ETO/MTO/MTS

Hey All
Can anyone tell me what the implications are of choosing a specific strategy group in create material (MRP 3). Does my choice here affect anything elsewhere in SAP?
(For example: Is it possible to put a product into inventory if it is registered as MTO or ETO?)
Thank you
Nina
Message was edited by:
        Nina Henriksen

Strategy group will decide how the production planning is to be carried out.
How the sales orders to be treated, how the PIR to be treated, how the net qty to be produced - is calculated.
There are many stg groups which will give different results depending on the fields in MRP3 view.
To get the detailed idea please go through the link below
http://help.sap.com/saphelp_47x200/helpdata/en/cb/7f9b7043b711d189410000e829fbbd/frameset.htm

Similar Messages

  • HI All --MTO-MTS-ETO

    Hi All
    can any one explain
    What  is the procedure of MTO , MTS & ETO
    Explain

    Hi Prakash,
    make to order:
    it is a buisness scenario where the company produces goods according to the
    needsand specifications of the customer,the product sold is not stored on the shelves.the product could be very similar but merely change a portion for differen t of its forms for different sales orders.the production cycle is trigered according to how the customer likes to see the product but not the company.
    Make to order Scenario
    1. Make-to-order production is a process in which a product is individually manufactured for a particular customer. In contrast to mass production for an unspecified market where a material is manufactured many times, in make-to-order production a material is created only once though the same or a similar production process might be repeated at a later time.
    2. You can use make-to-order production: (a) For branches of industry or products where a small quantity of products with a large number of different characteristics are manufactured (b) When a product has to be assembled particularly for a sales order.
    3. Stock keeping is not usually carried out for products that are made to order. In companies using make-to-order production, the demand program only determines the production area, in which various variant types are produced. Depending on how you track the costs associated with make-to-order production, there are two ways to process make-to-order items during sales order processing.
    (a) Make to order using sales order
    (b) Make to order using project system (not relevant for SD application)
    4. for make to order production using the sales order, all costs and revenues involved for an order item are held collectively at that item. A particular rule is used that can be changed manually to transfer costs to profitability analysis.
    5. make to order production is largely a production planning configuration. It is also controlled by the requirements type, which is determined by three things
    the strategy group (MRP 3) in MMR
    the MRP group (MRP1) in MMR
    the item category and MRP type (MRP 1)
    6. Make-to-order production is controlled by the requirements type. The requirements type is determined on the basis of the MRP group (MRP1) and the strategy group (MRP3) in the material master record. In addition, a plant must be assigned for make-to-order items in the sales order.
    make to stock:
    here the production is done irrespective of the customer orders, it is usually done on the basis of the sales forecasts not on the customer specifications, it is usually a push strategy,company produces the products and they are sold.
    there is no customising of the product.
    STO
    Whenever you need to transfer the materials from one plant to another plant belonging to one company or belonging to two company code stock transfer order is raised by the delivering company.
    STO:
    Transfer of goods from one location to another location,it may be between plants within the same company code or in different company code's plants.
    within the company code,bet plants, receiving plant will raise the STO in Supplying/issuing plant-ME21n,
    Supplying plant will deliver the goods to receiving plants , then we need to pick n post the Goods Issue-VL02n, nw when we can observe that the STO qtty will be added into receiving plant and reduced in Delievering plant.
    Configure Intercompany Stock Transport Order
    Material should exist in both the plants (Delivering & Ordering),
    Internal customer should be assaigned to the ordering plant ( MM -> Purchasing -> Purchase Order -> Setup stock transport order -> assign the internal customer to the ordering plant and assign the Sales area of the internal customer.
    Assign its Sales area to the delivering plant
    Assign the document type and Delivery type NB and NLCC
    Assign the Supplying plant --> Receiving Plant --> NB
    Take the delivering plant and assign the sales area.
    Vendor master has to be created and assaign the supply source ( Delivering Plant).
    Create a puchase order ME21N ---> Save
    Delivery VL10 G ---> Calculation rule (appropriate) --> Assaign the purchase order number here nt. and execute.
    Select the Delivery creation line and do the back ground process.
    Start the log display and see the delivery document number by the documents button
    Goto VL02N --> do picking and PGI --> Then do the MIGO with respect to the delivery docume
    Billing (Intercompany pricing conditions should be set).
    Assign points if useful

