Hi, we want system to control the GR qty from the production order by not exceeding +/- 10% of order qty. how to make this setting?

Hi
The settings for the tolerance to control during confirmation
1) OPK4 : Set the Error message for over delivery and Under delivery situated below Checks for the order type and plant combination.
2) In Material master work scheduling view give the % tolerance in Under delivery and over delivery
3) We can also set the % Tolerance limits in Production order
Regards
Brahmaji

Similar Messages

  • How to refer the work order status value from a different transaction in the step handler?

    Hi All,
    I have a requirement to check the status of the work order from a different transaction before doing some logic in the current transaction. The following transactions are done to replicate the issue
    1)changing the status to ONSITE to edit the work order (transaction 1)
    2)Adding some information which will do some logic (transaction 2)
    3)Completing the work order (transaction 3)
    The transaction 2 will have some logic and will be executed only if the status is COMP but even though the status is COMP now (transaction 3) my condition check in the logic is showing as ONSITE status(transaction.status=ONSITE) and it fails. How can i get the latest status of the work order in the device? Please advice

    Hi Jason,
    The CompleteWorkOrderFinish sub action does have Apply action (screenshot 1) and the transaction definition (screenshot 2)of CompleteWorkOrderFix transaction with the only property Status which has the following settings (screenshot 3)
    Also I am trying to add a status property in EditMeterFitDetaisl transaction and update this value with the current status of the work order using object collections filtering with key value. Please let me know if that approach can be followed. Thanks

  • How to stop PR creation from PM work order for a particular vendor?

    Hello Experts,
    We have following scenario for breakdown maintenance activities.
    When a machine breaks down, a breakdown order is created in SAP. The external manintenance services are planned in the order. When the order is released, a single PR (with multiple item numbers corresponding to number of services) is created by SAP. The PR has a release strategy. When PR is released, PO is created followed by the SES.
    The practice followed AS -IS for breakdown outside business hours:- If the breakdown happens outside business working hours, the person releasing the PRs is not available & hence PR can not be released resulting in no PO & no subsequent SES.
    In this case, the maintenance is completed by the external agency & the work order is TECO. The next day, TECO is reveresed, new PR is created, released, converted into PO, & then SES.
    TO-BE process:- Client expects that, for certain vendors identified, PR should not get created at all from the breakdown order. (The list of  vendors will be maintained seperately). For these vendors, a framework order will be created at the start of fiscal year & SES will be created as & when required agaainst the framework order.
    My concern is :- How to stop PR creation from PM work order for a particular vendor? OR delete the created PR?
    Highly appreciate your quick response.
    Thank you.
    Amit
    Note:- My ABAP consultant has checked following BADI's, but could not find it useful.
    IWO1_ORDER_BADI
    ORDER_COSTING_CK
    DATA_EXTENSION_CK
    VALUATION_CK
    ME_REQ_OI_EXT
    IWO1_PREQ_BADI
    ME_CHECK_SOURCES
    ME_REQ_POSTED
    IWO1_ORDER_BADI

    Dear Amit
    I am giving a different dimension to your question check if it fulfills your requirement -
    As we know Vendor selection comes at a later stage only after your PR creation, approval & RFQ etc. & PR generation from maintaine. order is controllled through control key PM03.  While triggering PR from order you have to specify Material group, Purchase group and vendor. Try to control it through authorisation as all these are authorisation objects. The persons executing breakdown order shall no t be given this authoriations
    shakti

  • Generating the RM requirement based on the work order?

    Does Oracle Disceret MFG has the provision of generating the RM requirement based on the work order?

    Hi,
    If you mean RM requisition as Material indent from Stores , then Yes, Component Pick Slip is the form
    Regards
    S

  • How do determine the work orders for a sales order?

