When we run the report KKBC_PKO for the material for the last period 10/2009.
system not showing the Target cost but it show the Actual cost values.
When we look the MB51 -Where production confirmation (backflush) and GI/GR happened for the particular period. It wa not happened.
If production confirmation was not done. how the Acutal cost is calculated.
What is basics to calculate the Target /Actual cost

Raj,
Without Confirmation / GI or GR, the actual cost cannot come. Why dont you check double click the cost records and see for yourself as from where the costs came.
Regards,
Prasobh

Similar Messages

  • Can someone explain how the background of this site was done?

    For learning purposes I'm trying to figure out how they did the background on this site.  Some of it I understand but I'm not clear on how the div / class of .mainbackground was done.  It's almost like it's partially behind the Content div yet it looks to be in front also, I see there might be some transparency involved but I can't figure it out...here is the site:
    http://www.lourdes.edu/donate.aspx

    Well, Ok, I kinda got that but I examined it with Firebug and the body has a background repeating image across which I totally understand, it's the div called .mainbackground that I'm not understanding.  Here is the CSS for the div I'm confused about:
    .mainBackground {      background: url("img/mainBackground.jpg") no-repeat scroll center top transparent;
    There is a Content div OVER that; how is the .mainBackground div 'under or behind' the Content div?
    I don't understand the transparent part either in the above CSS......

  • Target Cost was zero in production order

    Hello,
    We are experiencing every 1st day of the month target cost was zero for those production order which basic start date was on the 1st day of the month, this happen last march and this april it also happening but in january and february we did not experienced this issue. we wonder how this happening to us, since as we check those production order which basic start date was on the 2nd date and prior all has values in its target cost, this is for same finished material. How was this happening to our plant? how can we check and resolve this issue? am on a PP guy, as i have check the data of those order nothing peculiar for me, and it those material has cost estimate ok, this was released on the 01.01.2009 in this costing run will last untill of the year this was also been seen in the material master data current cost estimate.
    As we have search for the performance assistant in SAP it thus tells us:
    Total Target Costs
    Total value of the target costs.
    Calculated with the following formula:
    Total target costs = Target cost debit + Target cost credit.
    Use
    Target costs are the planned costs adjusted to the actual operating rate.
    The target debit on a manufacturing order is the sum of the activity-independent planned debit of the order and the activity-dependent planned debit of the order multiplied by the actual quantity of the order.
    The target credit of a manufacturing order results from the goods receipt postings to stock. The delivered actual quantity is valuated with the planned price according to the price control.
    The total value of the target costs is the sum of the target debit and the target credit.
    The target costs are calculated during variance calculation and updated to the database.
    The target costs cannot be shown until you have performed variance calculation for this target cost version. The target credit for the calculation of the total variances and production variances cannot be calculated until an actual quantity for an order exists after a goods receipt posting.
    For the calculation of variances, the target costs are compared with the control costs.
    Dependencies
    The calculation of target costs depends on the selected target cost version.
    But still we don't know how to check the issue and fixed it:
    Please help us and guide us to resolve this issue
    Thanks

    Hi,
    in some more details i have found out on our issue, one of the prerequisite for our variant calculation is Variance calculation at the manufacturing order level requires that the order is fully delivered (final confirmation is done) and technically completed ( except order pass through the mid night of period end ). Those informations can be displayed in the manufacturing order status.
    order should be TECO right? but as said on this order pass through the mid night of period end can be have variance calculation, thus am right? this could be affect why the target cost was zero?
    Thanks

  • Split valuation for Finished Goods - Target cost was not updated

    Hi,
    We are following split valuation for 'Finished goods'.
    Valuation typte 1 is for 'manufacture' and
    Valuation type 2 is for 'External procurement'
    For production orders with this material, we are not getting target costs. It is showing zero.
    We have done release of standard cost estimate before creation of production orders and goods receipt for these orders. But still it is not updating.
    Pls guide me.
    Regards
    MadhuSekhar Gupta

