Difference between MRP & MPS

Iyappa D

<copy&paste_and_everything_else_removed_by_moderator>
Girish
Edited by: Julius Bussche on Sep 3, 2008 8:51 AM

Similar Messages

  • Difference between MRP and MPS..

    Hi ALL,
    I am aware that MPS planning is done for the materials which are high-valued....Main aim is to reduce costs and to increase planning stability...
    Also these type of Materials can be planned using MRP...
    Then why do we go for MPS Planning only...?
    Thanks..
    Regards,
    Ameya K.

    Hi Ameya,
    MPS
    1.In the MPS run, the materials  marked MRP Type  as MPS (ie. M0,M1) only will be included . The planned orders are created at the MPS Material level only.
    2.The BOM is exploded for next one level down only.Further level will not be exploded,that means Dependent requirements are created for the BOM components one level down, further level will not  processed.
    This allows MRP controller can ensure that the MPS items are correctly planned  before any MRP run takes place. This allows the planner to check and change the planning result, before any MRP run takes place for other materials.
    For example,consider this business scenario, suppose one wants to do planning for finished Goods once pre week, but it is necessary to do planning for their components on daily basis.
    so for this exmple, you can define Finished materials with MRP type as MPS and all the components with MRP type as MRP.
    MPS run is carried out before the MRP run. So that the Planner can ensure planning result before the MRP run.
    MRP.
    MRP Run will plan  all  BOM level of  Materials.
    i hope i have tried  to clear your doubt some what.
    for more information please see following links
    http://www.sap-img.com/production/difference-between-mrp-vs-mps.htm
    http://www.sap-basis-abap.com/sappq002.htm
    thanks
    pradeep.

  • Difference between  MRP & CBP

    Dear All,
    Can any body  tell me what is the difference  between MRP  &  consumption base planning (CBP),
    Best regards,
    ABBAS

    http://help.sap.com/printdocu/core/Print46c/en/data/pdf/MMCBPCBP/MMCBPCBP.pdf
    Materials Requirements Planning (MRP)
    MRP is a planning tool geared specifically to assembly operations. The aim is to allow each manufacturing unit to tell its supplier what parts it requires and when it requires them. The supplier may be the upstream process within the plant or an outside supplier. Together with MRP II it is probably the most widely used planning and scheduling tool in the world. MRP was created to tackle the problem of 'dependent demand'; determining how many of a particular component is required knowing the number of finished products. Advances in computer hardware made the calculation possible.
    Master Production Schedule
    The process starts at the top level with a Master Production Schedule (MPS). This is an amalgam of known demand, forecasts and product to be made for finished stock. The phasing of the demand may reflect the availability of the plant to respond. The remainder of the schedule is derived from the MPS. Two key considerations in setting up the MPS are the size of `time buckets' and the `planning horizons'. A `time bucket' is the unit of time on which the schedule is constructed and is typically daily or weekly. The `planning horizon' is how far to plan forward, and is determined by how far ahead demand is known and by the lead times through the operation. There are three distinct steps in preparing an MRP schedule:
    exploding
    netting
    offsetting.
    Exploding
    Explosion uses the Bill of Materials (BOM). This lists how many, of what components, are needed for each item (part, sub assembly, final assembly, finished product) of manufacture. Thus a car requires five wheels including the spare. BOM's are characterised by the number of levels involved, following the structure of assemblies and sub assemblies. The first level is represented by the MPS and is 'exploded' down to final assembly. Thus a given number of finished products is exploded to see how many items are required at the final assembly stage.
    Netting
    The next step is 'netting', in which any stock on hand is subtracted from the gross requirement determined through explosion, giving the quantity of each item needed to manufacture the required finished products.
    Offsetting
    The final step is 'offsetting'. This determines when manufacturing should start so that the finished items are available when required. To do so a 'lead time' has to be assumed for the operation. This is the anticipated time for manufacturing.
    The whole process is repeated for the next level in the BOM and so on until the bottom is reached. These will give the requirements and timings to outside suppliers.
    There are three major assumptions made when constructing an MRP schedule:
    The first, and possibly the most important, is that there is sufficient capacity available. For this reason MRP is sometimes called infinite capacity scheduling.
    The second is that the lead times are known, or can be estimated, in advance.
    The third is that the date the order is required can be used as the starting date from which to develop the schedule.