  • Reg. Accounting Revenues for MTO & MTS in SAP PP

    Hi all,
      I am having few doubts in Costing aspects of SAP PP.
    What is Accounting revenues for MTO & MTS scenario how its to be defined.Please explain?
    What are the Costing impacts of SAP PP.How the Costing of a Product in the production aspects to be addressed.What are the prerequistes for that.Please provide me help materials with detailed examples.
    Thanks in advance,
    M.Badrinarain.

    Dear Badri,
    Plz refer the below link, this is current thread of CO Forum, Reply by Mr. Mangalraj
    [Product Costing;
    Regards
    kumar
    Edited by: kumar kumar on Nov 9, 2009 11:07 AM

  • Material Issue for both MTO & MTS

    Dear Guru's
    I have to do REM Backflush for a MTO scenario.
    The corresponding raw material are available in stock which was not purchased over a period of  time.
    When I try to do post with correction the system is not allowing me to do the posting, the system is giving error as sales order item is not available.
    Can anyone help me consumming the raw material available in the stock .
    Is there any settings to be done to consume the material which is available in the stock for bothe MTO & MTS.
    Kindly do the needful.
    Helping hands will be appreciated with good points.
    Thanks & Regards,
    Arul.

    Hi Arul
    Please check the below in your DEV server.
    If you put the Individual/coll indicator to 2 in MRP 4 view in material master the raw materials can be taken from unrestricted use stock while back flushing.
    Or
    IN MB1B you can use mvmt type 412E to convert unrestricted use stock to sales order stock.
    SO u can do the backflushing after the conversion.
    Cheers
    JOJI

  • FOR MTO & MTS scenario when the Production order shows the Sysy status DLV?

    Hi ALL,
    In the MTO & MTS  scenario when the Production order system status become DLV ?
    Regards
    Satish

    Hi Satish,
    For both the planning strategies (MTO/MTS)..
    The status of the production order becomes DLV ,
    when you do GR for the order with 101 movement type.
    (OR) 
    At the time of final confirmation if automatic goods receipt is activated.
    Regards,
    Anil

  • MTO & MTS

    Hello Gurus,
    What are the MTO & MTS. Explain me clearly with example.
    Bye

    Hi,
    MTO  - Acronym for Make -To- Order. Material which are made against a specific sales order / project / network order. The requirement created for MTO materials will be individulal. Stock of the materil will be maintained in separate stock segment of the order / project. Stocks can be valuated on non-valuated. In valuated stock, every material movement creates a corresponding accounting document, whereas in non-valuated stock materal movements do not create aaccounting document. production orders / puchase orders for MTO materilas will be account assigned to sales orders / networks / WBS element etc.
    MTS - Acronym for Make-To-Stock. Stock is maintained at plant level. There is no separate stock segment. Production order / Purchase order etc. are not account assigned. Every material movement creates an accounting document.Requirements / inventory are mainatained and tracked at plant level.
    Hope it provides basic information sought by you.
    Regards
    Muraleedharan.R