    Hi,
    Thanks for your reply.
    At the time of variance calculation only the credit part of target cost will update and at the time of goods receipt debit part of the target cost will update.
    Our client has done goods receipt but debit part of the target cost was not updated. and the order status is DLV.
    I simulated the scenario in QAS by creating new finished goods materials (Industry-Construction) one is with split valuation and another is without split valuation, then the debit part of target cost was updated at the time of goods receipt and credit part was updated at the time of variance calculation for both the materials. So this problem was not arised because of split valuation.
    Was this problem arising because of the material master data, because for one material it is updating and for another it is not for the same configuration?
    Regards
    MadhuSekhar Gupta
    Edited by: gms gupta on Oct 22, 2011 3:39 PM
    Edited by: gms gupta on Oct 22, 2011 3:41 PM

  • The target costs in target cost version 0 are missing

    Dear Experts,
    I am getting following error while running Varience cost through KKS2:
    Only remaining var. in version 0 - no target costs for 000001061683 0001
    Message no. KV151
    Diagnosis
    For the calculation of variances with 000001061683 0001, the target costs in target cost version 0 are missing for the following reasons:
    There were no planned costs and/or planned quantities (see earlier message).
    The quantities on which the planned costs were based are zero in the time period concerned. This may be caused by the fact that no goods receipt for a cost object (such as a product cost collector or production order) has been entered.
    This results in target costs of zero.
    System response
    Because no target costs were calculated, the difference between the
    planned and actual costs could not be broken down into variance categories. The difference is updated as a remaining variance.
    Please suggest, How to proceed.
    Regards

    First check this...
    1.Go to t.code OKEV.Select Controlling Area 2222 and create Plan / Target version.
    The standard system supplies the following target cost versions:
    Target cost version 0 ( total variance)
    The amount of the total variance generates a posting in Financial Accounting during settlement.
    For this version, select actual costs as the control costs and standard cost estimate as the target costs.
    Target cost version 1 ( production variance)
    For this version you choose actual costs as the control costs and planned costs as the target costs.
    Target cost version 2( planning variance)
    With target cost version 2, the costs from the preliminary order cost estimate are interpreted as control costs. For this version, select planned costs as the control costs and current cost estimate as the target costs. You cannot calculate planning variances for the product cost collector.
    Target cost version 3 (production variance of the period)
    You compare the planned costs of the period calculated on the basis of an alternative material cost estimate (such as a modified standard cost estimate) with the actual costs of the period on the basis of the yield delivered to stock in the period.
    2.Also try In CO02 goto cunctions...cost...
    3.Go to transaction OKV6 these settings control what values are used to update the target costs.
    Target cost comes from the standard price calculated when doing a costing run. Actual costs are costs that you incur during the production order (we can reassign costs during the order so this could be different from the standard price).
    Target Costs=Actual Quantitiy X the Standard Cost Estimate Price..
    Probably the stand.cost estimate will be missing in ur case...

  • How the Material costs and Overheads flow from Logistics to COPA

    Hi,
    I know that Revenue will flow to COPA from SD Condition types which we assigned to value fields in KE4I.
    But i am not clear how the Material cost will flow to COPA?
    How the Overheads will flow to COPA?
    Kindly help me in understanding the flow...
    Thanks
    KB
    Moderator: Please, read available SAP material for basic questions

    Hi,
    check this link:
    http://help.sap.com/saphelp_erp60/helpdata/en/7a/4c48c64a0111d1894c0000e829fbbd/frameset.htm
    Go to: "Flows of actual values" to get the big picture of CO-PA value flow.
    best regards, Christian

  • How the Landed Cost Absorption will be null

    Dear ,
    I create a new PO amount is 1000 $ with landed cost shipment is 50 $ . After received the shipment system creates the following GL entries.
    Receiving Entry :
    DR Accrual Account = 1050
         CR Accrual Account = 1000
         CR Landed Cost Absorption = 50
    Material Entry :
    DR Inventory Account = 1050
         CR Accrual Account = 1050
    After create a invoice and match with receipt and shipment the "Accrual Account" is "0" which is ok. But what about Landed Cost Absorption which is still reamins the balance in GL "50" $ after complete the full cycle. Please advise when or how the Landed Cost Absorption will be "0"

