FI/CO integration with PM, PS, MM modules

Hello,
Any body have information about ' FI/CO integration with PM, PS, MM modules
Could you please some explore above topic
Thanks,
Alex

HI Luciano,
It works as designed because of the following reasons:
1. The WBS ID in ERP system must be unique.
2. The phase-id in the cProject is NOT unique, you have e.g. same phase-id for two phases.
That is why the replication does not use the phase-id to create the WBS ID.  The internal ID of phase is (default ID during creation of a phase) is used for replication
Though there is a Badi method let you change the the WBS ID, but I would not recommend you to do it because of above reasons.
Kind regards,

Similar Messages

  • SAP E - Recruitment Integration with SAP PA ES Module

    Hi all,
    I have SAP Recruitment Application to be integrated with SAP PA_ES Module (SAP HR) through XI..
    Now I have 2 questions;-
    1.Does SAP recommends both the above mentioned applications on same SAP BOX ie the system will have both the application with the different clients  on SAP system or a sort of addon...If yes , how the integration can made?
    2.What is recommended/Suggested scenario for integration i.e. which adapters shall be used for this configuration??
    it would be really very helpful if someone could throw some light on this
    Regards,
    AshwinM

    Aswin
    Why dont you check the following thread for more info
    E-Recruitment
    regards
    krishna

  • WBS element integration with Trade Claims Management Module

    Hi All,
    anybody knows if Trade Clams Management module of CRM is integrated with management of WBS elements?
    We actually want to post the amounts paid to customers through Trade Claims Management into CO-PA; we're trying to understand if using WBS element is a viable solution. Moreover if this is the case i'd be curious also to understand how COPA posting of accruals would work.
    Regards
    C

    m

  • CATS INTEGRATION WITH PP AND PM MODULE ( TO FIND ACTUAL MANPOWER COSTING THROUGH ACTIVITY TYPE)

    Hi Experts,
    We have a scenario like, Client wants to track the actual manpower costing through activity type ( Ex: How much hours an employee worked on a particular work center to produce an “X” product, So that his actual cost should be loaded on that product.
    We have employee ( 1. Staff 2. Worker 3. Contract labor employee and apprentice from third party roll and staff and worker we plan to go with negative time management and for contract labor and apprentice will go with through cats.
    Since we are not going to run the payroll for contract labor employee and apprentice, we just maintaining the employee data as a group ( Ex: Group A,B,C etc.. Each group consists 20 or 30 employees, According to system each group as one employee and according to us each group consists as 20 or 30 employee.
    The Activity type as well cost center will be created by Co module, the same will be assigned in info type 0315, but still i want more input from experts on the same, since i am new to cross application time sheet configuration, could any one help me out to find the actual manpower costing in a better way.
    Regards,
    Prem

    Hi Experts,
    Can any one please reply on the same.
    How to arrive the exact manpower costing through activity type ?..
    Regards,
    Prem

  • Best practice to develop internet app integrating with backend R/3 modules

    While we wait to upgrade from R/3 4.6c, going forward we want to stop investing in ITS Flow Logic applications.
    What is the best practice around using backend RFCs/BAPIs to expose SAP functionality as a web application that is accessible on the internet? One thought looks like using WAS 6.4 - utilizing JRA to call RFCs and using JSP/Servlet; another is to use Webdynpro based development. Will appreciate some architecture advice along side - especially if we also wanted internet surfers to set up user accounts. Thanks!

    Hi Vito,
    I do have the same situation as you and also some of the guys mentioned above as well. I have Portal only users and also users who uses the SAP GUI.
    Thus, what I would advise, taking into consideration of audit as well, is to have the below scenerios:
    1) Users who login to backend with SAP GUI on Citrix only
    We have changed the system parameter: login/password_change_for_SSO=2
    The password change dialog box appears and the password must be changed (input: old and new password). Also we have setup SNC (CyberSafe) so that in our SAP GUI, users can click on the system with SNC setup and login to backend without having to enter userID and password
    2) Users who login to backend with SAP GUI on client (local)
    Users will login with userID and password
    3) Portal user with SSO and no login to backend vwith SAP GUI 
    Portal users will have their password deactivated.
    Explaination to Audit for Portal users:
    We have 90days password reset on Windows (AD). So our Portal users are respecting the audit request of having 90days password reset, but instead of having it in SAP, its in our Windows. Furthermore, SSO is setup as such that the coinnection for these Portal users to the backend is secure.
    We are not able to set login/password_change_for_SSO=3 as we have sites which does not use Citrix. Thus, these sites will have local SAP GUI install.
    Hope that can share some experience of mine to those who are also in my past situation.
    Ray