  • Difference between MRP & SRP

    Hello everyone,
    Can anyone help me out by providing me the difference between Material Requirement Planning (MRP) & Stock Requirement Planning (SRP)
    Regards,
    Indranil

    http://help.sap.com/printdocu/core/Print46c/en/data/pdf/MMCBPCBP/MMCBPCBP.pdf
    Materials Requirements Planning (MRP)
    MRP is a planning tool geared specifically to assembly operations. The aim is to allow each manufacturing unit to tell its supplier what parts it requires and when it requires them. The supplier may be the upstream process within the plant or an outside supplier. Together with MRP II it is probably the most widely used planning and scheduling tool in the world. MRP was created to tackle the problem of 'dependent demand'; determining how many of a particular component is required knowing the number of finished products. Advances in computer hardware made the calculation possible.
    Master Production Schedule
    The process starts at the top level with a Master Production Schedule (MPS). This is an amalgam of known demand, forecasts and product to be made for finished stock. The phasing of the demand may reflect the availability of the plant to respond. The remainder of the schedule is derived from the MPS. Two key considerations in setting up the MPS are the size of `time buckets' and the `planning horizons'. A `time bucket' is the unit of time on which the schedule is constructed and is typically daily or weekly. The `planning horizon' is how far to plan forward, and is determined by how far ahead demand is known and by the lead times through the operation. There are three distinct steps in preparing an MRP schedule:
    exploding
    netting
    offsetting.
    Exploding
    Explosion uses the Bill of Materials (BOM). This lists how many, of what components, are needed for each item (part, sub assembly, final assembly, finished product) of manufacture. Thus a car requires five wheels including the spare. BOM's are characterised by the number of levels involved, following the structure of assemblies and sub assemblies. The first level is represented by the MPS and is 'exploded' down to final assembly. Thus a given number of finished products is exploded to see how many items are required at the final assembly stage.
    Netting
    The next step is 'netting', in which any stock on hand is subtracted from the gross requirement determined through explosion, giving the quantity of each item needed to manufacture the required finished products.
    Offsetting
    The final step is 'offsetting'. This determines when manufacturing should start so that the finished items are available when required. To do so a 'lead time' has to be assumed for the operation. This is the anticipated time for manufacturing.
    The whole process is repeated for the next level in the BOM and so on until the bottom is reached. These will give the requirements and timings to outside suppliers.
    There are three major assumptions made when constructing an MRP schedule:
    The first, and possibly the most important, is that there is sufficient capacity available. For this reason MRP is sometimes called infinite capacity scheduling.
    The second is that the lead times are known, or can be estimated, in advance.
    The third is that the date the order is required can be used as the starting date from which to develop the schedule.
    Hope this helps you.
    Do award points if you found them useful.
    Regards,
    Rakesh

  • Difference between MRP group and plant parameters

    hai friends,
    please let me know, what is the main difference between the MRP group and plant parameters?,
    what are the extra activities or features with one, when compare to the other?.
    Edited by: Mourya.v on Sep 22, 2010 6:36 AM

    Dear Mourya,
    Why to assign MRP group? - If planning for each plant is not specific enough for your purposes and you would like to assign
    control parameters that differ from the control parameters defined for the plant to certain material groups.
    1.For all materials without an MRP group, the system uses the plant parameters that is the settings present in OPPQ, or the
    entries in the initial screen of the planning run.
    2.For all materials with an MRP group, the system uses the parameters recorded in the MRP group that is the settings in OPPR.
    3.The MRP group is an organizational object that can be used to allocate special control parameters for planning to a group of
    materials. You can maintain MRP groups if planning control per plant is not precise enough for your requirements and you want
    to allocate certain material groups different control parameters from the plant parameters. For this purpose, MRP groups are
    defined with these specific control parameters and are assigned to the material in the material master record (MRP 1 screen).
    4.The MRP group, groups material from the material requirements planning point of view to allocate them control parameters for
    planning.The control parameters include the strategy group, the planning horizon and the creation indicator for the planning run.
    Also check this link [Settings in OPPQ & OPPR|oppr and oppq]
    Regards
    Mangalraj.S

