Hours worked uncoupled from Percent complete

It seems that the work hours and Percent complete are tied together (for updating tasks).  is there a way to remove this feature?
I tried looking into the enterprise custom fields, but since it is a part of project OOTB, it is not there.   is there another place i can find and change this?
or perhaps a workaround?
for example,  i have 1 person assigned to a single 8 hr task,   due to some unforeseen circumstance, he has worked 6 hours and is only 50% done,  however, when he goes to his tasks to update his work, he can not enter both of these at the
same time.
he can either update to 50% done (4 hrs filled in automatically )
or he can enter 6 hours worked (75% done filled in automatically, overriding his 50% done if entered)

Hi efrizzel,
   I would advise you to make your tasks as effort driven with a range of date for completion of task.  That would help you get actual reported tasks over a period of time with better accuracy. 
Regards, Syed Faizan ur Rehman, CBPM®,PRINCE2®, MCTS

Similar Messages

  • Payroll should pick no of hours worked from attendence infotype

    Hi ,
    I got one requirement. When we are running pay roll no of hours worked is picked from workschedule.But my requirement is it should pick up from attendence infotype . Can anyone tell me the rule name that attendence will be picked up.
    Please throw some light on this issue.
    Thanks and Regards
    Visali.Malepati.

    Hi Manu,
    Instead of creating a customized rule directly first  I want to know is there any SAP std rule  to do this.
    Please kindly help.
    Thanks and Regards,
    Visali.Malepati.

  • My mac hung up while installing an update. It took hours and still did not complete the update. I restarted my mac. Upon turning it back on, a wheel has been spinning on a grey screen. I tried to reinstall OS X from utilities, but encounter an error. Why?

    My mac hung up while installing an update. It took hours and still did not complete the update. I restarted my mac. Upon turning it back on, a wheel has been spinning on a grey screen. I tried to reinstall OS X from utilities, but encounter an error. What do I do?

    Hey Manaskala,
    First point of call on all grey screen issues is the following:
    http://support.apple.com/kb/TS2570
    Given this issue has appeared after a software update, I'd advise you do the following instead though:
    1. Get an external hard drive, with enough space to put the entire hard drive of your Mac onto. Make sure you've safely copied any data you have off of it, as the next step will erase it.
    2. In the recovery HD of your machine, use Disk Utility to format you EXTERNAL hard drive with the partition table as GUID, and the format as Mac OS Extended (Journaled).
    3. Get out of Disk Utility, and click Reinstall Mac OS X.
    4. When asked where, choose to install onto your external hard drive.
    5. When the download and installation is complete, your Mac will reboot into a clean fresh setup screen. Make your user account an administrator, and make up a name and password; I use 'Test' and 'test'.
    6. Your machine is now running from the external hard drive, not the internal hard drive, so don't be alarmed when you don't see your files.
    7. Open the finder, you should see 'Macintosh HD' in the sidebar. This is the internal hard drive of your computer.
    8. Open Macintosh HD, and copy out the following folders into a new folder on your desktop:
    -Users.
    -Applications.
    -Library. (This only needs to be done if you use 3rd party software that saves things in the /Library, do a quick google and see if it does e.g. Photoshop, Protools).
    9. When these have copied (it'll take quiet a while), you can now use Disk Utility to erase your hard drive. Don't erase Macintosh HD but the ENTIRE hard drive on the inside of your Mac, and as Thomas A Reed mentioned, there was likely an existing issue on your HDD so please go to Security Options and choose 'Zero Out' before clicking erase. This will rebuild the partition table which was a possible cause of the failed update.
    10. Reboot the machine holding 'Option', go to recovery HD.
    11. Choose 'Reinstall Mac OS X', this time onto your INTERNAL hard drive.
    12. When this is complete, make another admin user called test and password test, like you did last time.
    13. Run Software Update from the  menu of your Mac.
    14. In the Finder, you should see your external Hard Drive. open it up, inside that you should see your desktop etc, and on the desktop will be your folder containing Library, Applications and Users.
    15. Go to Finder up next to the  and choose File -> New Finder Window.
    16. In your second finder window, open up Macintosh HD (through the Go -> Computer menu), and go to your Users folder.
    17. Open the Users folder in your first finder window, and copy your user folder (has your name on it) into the second user folder (the one inside Macintosh HD).
    18. This might take a while.
    19. When complete, go to System Preferences -> Users and Groups and unlock the padlock.
    20. Click the '+' sign, and make a new administrator user.
    21. Now, the fun bit. Note the name of your user folder you copied, e.g. 'Nathan', containing all of your stuff. Note the difference between your user folder (has your name on it) and the Users folder (contains YOUR user folder, guest folder and shared folder).
    22. Make the ACCOUNT NAME of your new adminstrator user the EXACT name of your user folder (normally lower case and without spaces), this is case sensitive folks. Your full name can be whatever you want, usually your full name.
    23. Then click create. You should be informed that a home folder with that name in it already exists in the Users folder, would you like to make your new account from that folder? say YES!
    24. When this is complete, log out of the Test user, log into your new account we've just made, all your stuff should be there.
    25. ???????
    26. Profit.
    There's a few little bits that may need to be cleaned up afterwards, applications folder from your external hard drive should replace the applications folder on your internal hard drive, if the previously mentioned /Library folder contained important goodies then that should replace the /Library folder on your new Mac.
    Hopefully that will help you out, straight after that is done make sure your stuff is there, erase your external hard drive and turn on time machine!

