Delete a planned order for materials changed to ND (No planning) MRP1 view

Hi guys !
1. I changed the MRP Type "reorder point" to "no planning" (ND indicator in MRP1 view) for some materials.
2. ¿There is a process to regenerate or delete the planned order created before or have to be a manual process, for example from MD15?
Regards & thanks in advanced !

>
FRANCISCO RODRIGUEZ wrote:
> Dear  kumar kumar,
>
> Before put the question, i was testing the MRP with delete & create new planned order but it doesnt work..why? because when you changed the material to ND, the MRP transactions like MD01, MD02, MD03, send a error message: "Material not plannig" so they does not consider the material anymore.
>
>  Definitly, i think to delete in a manual process (MD15).
>
> Thanks to everybody.
Dear,
even i know ND will not plan ( MRP )
My view was before changing to ND, delete the existing header material demand & Run MRP
with option 3, so that system will delete all plan orders of this material ( No Manual process )
Anyways Good Luck !!!
Regards
Madhu

Similar Messages

  • Unable to Delete PO (Purchase Order) due to changed Invoiced value. Helppp.

    If you create a service entry sheet, process the service entry
    approval,post an invoice for an amount greater than the Service entry
    then, cancel
    the entry sheet and add a new service specification (i.e. same entry
    sheet), the following problem occur:
    1. You can no longer cancel the invoice if the services of the entry
    sheet are deleted.
    2. After changing the entry sheet and renewed acceptance of services
    performed, a posting takes place where the value differs from the
    value of the entry sheet.
    Steps to Reproduce:
    1. Create a Service Purchase Order of $2,000.00
    2. Create a Service Entry against the Purchase Order for $2,000.00
    3. Approve Service Entry against the Purchase Order for $2,000.00
    a/c postings Dr Expense $2,000.00
                         Cr GR/IR $2,000.00
    4. Create an Invoice against the Service Purchase Order for $5,000.00
    a/c postings Dr Expense $3,000.00
                        Dr GR/IR $2,000.00
                        Cr Vendor $5,000.00
    5. Revoke the Service Entry
    a/c postings Dr GR/IR $5,000.00
                        Cr Expense $5,000.00
    I am expecting the Reversal of the Service Entry figure is $2,000.00, but instead, the Reversal of the Service Entry figure is $5,000.00. Why is that so? I need to be able to Reverse/Delete the PO.

    If you create a service entry sheet, process the service entry
    approval,post an invoice for an amount greater than the Service entry
    then, cancel
    the entry sheet and add a new service specification (i.e. same entry
    sheet), the following problem occur:
    1. You can no longer cancel the invoice if the services of the entry
    sheet are deleted.
    2. After changing the entry sheet and renewed acceptance of services
    performed, a posting takes place where the value differs from the
    value of the entry sheet.
    Steps to Reproduce:
    1. Create a Service Purchase Order of $2,675.00
    2. Create a Service Entry against the Purchase Order for $2,675.00
    3. Approve Service Entry against the Purchase Order for $2,675.00
    a/c postings Dr Expense $2,675.00
                         Cr GR/IR $2,675.00
    4. Create an Invoice against the Service Purchase Order for $6,452.50
    a/c postings Dr Expense $3,777.50
                        Dr GR/IR $2,675.00
                        Cr Vendor $6,452.50
    5. Create Credit Memo $1,537.00
    6. Revoke the Service Entry against the Purchase Order for $2,675.00
    I am expecting the Reversal of the Service Entry figure is $2,675.00, but instead, the Reversal of the Service Entry figure is $1,537.00. Why is that so? I need to be able to Reverse/Delete the PO. Please help...
    Thank you.

  • Regading deletion of existing order for customer

    hi friends
    i nedd to delete existing order for particular customer when creating new order for that customer by useing API. how to delete order by useing API and one more thing how to do i mean which parameter or procedure useing for that
    thanks
    cahndra sekhart

    Please be more clear about what you're trying: tools used, statements, examples, ...
    I suspect this is no issue with the SQL Developer tool. If it's pure SQL, please post these questions under the dedicated SQL And PL/SQL forum.
    Regards,
    K.

