Dear all,
We send material to subcontractor using movement type-541, but due to some problem the subcontractor has not completed the job and we need to take stock back from him and we will take with 542 mvmt, our requirement is can we generate an inspection lot for this mvmt type( we need to test material coming from subcontractor)
Thanks i n  advance
Madhav

Hi,
I would suggest to post this query in QM forum to get a better help.
However based on my little knowledge on this, you can manually create an inspection lot via QA01. The inspection type would be 08. Maintain this inspection type in the QM view of the material master. Check with your QM personnel if this can meet your need.
Regards,
Vivek

Similar Messages

  • Material Return from 542 movement type without purchase order

    HI Expert
    I have a problem regaring material return from vendor through 542 mov type against purchase order.
    when i transfer material to vendor with mov type 541. and after grv if we return material from vendor against purchase order.
    system doesnot allow to return material against purchase order. it allows mov type 542 for returning material from venodr without pruchase order.
    Suppose we have 10 quality for a component to transfer vendor we take grv and issue 5 qty through 543 move type automatically. if we want to take return 5 remaining qty from vendor against purchase order .
    system doesnot allow to return component from vendor against purchase order.
    but allow  to return component from vendor without purchase order.
    vendor stocks becomes less but purchase order still open for open quantity.
    how we could control vendor's returing material with the reference of purchase order after grv.
    with regards
    sanjay agrawal

    HI,
    Are you creating return Po for subcontracting vendor with item category L.?
    we used movement type 541 to send material to vendor ,now you want movement type 542 in system means take back from vendor?
    I don't think so it will make work and make any sense
    why you are not adjust your component with subcontracting adjustment in sap mm
    check following link
    [http://help.sap.com/saphelp_470/helpdata/en/4d/2b908943ad11d189410000e829fbbd/content.htm]
    Regards
    Kailas Ugale

  • Excisable material return from subcontrator as it is

    Hi SAP Expert,
    I have a question which need to be addressed?
    I have sent a material ( recursive or BOM component) to subcotracter with 57F4 challan of qty 1000.
    Due to some reason qty 200 to be withdraw  using 542 movt .type.
    I want the transaction flow wrt Excise treatment for 542 movt type also for the qty of 200.
    Please help me to resolve the issue.
    With best regards,
    Manoj

    You need to recieve material using 542 mvmt with reference to p.o,reconcile matl doc. using J1IFQ.
    If all quantities were recieved from subcontractor,then you can complete challan using J1IF13

  • Reg Material Return Note

    Dear Gurus,
                       here in our client place they want to prepare material return slip (materials returned from production to stores)  as a form. kindly tell me where to assign output type and how to preview the slip before printing. Thank you

    Hi
    Check this out or refer the forum. I took it from the forum only
    1. Maintain the Printer Name in SPRO->Matl Mgmt->Inv Mgmt and Phy Inv->Print Control->Gen Settings->Printer Setting
    2. Ensure that in SPRO->Matl Mgmt->Inv Mgmt and Phy Inv->Print Control->Gen Settings->Item Print Indicator, 2 stands for return delivery print out
    3. In SPRO->Matl Mgmt->Inv Mgmt and Phy Inv->Print Control->Gen Settings->Print Version, maintain Print Version 2
    4. In SPRO->Matl Mgmt->Inv Mgmt and Phy Inv->Print Control->Maintain Print Indicator for GI/Transfer Posting Documents
    5. In SPRO->Matl Mgmt->Inv Mgmt and Phy Inv->Output Determination->Maintain Output Types, for the Output types WA01,WA02,WA03,WE01, WE02 and WE03, ensure the foll:
    a. Default Values: Dispatch Time is 3 or 4 as per reqmt. and Tr medium is 1
    b. Print Parameter is 7
    6. In SPRO->Matl Mgmt->Inv Mgmt and Phy Inv->Output Determination->Printer Det->Pr Det by Pl/StoLoc, maintain the Output device for all your Plants
    7. Go to MN21, for Tr Type WE, Print Version 3, maintain Print Item as 1.
    Now the settings are ready for Printing Material doc
    8. While doing MIGO, ensure that in General Tab, you get "3 Collective Slip" beside the Print Indicator and you tick mark the field.
    9. Now depending on the setting in 5a, the Matl doc is printed. If it is 3, you have to print it using MB90. If it is 4, it is printed immediately