    Hello
    Please accept my appology for this delay,
    I know it is too late for this reply, but I just following this discussion for the general benefit of this community (sure, if you still following this, it will be greate)
    Generally, by referring to Oracle Support Document ID 782920.1, Landed Cost Absorption account should not be zero if the following conditions are met:
    1.  Default Charge Account (in Receiving options of LCM enabled organization) is different that account used for Landed Cost Absorption Account, and
    2.  Estimated LC amount differs than Actual LC
    Accordingly, the opposite is true, you have to use the same account for LCM charge and absorption and LC estimated amount(s) are the same as actual LC actual charge amounts
    For complete explanation just review the following oracle support document:
    How Landed Cost Management and Accounts Payable Accounting flow (Doc ID 1310019.1)
    Regards

  • Difference between the planned cost and the target cost

    Hello guys,
      I am really confused between the planned cost and the target cost.As Per the sap help target cost is cost required to produce certain quantity of material.And planned cost even carry the same definition.
        So is there any difference between these two cost.Are they same?

    Jitendra,
    Genarally in CO we will define Target cost is getting calculated in the Production order based on the "Standard Cost Estimate" after GR. Planned costs are calculated based on the current costs.
    Example:
    Assumption: Assembly Material A with Standard Price, Component B and Component C is maintained with Moving average
    Material A Cost 1EA = (component B = $10 + Component cost C = $20+ Activity Price $1) = $31, this is the standard cost estimate for the material.
    Now I create a production order on 15th of the month, and the Moving average price for component is now $20 due to subsequent GR with higher price. Now the planned cost for the order would be (20201)=$41, whereas the Target cost would be still $31.
    Hope I was able to clarify,
    Regards,
    Prasobh

  • Transfer to PA the target costs of a production order

    Hi everyone,
    How can I transfer to PA the target costs of a production order?
    Thanks
    Cátia Pereira

    Hi
    1. Check your settings in KE4U - Strategy 001 must be assigned to PV=01 and Rec Type F
    Tick the "Mat Cstng" indicator and assign COPA Qty Field ABSMG
    2. Assign costing key to Mat Type in KE4J or KEPC
    3. assign Cost Comp Str to VF in KE4R
    4. Assign Value Fields to your variance categories in PA Transfer Structure....
    Tick "Variances to Costing Bsed COPA" in your settlement profile
    Br, Ajay M

  • How the freight cost are transferred from condition type of shipment cost document to service entry sheet and collected in service PO item

    Dear Experts:
    could you please share with me the knowledge for below topic:
    How the freight cost are transferred from condition type of shipment cost document to service entry sheet and collected in service PO item, because these three objects use three different pricing procedures, and different condition type.
    how did the condition type of service entry sheet know to copy the value of whcih condition type in the pricing procedure of shipment cost document?
    Is this SAP standard function OR there need an enhancement to do that?
    I didn’t find related condition value copy setting in background, could you please share related setting with me? Thank you very much for your kind help!
    Best regards,
    Andy

    Hi, Gopi,
    Glad to see your feedback, but i still have question on your feedback:
    which condition type in the pricing procedure of service entry sheet should know to capture the net value of shipment cost doc? becasue there are so many condition types,
    And i have checked the corresponding condition type (PRSX) of service entry sheet pricing procedure in my SAP system, this is a self-defined condition type, but NO any calculation routine maintained for the condition type (PRSX), how did the condition type (PRSX) know to copy the total cost of shipment cost document?
    Below is the example and another question:
    what the relationship between the pricing procedures at service PO item level and service line item level?
    1. The freight cost in shipment cost document—including used condition type and pricing procedure
    The pricing procedure of shipment cost document
    2. The freight cost in service entry sheet—including used condition type and pricing procedure
    The pricing procedure of service entry sheet--the pricing procedure at service line item level
    3. The freight cost in service PO item—including used condition type and pricing procedure:

  • I upgraded to the mew iMovie (purple star) vers 10.6 from the old I movie (yellow star) in the old one when i was done with my project i could finalize it and share it to idvd to burn a dvd, i don't see how to do that in the new iMovie.  is there a w

    i upgraded from the old imoive(yellow star) to the new iMovie(purple star) , in the old iMovie when i was done i was able to share my project to idvd, i don't see how to do this on the new iMovie. Does anyone know how to burn a dvd with your project from the new iMovie(purple star)?  if can't be done can i export my project to the old iMovie and burn to idvd like i used to?