  • Integration with modules in different clients

    Hi Experts,
    We are designing a PS solution and its integration with MM and CO modules. The difficulty comes as these modules are maintained in a different client than the PS module. My questions are:
    Is there any standard mechanism that SAP provides to make this integration out of the box?
    For business strategy reasons we may have to choose a PI based integration scenario. Given that we have retreived the values we need from the different clients, how can we avoid the standard checks SAP performs before saving the data?
    Have anyone experienced this situation before? Could you explain the main difficulties that you faced?
    Thanks a lot in advance for your answers
    Kind regards,
    Neil

    Not really,
    in the past we had a split to:
    Box with masterdata
    Box for sales and purchasing
    Box for Finance
    In the master data I see still things like Logical System ( D00CLNT100)
    We went go back to 1 box and had to upload the data from the"old" boxes to 1 box.
    Perhaps you can better put this question in the technical forum, It should be possible what you want

  • DMS integration with PP and PS.

    Hi SAP PLM experts,
    I would like to know how mySAP PLM's DMS module  is integrated with PS and PP module.
    Any small scenario with T codes and configuration help is highly appriciated.
    If you guyz have any documents/materials for this question, please mail the same to sudhu03 at gmail dot com.
    Thanks in advance,
    S.Achar.

    It is only through the object linkwhich you provide.
    In the business perpective, we attach the contract documents, design drawings and other doucuments to the project for ready referance.
    You can create the DIR directly from PS transaction or you can create it in DMS and attach it to the Project.
    We do have the red lining to identify teh changes reqd in the document.

  • Oracle Sales Integration with other modules - Flow Diagam

    Hi,
    Where can i find a flow chart showing Oracle Sales Integration with other modules?
    Thanks,
    Hari

    Hi
    You can refer to my publishing in this site which might help you to some extent
    http://apps2fusion.com/at/sk
    Hope this helps
    Regards
    Sivakumar

  • QM with SD and PP  module integration

    hi ,
    Actually i am new in QM field and i already maintained SAP QM and MM integration , please suggest what the thing i mantained, edit and add so that i done the QM with SD and PP  module integration too
    Your suggestion is very appriciable
    Thanks
    Maashish

    Hi
    Kindly refer the following links:
    QM with MM:
    http://help.sap.com/saphelp_47x200/helpdata/en/c2/b9b3341a933f50e10000009b38f83b/frameset.htm
    QM with SD:
    http://help.sap.com/saphelp_47x200/helpdata/en/83/a8b43446a1c564e10000009b38f83b/frameset.htm
    QM with PP:
    http://help.sap.com/saphelp_47x200/helpdata/en/89/9bb43418e43b4ae10000009b38f83b/frameset.htm
    Thanks

  • What SAP-modules can be SAP HR integrated with?

    Hi to all!
    I have a following question:  What SAP-modules can be SAP HR integrated with? What HR objects and business processes could be involved in integration. What are the main advantages of this kind of integration.

    The best advantage of SAP HCM is that we have Integration with other Modules
    as per as SAP HCM i worked integration with FICO , SD 
    Business objects form FICO side will be Cost Center
    and there are many Advantages with the integrations with other modules

  • PS integration with other modules

    Hi Experts
    Pl tell me  from configuration point of view how ps integrates with MM , SD and FI. What are all the necessary steps we have to do in integration .
    Thanks in Advance

    Hi Amit,
    PS is integrated with all modules of SAP.
    MM and PS, we can create Purchase requisition in PS itself rather than doing in MM. This PR can be converted into Purchase order. To create PR in PS, we have to use the MM master data.
    SD and PS, we can check the revenues in PS. This can be done while creating the Sale order we have to give the WBS element.
    FI and PS:  We can provide the direct financial entries in FI to post cost to the project in PS by selecting the WBS element.
    I hope i clarified your query
    Regards
    Sankar

  • Integration with other modules

    Hi Sap Gurus.
    Hi,
    Plz explain...
    MM module is integrated with which modules .
    And how it is Integrated??
    How MM module to integrate with CO(Product Costing).
    If thr any material please send me to [email protected]
    Thanks..
    Raju