  • Is it normal for iPhone 5 to take about 4 hours and 15 minutes to completely charge from 0%?

    My iPhone 5 takes just over 4 hours to completely charge from a complete battery drain. I am very curious as to whether or not this is normal or abnormal? My previous device was the Droid Razr Maxx HD which took about 2 hours to completely charge. Am I stressing over nothing?

    From the horse's mouth: http://www.apple.com/batteries/
    "Most lithium-ion polymer batteries use a fast charge to charge your device to 80% battery capacity, then switch to trickle charging. That’s about two hours of charge time to power an iPhone to 80% capacity, then another two hours to fully charge it, if you are not using the iPhone while charging. You can charge all lithium-ion batteries a large but finite number of times, as defined by charge cycle."

  • Complete work orders without complete notifications from Overall Completion

    We have a work order assigned to a notification type and we need to complete the work order from the overall completion transaction  (IW42) without completing the notification when clicking on technical completion button.
    Is it possible?

    You can check with your netweaver team if this could be controlled from user authorizations. Do check if the following Business Transactions are available against the tcode "iw42"
    PMM2     Put notification in process     
    PMM4     Complete notification     
    PMM6     Put notif. in process again     
    I hope this will help.
    Regards

  • Hours worked from PS and CS

    Hi,
    I'd be grateful if anyone could indicate what standard extractors and InfoProviders one can use to extract/store information about hours worked. The hours are stored in table AFVGD and field ISMNW.
    Cheers

    Hi Markus,
    DataSource: 2LIS_18_I3OPER – Service order operation and 2LIS_17_I3OPER – Maintenance order operation
    Please see these:
    http://help.sap.com/saphelp_nw04/helpdata/en/bc/de163d5abd752de10000000a114084/content.htm
    http://help.sap.com/saphelp_nw04/helpdata/en/a7/fb0d3dbd82f72ce10000000a114084/content.htm
    Hope this helps...

