Hi everybody.
I'm facing an issue that is driving me crazy <:-)
I want to configure a payment method of type "bill of exchange" (in Spain, "pagaré"). I have several due invoices (due dates: 30/11/10, 31/12/10...), which have this payment method. Some other items are not yet due (30/1/11).
When carrying out a payment run thru transaction F110, the system asks for the bill of exchange issue date, which I have populated as 30/11/10. At another tests, I have populated as 10/1/11.
When running F110, the vendor items are then classified as exceptions, with error FZ731 "Pymt method I in the item requires payment by b./exch. before due date", and also message FZ732 "Item not due in 000 - 000 days".
I think this problem may be motived because the definition of the payment method "I" (company code data) says: Days until due date: 0. But this field is not updatable.
I've searched the message numbers in the forums, but found no answer.
Anybody can help? Kind regards,
Alvaro

Never mind, I just had to update the Paying company code, fields Bill of exchange due date... > Earliest-lates due date in...days.
Regards.

Similar Messages

  • BE (Bill of Exchange) purchased back from bank before due date

    I have posted BE through either FBW1+ FBW2 or through F-36. Due date is 1 mth in the future. Then i have discounted it through F-33 using bank clearing liab account (credited here and Post automatically only) Settings in OBYK have also been done for Collection, discounting and forfeiture.
    If the BE is purchased back from the bank before the due date, I am not permitted to reverse the BE liab in F-20 as it says that due date is not reached. This is a common scenario with our client and I need to be able to make this work in SAP.
    Please offer me any solution
    thanks

    Never mind, I just had to update the Paying company code, fields Bill of exchange due date... > Earliest-lates due date in...days.
    Regards.

  • Vendors Payment Before Due Date

    Dear All,
    We could like to restric the release of Vendor payment before the due date.
    We feel there is a system in SAP by which it should give a Error/ warining message (pop up) if any payment is made before the due date.
    Do suggest.
    Regards,

    SAP will give you message if your posting date for e.g. is in past or in future, but the next posting date in F110 parameter decides if you can pay some not due items today or not. SAP will not give you a warning message even if the next posting date is 10 days ahead of today's date.
    In the F110 parameter please make sure Next posting date is always the very next day of the payment run date or Posting date and in the Additinal log tab, please check the indicator Due date check
    This user procedure will make sure that payment is never released before the due date.
    But if still you want some system message to pop up, then SAP standard setting I think will not be of great help, you need to use the BTE00001830 (functional module SAMPLE_PROCESS_00001830) which will help group all the not due items in a group, and exclude the entire group from payments. Information about the group will be received by FM in structure C_REGUH and its line items in table T_REGUP
    By Setting the field XIGNO in C_REGUH to the value "X" the entire group of not due items can be excluded from payments. Please take your abaper help
    Thanks
    Ron

  • Vendor Payment before Due date

    Is there any setting whereby the system will not allow me to pay the vendor before the due date?
    Or else it will give the warning message for the due date.

    Hello,
    You should set all the dates in F110 correctly.
    (eg: Documents entered up to, Next pmnt date)
    If you want to pay only a few items just for now,
    better to select a long period and edit the proposal (EDIT-> PROPOSAL-> EDIT)
    and select the only items you wanna pay for now.
    Hope this helps!
    Endre

  • Paying before due date through payment program

    Hi friends,
    How do I pay to the vendor before the due date for certain invoice through payment program.
    and
    How does system calculates discount on that invoice in automatic payment program.
    what details do I need to enter to make system pay before due date and calculate discount as per payment terms.

