How manage SPDD change request

Hi all,
Later the first upgrade phase from 4.7.2 to ECC 6.0, I finished SPAU and SPDD. I have a only CR for SPDD, the objects are not activated and tasks and change request are open. Exactly, when I have to activeted objects? When I have to release tasks and CR? How I have to manage the "Select for Transort" by SPDD?
Regards
Antonio

Hi Antonio,
Have you pending request before upgrade. If yes then you have to transport these tpt. If no then you can activate now.
Regards,
Anil

Similar Messages

  • How to control change request creation for particular IBase Component?

    Dear Experts,
    Can anybody suggest , how to control change request creation for particular IBase Component?
    We have implemented ChaRM which is integrated with SAP ECC & SAP BI.
    ChaRM is not integrated with SAP Solution Manager.
    End Users are creating support notifications from -Help Menu- Create Support Notification.
    The IBase Component is not editable once notification is created. This Ibase is copied to change request when the action-create change document is saved.
    Requirement is that, during creation of change document, system should check the IBase component of support notification. If the IBase is related to solution manager system, system should restirct the change request creation.
    Kindly suggest how to achieve this.
    Regards
    Vivek

    Hello Vivek,
    The way to do what you want is to create a schedule condition for action Create Change Document. The action has to be displayed only when the IBase/Component value differs from SolMan. To add the IBase/Component value to the container so that it can be evaluated during runtime, you will have to create a subtype of BUS2000116 on which condition can be buit.
    See the following posts for more information :
    Hope this helps,
    BR.
    Stéphane.

  • How to create change request

    HI,
    how to create change request for a program and how to compare versions ? how to release the task ? where we create change request ? how to transport it ? who will transport ?
    In real time who creates change request ? developer  or Team leader or Basis mainly in supporting project ?

    The Change Request is that request when you do changes or create a program or configuration in the system. The system will automatically popu with the change request pop box , when you can give request name as defined by the system or can give your own request name with heading of what changes you have made while customization. The system will generate a request number and you save it. (e.g.:- SEDE-2785467) SEDE- means the Clients System name then followed by the system generated request number. 
    Now when you want to release the request you have to use the <b>T-code SE10</b> where you can see the requests under the heading modifiable or released. Go to the modifiable option. Each request will have again an internal request number. First you have to release the internal request and then release the external request number. This will in turn released by the basis guys thru the <b>T-code SM64</b> in a group when all the requests are pooled from different users.
    The task  is nothing but the what task you have performed while customizing the client system and the heading name which have given it for that task and generated a request for that task.
    regarding your last question, change request is usually created by the developers or team leader. But the transporting is mostly done by basis.
    regards
    vivek
    <b>please reward points if this helps</b>

  • How to download Change request?

    Hi all,
    How to download change request from one r/3 server, and then upload to other r/3 server.
    I guess that it can do, but I don't find where to do?
    Thanks.
    Aaron

    Hi Aaron,
       First release the TR and then plz follow the following procedure.
    Case 1: if u want to import the request from one R/3 system to other.
    Send the TR no to basic people specifying the target system name and then they will do the necessary actions.
    Case2: if u want to download the TR from DEV to QUALITY system.
    1. go to STMS_IMPORT
    2. find ur request is existed in the list or not,
        if it exist in the list, select the TR and then press Ctrl+F11 ie Import Request.
        if it is not exist in the list, then goto
        Extras - > other requests
        and give ur TR no and then give the client no.
        now the TR is displayed at end of the list.
        select that TR and then press Ctrl+F11.
        Now the TR is successfully imported into the QUALITY system.
    Reward if helpful.
    -Prasanth