  • Calculate the performance of an activity according to the hours worked

    Hi for all,
    I need to calculate the performance of an activity according to the hours worked by anyone. Someone could tell me how can I do this?
    timetable of staff
    ID  HR1  HR2  HR3  HR4   DAY
    1   492  720  780  1080  Monday
    1   612  720  780  1200  Tuesday
    1   492  720  780  1080  Wednesday
    1   612  720  780  1200  Thursday
    1   492  720  780  1080  Friday
    2   492  720  780  1080  Monday
    3   492  720  780  1080  Saturday
    SQL> Select to_date(to_char(trunc(sysdate) + 492/1440,'dd/mm/yyyy HH24:MI:SS' ), 'dd/mm/yyyy HH24:MI:SS') from dual;
    TO_DATE(TO_CHAR(TRUNC(SYSDATE)
    20/01/2011 08:12:00
    Table Holidays
    ID DATE_HOLIDAY HOLIDAY
    1  01/01/2011   Holiday X
    1  03/15/2011   Holiday Y
    1  07/04/2011   Holiday Z
    2  01/01/2011   Holiday X
    Input Values
    Start Date : 17/01/2011
    Qtd Days   : 0
    Qtd Hours  : 11
    Qtd Minutes: 0
    Result
    18/01/2011 13:24Regards,