    Hi,
    Please try this to remove the check box 'Payment per due date' is selected in your FBZP   > Payment method for company code settings. If you have switched off the flag and carried out testing.
    Please assign points if it useful
    Regards
    Ravinagh Boni

  • Update AP Invoice Payment Schedule (Due Date)

    Dear All,
    Is there any API for AP Invoice Payment Schedule (Due Date) in Oracle EBS R12.
    Please advice.
    Thanks

    Hi there,
    Im afraid there is no setting that will have the system post different payment terms in the invoice reduction
    than what is in the invoice. In MIRO, if you use PO reference to create the IV document, the payment terms are copied from the PO and not from the vendor master. The business reason is, that the PO represents the contract between vendor and customer including the terms of payment. Also check out note 322430 as this gives a good description of the proposal logic for the terms of payment.
    I hope this helps,
    Best regards,
    Adam.

  • F110 - Bill of exchange - latest due date more than 999 days ?

    Hi all:
      We have a problem about Payment run / F110.
      Because finance department want to open "Check" to bank  and the due date is about 4 years later (1500 Days).
      And we run the payment run it shows error message " FZ 732 Item not due in 000 - 999 days " .
      I think the reason is because the maxium latest due date only allowed 999 days,right ??
        "Latest due date in" of "Bill of exchange due date for outgoing payments" in paying Company Code  (OBVS)
      Is there any way ( IMG / Exit / Enhancement ) can resolve this problem ??
      thanks a lot.

    Hi Mauri:
      Thanks your reply.
      actually, we have asked user to open their check - more then 999 days - manually.
      Because this is the second case we met in past 6 months, so we are looking for any solution ( Exit / Enhancement ) to meet user's requirement. 
      We won't create any new add-on program to meet user's requirement, but hope exit or enhancement can make it, anyway, thanks again.

  • Error importing Incoming Payments using the Data Transfer Workbench

    Every time I try to import Incoming Payments using the Data Transfer Workbench I get an error that the Update Failed - Can not find this object in B1Application-defined or object-defined error65171. I'm using the 3 templates for Payments, Payments_Checks and Payments_Invoices. I've filled them out as I've seen in other postings in this forum. Based on the error message, I really can't tell what I'm doing wrong. Could someone please take a look at my files and let me know what might be causing the error?
    I'm using SBO 2007A PL41. Here's what I have entered in my templates for my test file.
    Payments file
    RecordKey 1
    DocEntry (blank)
    CardCode 1033985
    DocDate 20081215
    DocTypte rCustomer
    TaxDate 20081215
    Payments_Checks file
    RecordKey 1
    LineNum 0
    AccounttNum 0
    CheckAccount _SYS00000002152
    BankCode CC
    Branch 12345
    CheckNumber 1
    CheckSum 78.7
    CountryCode CA
    DueDate 20081215
    Trnsfrable tNo
    Payments_Invoices file
    RecordKey 1
    LineNum 0
    DocEntry 31791
    InvoiceType 13
    SumApplied 78.7
    Thank you.

    Hi Suda,
    As far as I can tell from the threads you forwarded (and other searches I've done on here), my files are correct. I tried filling out the templates exactly as explained in the first link (see my data below) but it still isn't working. It just gives me the same generic error. 
    Payments
    Record Key....CardCode.....DocDate
    1...................1033985.......20081217
    Payments_Checks
    RecordKey....CheckAccount........CheckNumber....CheckSum
    1.................._SYS00000002152..1.....................  78.7
    Payments_Invoices
    RecordKey....DocEntry.....SumApplied
    1..................31791..........78.7
    Is it correct that the Payments file should not contain anything in the DocEntry column? (I know that the DocEntry in my Invoices file is the DocEntry of the Invoice). I have a feeling that I'm making a stupid mistake somewhere but I just can't figure it out. Any ideas?
    I really appreciate your help with this.
    Thanks,
    Charlotte

  • Payment Stop Before Due Date.

