Damage Material at Subcontractor

Hi,
There is scenario in case of Subcontracting PO.
I have created subcontracting PO having parent material with 1 Qty.
Child parts issued to vendor in a bulk it can be 1000 qty or more.
Subcontractor Process the materials he required 100 child parts to create the 1 parent material.
now while subcontracting he damages the 10 qty out of 100 and he is responsible for these 10 damage items.
how the damage materials can be treated in the system.

Initially I have issued 100 Qty to vendor he damages the 10 and then more 10 Qty issued to him, now total Qty has been provided to subcontractor is 110.
Goods Receipt will be posted with 100 Qty.
and for 10 (Damage Qty) credit memo will be posted.
but 10 qty (which was issued later) still have status "Stock provided to Vendor" because GR is posted only for 100 Qty so how it will be adjusted in the system. either physical inventory or any other way ?

Similar Messages

  • How to track cost of damaged material reparied at workshop

    Hi Pm gurus
    My scenario is :
    Material is damaged and replaced at site with new one from stores and Damaged material is send to workshop to repair.
    After repairing then we have to send the material back to stores from the workshop and stock it in stores for future.
    Please help me out what steps should I use to capture it in SAP
    Regards
    Ek

    Dear,
    You are saying, Damaged material.Hope its not  an equipment.If it is a spare part that you would like to reuse, then it is having impact on moving average price of that material while updating stock in INVENTORY.
    If you are considering the material as a sub asset of that equipment, then you need to valuate the useful life of that material and the depreciation value.
    In standard SAP , the simple way of returning to stores for maintenance department is through maintenance order by putting the qty. with negative sign. for example "-2" Nos.If you post the goods issue of the maintenance order , system updates the stock.But I donot suggest this procedure for used material because of impact on MOVING AVERAGE PRICE.
    If you are using split valuation, situation would be different and you can opt this process as "repaired" material valuation type.Then you can have option to trace the cost of the material at workshop through maintenance orders.
    If you want to reuse the equipment and after overhauling at work shop, its better to be processed through REFURBISHMENT process.
    Regards,
    Pardhu

  • Damaged material adjustment posting

    Your help is required for the following scenario.
    Material received from the foreign vendor against import PO.
    Total qty is entered in SAP through MIGO posting with movement type 101.
    Partial qty damaged received which are to be settled by the insurance as per
    agreement and damaged material not to be send back to the supplier.
    If we adjust it through MIGO with movement type 122 (Return delivery to vendor)
    that changes the PO status and shows PO open for the qty that has been rejected and settled against insurance claim.
    PO should be closed manually or other way for rejected material posting that does
    not reopen the PO.
    Your suggestion is required.

    hi
    please check below thread
    Insurance document at the time of GR?
    regards
    vijay
    Edited by: vijju489 on Aug 24, 2010 12:18 PM

  • How to enter / Post Goods receipt of Raw Material from subcontractor

    Dear Experts,
    As standard subcontracting procedure, Raw Material Transfer posting is made to Subcontracting Vendor
    and the Semi finished material [Assembly] is received from the subcontractor.
    If in case extra or by any reason, raw material stock is with subcontractor, he want to return the raw material stock.
    How to receive raw material stock from subcontracting vendor and how to handle subcontracting challan transactions in SAP ?
    Thanks in Advance !

    Hi,
    >>Receive the RM using MB1B / 542
    >> Reconcile using J1ifq
    >> Complete challan using J1if13
    Thanks,
    Rajoo

  • Purchase order : sales order specific material  to subcontractor.

    I want to send a cir specific material to a sub contracting vendor.
    Scenario:
    Sales Order punched for material A.
    To get material A a sub contracting purchase order is made specific to sales order.
    Material B is there in the BOM of material A.
    Material B is also purchased from other vendor say vendor B with sales order specific purchase Order.
    when doing GRN for Material B it is sales order specific.
    now i want to transfer material B to vendor specific stock which is already . Can u help how should i do this as my material B is also sales order specific.

    Create the sales order for Material A
    than this reqmt will be transfer to MM and if the stock is not there than it will be a requirement of Material A in MRP
    now if you have set up material A as sub contracting in MRP2 view as Special procurement Key Sub contracting than based on this system will generate the Sub cont PR and mateiral B is part of MAterial A BOM than MRP will, also generate the requirement for Materisl B as external procurement
    convert Mateiral B pr into the PO and make delivery address as sub contractor rather receivng in your system.
    that way you can deliver mateial B directly to the vendor and once vendor send oyu the Material A than do GR which will consume the material B.

  • Transfer Posting Material to SubContractor

    Dear Experts,
    Can we Issue material which are not included in the Subcontracting PO Item BOM to a Sub Contractor.
    Regards,
    Suman.

