted document today so it should either come from 1 to 30 day range or in 240 to 300 day range as balance is outstanding from that date.
    Help me to resolve the issue.

    Hai
    The duedate is calculated according to the baselinedate which u will maintain in terms of payment(OBB8).In terms of payment u will maintain baseline date as document date or posting date or none.mostly u would be selcted the duedate as document date thats why i  believe ur line item is showing in between 31-60 days.
    Regards
    Raghavendra.M
    SAP-Practice

  • EBS posting to clear customer open items - Function not working?

    Hello SAPers
    I have an issue I just canu2019t seem to resolve! We are receiving MT940 statements and receive customer invoice reference details with field: 86 as follows:
    :61:090910C1500,00FOSB1000270 //100909050      0        035315
    :86:DEPOSIT
    Remitter:1000270 MISSION AUSTRALIA   Ref:1200000017
    Immediately following the BTC FOSB the bank quotes the customer number however I am not using this as standard SAP should identify the customer by document number within the note to payee field?
    I am using a 2 step process in posting to the clearing account and customer. Config as follows:
    Pst Type 1
    40     Bank
    50     Clearing
    Pst type 2
    40     Clearing
    15     BLANK          DZ     3      15
    I have also set up a string to look for the documents ^(12########)$. When we load the statement the first posting is successful however the second does not post to the customer or clear based on the invoice reference. I am using algorithm 020. The error that occurs is F5 102 Customer does not exist in company code xxxx. It actually does exist in the company code.
    I have loaded the EBS to the buffer and simulated the search on BELNR and it picks up the document?
    I am sure this is standard and a CMOD is not required on this type of functionality? What have I not done to allow posting to the customer based on document number or to post on account where it is not cleared?
    Any assistance on this issue is appreciated? Thanks in advance.

    Function Module for GL open Items
    how to clear customer open items by another  customer open item
    Function Module for GL Open Items
    Reward points..

  • Function module to clear customer open items

    Hi ,
    I have a requirement in FI module to clear the customer open items through Function Modules.  The standard functionality is done through the tcode f-28 / f-32.
    Please let me know if there is any program or Function Module to clear the customer open items.(without using BDC).
    Thanks in advance.

    Function Module for GL open Items
    how to clear customer open items by another  customer open item
    Function Module for GL Open Items
    Reward points..

  • Customer open item report

    How to pick from SAP the customer open line items ?
    Per the client, they need the balance amount currency for each invoice . for eg : there is an invoice for $1000 and an incoming payment of $200 .
    Client needs in a single line under two columns
    Balance amount in currency - $800 (which is a problem)
    Collected amount in currency - $200 .
    In short, they would need outstanding balances at Invoice level/rather than at customer level.

    develop the Z report using ABAP.
    CHANDRA

  • Customer open item not cleared

    Hi experts
    For a customer open item,when deposited cheque in bank trough t code ff68
    the line item remains as open but not cleared.
    thanks in advance

    Hello,
    After the end of the process you should check the results in order to identify if the account informations were found in order to clear the item.
    Regards,
    REnan

  • Customer Open Items Document Details

    I am building an application for a client for Purchase Card Processing using Visual Studio 2005. I am able to use VS 2003 to create the necessary object to get the Customer List, Customer Details, and the list of Customer Open Items.
    I am totally new to SAP, and need some help to figure out my next steps.
    1. What call(s) will return an Open Item (Document) given the Document Number, along with the individual line items. With that info I can post a Level 3 transaction and get an authorization code.
    2. What is the process to post the purchase card authorization, essentially a payment, back to SAP for the open item.
    3. What is the best source for reference details on BAPI?
    Thanks in advance for any assistance.

    Thanks for the response,  but I have already madie it that far...   " I am able to use VS 2003 to create the necessary object to get the Customer List, Customer Details, and the list of Customer Open Items.
    with the list of open items,  I get a  Bill_Doc.   What calls will return the details of the Billing Document?

  • Report s_alr_87012178 :customer open items  - Customer classification

    Hi all. The problem concerns the report  s_alr_87012178 which is used to display customer open items.I am selecting  'Customer classification' from the dynamic selections and filling it with a value e.g C.
    I have assigned risk class A for my customer in XD02 : Marketing tab. When i am running the report, it is displaying the customer even though i have filled in a different customer classification value.
    Thanks for input.

    Hi Antish,
    Were you able to resolve this?  If so, could you let me know what was done. I have a similar issue with Customer Classification on FBL5N.
    Thanks,
    Sam

  • Report for customer open item exclude vat

    Dear Experts,
    Is there a report in SAP which can extract the customer open items with VAT amount excluded?
    Thank you

    You have to customize a report. There is no standard report for this.

  • Customer Opening Or Closing Balances

    Moderator message: do not offer points
    Hi,
    Can anybody tell me the Table or T.code where the Customer Opening/Closing Balances are maintained.
    <<Text removed>>
    Thanks.
    Kamal
    Edited by: Matt on Nov 22, 2008 6:04 PM

    Hi Kamal,
    pls check following tables,
    KNC1,
    BSID,
    BSAD
    and tcodes is,
    FBL5N,
    Regards,
    Arpit