  • MTO/MTS--------------------Yesterday

    Hi all
    Very one Explined MTO/MTS Yesterday very nice
    Can any one send materail for configration
    pls

    hi,
    Business procedures material based on MRP irrespective of the sales order ie Make to order
    If the standard product is going to be change slightly according to the customer requirement then businss manufacturing that particular material for particular customer called as Make to order.
    Inventory is going to be maintained in special stock indicator E order inhabd
    Configuration
    Create material master by maintaining general item category group- 0001(make to order)
    Availability check - 02
    Transportation Group - 0001
    go to va01 and raise sales order
    item category:TAk
    Schedule line category : cp
    Requirement type KE
    Requirement class 040
    Check TOR and avalability check
    special stock : E
    VOV7
    of TAK
    billing relivence : A
    Pricing :X
    go to mb1c
    maintain stock with a special stock indicator E
    mavement type 61
    Special stock E
    specify sales order number line item number and saveit
    go to VL01N main data
    Go to VF01
    save it
    note for make to order you cannot maintain availability check
    sreekanth.vaka

  • Re: MTS to MTO+MTS

    Dear Expert,
           we are currenlty using MTS scenario & now plannig for MTO + MTS scenario. For fert level we will do MTO & Semifinish, raw material level will do MTS scenario.
    can any one tell how to map this scenario/any configuration changes ?
    which plannig strategies are need to be used in material master?
    i have tested with Planning stratgies 20 but it is not generating accounting document, so please help me.
    Regards,
    Ishwar J

    Dear Ishwar,
    1.First check whether planning strategy 50 will be suitable your business requirement,here PIR's will be entered at FERT
    material level and all the planned orders for the dependent requirements can be converted and produced and kept in stock ,but
    for the final product alone only after recieving a sales order its planned order can be converted into production order.
    The system generates a planned order which is convertable.
    2.In this case if this not suitable check with planning strategy 40.
    3.If this is not suitable means create a strategy group by combining one make to stock and one make to order planning strategy
    and check the output.
    Regards
    Mangalraj.S

  • Difference between MTO/MTS vs Consumption Based Planning?

    Hi,
    What is the Difference between MTO/MTS vs Consumption Based Planning?.
    In what scenario we used these types?? could you please explain me with examples...
    Regards,
    Raj

    Hi,
    MTS = Make to stock, you are simply wanting to build up stock and so this will generate requirements even if there are no Sales orders or demand of any kind. This is the most common option
    MTO = make to order, you only want these items when there is a specific
    But consumption based planning is not completely different, you are still using MTS / i.e. you are creating requirements based on the settings in MRP instead of any demand (but the same applies to MTS)
    So MTS and consumption based planning are more or less the same thing.
    You would use MTO if you produce items only when you have an order.
    So if you have warehouse space and sell a lot of an item, you can use MTS or consumption based planning because you know that you will always be likely to be able to sell the stock.
    If you make things for specific orders (such as special sizes or specifications to match the customer's requirements. Or if you don't sell many of an item and the lead times for production are very short (or you don't have much warehouse space) then you would wait for an order before making the item (MTO
    Steve B

  • Re: MTO & MTS for same product

    Hi Experts,
    How to configure both MTO & MTS for a same product.
    Regards,
    Vivek

    Hi Experts,
    I am having a requirment for MTO Subcontracting order.The customer issues raw material for the production for the FG product. Now I want that the system should do the Planning for the FG by MRP & also to calculate the the raw material required. The system should also be able to created purchase requisition for the deficit raw material. The raw material should not have any financial implication i.e. they are are only relevent for stock posting & not for any valuation purpose.
    Here my client is the subcontractor. So he does production for Other clients as well.
    Please advise.
    Regards,
    Vivek

  • Mto /mts/eto -process difference

    Hi
    what is the diffrence between
    1. make to order
    2.make to stock
    3. engineer to order
    pl explain & what configuration setting differences does these process have

    Please make a search in this forum as umpteen number of times,  this topic was discussed.
    Production will be initialized only after sale order creaation is Make To Order scenario.
    Irrespective of sales requirement, materials will be produced is Make To Stock scenario
    thanks
    G. Lakshmipathi

