How to change duration of Preventive Maintenance cylce in strategy plan?

Hi,
How one can change duration of Preventive Maintenance cylce in strategy plan?
e.g. In IP11 we set Preventive Maintenance schedule as monthly and we want to change it as quarterly i.e. every 3 months from starting date.
With Best Regards,
Rajkumar

Hi Mr Ramesh
Thanks for reply .
Kindly guide us about as what steps /Tcode need to be used to perform the following actions as suggested by you :
a) Delete orders.
b) Go to IP10 and Do a 'manual call' by entering the planned date to create orders for the deleted packages.
Or
Reschedule the Whole Maintance plan by entering appropriate dates.
c) Also please clarify , that how the new Orders will get generated against the Deleted Orders .
With Thanks and Rgds
Sonia

Similar Messages

  • How to change the status of test cases in Test Plan from Design to Ready using Excel VBA

    HI,
    How to change the status of test cases in Test Plan from Design to Ready using Excel VBA

    Thanks Florin,
    Your piece of code has worked alot, and it was very helpful in changing the Status of the Workitem to "READY" for all the Users fo the workitem.
    Points have been rewarded for your help.
    Process: We have acheived this using the "Work Item Exits", Usng "AFTER_EXECUTION" Method.
    Note: The Exit will be executed if "exit_cancelled"  statement is present/used in the work item method. if not it is not taking to the exit code. I'm unable to find the reason for it. Florin can u please explain this point.
    Please check the link for adding the code in Work Item Exits.
    http://wiki.sdn.sap.com/wiki/display/ABAP/ProgramExitsIn+Workflow
    Please find the Code:
    method IF_SWF_IFS_WORKITEM_EXIT~EVENT_RAISED.
    Get the context of the workitem
      me->wi_context = im_workitem_context.
    After execution of the workitem call the method AFTER_EXECUTION
      if im_event_name eq swrco_event_after_execution.
        me->after_execution( ).
      endif.
    endmethod.
    METHOD AFTER_EXECUTION.
    This method acts as the Event Handler for SWRCO_EVENT_AFTER_EXECUTION
      DATA: LCL_L_WID TYPE SWW_WIID,
            L_STATUS TYPE SWR_WISTAT-STATUS,
            L_NEW_STATUS  TYPE SWR_WISTAT,
            L_SWR_MESSAG  TYPE STANDARD TABLE OF SWR_MESSAG,
            L_SWR_MSTRUC  TYPE STANDARD TABLE OF SWR_MSTRUC.
    Get work item
      CALL METHOD WI_CONTEXT->GET_WORKITEM_ID
        RECEIVING
          RE_WORKITEM = LCL_L_WID.
      L_STATUS = 'READY'.
      CALL FUNCTION 'SAP_WAPI_SET_WORKITEM_STATUS'
        EXPORTING
          WORKITEM_ID    = LCL_L_WID
          STATUS         = L_STATUS
          USER           = SY-UNAME
          LANGUAGE       = SY-LANGU
          DO_COMMIT      = 'X'
        IMPORTING
          NEW_STATUS     = L_NEW_STATUS
         RETURN_CODE    = SY-SUBRC
        TABLES
          MESSAGE_LINES  = L_SWR_MESSAG
          MESSAGE_STRUCT = L_SWR_MSTRUC.
      IF SY-SUBRC EQ 0.
      ENDIF.
    ENDMETHOD.
    Thank You Once Again,
    Ajay Kumar Chippa

  • How to take list of preventive maintenance jobs for every month- kindly hel

    dear friends,
    kindly help -how to take the list of preventive maintenance jobs for month basis.
    kindly provide me T-CODES.
    regards,
    g.v.shivakkumar

    Shivakumar,
    Use transaction "IW38" to select all PM orders for the month. The selection can be based on specific "order type", Status ", "Equipment"/ "Functional Location" or " "maintenance plan" with period interms of date.
    Hope this helps...Reward your points and close the thread.
    Regards,
    Prasobh

  • How to track reason for Preventive maintenance not completed?