  • Subcontracting Extra Material Return From Vendor

    Dear Sir,
    We have a following scenario :
    We had made a Subcontract Challan for a Material of quantity 50 nos . Vendor processed the Material and GR was made for 45 nos Processed Items .
    The 5 nos pieces are now left with the Vendor .  Vendor need to return these 5 nos items as it is (Un-Processed) . Kindly guide us as what steps need to be followed to receive back these 5 nos and reconciliation of the subcontract challan .
    I would be highly grateful for the suggested solution pl .
    Rgds
    Sania Agarwal

    Hi
    in subcontracting configuration for CIN you need to give list of movement types for material issue and reversal or consumption. In that you need to add 542 also. Then during reconcillation system will consider 542 documents also along with 543 documents.
    Hope you are clear.
    Regards
    Antony

  • Process for material returns from Customer, mapped in CIN

    Hi Gurus,
    I have some queries (below) pertaining to CIN.
    1. How is the Customer Materials returns is handled in CIN? What is the process flow (transactions)? Since, the goods are returned we can avail the excise duty paid earlier? So, is the RG23A Part 2 and RG1 register updated? How?
    2. Due to incorrect excise values, if cancel the excise invoice, then is the RG23A Part 2 updated? What about RG1 updation? After cancellation of the existing excise invoice, if we create a new excise invoice is the RG1 updated with new Excise duty values?
    Please share your inputs.
    Appreciate a process flow document for above, if anybody has. Please mail at [email protected]
    Thanks,
    Amit

    Hi amith,
    for return process you have to follow RE document type and LR for pgr
    while coming to excise you should have to do J1IEX without purchase order the the values of excise will be reversed .
    it should resolve your issue
    bvdv

  • Material Return/Scrap Material from production generate inspection lot

    Hi experts,
    I would like to confirg the following:
    When material return or scrapped material return from production(mvnt type 262), system is required to generate inspection lot.
    How can I config this scenario?
    Thanks!
    Regards,
    Daniel

    The inspection lot origin '05' is assigned to movement type '262'.
    (You can check this in update control at transaction OMJJ.)
    So you have to activate the inspection type '05' or new one.
    But you should be 'careful' because an inspection lot will be create even if other movement like '501'.
    Regards
    Luke

  • How to enter / Post Goods receipt of Raw Material from subcontractor

    Dear Experts,
    As standard subcontracting procedure, Raw Material Transfer posting is made to Subcontracting Vendor
    and the Semi finished material [Assembly] is received from the subcontractor.
    If in case extra or by any reason, raw material stock is with subcontractor, he want to return the raw material stock.
    How to receive raw material stock from subcontracting vendor and how to handle subcontracting challan transactions in SAP ?
    Thanks in Advance !

    Hi,
    >>Receive the RM using MB1B / 542
    >> Reconcile using J1ifq
    >> Complete challan using J1if13
    Thanks,
    Rajoo

  • Return Material back from Vendor without PO

    We are having problems returning material back from a Vendor without a PO. We had sent some of our product to a Vendor to have them restack the pallets. Now we cannot bring the material back in without referecning the PO. (RGA) (VA01). We are allowed to do this on the sales side of our business when we are dealing with customers but not with a regular Vendor. Is there some flag on the Vendor that I need to check? Please let me k now.