    I'm forced to calculate our costs by sales order.  So for a given sales order number, how is this linked to the work order that created the items on the sales order?
    Thanks

    Hi,
    Check this:
    Re: Open Production Orders List with a Field from Sales Order
    Thanks,
    Gordon

  • Release strategy for PREQs created from PM work order

    Hi All,
    I have an issue with determining  release strategy for purchase requisition for external services created via PM work order (iw31 transaction).
    We have activated release strategy for Purchase requisition based on the following characteristics:
    CEBAN_PLANT
    CEBAN_COST_CENTER_GROUP
    CEBAN_MANUAL
    Characteristic CEBAN_COST_CENTER_GROUP is defined via user exit based on the cost center used in the PREQ and a z table which contains all cost centers mapped to the corresponding  cost center goups.
    In the user exit we have consider to cases:
    The first one is when a purchase requisition is created with account assignment K (cost center) then system is checking the z table and determines the right cost center group.
    The second case is when a purchase requisition is created with account assignment F (internal order) then based on the order type and number the cost center in the order is defined and based on it the corresponding entry in the z table cost center group is assigned.
    The third case is when purchase requisition for services is created automatically from PM work order. In this case the PREQ is again with account assignment F, but at the time when user exit is checking the input parameters the real number of the work order does not exist and system can not defined the other parameters.
    We have defined  for this requisitions in the release strategy for characteristic CEBAN_MANUAL creation indicator " F".
    Has anybody of you defined release strategy for PREQs created out of work order before. How did you manage to trigger the release strategy?
    Best Regards,
    Desislava

    Hi,
    For PM order find the costcenter in the settlement rule of the order or else find the costcenter in the Location tab of the order.
    Consider this filed from order & write in the Z program to pick up the costcenter from there to find out the cost center group.
    Regards,
    Raj

  • Scheduled start and finish dates in the Work order.

    Hi Friends,
    I am facing peculiar issue that once the Work order has been released schedule start and finish dates should be derived from the control key and
    operation hours and work center capacity,infact in my case while releasing the Work order,these dates (scheduled start & finish) are not been
    populating in the Work order,(but SAP standard behavior is while releasing WO,the dates should be populated).
    though i have maintained proper configuration
    could you please light up some thing on it.
    Regards,
    Srinika

    Check Scheduling Parameters assignment to order type, Scheduling option in Control key.

  • Is there a process for moving costs from maintenance work orders to capital

    Is there a process for moving costs from maintenance work orders to capital projects?
    We have reversed the settlements on the work orders, and then trying to put the relevant NWA in , then receive error message :
    Rule for allocation of PM order to PS network is not maintained.

    hi
    check the allocation structure and the settlement related customization settings.

  • How to create planned order from the sales order for a processing item

    In the MTO sceanrio, assembly order is created directly from the sales order. I would like to create a planned order from the sales order.
    I tried the Planning strategy group 81 in the material master but it didnt work.
    Could you please let me know how to do it? Is it Schedule line config that controls whether planned order is created?
    Thanks
    Harish

    Narayana,
    Planning strategy 82 is the best & standard way of getting production order created on sale order create.
    just assign this strategy  in MRP 3 view under strategy group.
    If not then using sale order reqt type ( KMFA- Assembly with production order) & assigning this to your sale order item category is also another way to create prodcution order without using planning strategy in material master.
    Follow steps in SPRO-->Sales & dist --> basic functions >avail check &transfer of requirements> transfer reqts-->determination of reqt type using transaction
    Here you may select the item category you in sale orders & assign KMFA to your item category. this will then give option in sale order create to change reqt type to KFMA for assebly orders.
    If you need KFMA to be default assign it to Item cat/ MRP type ( PD) combo.
    Regards
    Ritesh

  • BAPI or FM to get the work order number

    Hi
    Kinldy let me know if there is any BAPI or FM to get the work order number (aufnr)  from to Purchase requisition number (banfn) & Item number of the purchase requisition in the order(bnfpo).
    Thanks ,
    Arun

    Table EBKN will help you.

  • Why the "Work Orders" Menu Item is hided in 2005 Edtion?

    David:
      Thank you!
      The "Work Orders" menu item in 2004 edtion is must useful, But it be hided in 2005,Why ?
      and whether can I show it and use it?
      help me, please!
      thank you!

