How sales order gets shipping date

Dear all,
Please tell me how to get these vales in sales order/Schedule line/Shipping.
Delivery date             D         2010/11/16
Goods issue date                 2010/11/15
Loading date                         2010/11/12
Material avail.date                 2010/11/11
Transportation Plan. Date     2010/11/11
I don't konw how to calculate  the deta of 'Loading date' ,and "Goods issue date".
Thank you very much.

hi ryo,
this is to inform you that,  you have asked all the topics in one single question.
in simple terms:
from schedule line date these all will get added according to the informatinon furnished in shipping point.
this information is automatically calculated by the system
regars,
balajia.

Similar Messages

  • How to consider production capacity plan on sales order's delivery date.

    HI experts,
    How to consider production capacity  on sales order's delivery date.
    Say for example :
    Production workcenter capacity to produce the XYZ material 10qty in a Day.
    today i have created the sales order XYZ materail qty of 100. lead days has give based of MMR 21 days 17-07-2010( 3 sundays)
    and in same day i have created other sales order XYZ material qty 5000 ,the lead days again it will came 17-07-2010.
    Now my client requiremnt is when the schedule days is confirming in the sale order it sholud also consider the production capacity planning also
    Even though my work centers are overloaded it is confirming the sales order on 17-07-2010 (based on leads days in MMR)
    Thanks in Advance..
    Sudha

    Sudha,
    Tell your client he needs to install SCM.  Here, you can use either CTP or MLATP to confirm orders based on production capacity.
    There are a couple of standard workarounds available in R/3. 
    One is to create a constrained forecast for planning materials, consistant with capacity, convert the forecast to PIRs, and then perform ATP against 'Planning' rather than against product, using MRP Strategy 63.
    http://help.sap.com/saphelp_erp60_sp/helpdata/en/a2/4e799a927d11d1800f00c04fadcb73/frameset.htm
    Another method is to leave the Sales orders unconfirmed at original order entry (eg, no lead time).  Run MRP, run capacity levelling, firm the levelled planned orders, and then run BOP (called 'rescheduling' in R/3) against the unconfirmed backlog, with an ATP that considers firmed planned orders as supply elements.  The sales orders will confirm against the planned orders, which are scheduled according to available capacity.
    Either of these two methods will work, but the CTP SCM solution is by far the better answer.  Downside of SCM solution in general is the substantial implementation effort required.
    Rgds,
    DB49

  • Sales Order - Requested Delivey Date

    Hi All,
    Please help me resolve this requirement.
    In sales order we have a field 'Requested Delivery Date', Normally the requested delivery date is default todays date only. If not proposed by system, we have to enter it manually.
    In our project we have maintained cusotomer calendar, where some dates in an year are specified.
    Only on such dates order is possible to be delivered to the customers.
    While creating such order, we get an information message, that "no goods accepeted on 24.06.2008, the next possible date is 28.06.2008"
    This date (28.06.2008) comes from the cuustomer calendar attached to the customer master in view Unloading points.
    Now how can this date be automatically copied to the requested delivery date field so as to make the order not possible to be delivered on the todays date, & only possible to deliver on the date (28.06.2008) which is the date from customer calendar.
    I repeat, instead of automatic determination of req delivery date, or instead of manual entry, system should pick the date automatically from customers calendar after entry on Ship to party in the sales order.
    Regards
    Dhananjay

    Hi,
    sorry I just forgot to share it with all.
    See, our requirement was sales order should have delivery date into it, not proposed by system by to be fetched from the calendar maintained in the ship to party customer master record.
    We acheived this by using a feild exit for Data element "KETDAT" - Requested delivery date of the document.
    In this we incorporated the logic like to fetch the date from the calendar, additionally a function module "DATE_CONVERT_TO_FACTORYDATE" was also used.
    Whenever user creates a sales order, the system date automatically comes by default, by is replaced by the date from calendar, & a message is also passed "Change in the route calendar date"
    I am glad to inform you this worked out very well.
    Hope this is helps you all.
    Regards,
    Dhananjay