    Hi
    You could do a goods receipt with movement type 501 whish is Goods receipt without a Purchase Order but be careful has this has the effect of making stock appear from nowhere.
    This can be done with transaction MB1C
    I hope that this helps

  • SAP Inventory Manager 4.0 (WM 1.0) issue downloading material returns on Goods Receipt

    Hi all,
    We're facing an issue related to GR and material returns, connecting to SAP backend system.
    On this first screen we're using MIGO transaction and you'll see that we have a PO (4200000027) with one material (MATERIAL-1) which has a pending quantity of 298 EA to be received.
    However, on this second screen, you'll see that when the PO gets downloaded to the Agentry client, it shows that only 295 EA are pending and that it shows that 5 EA has been received, while there are no items reversed or returned.
    Finally, when we go to verify the Purchase History for the material using ME23N transaction, you'll see that indeed 5 EA have been received of the material, but also several returns have been made. So, after calculating the difference, the total quantity of items received are 2.
    From this I understand that the SAP IM application has not downloaded the returns, and that is only considering the receipts that have been done. For that reason, it thinks that 295 EA are pending, when in reality it's supposed to be 298 EA.
    Has anyone faced this issue before? Is this a known bug? Am I missing some configuration?
    Thanks for your help
    -Omar

    Omar,
    I'm not aware of any  known issues with respective to calculation of open  quantity which is   quantity ordered - ( Total received ) - Total returned.  In your case it is not working I guess.
    what I would I suggest is to put  a break point on SAP side for Purchase order fetch and check if it is something wrong with calculations.     if it something to do with calculation then please open OSS message with SAP support team  for IM  4.0 product.
    Thanks
    Manju.

  • How to Customize the Message "No Row Returned" from a Report

    Hi,
    I've been trying to customize the Message "No Row Returned" from a Report.
    First i followed the instructions in Note:183131.1 -
    How to Customize the Message "No Row Returned" from a Report
    But of course the OWA_UTIL.REDIRECT_URL in this solution did not work (in a portlet) and i found the metalink document 228620.1 which described how to fix it.
    So i followed the "fix" in the document above and now my output is,..
    "Portlet 38,70711 responded with content-type text/plain when the client was requesting content-type text/html"
    So i search in Metalink for the above and come up with,...
    Bug 3548276 PORTLET X,Y RESPONDED WITH CONTENT-TYPE TEXT/PLAIN INSTEAD OF TEXT/HTML
    And i've read it and read it and read it and read it and can't make heads or tails of what it's saying.
    Every "solution" seems to cause another problem that i have to fix. And all i want to do is customize the Message "No Row Returned" from a Report. Please,...does anyone know how to do this?

    My guess is that it only shows the number of rows it has retrieved. I believe the defailt is for it to only retrieve 50 rows and as you page through your report it retrieves more. So this would just tell you how many rows was retireved, but probably not how many rows the report would contain if you pages to the end. Oracle doesn't really have a notion of total number of rows until the whole result set has been materialized.

  • No data return from BI7 via MDX drvier in Crystal report

    I have:
    Windows 2000 SP4
    SAP BI7 patch level 16
    SAP GUI 710 patch level 7 (BW3.5 addon patch 3, BI 710 patch 5)
    Crystal report XI R2 SP4
    SAP_Integration_Kit_XI R2-SP4
    and the BW tranports already imported in BI7.
    I can create a report over a Bex query in Crystal report using BW Query driver and retirved datafrom BI7
    Then I tried to create a report over the same Bex query in Crystal report using MDX driver, I got no data return from BI7.
    So I used the RSRTRACE transaction to trace the log when refreshing data in Crystal report, and then go to debug the call 10- GET_CELL_DATA and I have data from the MDX excution in BI7.
    So I think Crystal report can pass the MDX query to BI7 and BI7 can excute it without any problem, the issue is no data return to Crystal report.
    Could anyone help please?
    Thanks.