  • How to deactivate Change Request Management workflows task

    We are in a situation where we are switching external SAP service
    organisation and we cannot at this stage introduce any new procedures
    regarding sceduling-tasklists/TMS/etc. Our ChaRM implementation project
    must be set back in to a possision where we can maintain our normal
    system maintainance processes without using a fully implementated
    CharRM functionallity. The implementation of CharRM has to be realized
    in 2 steps:
    a) activate only ChaRM documentation system/flow as an extention of
    servicedesk, implement this in our organisation
    b) activate fully ChaRM functionality with interaction with
    SLD/TMS/tasklists/etc after we have switched service organisation
    Needs:
    1) How to deactivate ChaRM IMG setting SAP Solution Manager-
    >Configuration->Scenario-Spesific Settings->Change Management->Change
    Request Management->Standard Configuration->General Activities-
    >Activate Integration with Change Request Management and related
    settings.
    We had in an earlier stage the total service process/documentationflow
    up and running and with possibilities to interact/respond on
    servicemessages for these roles: User, Servicedesk, Change Manager,
    Change Advisory board, Developer, Tester, IT Operator equal to ChaRM
    process.
    2) Ensure availability to use ChaRM as a extention to servicedesk
    regarding administration and documentation of SAP changements.

    Hi,
    Find the guides : on help.sap.com
    Change Management:
    http://help.sap.com/saphelp_sm40/helpdata/en/0c/5b2160f6fa4b83a3674a210b1cdeb0/frameset.htm
    Service Desk:
    http://help.sap.com/saphelp_sm40/helpdata/en/45/51fbdbd4941803e10000000a1553f7/frameset.htm
    Regards,
    Siddhesh

  • How to include Change Request Title and Description in Approval email

    Trying to figure out how to include the title and description of a Change Request in the email that goes to the managers when they approve it. Below is what we have now in the email template.
    Change request $Context/Path[Relationship='CustomSystem_WorkItem_Activity_Library!System.WorkItemContainsActivity' SeedRole='Target' TypeConstraint='WorkItem!System.WorkItem']/Property[Type='WorkItem!System.WorkItem']/Id$: $Context/Path[Relationship='CustomSystem_WorkItem_Activity_Library!System.WorkItemContainsActivity'
    SeedRole='Target' TypeConstraint='WorkItem!System.WorkItem']/Property[Type='WorkItem!System.WorkItem']/Title$, created by $Context/Path[Relationship='WorkItem!System.WorkItemCreatedByUser' TypeConstraint='System!System.User']$?$DisplayName$?, requires your
    approval.
    You can complete this request by replying to this message with [Approved] or [Rejected] in your message body (note the brackets).
    Alternatively, you can complete the request by looking up Review Activity $Context/Property[Type='WorkItem!System.WorkItem']/Id$ under the Activity Management views in the Service Manager Console and manually approving or rejecting it there.
    This basically translates to:
    Change request CR#: Test Change Request, created by TestUser1, requires your approval.
     You can complete this request by replying to this message with [Approved] or [Rejected] in your message body (note the brackets).
    Alternatively, you can complete the request by looking up Review Activity RA# under the Activity Management views in the Service Manager Console and manually approving or rejecting it there.
    When I click on Insert, there is a huge list of items and sub-items with all kinds of properties and I don't know what to select.
    The Targeted Class of the template is Activity

    $Context/Path[Relationship='CustomSystem_WorkItem_Activity_Library!System.WorkItemContainsActivity' SeedRole='Target'
    TypeConstraint='WorkItem!System.WorkItem']/Property[Type='WorkItem!System.WorkItem']/Title$
    This translates to the Title of the CR (given that the targeted activity is contained in a CR). Simply replace
    Title with Description.
    Also if the Change Manager can approve a CR just by the description you have bigger issues (or just putting everything in the description). What about a reason? Implementation
    plan, rollback plan, testing, etc.?
    http://codebeaver.blogspot.dk/

  • SAP IDM on Solution Manager with Change Request Management

    Hi Experts,
    I'm facing a question. Does SAP Identity Management manage association between user in Solution Manager and links in PPOMA_CRM tree for Ticket validation on Change Request Management project ?
    It seems that it could be done using Compliant User Provisioning from GRC Access Control application.
    Thanks for your help,
    Ben