    Hi,
    FI-MM Integration:
    When you go for transactions like GR,GI,SES,MIRO,STO,Payment then your respective G/L account updated.For updatinging the G/L account, You have to go for Automatic Account determination and steps are as follow;
    1.OMSK: Creation of valuation class and assigning account category refrence,
    2.OMWM: Active valuation Grouping Code,
    3.OMWN: Active movement type with G/L account,
    4.OMWD:Active valuation Area,
    5.OMWB: Active chart of account, transaction key,valuation grouping code,account grouping Code, valuation Class and G/L accounts.
    Data flow to costing in the concept of cost element.
    SD-MM Integration:
    Generally SD is integrating with MM in Stock Transport Order (STO) and Third Party Order.
    Basically STO is divided in to three types,
    A.STO with SD delivery
    B.STO without Delivery
    C.STO with SD delivery and billing.
    FI-SD Integration:
    In T.Code:VKOA
    If helpful then reward.
    Regards,
    Biju K
    Message was edited by:
            Bijay Kumar Barik

  • DO integration with other modules

    Hello Gurus,
    When delivery is created, this means , it can be saved without picking packing or pgi or it can be pgi just done.
    When this is created, why is there no integration with MM? for example , when PGI, the stock count is it reduced in MM?
    So, it should reduce MM stock but not Reserve MM stock in this situation?
    Also, how is it integrated to PP?
    Will the delivery place demand in PP when it is created? Should the demand not already placed at time of order creation?
    regards
    M Russo

    First of all, please dont get confused with the postings happening in SAP with each module.
    SAP has distinguished different modules for easy way of operation and to have certain control over the related activities. Having said this, you cannot treat (assuming that you intend to say unrestricted stock)  the stock as MM.  In fact, MM activities would  come to an end once they inward any component and made the relevant FI / Excise postings.  Subsequent to this, PP activities starts where only, the stock will be posted to unrestricted subsequent to which SD activity starts. 
    why is there no integration with MM
    There is an integration with MM/PP once you create a sale order which is based on customization in OVZG and VOV6.
    Based on the above settings, stock will get reserved to either sale order or delivery.
    thanks
    G. Lakshmipathi

  • PP module integration with SAP-OER & SAP-AII

    Dear All,
    What is SAP-OER & SAP-AII module?
    How this module integrated with SAP PP?
    Maulik

    Please go to
    http://help.sap.com/erp2005_ehp_05/helpdata/en/52/16a979543311d1891c0000e8322f96/frameset.htm

  • PM Integrations with Other Modules

    Dear Experts,
    Can u all pls list out what are all the major INTEGRATION of Plant Maintenance module with other modules?
    And how it can be done?
    Regards,
    Rajesh

    Hi Rajesh,
                Let us consider one practical issue of Spare Parts purchase.
    We prefer to inspect incoming material for compliance of our requirement.
    1.While creation of material master, tick the 'Post to insp. stock' box in the Purchasing Tab.
    2. If we do not want a task list / Result recording oriented inspection, in Quality tab, choose appropriate selections,
    3.When that Spare is received, it will go to Quality Stock.
    4. Maint. person can check it and transfer the stock to "Unrestricted Stock" through MB1B via 261 movement, giving a reason as Accepted after Inspection or Rejected.
    5. Above procedure is a practical example of PM QM integration.         
    Integration between PM and PP
    In the equipment Master, under the location tab, mention the PP work center, and in the task list under the Header give the system condition "0" ie M/C not in operation, before doing this in the custimosation under Maintennace and service order-general data-- "Create System Conditions or Operating Conditions" check the box for PM reservation.so when ever a maintenance order is raised against that equipment, it will block the prod.
    The integration aspects of MM-PM are:
    1) for non stock materials requirement, purchase requsition can be created from the plant maintenance order. PR is converted to the Purchase order. when ever goods receipt is done , the cost is directly booked to the plant maintenace order.
    2) for stock materials requirement,,reservation can be created from the plant maintenance order and the material can be issued to the order against the reservation.
    3) Like materials , for services also PRs can be created from the plant maintenace order.
    Another integration is BOM - Bill Of Material.
    With Equipment BOM, you can create a list of material through which equipment is created or in othre words you can mention the spares that you may require during the maintenance of the equipment. 
    FICO-MM-PM Integration 
    the integration points between PM and MM/FICO during the PM configuration.
    Below are some integration aspects:
    Integration with MM:
    1.Material master record for Batch Managed material as Equipment
    2.Reservations and Goods Issue for Maintenance Order
    3.Material valuation class/types for refurbishment materials as equipment
    4.Triggering PR from Maintenance Order
    Integration with FICO:
    1.Asset/Sub-Asset numbering in Equipment Master Data
    2.Activity based costing for Operations performed through Maintenance Order
    3.Settlement of accrued costs in Maintenance Order to G/L Account,Cost Center, Asset etc.,
    If it is reallyuseful to you pls reward me with points
    Regards
    Satish
    Edited by: P.Shanmuga Satish Kumar on Jan 24, 2008 6:57 AM