How system calculate the required qty. after MRP RUN

Hi,
I want to know if we are using MRP Type as PD and also we are calculating automatic saftey stock and re order point qty. after MRP RUN according to which rule formula system calculate the safty stock, reorder point qty. and the required qty. as a PR.
and if we are not using calculate safety stock automatically and if we set safety stock qty. manually in this case how system will calculate the required qty.
regards,
zafar

please check the below links.
http://help.sap.com/erp2005_ehp_04/helpdata/EN/6f/b441a9a1b011d3a82d0000e82a3c24/content.htm\
http://help.sap.com/erp2005_ehp_04/helpdata/EN/f4/7d256344af11d182b40000e829fbfe/content.htm
http://help.sap.com/erp2005_ehp_04/helpdata/EN/ff/515c4749d811d182b80000e829fbfe/content.htm
please check the above links may get some idea.
Regards,

Similar Messages

  • Stock requirements display after MRP run

    Dear Experts,
      I have an FG "A" which requires a,b & c as components. Further a & b are inhose produced for which BOM has been maintained. BOM of a contains x & y as its components where as BOM of b has p & q as its components.
    Now when i execute the MRP run, the system is displaying only a, b & c but not displaying x,y,p & q
    in planning result. The scenario is MTO. Please suggest how to get the required results.
    Thanks in Advance,
    Shaiz.

    Dear,
    If you have run the MRP in MD50 then again run MRP through MD02 then you will get the result for child items.
    For collective indicator setting refer this link,
    https://forums.sdn.sap.com/click.jspa?searchID=26950588&messageID=6120172
    Regards,
    R.Brahmankar

  • How system will generate schedule line for PO after  MRP run.

    Dear Experts,
                                 i have updated  MPS in MD61, the period indicator was  M (monthly),  after  MRP run, system  generating schedule  lines  on daily basis for Scheduling Agreement(ME38), i want  schedule lines   on mpnthly basis, how to achive this,
    thanks in advance.
    regards
    rajakarthik

    Hi
    1. Are you maintaining any Planning time fence period for MPS- No 
    2. What is the PIR qty you maintained in MD61:
                                                                                    i.) FG01 is having BOM  child part RM01.
                              To  produce 1 nos of  FG01 , I need 1 nos of  RM01                                                                               
    ii.) i maintained  FG01 in MD61  with PIR  Qty 5000. in MD61,Planning period is M  and planning hirizon1- jan10To 31-Jan10
           ii.)  i maintained lot size:Monthly lot size for RM01.
           iii.)  there is  no stock  available for  both RM01 and FG01.                                                                               
    3. After MRP how much qty is get planned on what date-     
         i)   planned order created for FG01 in co41 with qty-5000 nos.
         ii)  in ME38, schedule  line created for RM01,  on 01-01-2010, with 5000 nos,  currently Category of Delivery Date
    field is D and delivery date is   01-01-2010, but i want Category of Delivery Date should  be M and delivery date should be 01.2010.
    thanks
    raja

  • How the system determines the Requirement type  for one sales order

    Hi,
    SAP-SD Gurus,
    Please tell me how the system determines the Requirement type  for one sales order?
    Thanks & Regards,
    Sreenivas.P

    Hi,
    System follows some search criterial to determine the requirement type
    1. First, an attempt is made to find a requirements type using the strategy group in the material master.
    2. If the strategy group has not been maintained, the system will determine it using the MRP group.
    3. If the MRP group has not been defined, the system uses the material type instead of the MRP group when accessing the corresponding control tables.
    4. If no requirements type is found here, the system assumes a special rule and attempts to find a requirements type with the aid of the item category and the MRP type.
    5. If this is not possible, a last attempt is made to find a requirements type with the item category only.
    6. If the last attempt fails, the system declares the transaction as not relevant for the availability check or transfer of requirements.
    Please check the path
    SPRO->SALES & DISTRIBUTIONS->BASIC FUNCTIONS>AVAILABILITY CHECK AND TOR->TRANSFER OF REQUIREMENTS--->DETERMINATION OF REQUIREMENT TYPE USING TRANSACTION.
    Hope it will clarify
    regards,
    santosh

  • How to calculate the coordinate after implementing Affine Transformation?

    Hi, guys!!
    I am working on a Map makeing program, like MS Visio. Then, I need to put an icon on the working space. And the icon can be moved, rotated, and scaled, when mouse drags handles (8 small circles) around the icon. However, the problem is that after the icon is scaled or rotated using AffineTransform class, I do not know how to calculate the coordinate to paint the mouse handles.
    Please give me your suggestions!! Thanks in advance!!

    Sure. The idea is that you track your translations, scaling, and rotation separate from the AffineTransform. That way, you know what you need to revert:
    AffineTransform at = new AffineTransform();
    at.translate(20, 20);
    at.scale(2, 2);
    at.rotate(45, 10, 10);
    At this point, let's assume you want to translate again. First you have revert the rotation and the scale:
    at.rotate(-45, 10, 10);
    at.scale(1/2, 1/2);
    at.translate(10, 10);
    In order to do this, you need to track your scaling and rotation values when you change them. If this isn't feasible, it's certainly possible to derive the values from the AffineTransform, but that's a bit tougher.
    Michael

  • How can I require a password to change the "Require password after sleep or screen saver begins" setting

    My son has a habit of disabling the "Require password after sleep or screen saver begins" setting whenever my wife lets him play a game on her account.  I notice every other setting on the "Security & Privacy -> General" tab is protected by the lock on the lower left corner.  I've never understood why this one is not.  Is there any way that I can get that setting to also be controlled by the lock?