  • Difference between MRP Type

    Hi Experts:
    Anybody can explain me about Types P1, P2, P3, P4?
    Thanks.
    Diego

    Please check this..
    [http://help.sap.com/printdocu/core/Print46c/en/data/pdf/PPMRP/PPMRP.pdf]
    And
    MRp Type P1 or M1:
    Ans: THe order proposal that lies within the planning time fence is firmed automatically as soon as its date lies at least one day before the finish date of the planning time fence. The date of new order proposals that are actually created in the planning time fence are rescheduled out to the end of the planning time fence. Therefore, these new order proposals are not firmed
    MRP type P2 or M2:
    Ans: An order proposal that lies within the planning time fence is automatically firmed as soon as its date lies at least one day before the end of the planning time fence. The system does not create any new order proposals within the planning time fence. That is, the shortage situation is not adjusted within the planning time fence.
    MRP type P3 or M3:
    Ans: Order proposals that lie within the planning time fence are not firmed automatically. The order proposals required to cover the requirements are moved to the end of the planning time fence
    MRP type P4 or M4:
    Within the planning time fence, the system creates no order proposals automatically. That is, the shortage situation is not adjusted within the planning time fence.
    M4 is to classify the MS parts and P4 is for normal MRP items. BOm will be exploded in both cases to lower levels if procurement proposals created within or outside the time fence.
    karthick

  • Difference between MRP Type PD and VB

    Hi All,
    I have a scenario, in which i have some doubts which i have mentioned below.
    1. MRP Type 'PD' with maintaining Safety stock for the materials which have longer lead time. Will the safety stock which exists will cover both excess material consumption within the replenishment lead time and any additional requirements that may occur due to delivery delays.
    2. MRP Type 'VB' with maintaining Safety stock, reorder point, Maximum stock level for the materials which have longer lead time. Here the safety stock which exists will cover both excess material consumption within the replenishment lead time and any additional requirements that may occur due to delivery delays.
    3. MRP Type 'ND' with maintaining Safety stock.
    Of all these 3 MRP Types, what will be the outcome after doing the MRP Run? Should I go for separate MRP run for VB type materials?
    Please give the solution.
    Regards,
    Ram

    Hi Ram,
    PD: this requirement type considers teh requirements in terms of Sales orders,PIRs stock transfer requireements etc for the material and then does the net requirement calculation and creates procurement proposals accordingly. it also considers safety stock while doint the net requiremetn calculation.
    VB: generally used for items with a fairly consistent consumption pattern. here the requirement depends on the safety stock and the current stock. if the current stock goes below the reorder point, then only a requirement is generated. besides the safety stock it does not consider any othe requirement.
    ND; these items are not planned. so no effect of MRP run
    normally for the VB type materials, a background job is scheduled that does the MRP run at predefined schedules.
    even for items with PD, the MRP job can be scheduled at predefined intervals according to the MRP controllers or some other parameters like production schedulers, MRP group etc.
    please let me know if u need more details
    Edited by: vishal ashar on Jan 21, 2009 7:22 AM

  • Difference Between VB & PD

    Dear All
    I am basically PM consultant & trying to learn MM module. What is the difference between MRP type VB & PD??
    Regards

    Hi,
    MRP type PD is net requirement planning:Which means system will check how much stock is availiable and how much is the requirement.If there is a shortage then system will create procurement proposals
    MRP Type VB:Manual reorder point planning:Here you need to define reorder point in material master in MRP view.When the stock level reaches the re order point then system will create a procurement proposals
    Regards,
    Manish

  • Mrp & mps

    hi friends,
    coud u plz solve my issue given below.
    we have seperate background jobs for running MRP(daily) and MPS(weakly once). can 1 material participate in both MRP & MPS.
    thanks in advance.
    regards,
    priya s

    Ideally it may not be feasible as the demarcation between MRP & MPS is based on MRP Types
    A material can have either MRP Type i.e. PD or P1 - P4 & if it is of MPS; it will have MRP Type M0 to M4
    How can a material have both types of MRP Types?
    Second thing; the MPS run is conducted without a BOM explosion whereas during MRP run system will not plan MPS parts again but only dependent assemblies and parts will be planned & clubbing both for a common material does not seem to be feasible
    However if u find some solution; do revert
    Rgds