    Okay here is my second attempt.
    With schedule_of_work As
         Select 1 ID, 492 HR1, 720 HR2, 780 HR3, 1080 HR4, 'Monday'    Day_of_week from dual union all
         Select 1 ID, 612 HR1, 720 HR2, 780 HR3, 1200 HR4, 'Tuesday'   Day_of_week from dual union all
         Select 1 ID, 492 HR1, 720 HR2, 780 HR3, 1080 HR4, 'Wednesday' Day_of_week from dual union all
         Select 1 ID, 612 HR1, 720 HR2, 780 HR3, 1200 HR4, 'Thursday'  Day_of_week from dual union all
         Select 1 ID, 492 HR1, 720 HR2, 780 HR3, 1080 HR4, 'Friday'    Day_of_week from dual
    ), parameters AS
            /* Creating a single row of input values that can be used multiple times */
            SELECT TO_DATE(:job_start_date,'MM/DD/YYYY HH24:MI')             AS job_start_date
                 , TRUNC(TO_DATE(:job_start_date,'MM/DD/YYYY HH24:MI'),'IW') AS beginning_of_week
                 , NVL(:days,0)
                 + NVL(:hours,0)/24
                 + NVL(:minutes,0)/(60*24)                                   AS job_length
            FROM   dual
    ), holidays AS
            SELECT TO_DATE('01/01/2011','MM/DD/YYYY') AS dt FROM DUAL
    ), date_range AS
            /* Trying to generate a date range that should encompass the maximum date it would take
             * to complete the task. Rough estimate is number of 8 hour work days plus a padding of 10 days.
             * You may want to adjust this to something more suitable for your business or set it to an artificially
             * high value. Be aware of possible performance implicications the higher you set it.
            SELECT TRUNC(job_start_date) + (ROWNUM - 1) AS dts
            FROM   parameters
            CONNECT BY ROWNUM <= TRUNC(job_length*24/8) + 10
    ), schedule_as_dates AS
            SELECT sowo.id
                 , sowo.day_of_week
                 , dara.dts
                 , holi.dt
                 , CASE
                        /* Only perform the effective hours when the day is not a holiday
                        * and it matches a date in the date range. Otherwise set effective hours to midnight
                        * making the running sum below zero.
                      WHEN sowo.day_of_week IS NOT NULL AND holi.dt IS NULL
                       THEN dara.dts + HR1/(60*24)
                       ELSE dara.dts
                   END                                    AS start1
                 , CASE
                       WHEN sowo.day_of_week IS NOT NULL AND holi.dt IS NULL
                       THEN dara.dts + HR2/(60*24)
                       ELSE dara.dts
                   END                                    AS end1
                 , CASE
                       WHEN sowo.day_of_week IS NOT NULL AND holi.dt IS NULL
                       THEN dara.dts + HR3/(60*24)
                       ELSE dara.dts
                   END                                    AS start2
                 , CASE
                       WHEN sowo.day_of_week IS NOT NULL AND holi.dt IS NULL
                       THEN dara.dts + HR4/(60*24)
                       ELSE dara.dts
                   END                                    AS end2
            FROM      date_range       dara
            LEFT JOIN schedule_of_work sowo PARTITION BY (sowo.id) ON sowo.day_of_week = TO_CHAR(dara.dts,'FMDay','NLS_DATE_LANGUAGE=English')
            LEFT JOIN holidays         holi                        ON holi.dt          = dara.dts
    SELECT
           CASE
           /* This means that we need to go into the second shift (start2-end2) to calculate the end date */
           WHEN  work_remaining > end1 - start1
           THEN  start2 + work_remaining - ( end1 - start1 )
           /* This means we can complete the work in the first shift */
           WHEN  work_remaining < end1 - start1
           THEN  start1 + work_remaining
           END   AS finish_time
    FROM
            SELECT b.*
                 /* Determine how much work is remaining from the previous days value */
                 , job_length - prev_work_time                               AS work_remaining
                 /* Calculate the smallest delta value to pick the right day of the week
                    to calculate the end date
                 , ROW_NUMBER() OVER (partition by B.ID ORDER BY DELTA desc) AS RN
            FROM
                    SELECT a.*
                         /* This computation is used to determine which day of the week we need to use
                            to determine the end date of the task
                         , job_length - effective_work_time AS delta
                         /* retrieve the previous effective_work_time. This will be used above */
                         , LAG(effective_work_time) OVER (PARTITION BY ID order by start1) AS prev_work_time
                    FROM
                            SELECT job_start_date
                                 , job_length
                                 , id
                                 , day_of_week
                                 , start1
                                 , end1
                                 , start2
                                 , end2
                                  /* Compute the amount of time an employee can work in any given day. Then take a running total of this */
                                 , SUM
                                     CASE
                                         /* When the job_start_date is the same day as the first eligible work day we need to diskount (spam filter misspelled on purpose the
                                          * effective work hours because the job could start in the middle of the day.
                                         WHEN TRUNC(job_start_date) = TRUNC(start1)
                                         THEN
                                              CASE
                                                   WHEN job_start_date BETWEEN start1 AND end1
                                                   THEN (end1 - job_start_date) + (end2 - start2)
                                                   WHEN job_start_date BETWEEN start2 AND end2
                                                   THEN (end2 - job_start_date)
                                                   WHEN job_start_date < start1
                                                   THEN (end2 - start2) + (end1 - start1)
                                                   WHEN job_start_date > end2
                                                   THEN 0
                                              END
                                         ELSE (end2 - start2) + (end1 - start1)
                                     END
                                 ) OVER (PARTITION BY ID order by start1) AS effective_work_time
                            FROM       schedule_as_dates
                            CROSS JOIN parameters
                    ) a
            ) b
            /* Only interested in delta less than zero because the positive deltas indicate more work needs to be done. */
            WHERE delta < 0
    WHERE RN = 1I got slightly different results then you. My query got me 1/24/2011 at 13:12. I double checked the math and I think that's right.
    Hopefully this works out for you. My apologies for any mistakes.
    EDIT
    Query is fully posted now.

  • Cancellation of hours worked

    Hello all,
    I am new to the SAP world and could use some advise. We are using CRM field service and are using service confirmations to log our enginners time spent on the job. We also use the service confirmation for invoicing the hours worked. What we are trying to test is, if we enter hours worked change the status of the service confirmation to "In Review: which is a status used for getting approval from the manager that we delivered what we promised. In this stage hours doesn't get transferred autiomatically to ECC ( HR ) unless the status of the service confirmation is set to "Complete" However we manually ran the ECC transaction CAT7 to transfer those hours to ECC. We then changed the service confirmation status to "Cancelled" Now what we want to see is the cancellation of the confirmed hours to controlling in SAP. However now when we try to run CAT7 again there is no documents found. Does anyone know the proper process to cancelling a service confirmation so that the cancelled hours in CRM get transferred to ECC? Any advise is greatly appricated.