  • User Exit/BADI to Lock Sales order for any changes in VA02 (Excluding Prici

    Hi All,
    I am looking for an User Exit or BADI which disallows any kind of changes in Sales Order on a particular condition.
    This can't b controlled through Authorization, so have to look for an exit. Please suggest.
    If possible, please provide the example.
    Thanks

    Hi,
    Check the user exit MV45AFZZ in this exit u will be finding the Lot of stages where we can control the VA01 or VA02 . Please find the exit with the name SAVE before. Try to check any changes For sales order in CDHDR and CDPOS and give some error message .
    Thanks and Regards,
    Srinivas.

  • How to create automatic Transfer Order for posting change delivery mvt.321?

    Hi,
    We are using HU with WM functionality; While posting stocks after UD, the system creates a posting change delivery instead of directly posting the stock to unrestricted stock from quality stock.
    Now that we have to process the ourbound delivery bu creating a transfer order and confirming it and also do a Post Goods Issue against delivery then only the system posts the stock into unrestricted stock.
    Our client doesn't want to go thro' these process steps. They would like the stock to be posted to unrestricted automatically after UD stock posting (movement type 321). Is there a way out to automatically process the posting change delivery in the background including Transfer order creation and confirmation and PGI please?
    Thank you,
    Regards,
    Madhavkrishnaa.

    Pls see the customizing.
    SPRO:  Logistic Excution>Warehouse management>interfaces-->Define Quality management

  • Need to get order for Adobe Photoshop 13 amended to reflect 32 bit system and for second order for same system deleted.

    I accidentally deleted partially completed order for for Adobe Photoshop 13.  It had my credit card info filled in but not the size of the computer (32 bit VS 64 bit)  I need order page to reflect 32 bit.  Trying to recover original order, I reordered a second Photoshop 13 by mistake and need it to be deleted . I don't know how to get corrections done?

    contact adobe support, https://helpx.adobe.com/contact.html

  • Text Instruction for spipment for materials w/o production order

    Hi all,
    Where can i put text instruction, for the warehouse guy, in sales order for materials that do not require production order.
    I hope i have not made is confusing.
    Genaraly for all the materials which have production order if i put special text in header it appears in production order. so warehouse guy comes to know how to do production.
    Thnaks,
    Utpal

    What is the warehouse guy supposed to do in case no production is required?  If no production is required, the items do not appear on the production order and the production guy has nothing to do.

  • How generate transfer order for release strategy setting

    hi expert,
    I change the value for  one release stragegy-> Classification -> Characteristic (GNETW) amount through t-code SPRO, but i can't get the transfer order for this change? Could you please suggest how to get a transfer order for this change?
    thanks

    i also can update the characteristic through CL20N. My question here, are the two places have the same effert?
    Cheers
    Have a Merry X'mas!

  • How download  data of me2s   'po order for external  services: in cxcel'

    THIS IS sandipan. I am very new in this field . My requirement is when i am going  to me2s  t.code. then i am giving purchasing group , plant , Service Number as input. then it showing purchase doc . , item , porg , matl... , plant , crcy . It's ok. but after that when i am clicking  purchase order it displays Purchase order for external services : overview screen in a hiarirchical view  and no download option is available here.  I need to export the data of that screen to a excel sheet . how Is it possible ? please help me ...
    Moderator message: please do not open multiple threads for the same or similar issue.
    Edited by: Thomas Zloch on Jan 7, 2012 10:22 PM

    Hi
    T165A is used for 'Services Pricing'.
    Please note that for Services PO, you will have two pricing schema.
    1) At PO-Item Level : RM0000 (or whatever you define in schema determination in Purchasing ->Conditions IMG and assign in your vendor master)
    2) At service line level : Based on settings in T165A.
    If you check in Services level conditions screen and click on Analysis, you will find that ZS0001 is triggered.
    Best regards
    Ramki

  • MTO - how to prevent a second planned order for a sales order?