    Fu
    in the SAP help the following is written:
    Work Order Window
    Definition
    The Work Order Window, from earlier versions of SAPBusiness One, has been replaced by the Production Oder. However, if you had open Work Orders when upgrading, the old Work Orders can still be viewed.
    When a Production Order is open, click on the base document icon  on the toolbar to display the Work Order on which it is based.
    i recommend you to use F1 in your sbo client
    and search for "work orders"
    than select title "Work Order Window" and there is everything in Detail !
    regards
    David

  • STO creation against the Work Order

    How to specify the source plant or source storage location within PM Work Order for the components/materials.
    Currently on the components page of work order, we can specify the material and vendor. In our case the vendor is other storage location within same plant or diff. plant.
    How can we specify the source in components page so that PRs and reservations are created correctly.
    In details here is the problem-
    During work order (PM Order) creation user is specifying a non-stock material and issuing storage location "0002". The material will be issued by sto. loc. 0002.
    Storage location "0002" sources this material from other storage location "0001".
    So we want to generate a Purch Req. with item category "U", account assignment 'F" (with work order) and ability to specify the source plant-storage location.
    But the system is creating a normal expense PR with account assignment "F" to the work order. This PR is having grayed out item category so not able to convert into Stock Transport STR by specifying the source plant and storage location.

    Hi MM
    Have you solved your problem? What did you do to create the STR?
    Regards
    Eduardo Chagas

  • Display construction type on the structure list within the work order

    I have a work order written against an equipment which has a construction type assigned to it.  When using the structure list from the components tab of the work order, the construction type does not display under the equipment in the list.  If I run the same structure list from transaction IH03, the construction type does display under the equipment.  How can I add the construction type to display on the structure list within the work order?  We are on release 4.7
    Thanks,
    Terry Gaskin

    Thanks PeteA, we know we can do that, but we are looking to get it consistent with IH03, where the construction type shows without being added to the BOM.  The construction type is listed immediately below the equipment in IH03.
    Thanks

  • Excise rate and value is not getting defaulted from the purchase order

    Hi all,
    While capturing excise invoice , the excise rate and value is not getting defaulted from the purchase order and in Excise Item Tab BED,AED,ECS is Zero at both header as well as item level for only one material in STO process and if we are doing same process taking other material all things are coming perfectly and We are maintaining condition with respect to vendor,plant and material combination.Any input related to this will be helpfull and rewarded.
    Regards
    Vishal

    Hi,
    Follow STO Process for this;
    1.Create a vendor for the company code of receiving plant, using account group: 0007 using T-Code XK01.
    2. Assign this vendor to Delivering plant
    Go to XK02 >Purchasing view>Extras>Add. Purchasing data>Plant
    3. Create internal customer with the sales area of the vendor. Go To XD01
    4. In pricing procedure determination relevant to STO, assign document Pricing Procedure and customer pricing procedure appropriate for STO to get the pricing in the invoice.
    5. Maintain condition records for the relevant pricing condition.
    6. Some more setting for STO: Go to MM> Purchasing > Purchase Order > Set up STO > define shipping data for plants > Go to Receiving plant >assign customer here & Supplying SA (for billing) to Receiving plant here
    7. Go to MM > Purchasing > Purchase Order > Set up STO > define shipping data for plants > Go to Supplying plant and assign the sales area of receiving plant.
    8. Go to MM > Purchasing > Purchase Order > Set up STO > assign delivery Type & Checking rule
    Assign the delivery type to document type. In this case, Delivery type NLCC is assigned to Document type NB
    9. Go to MM> Purchasing > Purchase Order > Set up STO > Assign document Type, One step Procedure, Under delivery tolerance
    Assign the document type NB to supplying plant and receiving plant
    10. After all settings, Create the STO using T-Code: ME21N and maintain pricing conditions of freight and Save.
    11. In supplying plant Maintain condition record in sales using VK11 the same will flow in receiving plant when referring the OBD no during MIGO.
    10. Create Delivery: VL10G
    12. Picking, PGI: VL02N
    13. Billing: VF01
    Save the document and its done
    14. J1IIN - Outgoing Excise Invoice
    15. MIGO - Goods Receipt against outbound Delivery
    16. J1IEX - Capture & Post Excise Invoice
    Rgs

  • Is there any way to remove a hyperlink from the tab order?

    My form is 4 pages long and after I tab through all numbered tab fields, my mouse moves to the hyperlinks on page 1 instead of the next field on page 2. The hyperlink fields do no appear in the list of tabbed fields and I can't move it to the end of my document (page 4).

    No, you can't remove links from the tab order.
    On Wed, Apr 29, 2015 at 11:26 PM, andrea kas. <[email protected]>