  • ETO - MTO scenario

    We have an ETO scenario where we have a Sales Order assigned to a WBS element. Project creates MRP for material procurement and assembly. So all the purchased components are account-assigned to the Project and the project creates Producttion Order for in-house production of FG.
    At the month end should the variances on the production order be settled to the Material and COPA or should it go to the WBS (or should it be network)? The reason I am asking this is because when we run the s_alr_87013533 report for projects we do not see any production order related actual costs in the actual costs column of the report.
    Please advise.
    thanks
    raj

    Raj,
    Yes. Process for ETO is similar to MTO.  MTO has sales order as settlement received ,if production order is tied to Sales order.
    In ETO , it is just replaced by NWA.....
    In both scenario , if you decide to delink production order , then Settlement received should be material.
    Hope it helps,
    Jatin

  • MTO & MTS scenario

    Hi,
    I am having a requirement where my final product ius MTO and input products are MTS..
    PPM is defined at all levels, when a Sales Order is created for the final product and I take a CTM run Order segment is created for that order and corressponding Planned Orders are created at subsequent levels which are assigned to the same order segment eventhough the input material is MTS.
    I just wanted to know in this scenario can we generate Planned Order for MTS material which will not be assigned to any order segment and which can be pegged to any MTO Sales Order for the final finished component.
    I am using CTM for planning.
    Thanks & Regards,
    Sanjog Mishrikotkar

    Hi Sanjog,
    Please refer to SAP thread [Sales Order on 1 product and Need to consume Forecast on another product|Re: Sales Order on 1 product and Need to consume Forecast on another product] .
    here forecast product is MTS and Sales order product is MTO.
    You can map a planning material scenario to achieve this.
    Regards,
    Digambar

  • ETO & MTO

    Hello,
    What is the difference between Engineer To Order (ETO) & Make To Order (MTO) Process.
    Regards,
    Naveed Ansari.

    Dear Naveed
    We can call ETO as pre sales activity which involves exclusively for new product development, for which there will be a separate department to look after these sort of activities.
    -  study feasibility report
    -  Inform customer whether the development is feasible or not
    -  If feasible, give a quote with development cost
    -  If customer approved the quote, ask for tool cost
    -  Once tool cost is received, develop a die for tooling
    -  Indicate a tentative despatch plan of pilot samples
    -  Prepare drawing according to customer spec
    -  Submit samples for customer approval
    -  If approved, transfer the drawings to delivering plant
    -  If not approved, study customer comments and redespatch samples for approval
    Whereas, in MTO scenario, you will be initiating productiion for your regular items.
    thanks
    G. Lakshmipathi