    Hello Ben,
    as far as I know currently there is no "business level" integration between IdM 7.1 and SAP Solution Manager. You only can create SU01 user data as for any other SAP ABAP system.
    I have heard that it is planned for the future to integrate the Solution Manager also in the business suite integration options the IdM product already provides for applications such as CRM, SRM and others.
    Nevertheless you could create your own implementation for your requirements.
    Regards,
    René Feister
    SAP Consulting Germany

  • Releasing Transport task from  either schedule manager or change request

    Hi Gurus,
    I had a doubt regarding releasing of tasks of a transport request.
    Is there any way where I can release a task along with the transport request in the Correction transaction itself?
    Or is it a standard behavior of SAP Solman process where in I have to login to the Satellite system , do the configuration and then release the task from se10 t-code and then finally release the transports.
    Require ur expertise on this point.
    Regards,
    Anubhav

    Hi Anubhav.
    Manually releasing the task in the satellite system (using SE10)
    prior to releasing the transport request in CHARM is a SAP standard process for CHARM in SOLMAN.
    I think SAP made it this way as a precaution in case there are several task included in the transport request
    (assigned to different developers). Manually releasing your task means that your confirming that
    you have completely applied your modifications and ready for import into the test system.
    If this process is included as an automated process along with the releasing of transport request in CHARM,
    you may mistakenly release another person's task which may not be ready for import yet.
    I hope this helps.
    Regards,
    Tess

  • Change request management in solution manger release 7.1 or 7.0

    Hi All,
    Can any body please explain me how to configure change request management in solman release7.1 and if it is possible please send document to my below maild Id.
    And please let me know what are the steps needs to be done satellite systems, we have EP7.0 landscape also there .do we have to do any additional configuration for that in solman side?
    I appreciate for your prompt response
    Thanks in advance
    My Id: haritechies gamil.com
    Regards,
    Hari Prasad . L

    Hi
    Adding more to it
    Use the following link,
    /people/dolores.correa/blog/2008/07/26/first-steps-to-work-with-change-request-management-scenario
    https://websmp202.sap-ag.de/~sapdownload/011000358700000657692007E/ECTS_CHARM_SP12.PDF
    Regular correction
    https://websmp202.sap-ag.de/~sapidb/011000358700000086572008E.sim
    Later login to solman enter tcode SPRO and goto scenario specific Change Request management node and start configuring by
    going through the IMG Help and as per requirement.
    Create a maintenance project and Activate Charms
    https://websmp202.sap-ag.de/~sapidb/011000358700005479242006E.sim
    Regards
    Uday

  • Document for Change request Management in Solution Manager

    Hi,
    We are setting up Solution Manager. I know service desk configuration. But I need a document on how to configure change request management in Solution Manager.
    Also I need a steps or a document for monitoring of EP 6.0 from Solution Manager.
    Thanks a ton for help in advance.

    Hi,
    Check out these links
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/media/uuid/b4406827-0a01-0010-3da2-f56b36d88510
    BI and Portals 2006 [original link is broken]
    very good collection of eclasses. for making use of solution manager.
    Feel free to revert back.
    --ragu

  • Add new system to an Existing project in Change Request in Solution Manager

    HI,
    Is it ok to add new systems and remove systems to an existing Project in Solution Manager with Change Request Management activated?
    Currently, Change request is already set-up in our solution landscape, however, a new BI Dev and QA systems were created to replace the old Dev and QA systems that was initially set-up in our Charm. Can you please share with me the steps that I need to do to successfully remove old Dev and QA from Charm and replace them with the new systems? Is it safe to do this in an open project and maintenance cycle?
    Thanks!

    Hello,
    Please, check the topic "6. Changes in the logical components of a project where Charm is already activated" of the link below:
    /people/dolores.correa/blog/2009/07/22/change-request-management-scenario-usual-questions-and-known-errors
    I think that this link can help you.
    Best Regards,
    Diego Fischer

  • Change Request Management for Implementation Project

    Hello gurus!
    I have a problem with execution change request in implementation project.
    I have created Implementation project and task list for him."Change request management" is active for this project.
    I can create document Change Request, but I can not to create Correction linked with Task plan...
    Dmitry.