    Dear friends,
    We are working on Make to Order process (Planning strategy group 20).
    No Production/process order is used
    Shop floor uses a different system --> details from planned order is passed to the shop floor system; and finished product is delivered/posted into SAP Sales order stock - through interfaces
    No QM in place
    A typical day-to-day scenario –
    Sales order Qty = 100
    MRP Run à Planned order qty = 100
    Raw materials posted to ‘Sales order stock’
    Planned order is firmed
    For example if Produced qty = 90
    sales order stock of the finished product = 90
    Balance 10 cannot be produced / delivered for various reasons
    Planner posts the raw material to cost center / rejections / own stock etc., and ensures that the ‘sales order stock’ of the raw materials are zero.
    Planner deletes the planned order
    Next MRP run triggers a new planned order for the balance qty 10
    Now, the requirement is to prevent the new planned order getting generated for the balance quantity, during the subsequent MRP run (despite the shortage in the Sales order stock of the finished product).
    The following options have been evaluated –
    Once the final good receipt is done & before deleting the planned order,
    o       Change the Sales order quantity to match the total produced quantity
    o       (or) Change the schedule line category for the Sales order item from CP to CN
    §         Since the Sales order and planned order are handled by different teams, considering the frequency of correspondence/coordination needed between these two teams to get the sales order items corrected, this idea is not accepted
    §         Additional authorization for the planner to change the sales order item is not acceptable
    Include Under delivery / Unlimited tolerances
    o       at the customer (master) level
    o       (or) Sales order level…
    §         In this case, System seems to consider the tolerances only when the  delivery for the Sales order is posted; and not when the sales order stock is received within the tolerance limits;
    §         Considering the time gap between the GR and Delivery of the finished product, this option is not accepted
    Kindly suggest the other options / settings / processes, to meet this requirement
    Thank you for your time and efforts.
    With Best Regards,
    Senthil

    Closing this thread
    Thanks
    Senthil

  • Planning release order for a Stock Transfer Requisition (PRqRel)

    Hello all,
    Is there a possibility to stop MRP/MPS from planning a 'Release order for a Stock Transfer Requisition (PRqRel)' ? I would want them planned after they are released (OrdDS).
    Please do help out.
    Regards,
    Rahul

    Hello again...
    The sample code provided on method CHANGE_MDPSX_MDUA of this BAdI should do the trick:
    method if_ex_md_change_mrp_data~change_mdpsx_mdua .
    *  Makes stock transport purchase requisitions not availability-relevant
    *--> substitutes part of the modification of note 190298.
    * For the other parts the same has to be made in methods:
    * CHANGE_MDPSX_MDUP for stock transport planned orders
    * CHANGE_MDPSX_MDUB for stock transport orders.
    *--> delete flag for availability
       clear ch_mdps-vrfkz.
    *--> set changing flag
       ch_changed = 'X'.
    endmethod. "IF_EX_MD_CHANGE_MRP_DATA~CHANGE_MDPSX_MDUA
    BR
    Caetano

  • Can MRP only create planned orders for ROH, not for FERT?

    HI all,
    Is there any way to only generate planned orders for raw materials after MRP, forbid creating planned orders for FERT?
    We want create planned orders for FERTs manually.
    Thanks,
    Harvey

    Harvey,
    Yes, that was also my understanding of your scenario. Did you try X0 for Fert?  Run MRP against the entire plant, and MRP will not create any new planned orders for the X0 parts.  It will explode the BOM and create dependent requirements in the components.  In addition, you can create FERT planned orders manually, or using an external planning system, and these manually created orders will also create dependent demand on your components.
    If you are also using Sales orders to consume your PIR, you will also have to look at requirements determination for Sales orders.  This is configured based on MRP type.  If you change existing MRP types, you may have to add SD config so as to continue to pass requirements to MRP.  Your SD resource should be able to help you through this, or I can give you basic instructions if you decide that the PIR/demand/planned order/dependent requirements works to your satisfaction.
    Rgds,
    DB49

  • Workflow for Notify Planning team When Reservations For Materials

    Hi,
    Did any one worked on below Workflow Scenrios.
    We need to Notify via Email to Planning team When Reservations For Materials On An Operation Have Been Filled And All Non-Stock Components Have Been Received.
    This request extends the current functionality where when all non-stock components on an operation have been received the operation status is changed to PR (parts received) and an email is sent to the requisitioner (the person who added the non-stock component to the work order).
    Appreciate anyhelp on this
    Regards
    Manish

    Hi Manish,
    it will be great if you could give some more details like transaction you are using.
    what is understood is, you want to send a mail when the status is changed to PR.
    if this is the scenrio, you can use Status Management.
    Please confirm so that i could give you more details.
    Naresh.