    Dear All.
    I need to know is there any option we have to stop the processing of Vendor Payment against the NON DUE ITEMS.
    Here in my client, normal terms of payment is for 45 Days. Now the users are asking that, if a line item is Not Due as on Date, if by mistake we have selected such item for payment processing, the system should drop a error & stop the processing.
    The requirement is as follows as error message....
                 """ The Selected Item is Not Due"""""
    So, wht i have found out is, by changing the line item layout included the additional fields like:
    Due Date
    Item Due Indicators.
    But, here these are only for the information purpose, which dont have any control over item payment process.
    SO, CAN ANY BODY PROVIDE SOME IDEAS ON THIS, IF SUCH OPTION IS AVAILABLE IN SAP..
             """ LINE ITEM PAYMENT BLOCK IS NOT SUITABLE HERE """""
    Thanks
    Talluri

    Hi
    With my knowledge,  You have choosen the best process ie., brining the due date in the screen layout. even thou, the client required to make the error message, first work out the change of the message type
    or
    there is no such standard process to stop the payment voucher. Either you have to evaluate any routine
    or alternatively last option will be
    you can use the following procedure
    1. Maintain the Vendor Master -> Payment Transactions -> Maintain the Payment Block
    2. Generate the vendor line item daily with due date is "today's" date & select the MIRO document numbers.
    3. Release the documents through MRBR by selecting the above line items.
    This is for your information.
    Regards
    Anilkumar

  • Payment terms - due date on a particular day of the week say friday?

    Experts is it possible in SAP payment terms to configure a term such that due date is on a particular day of the week?
    I want use payment term to determine due date for weekly billing cycle (sunday to saturday) for the invoice to be due on Friday net 27 days from mid point of the week
    eg 1. if a customer is invoiced any day between October 4th to 10th, the due date should be Friday Nov 6th
    eg 2. if a customer is invoiced and day between October 11th to 17th, the due date should be Friday Nov 13th
    Is this possible?
    Thanks in Advance

    You need custom development for this. Using custom development, Substitution in FI or User exit in SD
    I. FI Substitution -
       Create substitution with exit, for field day1 (BSEG-ZBD1T) and baseline date (BSEG-ZFBDT). In exit, determine number of days for required Friday from baseline date you want to use (say document date). This way, due date will be on Friday.
    For determining Friday, use calendar or Ztables.
    II. Invoices created in SD - If you are gerenating invoices in SD, use exit EXIT_SAPLV60B_008. This exit has table ACCIT which also has same fields Day1 and Baseline date. Follow same logic mentioned above.
    I hope this helps.

  • Running Payment Program before Due Date

    Hi Gurus,
    I have a problem.
    I want to run the payment program -Tcode F110- before the due date and I need the document posting date to be the same as the due date.
    How could I sort it out?
    Please help,
    Samuel

    Your requirement can't be fulfilled by standard set-up, because SAP payment run can post with only one posting date in a single run. This posting date will be what you are entering in the parameters, and system will not split payment posting date separately based on Due date. You can group your items based on due date and can pay future due items as well but you can't split your payment posting with different payment posting date based on due date in a same payment run.
    You can possibly do following workaround.
    - Run vendor open item report (T-code FBL1N) and sort it based on Net Due column (if net due date column is not available change the layout to populate it). And decide for items with which due dates you want to settle today. Lets say you want to settle for following due date xx/xx/xxx, xx/xx/xxx1, xx/xx/xxxx2
    - Then you should run three payments run separately.
    Payment run 1 parameters-  Posting Date=xx/xx/xxxx, Next Posting Date=xx/xx/xxxx+1
    Payment run 2 parameters-  Posting Date=xx/xx/xxxx1, Next Posting Date=xx/xx/xxxx2
    Payment run 3 parameters-  Posting Date=xx/xx/xxxx2, Next Posting Date=xx/xx/xxxx3
    Imp: Note that Posting date=Due Date and Next Payment Run Date=Due Date1 in the parameters+
    This will involve more than one payment runs in a day but will satisfy your requirement
    Thanks
    Ranjit

  • Liquidity Forecast not considering payment term / due date

    I have configured liquidity forecast and it is picking up values just fine (ECC 6.0).
    My problem is that in FF7B it is not taking "Payment Term" and "Due Date" in to consideration at all. Thus as a result not showing what is due on which date.
    What do I need to do to ensure that FF7B (liquidity forecast report) show balances considering "Payment Term" and "Due Date"?
    Or is here some functionality missing, or I am facing a program error?
    Regards

    Hi,
    You do not have to give the Days there.
    Their functionality is different.
    Assign 15 in Payment terms Tab in No of Days, Percentage should be blank.
    Then the system will calculate the net due date 15 days from Document Date.