    Hi Dean,
    The data gets replicated from CRM to ECC only when the status of the Confirmation is set to "Completed". A CATS document gets created in ECC and when you run CAT7 then the actual costs (based on the actual duration of hours) is posted to the internal order.
    If you want to cancel this confirmation, then you need to search for the confirmation and then click on the "Cancel Confirmation" button displayed in the search page of the confirmation. Once this is done - a cancellation status is set to the CATS document.
    Now when you run CAT7 for the same CATS document - the actual costs posted to the internal order is reversed.
    Regards,
    Siraj

  • Project Physical Percent Complete IS not Getting updated in Fusion Projects

    Hi Everyone,
    I am Working on Fusion PPM Release9
    In Project Plan Type i have set Physical Percent Complete to Cost & Automatic But in dashboard the Project Physical Percent Complete is not Updating
    Please help me with the issue
    Thanks
    Shaan

    Hi Kedar,
    It should not happen.
    Question: Do such projects have a direct underlying task?
    I have know a problem, which occurs only that the project has direct underlying task.  If yes, I will find the note for it.
    Kind regards,
    Zhenbo

  • Need to get the overtime hours worked for Report

    Dear Experts,
    We have configured Overtime for client and it is working fine.
    But for custom report development we need to get the overtime hours worked.
    We have searched in B2 cluster and not able to identify exact overtime table.
    Request your suggestionsu2026u2026..

    Hi,
    after time elavualtion use t code PT66,  in this t.code double click on the each month(period) then you can get the internal table like ZES, SALDO, ZKO. again double click on the each internal table, you can get the information through the time types.  Like , now you want the overtime hours, 0903, 0904 with this time types you can get the each employee no. of. overtime hours.
    ZL, ZES, SALDO, TIP entries are internal table , you could not get any results from this table with using se11, se16.
    With PT_BAL00 with this report also we can get the overtime hours with the help of time events.
    Good luck
    Devi

  • I just reset my i phone 6, it take so long, almost 1 hour , only 10 per cent completed, is it normal. if not what can i do

    i just reset my i phone 6, it take so long, almost 1 hour , only 10 per cent completed, is it normal. if not what can i do

    PolishAngel756 wrote:
    Some friends have told me that their phone can last up to 2 days without charging??
    If they are getting 2 days without charging, it's unlikely they use their device very much.
    A full day is pretty good....and if I'm careful, I can easily get a full day of usage.
    For me, normal is charging the iPhone mid afternoon at work, but I use it a lot.
    My typical usage is 35 mins of listening to podcasts, checking email, checking my RSS feed, and checking a few apps while I ride my bike when I first get up.  Then listening to several podcasts at work.
    I typically stream music while working out during my lunch hour and use the Men's Health Fitness app to track my progress.
    By about 2pm I'm ready to charge the device as it's getting low (somewhere between 20% and 50%).
    I leave bluetooth, Wi-FI, and location services turned on all the time.
    Personally, I just do not see the point in going into settings to turn on the feature when I need it... just too much hassle.  All of my listening to podcasts and music is via Bluetooth.
    I know I'm not the heaviest user, but I just do not see how anyone can realistically make it two days on a single charge, it makes me think they simply do not use the features of the device and would be just as well served with a basic or feature phone.