    Hi,
    Yes, you can maintain manually those parts which are not in the BOM at the time of MB1B.
    If you entered parts with the +ve qty, system will post with 543 movement type.
    If you entered parts with the -ve qty, system will post with 545 movement type.
    Regards
    KRK

  • Reg material return from subcontractor

    Dear all,
    We send material to subcontractor using movement type-541, but due to some problem the subcontractor has not completed the job and we need to take stock back from him and we will take with 542 mvmt, our requirement is can we generate an inspection lot for this mvmt type( we need to test material coming from subcontractor)
    Thanks i n  advance
    Madhav

    Hi,
    I would suggest to post this query in QM forum to get a better help.
    However based on my little knowledge on this, you can manually create an inspection lot via QA01. The inspection type would be 08. Maintain this inspection type in the QM view of the material master. Check with your QM personnel if this can meet your need.
    Regards,
    Vivek

  • Material lying with subcontractor

    All SAP Gurus,
    We are using subcontracting PO and with reference to those PO sending the material to subcontractor.
    Then we make the GR against the subcontracting PO.
    Some stock always lye with the subcontractor.
    How to know the document numbers (transfer posting documents, Movt type: 541) against which the material is still lying with the subcontractor?
    Note: we are not using Batch Management.
    Regards,

    Hi Priyanka,
    From the list of open POs, we can have the approximate idea regarding the material documents against which GRs are still possible.
    But that list do not show the documents with movement  type 541.
    is there any report or Table available from which we can get the list of material documents for PO.
    Regards,

  • Purpose & Net Value of Return PO - For Damaged or Recycled Material or both

    Dear all
    As far as I know about the Return PO, they are summarized as follows:
    Examples for returns for purchase order:
    . You procure filters from a vendor. You return the dirty filters to the vendor for recycling.
    . You have agreed with your cable vendors that you can return cable remnants to them. You then receive a credit memo for the value of the copper contained in the cables.
    This is always happen after we have posted Invoice Verification (MIRO) in the system and make the Outgoing Payment (F-53).
    Question 01:
    Does return PO cover both scenario such as
    (a)Return the damaged material to vendor which we discover its defect after invoice verification or post outgoing  payment has been made?
    (b) Return the recycle material to vendor after invoice verification or post outgoing  payment has been made?
    Question 02:
    We are using Info Record for the material.
    (a) In the case of Return the damaged material to vendor, the return PO will have the net value suggested from info record
          and it makes sense since we want our AP (account payable) to be reduced.
    (b) In the case of Return the recycle material to vendor,  the return PO will have the net value suggested from info record but
          iit makes no sense as vendor will not agree to have the recycle material same price as the first purchase price.
    Please advise.
    Thanks.
    Edited by: Daimos on Oct 12, 2009 3:28 PM

    Hi,
    Q-1
    a) Return the damaged material to vendor which we discover its defect after invoice verification or post outgoing payment has been made?
    For damaged returns, you need to cancel the Gr Posted , movement type  102 and thenreturn it to vendor using movement type 122. So return P.o. function is not applicable here.
    b) Return the recycle material to vendor after invoice verification or post outgoing payment has been made?
    Yes , for recycled material as stated by you it is applicable.
    We use  return purchase order, when purchase order is made. Here we tick the Returns indicator in the item overview of purchase order screen.Movement type for return indicaort is 161.
    Also would like to add a example here;
    Q-2) In the case of Return the recycle material to vendor, the return PO will have the net value suggested from info record but
    iit makes no sense as vendor will not agree to have the recycle material same price as the first purchase price.
    Supopose you order a printer cartridges from your vendor for which you are creating retun P.O. then you must define top two material number one with full printer cartridges, for which you pay vendor and other material number for empty cartridges for which you create a credit memo when you return them..
    So when here you can create a Purchasing info record for empty cartridges with a price agreed with your vendor, and can create a credit memo.
    So now you have two info records one for full filed cartridges and other one for empty cartridges . So price issue will ntoa rise.
    Regards,
    Tushar Patankar
    Edited by: Tushar Patankar on Oct 13, 2009 11:47 AM

  • Material handling at Depot

    Hi,
    I have a scenario (MM-CIN) to configure....I am explaining below the scenario:
    Company has a depot which procures Steel coils as Raw Material from local as well as import vendor.
    Raw materials from local suppliers are received with excise invoice.An entry is maintained in RG23D register for incoming material.
    Depot is not selling the material as it is. Steel Coils need to be cut in different sizes as per customer's requirement. So the depot sends the material out to a Subcontractor for cutting the Coils.
    In one case, the cutting is considered as Manufacturing activity at Subcontractor and in other cases, it is not considered as manufacturing activity.
    In the first case, depot sends the steel coils with a Subcontracting challan > Subcontract processing happens at Subcontractor > Material is received at depot with a invoice for services done. Pls note that the finished material here has a different material code. Depot then send this material thru' SD route to customer and calculates the duty to be charged on per KG of steel basis, same being calculated from RG23D register details.All this thing are done manually.
    In the second case, where cutting is considered as manufacturing entity, depot sends the material to Subcontractor with the excise invoice, finished material is received with excise invoice and same being dispatched to Customer.I think this is a standard procedure.
    There are also scraps generated at Subcontractor's premise which are also sent along with FG. For example 100KG of steel processed at Subcontractor generates 5 KG of scrap.
    I need an opinion on the best practices to be adopted in context with above business scenarios.
    Regards,
    Pankaj