  • Find Sales Order Item Basic Data by Elements query fails

    I am trying to consume Find Sales Order Item Basic Data by Elements in .NET 3.0.
    Every thing appears to be working fine -- I could query by PO number, Creation time, SalesOrganisationID etc.
    However, the most basic query is mysteriously failing. I just want to query by Sales order number, and have given a valid sales order number 6718 that exists in SAP.
    It fails giving the following errors:
    (in Log.LogItem.Note variable):
    <b>"Conversion failed: Invalid input format"</b>
    (in Log.LogItem.TypeID variable):
    <b>"701(SFB)"</b>
    Code is pretty simple, and I am just trying to query Saler Order number 6718. Of course there is nothing wrong with its format.
    From the ESOA site, all I could get was:
    <i>----
    QUOTE -
    The following values are optional selection criteria for restricting the search result:
    SelectionByID – Document number range
    INCLUSION_EXCLUSION_CODE
    INTERVAL_BOUNDARY_TYPE_CODE
    LOWER_BOUNDARY_ID
    Value
    UPPER_BOUNDARY_ID Value
    Value
    UNQUOTE -
    </i>
    I could not even have any  documentation on what to put in InclusionExclusionCode, and IntervalBoundaryTypeCode. They apper to be some Global Data Types for which I couldn't find any documentation. By sifting through Wiki, I just guessed a couple of values praying that it may work. I am a bit new to ESOA, but have expertise in .NET 3.0. Would someone guide me where to find the documentation for that, where are the error codes listed, so that I make the queries with little better preparation.
                querydata.SelectionByID = new SalesOrderERPItemBasicDataByElementsQueryMessage_syncSalesOrderERPItemBasicDataSelectionByElementsSelectionByID[1];//Single element array is good enough
                querydata.SelectionByID[0] = new SalesOrderERPItemBasicDataByElementsQueryMessage_syncSalesOrderERPItemBasicDataSelectionByElementsSelectionByID();
                querydata.SelectionByID[0].InclusionExclusionCode = "E";
                querydata.SelectionByID[0].IntervalBoundaryTypeCode = "6";
                querydata.SelectionByID[0].LowerBoundaryID = new SalesOrderID();
                querydata.SelectionByID[0].LowerBoundaryID.Value = "6718";
                querydata.SelectionByID[0].UpperBoundaryID = new SalesOrderID();
                querydata.SelectionByID[0].UpperBoundaryID.Value = "6718";

    How do you test with a SOAP Client  - I am trying to use same dataset as provided?
    I did with WSDL Test - SAP, SOAP Client and got the following error:
    <soap-env:Envelope xmlns:soap-env="http://schemas.xmlsoap.org/soap/envelope/">
       <soap-env:Body>
          <nr1:SalesOrderERPBasicDataByElementsResponse_sync xmlns:nr1="http://sap.com/xi/APPL/Global2">
             <Log>
                <MaximumLogItemSeverityCode>1</MaximumLogItemSeverityCode>
                <Item>
                   <TypeID>701(SFB)</TypeID>
                   <SeverityCode>1</SeverityCode>
                   <Note>Conversion failed: Invalid input format</Note>
                </Item>
                <Item>
                   <TypeID>701(SFB)</TypeID>
                   <SeverityCode>1</SeverityCode>
                   <Note>Conversion failed: Invalid input format</Note>
                </Item>
                <Item>
                   <TypeID>701(SFB)</TypeID>
                   <SeverityCode>1</SeverityCode>
                   <Note>Conversion failed: Invalid input format</Note>
                </Item>
                <Item>
                   <TypeID>701(SFB)</TypeID>
                   <SeverityCode>1</SeverityCode>
                   <Note>Conversion failed: Invalid input format</Note>
                </Item>
                <Item>
                   <TypeID>701(SFB)</TypeID>
                   <SeverityCode>1</SeverityCode>
                   <Note>Conversion failed: Invalid input format</Note>
                </Item>
             </Log>
          </nr1:SalesOrderERPBasicDataByElementsResponse_sync>
       </soap-env:Body>
    </soap-env:Envelope>
    Thanks..
    Vikas