  • Payment terms / Due date Schedule

    Dear experts, how do the Payment terms definen in FI - FICA, relate to the Due Date Schedule used in Student Lifecycle Management?. Do I define Payment terms for the contract account, or just the Due Date Schedule?
    Best regards.

    Hello:
    The Due Date Schedule (DDS) is used to split fees into payment plans (example 50% at beginning of term, 25% one month later and 25% two months later).  The DDS is maintained in the Academic Calendar. To define the DDS you first need to set up a Time Limit and Time Limit Sequences using the IMG path: SLCM>Master Data in SLCM>Academic Calendars.. Note that at least one DDS is required even if you do not provide payment plans for the students. This DDS will have one payment date.  The DDS can be assigned to the Program, Module, Student Account or Contract Object.
    Each partial payment is an orgianal open item which in turn can be split into an FI-CA installment plan using Transaction FPR1.
    As an alternative to the DDS you can use Transaction FPR1 to set up installment plans. This transaction provides more control over payments including dynamic definitoin of due dates.
    Regards,
    Patricia

  • Recurrent payment charged before due date. Refund ...

    Hi,
    I have skype premium (1 year).
    Last month I added another subscription for 1 month (recurring payment). I did this on August 08.
    I could cancel it before the due date but today I got charged again (September 5th). I don't get why this is not advised.
    So, I'd like to request a refund but I can't make it because the link is broken. The same happens with Live chat. There is no way to access there. All links are broken.
    If you access here https://support.skype.com/en/faq/FA297/how-do-i-request-a-refund ,
    there is this link to the request form:
    https://support.microsoft.com/skype/hostpage.aspx?language=en&locale=en-us&oaspworkflow=start_1.0.0....
    If you access, you'll be redirected to: http://support.microsoft.com/common/errors/ServerGeneric.htm?httpCode=403&errorCode=
    This link is not working neither: Skype Live Support Link:
    https://support.skype.com/support_selection
    I can see I'm not the only one and other have already posted this in the community forum. There is no support email to send this either.
    I need to request that refund. Please help

    edgard_shipley wrote:
    1. I can´t find where is that information. If it´s not available, how we are supposed to know this?
    When I got the email stating that the subscription was successfull, there is no advise on this.
    2. How can I request a refund now?
    Hello
    1. I'll escalate the point you make to see if the advice confirmation needs further clarification. Thanks for raising it.
    2. This should help:
    https://support.skype.com/en/faq/FA1170/how-can-i-contact-skype-customer-service?intcmp=SN-Mods
    TIME ZONE - US EASTERN. LOCATION - PHILADELPHIA, PA, USA.
    I recommend that you always run the latest Skype version: Windows & Mac
    If my advice helped to fix your issue please mark it as a solution to help others.
    Please note that I generally don't respond to unsolicited Private Messages. Thank you.

  • Advance payment before delivery date

    Hello experts,
    I have a requirement that after creating PO I need to make advance payment 2 days before receiving goods(delivery date) in case of local vendors, whereas in case of International vendors I need to make advance payment 8 days before delivery date.
    How can I achieve this functionality????
    Please help.

    hii shubh,
    u can achieve it the Payment terms
    define two terms of payment with t-code OBB8, in first give the amt of adv payment
                                                                                    in second, rest amt. here u tick INSTALLMENT PAYMENT
          one more u define terms of payment , there u click on block key with A or B.
    and assign it in OBB9.
    u search sdn also regarding this.
    Thanks.