    Hi
    It is also 101 and the register is Rg23D
    Reg
    Raja

  • Returning Demaged Material and getting new Material free of Cost

    Dear Experts
    As per my sceneriao ,one of our Bearing is got demaged and we told to vendor for the replaement.Once replacemnt is recived we will send back demaged material what is correct Cycle for this.
    Regards
    Raj

    Hi Raj,
    As per your scenario, one of our Bearing is got damaged and returned to vendor for the replacement. Once replacement is receivedwilll send back the damaged material the correct Cycle for this is as below.
    You can create a single PO for free of goods PO by ticking 'Free Item" indicator & item which has to be return with 'Return" tick.
    Now in MIGO, enter PO number & post the document. For free goods, there won't be accounting entry. Same you can not have liability to pay anything to vendor.
    For Return Goods, have to use movt type 161 which reduces your inventory & inventory account will get credited & GR/IR will get debited. If previously MRO vendor invoice posting was happened then you have do MIRO-Credit MEMO in order to reverse the amount. If you had carried out returned delivery before MIRO vendor invoice posting then system automatically take care of the qty when you performed MIRO which will post after reducing return delivery qty. Hope this helps you.

  • How to clear the stock of material provided to vendor(subcontracting stock)

    Hi SAP Gurus,
    Please let me know how to clear the stock of material provided to vendor(subcontracting stock) and need your help in what senario this stock will show in " Matl prov. to vendor "
    Thanks and Regards,
    SHARAN.

    Hi Sharan,
    Matl Povided to Vendor stock will appear in Subcontracting scenario.
    If at all you have given some material to a subcontractor , this will be consumed automaticaly when you will recieve the ordered material from subcontractor.that is 543 movement will take place in the backgroung when u do the GR.
    In case if u need to clear the stock u can do 542 and take the stock back to unrestricted.
    Edited by: Donsandy on Jan 21, 2009 6:19 PM

  • Subcontracting same material same vendor different operations

    All SAP Gurus,
    I'm providing components (in this case these are tools) for subcontracting.
    Accourding to the condition of tools, subcontractor will perform different opertions (eg. sometimes sharpening of the tools, some times chipping) over these tools.
    I don't want to create different material codes for components (as my material which I'm supplying to subcontractor and material which subcontractor is supplying to me against components are same).
    But processing charges are varying each time accourding to operations performed by subcontractor.
    Subcontracting PO picks up same price each time from Purchasing Info record (subcontracting).
    Is there any any out to pay different charges depending upon operations performed by the subcontractor.
    (We can not create service PO, as material is going out of factory on subcontracting challan).
    Please suggest,
    Regards.

    Hi
    Try changing the Price in the PO In the Conditions Tab of the PO line item.
    Or if the Prices are being adopted from the Inforrecord , update the Price there.
    Thanks & Regards
    Kishore

  • Material management

    Dear all,
    We are transferring goods from one plant to another plant. 10 quantity is transferred through a transport. The other plant received only 9 due to damaged made by the transport people. How to map this in SAP? How does it affect the FI?

    Hi
    Please use STO for this. For the damaged piece as it is intra company code, option one is either the STO is amended to the correct  the receipt quanity, or  in the receipt plant after receiving all the pieces in SAP, one pieces can be scrapped. Use the option which ever is easier for the user. The effects in FI will be normal as we wish it to happen for the damaged material.
    Best regards
    Edited by: samuel mendis on Apr 15, 2009 6:48 AM

  • Scenario of Import P.O from same material get money from vendor and custome

    Hi Experts,
    My client is procuring certain material Quantity 10 by Import, As when he recieve the 10 Quantity material he founds 8 Quantity is to be Okay and the other 2 founds to be damaged, As it is import material he cannot return it to import vendor, in this situation he takes the photocopy of the 2 damaged material and get debits from vendor without actual returning to import vendor apart from this the damaged goods he sells for lower price.
    So from the same material he gets the money double time one from Vendor and other from Customer.
    How to MAP this Scenario in SAP ?
    Plaese advice.
    Best Regards
    Javeed Ahamed

    Hi Javeed,
    Are u using QM module?  If u are using, u can activate quality inspection for this material.  You can do 101 movement for total qty i.e. 10 nos.
    Then in usage decision, you can accept 8 nos and reject and scrap 2 nos. 
    If u are not using QM module, u can still post 101 movement for 10 numbers.  Then you can screap 2 nos with movement type 551.
    Hope this will resolve ur problem.
    Award points if found useful