  • Difference between To maintain and initial in plant parameters in MRP custo

    Hi, Gurus,
                  Can anyone explain me about the difference between status showing
    to maintain and initial in plant parameters in MRP customization
    Thanks & Regards
    sathyanarayana

    Dear Sathyanarayana,
    In T code OPPQ - Maintain Plant Parameters,it does not
    mean we have to maintain a value in all the parameters
    present under different tab keys.
    IF you check generally MRP controllers,Floats,Number
    Ranges,BOM/Routing Selection,Planning horizon,Available
    stock these values will be maintained.
    Some of the settings like Start in Past will be as Initial(not
    allowed in the past).
    IF you use some special procurement key,then that settings
    has to be maintained.
    I hope this will help you.
    Regards
    Mangal

  • Difference between firming types

    Hello Experts,
    Since I am newbie, my question may be too obvious.
    What is the difference between firming type 0 and 4, and between 1 and 3 ?
    As I see that in the difference between 1 and 3 is:
    In case of 1 only the order proposals which date lies at least one day before the end date of the planning time fence are created, but with date after PTF. That means that order proposals on the last day of PTF are ignored? What is the logic?
    Thanks in anticipation,
    Artashes

    Hi,
    Firming type0: No firming to receipts, only applicable to MPS parts to diffrenciate between normal MRP iteams PD and MPS itesm. M0. No firming.
    Firming type1:: An order proposal that lies within the planning time fence is firmed automatically as soon as its date lies at least one day before the finish date of the planning time fence. The date of new order proposals that are actually created in the planning time fence are rescheduled out to the end of the planning time fence. Therefore, these new order proposals are not firmed
    Firming2: An order proposal that lies within the planning time fence is automatically firmed as soon as its date lies at least one day before the end of the planning time fence. The system does not create any new order proposals within the planning time fence. That is, the shortage situation is not adjusted within the planning time fence.
    Firming type3: Order proposals that lie within the planning time fence are not firmed automatically. The order proposals required to cover the requirements are moved to the end of the planning time fence
    Firming typ4: Within the planning time fence, the system creates no order proposals automatically. That is, the shortage situation is not adjusted within the planning time fence.
    If helps rewards points.
    Regards
    TAJUDDIN

  • What is difference between adjusting columns these two ways?

    Hi everyone,
    In my last post I learned that I could create a new Master Page that is designed as a 1-column format and apply it to the body pages I want to have as 1-column. (I have a doc that has 2-column formatted L and R master pages; only 1 page at the very end, the Study Guide, needs to be 1-column formatted).
    I recently learned from the Adobe lesson book that if I am in the body page that I want to change from a 2-col to a 1-column format, I can go Graphics>Object Properties and this brings up the Customize Text Frame window where I can change the number of columns to 1 and click set. I found this a lot easier than creating a new Master Page.
    What is the difference between applying a one-column design to one page using each of these methods, applying a 1-column master page versus just changing the number of columns as described above? Is one wrong or better than the other?
    Thank you for your help!!

    There are 3 basic* ways of obtaining a custom layout for specific pages:
    hack the local column layout
    apply a new master Page as a local override:
    Format > Page Layout > Master Page Usage > Use Master Page
    map the new MP in semi-automatically:
    Format > Page Layout > Apply Master Pages (AMP)
    1 & 2 are not stable. Unless it's a disconnected flow, adding or deleting text prior to that page can cause your special-needs text to re-flow onto a page with normal Left/Right layout (and unexpected text flowing onto your special layout).
    1 is also at risk from an update to the Left/Right MPs themselves.
    3 requires that some paragraph on the special-needs page have a unique format name (say, "Heading2_Single"). After you perform your first AMP, an UnstructMasterPageMaps table is created on Reference Page MasterPageMaps. Add the special para name, and the special MP name to it. Thereafter, AMP will make sure that text gets the page it needs.
    You can also perform an AMP during Update Book.
    It is not reliable in FM 7.x. I don't know about later versions.
    I always use technique #3, and perform a separate AMP as part of the pre-print workflow.
    * You can also fake the layout in some cases, on the normal page layout, by putting the special needs flow in a table or text frame within an anchored Frame. Anchor to an Across-All-Columns format as needed. It wouldn't be Framemaker if there weren't at least 5 ways of getting the same result .