    Because that setting is specific to the account currently logged in and doesn't potentially affect any others or the system itself, which is the level in general at which administrator or root access is required.
    (82759)

  • How does the system calculate the Taxes?

    Dear all friends,
    How does the SAP system calculate the Taxes?
    pls. explain with the example will be highly appreciable.
    thanx in advance to all
    best regards,
    Rajesh

    Hello
    The SAP system calculates tax based on the tax calculation procedure assigned to your country in OBBG.
    The tax calculation procedure is similar to the pricing procedure in materials management.
    As you have different pricing elements like gross price,discounts,freight charges, etc in pricing procedure, you will have different tax elements like Excise duty,Special excise duty,Cess,Edu cess,VAT,CST, etc in tax calculation procedure.
    At the time of PO creation, the tax base amount is communicated to the tax calculation procedure from the pricing procedure.
    And the tax values are calculated based on that and how you have configured your tax calculation procedure.
    In CIN, we have two tax calculation procedures
    TAXINJ which can be formula based or condition based and TAXINN which is condition based.
    In TAXINN, the tax percentages are picked from the condition records maintained.
    But in TAXINJ, it can be either from the condition records or the tax % given in the tax codes in FTXP. It depends on how you configure your system.
    Hope this helps
    Regards
    Gregory Mathews

  • Purchase requisition not generate for dependent requirement after MRP run

    Hello PP expert,
      In our MTO scenario after MRP run planned order generate for header material but no PR generate for BOM components, (BOM not explode) when we run MRP component level in MD02 PR generate, system showing message "40- No coverage not provided by master plan" in MD04 order tree. this problem coming after when we DIMP applied. I checked some OSS note also.
    Can any one provide right solution.
    thanks in advance.....its urgent as client requirement.
    regards,
    Amit Awasthi.

    Hi Amit
    You must select the green star for the correct answer, in order to close the thread.
    You may also select the yellow start for the helpful answers, in order to award points for those who helped you. See the blog below for more details:
    How to close a discussion and why
    I can see that most of your old threads are still open, therefore, I'd like to ask you to review and close them, by selecting the correct answer.
    BR
    Caetano

  • How to restrict RESCHEDULING after MRP run ?

    Dear All,
    We r using prodn. strategy 30. We don't take MRP run for finished material. First we create production orders for finished material & then we take MRP run to create planned orders for semifinished material.
    After MRP run , production orders of semifinished material of previous month gets rescheduled . How to avoid this ?
    We created production orders of NOV2007.
    When we take MRP run today i.e. SEPT2007  to create planned/prodn orders of OCT2007 m/c shop plan. It shows wrong results. It is not giving right requirement for blanks .
    PL' answer.

    Hi,
    In OPPQ/OPPR increase the tolerance value to a high value.
    The system compares this value with the ( order finish date - reqmts date) and if it is greater the system do reschedules.
    Ex tolerance value -
    2
          diff bet ( order finish date - reqmts date )  -
    5
         the system reschedules.
        so increase the tolerance value to 5 and see the results. The system does not
        reschedules.
    OR in OPPQ disable the indicator for production order
    Regards,
    nandha

  • How to calculate the variance in PO price history?

    hi
    i hav standard report ME1P, since i need to do some modifications in this program i copied to Y prgrm,,,'
    im getting all the values properly...
    but my prblm is im not getting how to calculate the variance? im not getting the logic behid it...
    can anybody expln me in breif plz....
    Regards
    Smitha

    Hi Venu,
    there is another way as well, however, you won't be able to see Variance and Variance% as a saperate keyfigure which is not under the period. Thats the reason I didn't mention it earlier.
    What you can do is, Drag the period to the columns, Now create a structure that has the two keyfigures std price, moving price. Here if you add Variance and Variance%, Then these CKF's would come under period as well, which you don't need. And the system won't allow you to add these CKF's outside this structure. The reason being because the interpretation of the data then wouldn't make any sense here. You can create a new structure as well with these CKF's but they would become a subpart of your previous structure.
    choose the required characteristics in the Rows section. Save it.
    Let us know, Sorry man, can't help u much at this problem.
    regards,
    Sree.