  • Sales order schedule confirmed date will consider Production capacity load

    As we know about schedule confirm delivery dates of sales order will consider based on material master lead time ,shiping point etc
    How to consider production capacity plan on sales order's delivery date.
    Say for example :
    Production workcenter capacity to produce the XYZ material 10qty in a Day.
    today i have created the sales order XYZ materail qty of 100. lead days has give based of MMR 21 days 17-07-2010( 3 sundays)
    and in same day i have created other sales order XYZ material qty 5000 ,the lead days again it will came 17-07-2010.
    Now my client requiremnt is when the schedule days is confirming in the sale order it sholud also consider the production capacity planning also(CR01,CR02)
    Even though my work centers are overloaded it is confirming the sales order on 17-07-2010 (based on leads days in MMR)
    Need your Inputs on issue

    Hi,
    This is a complex issue; best solution is by using APO/GATP.
    If not, then in ERP only, the second best is:
    1) Work with assembly processing in SO, meaning that a production/planned order is automatically created in the customer order during order creation.
    2) Then, after the order is created it is scheduled, and the delivery date proposal is based on that.
    3) Now you can check in the order that there are no capacity overloads, and all capacity required to produce on the proposed date is available. If yes, you're done. If not, it gets a bit complex, since you actualy need to switch to capacity planning, do capacity leveling and dispatch (PP), and the you get a new feasible schedule proposal based on that.
    APO/GATP could do all that automatically!
    Regards,
    Mario

  • Sales Order Item Shipping point (VBAP-VSTEL) value in APO table

    Hi,
    I am looking for Sales Order Item Shipping point (VBAP-VSTEL) value in APO.Can I  get this info in APO ?
    This information is not available in table /SAPAPO/SDORD or  /SAPAPO/SDFIELD.
    Basically table /SAPAPO/SDORD is completely blank. Table /SAPAPO/SDFIELD has entry for Sales Order Item but not for VSTEL. Shipping point is there in the Catalog table in ECC and I can see that it is getting imported to APO but why it is not avaibale in SDFIELD table.Any idea ?
    I cheked table /SAPAPO/SHIPPING also for the guid (Item guid) but not found any entry .
    Please help.

    RKS,
    Most data in SCM is not stored in tables, it is stored in LC.  In general, it is not the best idea to use APO for creating custom reports against  transactional data.  You do such reporting in the OLTP, and you use the standard SAP programs to keep these systems in synch.
    Some SD auxiliary data is sometimes stored in /SAPAPO/SD_DOC.and /SAPAPO/SDFIELD.  Check here, you might find something useful.  No guarantees......
    Best regards,
    DB49

  • List of Sales Orders wrt SHIP TO PARTY through T Code VA05.

    Hi Experts,
    Please let me know how can we extract list of Sales Orders wrt SHIP TO PARTY through T Code VA05. We can select Ship to Party option through Partner function tab in selection screen, but while executing transaction, we get list for SOLD TO PARTY.
    Please advise.
    Thanks,
    Abhishek Agrawal

    Hi,
    In the VA05 report selection screen, you have the option of selecting the relevant partner function that needs to be considered. Click on the "Partner Function" button and change it to "SH"
    Then given the ship to party number you want to analyze and execute the report.
    In the report output screen, you will see the  Ship-to Party in the header.
    In the detail level, you see the sold to party numbers. Since the report can be executed for one ship to or sold to at once, there is no requirement to see the ship to party in the line level.
    If you double click on the line, you can go to the sales order and verify your sold to and ship to details.
    Best regards,
    Anupa

  • If someone has wiped my ipad and changed passwords on icloud how do i get my data back

    if someone has wiped my ipad and changed passwords on icloud how do i get my data back? please could someone help me out thanks

    How did they wipe it?  By using Find My iPad and performing a wipe?  If so, that means they have your icloud ID and password, not a good thing.
    You could try connecting it to iTunes and performing a restore from iCloud.  But if they changed password, then you are out of the loop.  How did they get your password in order to change it?