  • What is the difference between scheduling agreement and delivery schedule

    Hi
    1. Can anyone explain me the difference between scheduling agreement output
        and scheduling agreement delivey schedule
        Will the both look same in T.code SP02 when seeing the output for a document.
        Can anyone send me T.codes for above ones in purchasing.
    2. when seeing the Detailed statement for rebate agreement,there is item number.
        In which table can we see the item number for rebate agreement

    Hi,
    If you have to deal with more complex situations, you can define a delivery cycle in the material master record in addition to the planning cycle. In so doing, you determine the days on whichthe vendor delivers his goods. The delivery cycle is entered in the material master record as a planning calendar in the Planning calendar field.
    You enter a delivery cycle if the delivery date (or the goods receipt date) depends on the day on which you order the goods. For example, you carry out the planning run and place your orders on Mondays and Tuesdays. If you place the order on Monday, the delivery is made on Wednesday, if you wait until Tuesday to place the order, the delivery is not made until Friday
    Where as Planning calander is Three character number (numeric or using letters) that specifically identifies a PPS-planning calendar. The difference between Planning calender and delivery cycle is If you have selected the MRP type "MRP" and have set a period lot-sizing procedure according to planning calendar, you enter here which planning calendar is to be used.
    If you selected the "time-phased planning" MRP type, the planning calendar that you specify here defines the delivery cycle. This specifies the days on which the vendor delivers the material. You can enter the planning cycle in addition to the delivery cycle

  • Difference between Delivery, Sales order and  Shipment

    Hi
    I would like to know difference between sales document, delivery document and shipment.
    When is the delivery created? What data will it have?

    Hi
    <b>Sales Documents </b>
    Sales-related business transactions are recorded in the system as sales documents. These are grouped into four categories:
    Pre-sales documents: inquiries and quotations
    Sales orders
    Outline agreements, such as contracts and scheduling agreements
    Customer problems and complaints, leading to free-of-charge deliveries and credit memo requests
    If your particular business processes require it, you can process deliveries and billing documents directly from a sales document. In addition, some sales documents, such as cash sales and rush orders automatically trigger the creation of subsequent delivery and billing documents.
    Basic Functions Within Sales Order Processing
    During sales order processing, the system carries out basic functions, such as:
    Monitoring sales transactions
    Checking for availability
    Transferring requirements to materials planning (MRP)
    Delivery scheduling
    Calculating pricing and taxes
    Checking credit limits
    Creating printed or electronically transmitted documents (confirmations and so on)
    <b>Delivery Processing</b>
    In its role as central object of the goods issue process, the outbound delivery supports all shipping activities including picking, packing, transportation and goods issue. During the outbound delivery process, shipping-planning information is recorded, status of shipping activities is monitored and data accumulated during shipping processing is documented. When the outbound delivery is created, the shipping activities, such as picking or delivery scheduling, are initiated, and data that is generated during shipping processing is included in the delivery.
    Range of Functions
    An outbound delivery can be created as follows:
    With reference to a sales order
    With reference to a stock transport order
    With reference to a subcontract order
    <b>Shipping </b>
    Shipping is an important part of the logistics chain in which guaranteed customer service and distribution planning support play major roles.
    In shipping processing, all delivery procedure decisions can be made at the start of the process by
    Taking into account general business agreements with your customer
    Recording special material requests
    Defining shipping conditions in the sales order
    The result is an efficient and largely automatic shipping process in which manual changes are only necessary under certain circumstances.
    Integration
    The Shipping component is integrated under the Logistics Execution component. Shipping is a subsequent activity of the Sales component.
    Range of Functions
    The shipping module supports the following functions, which include but are not limited to:
    Deadline monitoring for reference documents due for shipment (sales orders and purchase orders, for instance)
    Creating and processing outbound deliveries
    Planning and monitoring of worklists for shipping activities
    Monitoring material availability and processing outstanding orders
    Monitoring the warehouse's capacity situation
    Picking (with optional link to the Warehouse Management system)
    Packing deliveries
    Information support for transportation planning
    Support of foreign trade requirements
    Printing and transmitting shipping documents
    Processing goods issue
    Controlling using overviews of
              o Deliveries currently in process
              o Activities that still are to be carried out
              o Possible bottlenecks

  • Differences between MD01 and MD02.