  • CFM /TR - how system calculate amount based on rate FX 60A

    Hi all,
    i need to know how system calculates amount based on rate entered upon creating a contract (t-code TX01).
    steps input:-
    1. header - comp code, product type, trans type
    2. partner
    3. purchase curr & amount (eg. IDR 8,345,545,500)
    4. sale currency only (amount system will auto calculate) USD
    5. rate field = 11.553
    6. spot rate will auto pick up from rate
    7. value date
    8. contract date
    upon TBB1 no error. posting log as follows:-
    FX1000+ : 40 8,345,545,500 IDR bank GL acc
                    50 8,345,545,500 IDR clearing acc
    FX2000- : 40 722370.42 USD clearing acc
                   50 722370.42 USD bank GL acc
    but upon TPM18 error occurred as follows:
    DBT_C009 - GL not maintain in acc symbol 5.3.4
    DBT_E039 - no posting spec assigned to update type
    DBT_B018 : 40 0 USD, 431,977,511 IDR gain/loss
                       50 0 USD, 431,977,511 IDR clearing acc
    so, after maintained DBT_C009 as follows still error for DBT_E039:
    40  0 USD, 38 IDR clearing acc
    50  0 USD, 38 IDR P&L gl acc
    what i don't understand is how system calculate and get DBT_C009 & DBTE039.
    what is the function of TPM18?
    thanks.

    Hello Prarnod,
    I have done the first node only for actuals that come from the integration to the internal order.
    I have tried setting up 2 and 3 even though the 3rd one does not make any sense to me
    Thanks,
    Paul

  • Track Changes the qnantity change of PR after MRP run

    Hi Experts
    Please suggest as i am unable to find any solution of following problem.
    My CLient wants to keep track the changes made to PR's after MRP run. When running MRP, already existing requirements (PRs) are automatically changed. These changes are not taken into account by BW extractors since no change document is generated.
    for e.g ,if we check stock requirememt list (MD04), PR of qty 20 exists. Now if i create a manual reservation of qty 20 and then run MRP, the the PR qty will change to 40. But i am unable to track this in CDPOS or CDHDR tables.
    Please suggest.
    Pradeep Bansal

    There are 2 ways to track the PR changes
    1.Goto PR display ME53N  --> Environment ---> item changes
    2.Goto CDHDR Table ,input doc object - BANF ,object value as PR no and get the docuemtn no .Pass this doc no to CDPOS and get the change details
    Hope it helps

  • How system calculate exchange rate for two currency vise versa automaticaly

    Dear All, i have maintain exchange rate type M with USD to PKR with different time interval. When i run Project System report the system show transaction figures in Controlling Area currency is PKR. However, when i switch to USD currency with translation key (Mean rate as of today) . System do not allow to show the result.
    I know if i maintain exchange rate type M with PKR to USD then system display the result. But my concern is that system should automatically calculate exchange rate from PKR to USD for exchange rate M if as i have already maintained exchange rate m with USD to PKR.
    How system can do it?
    regards
    Saqib Usman

    Hi SAQIB USMAN ,
    Please set  the indicator for INV in OB07 for the exchange rate type M.
    This indicator might not be set in your case.
    Then system calculates using inverse ratio.
    Please read it for your reference and easy understanding
    Indicator: Calculation allowed with inverted exchange rate ?
        Indicator that in the case of a missing exchange rate entry in the system
        for the required translation from one currency into another, the inverted
        exchange rate relationship may also be used.
    Example
        If an entry is missing for the translation of USD into DEM in the system,
        then the translation takes place by means of the entry for the
        tranlsation of DEM into USD, providing the indicator is set.

  • How system calculate Exchange Rate for material?

    I have some doubt how system calculate exchange rate for material when doing GR.
    For example, standard price of material is 0.01 USD per ea. PO is created in foreign currency (THB) with qty: 40,000 ea (THB 2,852.00)
    Actually when I do GR ea then accounting doc is:
    Dr. Inventory 400 USD (12,800 THB)
       Cr. GR/IR    88.64- USD (2,852.00- THB)
       Cr. Variant 311.36- USD (9,948.00- THB)
    for 2nd and 3rd line item, exchange rate M (THB -> USD) is 0.03108 which is correct.
    Could anyone advise where system get exchange rate for 1st line item?

    Hi
    First of all, as mentioned by you, the exchange rate for Item 2 and 3 is not 0.03108.. It is as below, based on the figures given by you...
    Dr. Inventory 400 USD (12,800 THB)........ Exch rate is 0.03125
    Cr. GR/IR 88.64- USD (2,852.00- THB)....... Exch rate is 0.03108
    Cr. Variant 311.36- USD (9,948.00- THB).... Exch rate is 0.0313
    I guess the item 3 is just a derivation from Items 1 and 2.. The Price diff results as a difference between std cost and purchase price...
    I believe, the exchange rate would have been 0.03125 at the time of GR... You need to check this in your system... For sure, it uses  exch rate type M in the standard... Check if 0.03125 (USD -> THB) or 32 THB -> USD exists in your system at all
    Item 2 is based on your PO negotiated rate...
    Regards
    Ajay M

  • How to see the poduced qty workcenter wise

    Dear Friends
                            Will any body tell me , how to see the produced qty workcenter wise.
              were the following  things are maintained:
                             1. No of peoples for eg: operator ,contract ...
                              2. Shift  sequence

    Hi,
    You can use Order information system - COOIS to check operation wise confirmed yield.
    In COOIS select List - Operations, Profile - Standard Profile, Maintain selections as per your requirements.
    You should change the layouts to select the fields of your requirements viz, confirmed yield, dates etc.
    Pavan