  • Load a sales order with delivery date in the past

    Hi,
    We want to load in the system a sales order with delivery date in the past, and maintain the schedule delivery date in the past. To do that, in the customizing Sales And Distribution / Basic Functions / Delivery Scheduling and Transportation Scheduling / Define Scheduling By Sales Document Type, I selected the flag Blackwards. But the problem is that the rest of the dates in the scredule line: goods issue date, loading date, material avail.date and transportation Plan Date, are in blank and you cannot enter any data because the system deletes it.
    How can I have these dates informed with dates in the past?
    Thanks in advance,

    You can control this using the "Message Control" in the SAP IMG.
    Supplier Relationship Management>SRM Server>Cross-Application Basic Settings>Message Control>Influence Message Control
    Using this you convert Error to Warning or even swith off this message.
    Please refer this thread for complete steps:
    Re: How to change an error message to a warning message in SRM
    Note: you need to suppress the messages relevant to your case here.
    Regards
    Kathirvel

  • Complete MRP status according to Sales order schedule line data

    Dear All,
    Please help me to get technical configuration releted to
    "complete MRP status according to Sales order schedule line data"
    or MRP w.r.t. Schedule line
    Please send fields and table and logic specification .
    Thanks & Regards,
    Ashish Gautam

    You can use following Fm for change sales order
    CALL FUNCTION 'BAPI_SALESORDER_CHANGE'
      EXPORTING
        salesdocument     = p_vbeln
        order_header_in   = s_order_header_in
        order_header_inx  = s_order_header_inx
        behave_when_error = 'P'
      TABLES
        return            = it_return
        order_item_in     = i_order_item_in
        order_item_inx    = i_order_item_inx
        schedule_lines    = i_sched
        schedule_linesx   = i_schedx.

  • Changes in Sales order materail availabilty date.

    What is impact if we change Sales order materail availabilty date in sales order user exit using some program.

    Hi Mayuresh,
    Big impact.  Impact is smaller if you only intend to push the date into the future.  Could be a big problem if you move the date backward in time.  This means that YOU are now assuming responsibility that the Sales orders will be delivered according to business requirements.  You are also assuming responsibility for ensuring that all ATP data is consistant for these changed orders.
    SAP has constructed their ATP checks so that if you follow their best practices, the system will maintain the Material Availability date according to the business rules you have set.  Any time you artificially move this date backward, you are overriding all of the rules you have set into SAP.  Moving the date forward is usually less of a problem, except that it implies that you intend to send the materials to the customer at a later date.  As long as your Sales dept and your Customers accept this, then it can be done.  With testing.
    Some issues:
    MAD of a particular order affects ATPs of all other sales requirements for the same plant/material.  Altering the MAD of one doc could cause another confirmed sales doc to go on backorder.
    MAD is also passed to MRP and Cap Planning as a requirement.  Altering MADs will probably affect your forecasts and the feasibility of your production plans.
    If this is a non-negotiable requirement for your business, you need to test thoroughly all possible business scenarios.  Everything in Quote-to-Cash, and everything in Procure-to-Pay, using both forward scheduling, backward scheduling, and 'today' scheduling.  Also, you will have to be very careful HOW you change this date (which userexit).  SAP generally recalculates many dates and quanties in a sales doc each time it calculates MAD. All of these dates and quantities need to be consistant for the system to work properly.
    I have participated on a project where this was done.  We had a dozen expert users testing for three  weeks before we signed off and implemented in the live system.  After we implemented, we were STILL making emergency changes to the code and to the business procedures, two months after the implementation.
    Regards,
    DB49

  • Add buttons in Sales Order's Addtional Data B Tab

    Hi All,
    I want to add buttons in Sales Order's Additional Data B tab. I had try to draw a creen in painter and push a button in the screen, also assign a fcode to it.
    I had try to test the button, and I find that, it could work, but after it's action, a error msg give out and said there are no this request function.
    I think it may cause by the fcode passing between screen. However, I don't know how to fix it. Any sample coding could for me reference?
    Thanks!