    Dear SAP Experts,
    Please tell me the various differences between MD01 and MD02.
    In which specific cases, MD01 should be used??
    Thanks and regards,
    Kaushik Basu.

    Hi,
    1. Md01 is the MRP Run for  plant by giving planning scope.
    2. Md02 is the mrp run for single Material from plant .
    Also refer following T code for your information
    Menu Nodes
    Transaction
    Activity
    Master Data
    MD25
    Create planning calendar
      MD26
    Change planning calendar
      MD27
    Display planning calendar
      MDSA
    Display BOM explosion number
      MDSP
    Edit BOM explosion number
      MEQ1
    Maintain quota file
      OPPP
    Explode BOM by date
      MDUS
    Display project assignment
      MDUP
    Process project assignment
      MDL1
    Create production lot
      MDL2
    Change production lot
      MDL3
    Display production lot
    Planning
    MD20
    Create planning file entry
      MD21
    Display planning file entry
      MDAB
    Set up planning file entry in background
      MDRE
    Check planning file entry
      MD01
    Total planning online
      MDBT
    Total planning in background
      MD03
    Single-item, single-level planning
      MD02
    Single-item, multi-level planning
      MD43
    Interactive single-item planning
      MD50
    Multi-level, make-to-order planning
      MD51
    Multi-level project planning
      MF52
    Display planning table
      MF50
    Change planning table
      MF57
    Planning table by MRP lists
      MF51
    Planning table by production list
    Evaluations
    MD04
    Stock/requirements list
      MD07
    Collective access of stock/requirements lists
      MD05
    MRP list
      MD06
    Collective access of MRP lists
      MDLD
    Print MRP list
      MD45
    Planning result
      MD46
    Collective access of planning result
      MD44
    Planning situation for a material
      MD47
    Planning situation for a product group
      MD48
    Cross-plant planning situation
      MD4C
    Order report
      MD09
    Pegged requirements
      CO46
    Order progress
    Planned Order
    MD11
    Create planned order
      MD12
    Change planned order
      MD13
    Individual access of planned order
      MD16
    Collective access of planned orders
      MD14
    Individual conversion of planned order into purchase requisition
      MD15
    Collective conversion of planned orders into purchase requisitions
      MDUM
    Convert planned order into purchase requisition in background
      CO40
    Convert individual planned order into production order
      CO41
    Collective conversion of planned orders into production orders
      CO48
    Partial conversion of planned order into production order
      COR7
    Individual conversion of planned order into process order
      COR7_PC
    Collective conversion of planned orders into process orders
      COR8
    Partial conversion of planned order into process order
      MDVP
    Collective availability check
      MDAC
    Execute action for planned order
    Hope it clear to u.
    Edited by: Atul Zod on Nov 21, 2008 6:59 AM

Maybe you are looking for

  • BRIDGE CS3 - No thumbnails in Photo Downloader and no convert to dng

    I just installed Windows 7 and CS3. I also ran AdobeBridge 1.0.4 updater. I no longerhave thumbnail previews in the Bridge Photo Downloader, or in Bridge, and the Convert to PNG does not work. I am also now unadble to even open my .NEF files. I get a

  • Disappearing Swatch Library

    I frequently use Pantone solid coated colors in my work, and have to open that palette anew each time Illustrator has been restarted.  I know that in CS4 I could keep that palette available, but I haven't been successful doing the same in CS5.  I hav

  • How do I get money back from App that keeps purchasing without authority?

    Tap pet hotel keeps taking money from me how do I get it back I hav enow delted the app from computer and devices

  • Traversing DOM very very slow

    I've an XML Document quite big (240K) with a root, 800 first level nodes and an average of 6-10 second level nodes for each first level. I read the document from a file (very fast) and the I loop 2 or 3 times using data to transfer them in the legacy

  • Validity index in scheduling agreements

    Hi everybody, For contracts it is possible to call up a list with VA45 without entering a sold-to party, material or purchase order number. This is possible, because the validity index was activated. We tried the same for VA35, but it still doesn't w