  • Delete Work Item from PO Releaser's Inbox during Workflow

    Hi All
    How can I delete the previous Work Item that was created in the PO Releaser's Inbox if a PO was changed which re-triggered the PO Release workflow but this time to a different PO Releaser.
    The workflow is working correctly, i.e. creating the new release item in the new releaser'd Inbox but not deleting the old Work Item for the previous releaser.
    Any idea on how I can accomplish this?
    Kind Regards
    Utian Goliath

    PLease refer the below stuff................create a task and put the code inside the method.This task should be fisrt step in your workflow.
    User sets doc to Complete from FBV2 , Complete event triggered and workflow triggered.
    Workitem goes to approver .
    Now , the user immediately changes doc from FBV2 , sets it to Complete again and workflow triggered
    workitem goes to the same approver for the same document.
    SAP_WAPI_WORKITEM_TO_OBJECT - Worklist table will giv all parent id's for the object key concatenation of
    com code , doc no and fiscal year.
    SWP_WORKFLOW_INSTANCE_DELETE - Pass the parent id and will delete the entire instance but not
    parent workitem id.
    SAP_WAPI_WORKITEM_DELETE - Pass parent id everything will be deleted .( Check_final_state = blank ).
    No trace found in SWI14 and SWI2_FREQ.
    To remove the previous workitem , create a method in the begining of the workflow , use F.M.
    SAP_WAPI_WORKITEM_TO_OBJECT to get the workflow id's and then
    SWP_WORKFLOW_INSTANCE_DELETE or SAP_WAPI_WORKITEM_DELETE to delete the previous instance.
    data : lt_worklist type table of SWR_WIHDR,
           lw_worklist type SWR_WIHDR,
           lv_objkey type SWOTOBJID-OBJKEY,
           lv_return type sy-subrc,
           lv_id type SWP_HEADER-WF_ID.
    concatenate object-key-sourcecompanycode object-key-documentn
    object-key-fiscalyear into lv_objkey.
    CALL FUNCTION 'SAP_WAPI_WORKITEMS_TO_OBJECT'
    EXPORTING
      OBJECT_POR                     =
       OBJTYPE                        = 'FIPP'
       OBJKEY                          = lv_objkey
      TOP_LEVEL_ITEMS                = 'X'
      SELECTION_STATUS_VARIANT       = 0001
      TIME                           =
      TEXT                           = 'X'
      OUTPUT_ONLY_TOP_LEVEL          = ' '
      LANGUAGE                       = SY-LANGU
      DETERMINE_TASK_FILTER          = 'X'
      REMOVED_OBJECTS                = ' '
    IMPORTING
       RETURN_CODE                    = lv_return
      TABLES
      TASK_FILTER                    =
        WORKLIST                       = lt_worklist
      MESSAGE_LINES                  =
      MESSAGE_STRUCT                 =
       if lt_worklist is not initial.
    loop at lt_worklist into lw_worklist.
      object-instance = 'X'.
    move lw_worklist-wi_id to lv_id.
    CALL FUNCTION 'SWP_WORKFLOW_INSTANCE_DELETE'
      EXPORTING
        WF_ID                         = lv_id
        DO_COMMIT                     = 'X'
    EXCEPTIONS
      WORKFLOW_DOES_NOT_EXIST       = 1
      OTHERS                        = 2
    IF SY-SUBRC <> 0.
    MESSAGE ID SY-MSGID TYPE SY-MSGTY NUMBER SY-MSGNO
            WITH SY-MSGV1 SY-MSGV2 SY-MSGV3 SY-MSGV4.
    ENDIF.
    ENDLOOP.
    ENDIF.
    Second way is to create a fork , and use wait for event step in it with the same event that is triggering the WFL
    In the same branch take a process control to end workflow instance.
    In the second branch carry out normal processing.
    Necessary branch = 1.
    So incase the user triggers the event again, a new instance will be created ,
    and in the previous instance , the first branch will follow ending the
    previous instance and the workitems of other branch will be logically deleted.

  • Render Work Area only partially completes?