    Hi,
    yes u can add the button  with Fcode on Additional data B screen.But u have write the code in the PAI of the screen,inorder to do something,for that u need to have accesskey also...i hope while adding fields to Additional data B screen u ahve used teh accessskey for adding..zfields
    Regards,
    Nagaraj

  • TC 500GB died today - how do I get my data off of it?

    My TC has been working great until today when the power died.  Tried unplugging/plugging it back in, but still dead.  Currently I have it unplugged and will wait a few hours before I plug it back in hoping life will flow back into it.
    If not, how do I get my data off of it?
    SN: 6F914B92UJ

    Either remove the hard disk.. there are plenty of sites about replacing the hard disk in the TC.. if you do it carefully,, heating the rubber foot really hot with hair dryer or hot air gun,, then you can simply peel it back and undo the 10 small Philips head screws.. get a USB to sata converter at local computer store.. a bare one is less than $20.. a decent box might be $40..
    Or repair the TC.. in the end that is cheap.. you can get it repaired or do it yourself if you have a few clues.. and then sell it on ebay once you recover your data and wipe the drive. The repair is cheaper than sale price.
    Just type in google Time Capsule repair.

  • Sales order getting archived

    Hi
    We have a problem of sales order getting archived in ides server whenever any new sales order is created..Can u tell us how to solve the problem

    Consult with BASIS guy..as in the Archive Developer Kit (ADK)...some settings might have been changed.
    Regards,
    N

  • When i save sales order, Getting error.......

    Hi expert,
    I have created my own standard order (from company code to master data maintenance and Pricing Procedure).
    1. Here the problem is that when i save the sales order, getting message/error is that Financial document: No financial document assigned.
    2. If click "Header Output Preview Icon (ctrlshftF1)" in the sales order,getting error/message is that No Output has been Selected for Printing.
    Please help me out from this problem.
    Looking forward to hearing from Expert soon.
    Thanks in advance

    Dear Kaviya
    1)  Probably you are trying to create an export order for which the field "Financial Doc" is made mandatory. 
    As you may be aware, few export orders are to be executed against Letter of Credit which should be created through VX11N.  Once all the required datas are given in vx11n while saving, a document reference will be generated.  This reference you should assign in sale order.  To do the same, after giving the datas in sale order, select "Goto --> Header --> Billing Document".  Here at the bottom screen, there is a field "Financial doc no".  Assign the reference you got in vx11n.  Now try to save the order.
    2)  I dont know why you are trying to print the sale order.  Is it necessary.??
    thanks
    G. Lakshmipathi

Maybe you are looking for

  • BOM Uploading through LSMW

    Hi Experts,   I am Uploading BOM through LSMW by Direct Input method. I am having the following queries,   1.  In that BOM I have Header data and Item data. While doing the Step 7(specify file) it accept the text file only not the Excel file. If I as

  • Issue with importing effects settings from 3.0 to CS5.5

    Several times I've attempted to import effects settings from 3.0 into 5.5 using the 5.5 Import>Application Settings function.  Each time it says that it is unable to do it because of some unknown error.  Is there another way to import the settings? 

  • 2 GB RAM zu wenig für CS6 oder doch nicht?

    Sind 2 GB RAM für Creative Suite zu wenig, oder kann man doch noch zufriedenstellend arbeiten?

  • [SOLVED] How to create uncompressed packages

    Is there a way to convince makepkg to create uncompressed packages. I often tweak an official package or build from one the AUR and it takes a lot of time to compress the package that will be immediately uncompressed for installation. I would like so

  • How to add cursors on polar plot

    I want to add cursors on polar plot just like the XY graph has. I am new to LabVIEW and want to be able to move those cursors by mouse movements and get the respective Angle and Magnetude values. Since the polar plot is a picture I am unable to do th