  • ETO and MTS

    <b>What is ETO(Engineer to Order) and MTS(Make to Stock)?</b>

    Hi
    Make-to-Stock (MTS)
    The scenario Make-to-Stock (MTS) Production with Serial Numbers, QM and WM  focuses on: Sales-order-independent production by MTS (make-to-stock) combined with a variety of logistic functions, such as bulk material, scrap processing, missing parts management with workflow integration, rework processing, Handling Unit Management with serial numbers, batch management, warehouse / lean WM management with FIFO material consumption and QM in procurement.
    Process Flow
    This scenario involves the following processes:
    Costing run
    Sales order processing with availability check
    Material requirements planning (MRP)
    Procurement of components with purchase orders and scheduling agreements
    QM on procurement and quality inspection
    Make-to-stock production / Production order processing for finished good and subassembly
              o Order creation and release
              o Printing of shop floor papers with barcodes (optional)
              o Picking according FIFO strategy with/without WM (Full WM/Lean WM) integration
              o Scrap processing
              o Rework order process (for subassembly)
              o Order Confirmations
              o Workflow for missing parts
              o Bulk-material processing
              o Serial number assignment for finished goods
              o Goods receipt with Handling Unit Management integration (HUM only in DIMP)
    Batch management for finished goods and components
    Delivery with serial numbers and handling units (HUM only in DIMP)
    Overhead- / WIP- / variance calculation / order settlement
    Key Points
    Material requirements planning (MRP)
    Procurement
    Quality management in procurement
    Production order processing
    Handling Unit Management (HUM only in DIMP)
    Serial number management
    FIFO processing with warehouse management (full WM / Lean WM)
    Batch management
    Scrap processing
    Rework order process
    Workflow integration
    Cost Object Controlling
    http://help.sap.com/bestpractices/industry/indusmachinerycomp/v1470/IMC_DE/html/E79_MTSSerNo_EN_DE.htm
    Re: Make to Stock / Make to Order
    Engineer-to Order (ETO)
    One of your company’s main tasks is the production of high-quality and technically complex turbines, which you manufacture on behalf of power plant construction companies, and so on. You purchase some of the turbine components from suppliers, the rest you manufacture yourself. Each process, from component assembly, to plant acceptance and delivery to the customer, is extremely time-consuming. Delays may lead to severe contractual penalties, and therefore, should be avoided at all costs, or possible delays should be recognized as such long before they arise.
    You manage the manufacture of turbines as project business. This allows you to plan and monitor dates, costs, and revenue on a project-basis. Because of your long years of experience in this area, you already have standard project structures, such as project plans, and networks, as well as standard production data, such as task lists, prices, duration, and so on. You can use these templates at the start of a new project, and tailor them to the individual needs of each project.
    Process Flow
       1. On the basis of an inquiry, you create an operational project. Because you are experienced in designing and manufacturing turbines, you can make reference to an existing standard work breakdown structure (WBS) and standard networks in the system. First, you check the feasibility of the project dates. So that you can quote a sales price, you perform sales pricing on the basis of the project planning data.
          Inquiry and Quotation Processing
       2. On acceptance you create a sales order and release the project. You plan revenue using a billing plan in the sales order. You control the different billing dates using project milestones. In accordance with the contractual negotiations with the customer, a down payment is made on conclusion of the contract.
          Order Entry Processing
       3. You procure one of the turbine components externally from a supplier, and run through purchase order handling for that part. You manufacture one of the components yourself. The decision on which components are to be externally procured, and which are to be manufactured in-house has already been made.
          You place orders for long-lead items early to avoid delays to project progress. Your project controls the requirement for particular components in the manufacture of the turbine. As soon as all components are available, you assemble the turbine.
          Project Processing
       4. You deliver the finished product to your customer. Using confirmation, you create the customer acceptance and generate the final invoice.
          Turbine Assembly
       5. During project processing, you constantly control project earned value using confirmations and the cost/revenue situation, so that you can take any corrective action that may be required. You run several period-end closings, however only one is run as an example. On completion of the project you create the final invoice and close the project technically.
    Period-End Closing with the Schedule Manager
    http://help.sap.com/saphelp_46c/helpdata/en/95/aba1376695d703e10000009b38f8cf/content.htm

Maybe you are looking for

  • Not able to add Plugin in Adobe Reader

    Hello, I had given a plugin that is written in Visual C. And it is registered as the process written in developer guide. The keys are generated. Public Key is sent as required and on receiving the certificate the plugin's resources are recompiled. An

  • Do I have to previously open a pdf to launch the batch OCR tool?

    In Acrobat X, I could launch the batch recognize text tool as a wizard from the basic menu you have when opening Acrobat without any file open. Now with XI, I first have to open whatever PDF then go to tools and choose recognize then more than one fi

  • I used the drawing option in AppleWorks. What is an equivalent program/option for Lion?

    I used the drawing option in AppleWorks. What is an equivalent program/option in Lion? I use it to design quilts.

  • Sent mail - Yahoo mail

    Help please - my sent mail has completely disappeared apart from the last 3 days of sent mail.  I have not deleted or changed any settings.  Thats 5 years of sent mail completely gone.  Is there any way of getting it back?? What could have happened?

  • Where does iMovie save files

    A friend uses iMovie (sorry, not sure which version) and saves his files onto a large external hard drive. However, he keeps getting messages that the hard drive on the computer is full cose to capacity. Does iMovie place backups, or any other files,