    HI,
    Have you verified if your project definition is setup correctly ? Please verify with some of the steps available in the blogs
    First steps to work with Change Request Management scenario
    /people/dolores.correa/blog/2008/07/26/first-steps-to-work-with-change-request-management-scenario
    Change Request Management scenario: Usual questions
    https://weblogs.sdn.sap.com/cs/junior/view/wlg/15116
    Change Request Management scenario: Working examples
    /people/dolores.correa/blog/2009/07/23/change-request-management-scenario-working-examples
    Hope this helps.
    Cheers
    Sh

  • Change Request without development

    Is there a way to process a Change Request without actually going through development?  We have a situation where some development work will actually be done in another system not linked to Solution Manager, but yet we would like to be able to manage the change request for those changes in Solution Manager.  (The idea being that all change requests will be managed in the one Solution Manager system.)  As our current system is setup right now, we cannot get past the status of "In Development" without actually making any development changes. 
    Are there any suggestions on how to by-pass this?

    Hi Rita,
    actually i have the same problem and i think about how to connect non-sap-systems to the change request in sap solution manger.
    How did you connect theses systems to the solution manager? What did you do in transaction smsy?
    Did you create a project and a maintenance cycle for the change requests of your non-sap-system?
    Is therer a possibility to report theses change requests?
    Thanks in advance,
    Jens

  • How big effort it is to setup Change Request Management?

    We are interested in implementing Change Request Management into our Solution manager 7.0.
    What size of an effort in mandays it actually is and what kind of professional roles are required to set it up? Some background information for your responses:
    implementation project is already there in Solman (SOLAR01/02) and is already live
    satellite system connections within SMSY are already active
    no central CTS/CTS+ is currently in use
    when having CHARM it is assumed that also CTS+ should be used
    So, I guess we are in a typical situation where implementation project has ended and live and support organisation and tools are being setup. There we need CHARM and CTS+.
    I have read lots of SDN threads and blogs, but did not get a clear picture how big effort setting up CHARM is. Please note, I not looking for config guides now, just your experiences. Even if am not interested in config guides, could you at least describe the main steps that are necessary in setting up CHARM?
    br Kim

    Hi
    Adding more to it
    Use the following link,
    /people/dolores.correa/blog/2008/07/26/first-steps-to-work-with-change-request-management-scenario
    https://websmp202.sap-ag.de/~sapdownload/011000358700000657692007E/ECTS_CHARM_SP12.PDF
    Regular correction
    https://websmp202.sap-ag.de/~sapidb/011000358700000086572008E.sim
    Later login to solman enter tcode SPRO and goto scenario specific Change Request management node and start configuring by
    going through the IMG Help and as per requirement.
    Create a maintenance project and Activate Charms
    https://websmp202.sap-ag.de/~sapidb/011000358700005479242006E.sim
    Regards
    Uday

  • How to notify (email) Change Manager when new Change Request is created

    Hi there, I am battling to generate an email when a developer creates a Change Request directly in the SolMan system. When he creates a new Change Request via CRMD_ORDER by filling in the Sold-to-Party, Change Manager, iBase etc., the message is automatically in 'To Be Approved'. I want to notify the Change Man ager as soon as a new Change Request has been submitted, but when I check the Actions tab in the message, no email action is listed or executed. I have edited SLFN0001_STANDARD... in SPPFCADM with conditions set. How can I create a email notification for the Change Manager as soon as a Change Request is in To Be Approved status?
    Message was edited by:
            Bernardt Nel

    Hi,
    Create a action definition with the following information:
    Processing when saving.
    No restriction.
    Check Schedule Automatically.
    Check Partner-Dependent.
    Select Partner Function for Change Manager.
    Determination Using Conditions that Can be Transported.
    Then you have to create an Start Condition such as; userstatus = to be approved.
    No scheduled condition is needed.