    Hello everyone,
    I have searched the Forum but not found an answer or discussion on this problem.
    My problem is that Render Work Area only partially completes, i.e. if I have several clips in the work area (all showing yellow in the status area) and I apply transitions or effects to several of them, such that the modified segments show red in the status area, I expect to be able to Render Work Area [ENTER] and have it render all the segments that are red.  But it doesn't.  It renders the first few red segments then stops.  I have to manually hit ENTER several times to get it to render all the pieces.
    I'm pretty sure this is not how it is supposed to work.  In previous versions of Premiere, it would render all red segments in one go.
    Does anyone know what I need to do to make it render everything in one pass?
    I did find this post on a different forum:
    http://www.dvxuser.com/V6/showthread.php?211157-Annoying-Premiere-Pro-CS5-Preview-Render-I ssue
    But no solution was ever reported.  The person just re-installed on a new machine and the problem did not appear on the new machine.  But I don't have another machine to try this on.  My machine is a Windows 7 64-bit i7.  I am running Premiere Pro CS5 5.0.0.  My footage is from a Canon 5D Mark II, 1080p, 29.97fps.  The footage natively displays and previews fine.
    Thank you very much in advance for any help you can give.
    Best wishes,
    Lloyd

    > I am running Premiere Pro CS5 5.0.0.
    You should install the Premiere Pro CS5 (5.0.3) update. The recent updates fix a lot of problems.

  • How prevent movie from loading completely before playing?

    Hi,
    how do I prevent an swf from loading completely before
    starting to play in the browser? When simulating a download in the
    Flash application, several preload stages work perfectly, but not
    in the browser. Preload stages don't appear, instead it takes ages
    for the 3.5 mb file to completely load before displaying the first
    frame of the movie.
    I have tried inversing the load order in export settings and
    different flash versions, but just can't get it to work.
    Can someone help? Thank you!

    hi kglad
    I thought it should be that way; the point is that I don't
    want to add code that loads the entire movie before starting to
    play the first frame, but only a certain number of frames (i.e. 11
    out of 35, for example). I'm trying to do this with this code in
    the first frame:
    ifFrameLoaded (11) {
    gotoAndPlay("start");
    in the simulation, it works perfectly, but when uploading the
    movie and viewing it in html, the entire thing loads, and the
    preloader doesn't appear.
    Many thanks for your help.

  • Display universal work item from CRM work list

    Hello all,
    In ECC system, we have defined several workflows. We can see the work item from the universal work list via the portal.
    Now, we have a new request, we would like to see these work items form CRM work list.
    I have checked the custo and I have questions:
    1. spro- Customer Relationship Management under  UI Framework  Technical Role Definition  Define Navigation Bar Profile . Select the relevant navigation bar profile and add the specific UI objects WI_BOR.
    please check the link http://help.sap.com/saphelp_crmscen70/helpdata/en/e9/7fec7e8f954e7fb60d56dd6324e313/frameset.htm
    2. CRM->Basic functions->Worklists->Define Alert Inbox and Workflow Inbox->Define Object-Specific Navigation
    => here i am not sure if need to add entry, if yes, which entry ?
    3.  need to define  ??
      RFC destination
    . Transaction Launcher Logical Systems and URLs 
      and workflow substitute profile Id
    Thanks in advance for your help.
    Best Regards,
    Elsa

    I've found a solution.
    I've been told that this problem is occuring
    because the Work Item ID is not being passed correctly to the BOR basedtransaction.
    The solution in my case is:
    (1) Goto SPRO -> Customer Relationship Management -> IC Web Client ->
    Basic Functions -> Transaction Launcher -> Configure Transaction
    Launcher (wizard)
    (2) Give the launch transaction id in the 'Entries' screen. The launch
    transaction id is Z_ACTION_EXECUTE_WORKITEM in my case.
    (3) Keep all the parameters same in the further screens until you reach
    the 'Transaction Parameters' screen
    (4) In this screen, the value currently being passed to Object Key is
    //selectedAUI Workitem/WI_ID. Change this to
    //selectedAUIWFWIAttachments/OBJECT_ID.
    Goto last step and then say 'Complete'.

Maybe you are looking for