  • Workflow for Notify Planning When Reservations For Materials

    Hi,
    Did any one worked on below Workflow Scenrios.
    We need to Notify via Email to Planning team When Reservations For Materials On An Operation Have Been Filled And All Non-Stock Components Have Been Received. This request extends the current functionality where when all non-stock components on an operation have been received the operation status is changed to PR (parts received) and an email is sent to the requisitioner (the person who added the non-stock component to the work order).
    Appreciate anyhelp on this
    Regards
    Manish

    Hi Manish,
    it will be great if you could give some more details like transaction you are using.
    what is understood is, you want to send a mail when the status is changed to PR.
    if this is the scenrio, you can use Status Management.
    Please confirm so that i could give you more details.
    Naresh.

  • Production order for a multiple materials codes...

    Dear...
    Could you please suggest me the SAP solution for the below production strategy.
    This production process is of heat treatment. Actually I am doing heat treatment of Cast and Forge items. These items weights are in the range of 150 kgs to 40000kgs. For example I am having a 40 tons heat treatment furnace. So at a time I can load the materials upto 40 tons. I am having different materials of different sizes and chemical compositions.  But heat treatment cycle(Routing) is same. So I can load different types of materials i.e. upto 40tons for the heat treatment for which same type of heat treatment is required. Sometimes this may be a single item .. if the weight of the items is 40 tons. If it is single item...then there is no problem. If I am loading different items...and if execution process is same for all the items, then how can I map this in the SAP. So that I can create a single order for different Items of different materials and quantity. I need to do the confirmation of these items with respect to the same item. Please suggest me...how can we map this scenario into the SAP.
    Thanks in advance.
    Regards,
    Surya.

    Hi surya,
    As per the heat treatment process concern, total cycle time is constant, and load is also constant (if we havenot changed).
    i hope u have defined workcenter formula and routing accordingly.
    i think creating single production order for multiple material is not possible, instead of thsi, i would suggest one way,
    > Since u have to maintain stock for Heatreated items, create sepearte Material code for each item to be heatreated.
    > Create BOM ,Routing  for New Material code.
    > Acitvate Batch management for New Material Code has been created.
    >Now create Production order for each material to be processed in one cycle, Assign the Batch Number manually.Batch number repersents your Heat treatment cycle number and same can de used for traceability.
    >Confirm the each order seperately, Now the Heatrement process cost will be updated and stock will be posted to heatreated storage loaction.
    But i am worrying about capacity planning and scheduling, For my knowlegde purpose i would like to know your existing scenoria, like workcenter formula and  routing operation values has been assigned , if u wish plz share with us.
    Please come back with your ideas..
    regards
    Pradeep

Maybe you are looking for

  • Discount in separate GL Account

    Hi, we want to capture the discount on order(order management) in separate GL account, Oracle receivables automatically reduces the revenue (Debiting the Revenue account automatically),urgent help is required. Regards Farhan

  • MacBook Pro Hard Disk won't stop filling up!

    I was watching a DVD on my MacBook when suddenly I was prompted with a message telling me I had only 200mb left on my startup disk. I found it odd, and continued watching, only to find that 5 minutes or so later I had only 12kb remaining! Currently i

  • KE30 Report not displaying value in element line  , why ?

    Dear COPA Experts , IN KE30 ,there is a line element displaying for main prodcut (Value field used is Qty ) ,in the Same way i have created new element line for displaying by-prodcut qty (value field used is Qty ) ,after report generated and executed

  • Assigning Numeric Identifiers Based on Group

    Hi there, Currently I have a set of data consisting of an unique identifier (ID), four product properties (Brand.1.1, Brand.1.2, ...), and a preference. What I would like to do is for each product category (i.e. Brand, Price, and Preference) is assig

  • Sender FCC Details

    Hi, How to specify the sender fcc details for following structure <header>    <Record>          <field1>          <field2>