    [HKEY_LOCAL_MACHINE\SOFTWARE\Business Objects\Suite 11.5\SAP]
    "TraceDir"="C :\\Crystal Report\\"
    [HKEY_LOCAL_MACHINE\SOFTWARE\Business Objects\Suite 11.5\SAP\BW MDX Query Driver]
    "Trace"="Yes"
    "ExcludeSummaries"="Yes"
    Above are the right code in Reg and I have tried "C:\" as well, but still no trace file created.
    I was create the CR MDX report via SAP tool bar (and I create 2 reports base on the same Bex query with MDX and BW query just to compare, that one via BW query return data from BW)
    Thanks a lot.
    Allen
    Edited by: Wen Allen on Aug 25, 2008 5:32 PM

  • Return from customer movement type

    Hello,
    We use in our system 653 mov.type when we return goods from customer.
    Usually we create the return order with reference to the original customer order and the original customer order is MTO (make to order) . When posting the 653 mov.type the system take the cost of the material (VPRS) from moving average price of unrestricted stock.
    My question is : in cases that my return customer order is with reference to original customer order, is it possible to configure a movement type (or other way) that the system will take the cost from the original customer order and not from the cost in unrestricted stock and in advance it will affect the moving average price ??
    I will try to explain by an example:
    I have in stock 10 pieces each for 5 $,
    My return order has 4 pieces that has cost of 8 $ in the original customer order.
    The system behavior today after returning the stock with 653 mov type:
    I have 14 pieces with cost of 5 $ - no change in moving average price and VPRS cost for profitability analysis  is 5 $
    The desirable behavior according to my expectations:
    I will have 14 pieces with cost of (50+32)/14=5.8 u2013 the moving average will change according to cost in original customer order 8 $ and VPRS cost for profitability analysis is 8$.
    I hope I made my self clear enough
    Regards
    Idit

    Hello Kishore,
    Thanks for your answer.
    I can understand the idea that MAP changes only in case of Purchase of material not at time of sales returns.
    But I want to give you a case that causes problems in our view:
    Most of my sale cases are MTO, that means that I buy for order and therefore my MAP will not be affect.
    Example: my MAP 3 $ I buy to order for 5 $ and when I will do GR it will not affect the MAP (101E)
    When I will return the goods (653) I want that the cost from vendor (5$) will affect the MAP because this was the real cost from my vendor but when I return the stock I return it to unrestricted stock.
    I have cases that I transfer sales order stock to unrestricted stock and the MAP is change according to cost of sales order (411E/412E) u2013 it's the same in my logic - the MAP change according to the real cost from vendor.
    I will be happy to have your response.
    Kind Regards
    Idit

  • Goods Return from Production

    How the rejected goods (at prdn) can be return from Production to stores, as the function in production of goods return is not working.( Issued production order of 10 nos, production completed for 8 nos, the remaining 2 are rejected & to be return to stores for further material accounting)

    Shailesh,
    When you are receiving goods after production suppose you have to receive 10 goods out of them 8 are OK and 2 are defective then in the receipt from production form you can enter the first line item by choosing the production Order from the production order Tab below and change the Quantity to 8 which you would like to enter into the Main warehouse while in the next line item manually enter the same Production order no. and in the qty column enter the 2 no.s of Defective goods and change the Wahrehouse no. to Stores. and add the form.
    Now when you see the stock you will notice that in the Stores WH stock will increase by 2.
    Please let me know if this has solved your problem.
    Nagesh

  • Setting up a material master as Subcontractor

    I am looking to set up a material master to pull items from the warehouse and send to alter as another number. This will of course be the standard method for this item. I have two questions
    1. How do I set this up? I am use to production order material masters.
    2. How would I define the costing for this item (cost of component + current quote from subcontractor)? Quotes typically last one year. Can I enter this so the planned order will pull this information? Where would this information be entered?
    Thanks for everyone's assistance!!

    Hi,
          Not sure if this is what you looking for.
          Assuming your component is material A and your new material that this is going to alter into is material B. I will also assume that you are buy B from your subcontractor and giving them A in the process.
          You need to setup B as a HALB and it should have a single component BOM A.
          In the material master MRP view for material B, you will need to set the special procurement as 30 (subcontracting).
          When you raise the Purchase Order for B, you will need to raise this with item category L.
          Hope this help.