    i did what you said and saved the file to my desktop, but how do i get it in idvd now, when i open idvd and point to the file on the desktop either by open existing project or trying to open a new project the file is greyed out and i can't select it

  • Is there a way to resort an ipod touch to the point before a restore was done on it? It is telling me there is nothing in the icloud and I need to reset it back up.

    s there a way to resort an ipod touch to the point before a restore was done on it? It is telling me there is nothing in the icloud and I need to reset it back up. The reset was done before I could backup the icloud and itunes to the computer and it wasn't done with my permission.

    You may be able to get some info off the restored iPod by:
    via How to perform iPad recovery for photos, videos
    Wondershare Dr.Fone for iOS: iPhone Data Recovery - Wondershare Official     
    http://www.amacsoft.com/ipod-data-recovery.html
    iPod recovery software to restore lost music files      
    http://www.pcrecoverytools.com/ipod-data-recovery.html
    You can redownload most iTunes purchases by:        
    Downloading past purchases from the App Store, iBookstore, and iTunes Store         

  • How the **** do you actually email apple to make a complaint

    how the **** do you make a complaint to apple with regards to the fact they can offer free games to children but make it very easy and appealing to children to spend money they cannot and should not be spending

    For more information on the available restrictions, see:
    http://support.apple.com/kb/HT4213
    I think that if you read up on them, you'll see that Apple has indeed addressed this issue and that all you need to do is configure your iPod appropriately.
    Regards.

  • I think I've completely misunderstood how the Touch functions. I was under the impression that my iTunes music library, regardless of size and where acquired would be automatically synced to the Cloud for free? I s this not so?TIA

    Have I misunderstood how the Touch works? I thought that I could transfer my completre iTunes music library, regardless of size and how acquired, to the Cloud at no charge. True?

    What about it?
    It is not part of this service.
    You can pay for itunes match which will allow you store some non-itunes purchased music.
    http://www.apple.com/itunes/itunes-match/

  • How can I recover website that was done in Muse CC?

    Hi, I have just now updated all my Creative Cloud  apps and encountered a big problem with Muse 2014.
    When I wanted to open a newly uploaded website bilyz.com created yesterday in Muse CC it seems to have disappeared.
    I have searched my whole computer for the original file name without finding it.
    I need to make changes to the site but don't know how to find it. If I type bilyz.com into the search box it takes me directly to the browser.
    Regards
    Bill Watters
    (Running Windows 8.1 64 bit)

    You will likely get better program help in a program forum Help with using Adobe Muse CC
    The Cloud forum is not about using individual programs
    The Cloud forum is about the Cloud as a delivery & install process
    If you will start at the Forums Index https://forums.adobe.com/welcome
    You will be able to select a forum for the specific Adobe product(s) you use
    Click the "down arrow" symbol on the right (where it says All communities) to open the drop down list and scroll

Maybe you are looking for

  • Ipod touch 4G - doesn´t turn on anymore!

    My Ipod no longer turns on or is recognized by the computer (in all usb ports and in more than one computer) and I´m not able to charge it. I tried to restart it to no avail. Anyone knows what is going on? Some advice?

  • Random spacing between contents page sub headers (CS2, WINXPSP2)

    Hi, I'm a new user to Adobe Indesign CS2. I was creating a table of contents when I encountered this unusual problem. Here is a sample of what happens below: 2. System 2.4 system components 2.4.1 Intelligence Manager features........... 9 2.4.2 Video

  • Unable to restart and other oddness.

    I'm currently on my 3rd install of Leopard on this laptop hoping that something would change but It hasn't. Once I'm logged in on my account I'm fine until I try and restart or shutdown. I'll look like I'm going to do either but it goes to the time m

  • How to make a vertical lift or elevator in a platform game

    I am creating a side scrolling platform game using the book "Flash Game University" by Gary Rosenzweig. My protagonist has an instance of "hero". My current issue is trying to create a lift or elevator to carry the player up or down. The lift is not

  • Applet And Database

    Hi; Can i do database connectivity through applet if your answer is no then plz give me reasons why? thanks