    Hi Gurus,
    We know that when Maintenance plan was created then base on that maintenance call objects should be generated at particular date specified in Plan. I have requirement that due to certain reason (e.g. Machine not available due to production) if this preventive maintenance not completed at specified date, so how we can assign these reason for call objects (Notification/Order).
    Thanks in advance......

    I'd suggest using either
    1) Confirmations with Reason Codes
    or
    2) Notifications with Catalog Codes
    or
    3) User Status profile on Orders.
    EDIT: Note that for the former you might need to first have the Orders released, which might not be desirable, and you can't use this in conjunction with the "Do not complete" / "Wrap" / BABL transaction (to set status NCMP). The latter two options don't have this constraint.

  • How to change duration of selected still image Clips?

    iMove is great in all its simplicity. However coming from the Windows (Pinnacle Studio) side I have yet a few mysteries to solve: Changing duration of a single still image clip is trivial, but it seems impossible to do the same operation selecting two or more clips. Did I miss anything? You can specify the duration and apply to all clips, but I have found no way to apply e.g. 4 sec duration to half of the 220 slides in my slideshow. Cmd+R on 100 still images seems like a fairly unintelligent approach. Hints, anyone?

    Hi
    Anybody?
    I'm having the same problem.
    I have 500 stills in my timeline (iMovie 06 HD) and there seems to be no way to change the duration of more than one still at a time.
    This cannot be right. Please tell me what I am missing!
    According to another thread about this issue, the answer was that after I select my group of stills in the timeline, I should be able to open "Media" and "Photos" in iMovie, and then set the stills duration settings that way.
    But the button "Show Photo Settings" is greyed out, so I am unable to set the group stills duration.
    Any help?
    PLEASE?

  • How to change configuration of Automatic Maintenance programmatically ?

    is there API or specific task in windows task scheduler used to change settings of Automatic Maintenance ?

    I mean we can go to this path in control panel “Control Panel\System and Security\Action Center\Automatic Maintenance” and schedule for automatic maintenance to run at specific time and then form action center we can track last run , even we can force automatic
    maintenance to run .
    I know that automatic maintenance is group to tasks that all run at scheduled time , I do not need to go to each task and do “schedule \ track “
     ,  I want do to it all form one central place
     just like in control panel , so I need approach to do it by code
     (API , command ….)???/

  • How to change my subscription from "CC single-app Photoshop" plan to "Photoshop Photography" plan

    How to change my subscription from "Creative Cloud single-app membership for Photoshop (one-year)" plan to "Photoshop Photography" plan after purchase already and overlap?

    I waiting Live Chat about 2 hours and my thread not any support help to me or feedback.
    Why!

  • Maintenance orders againt strategy plans

    Dear PM Guru's,
    i am created strategy based plans and i given 85% call horizon, in strategy i mentioned 7days, one month, 3months and halfyearly. i started cycle on 06.08.2011, i get weekly order one day before but where as 1month i get order on same planned date? actually it should come before 5days. why system generates order on same planned date?
    please help me how i have to overcome this issue.
    regards
    jalu

    User exit IPRM0002 allows to change the planned date. Keep the call horizon 100% and advance the planned date by 0.15*package cycle duration through aforementioned user exit.
    New planned date = Original Planned Date - 0.15 * (Package cycle duration i-e 7 ,30 , 90,180 days)
    [http://www.sapfans.com/forums/viewtopic.php?f=7&t=316460]
    Regards,
    Tehsin

  • How to change width of table maintenance screen in sm30

    Hi,
    I want to change the width of table maintenance screen in sm30 of a view. I am trying to change it through screen painter.
    But its giving me error - screen or window limit reached. I want to increase the widht to show all the fields at once.
    Is there any way for this?
    Also, earlier in table maintenance generator of view, there was one step selected. I changed it to two steps and re-generated the TMG. But again Its showing only one screen in sm30.
    Kindly tell me which step I have missed out.
    Regards,
    Seema Naharia

    I guess the links below should help in your problem ..
    http://www.saptechies.com/how-to-create-table-maintenance-generator/
    Window size on SM30
    If these do not please tell ..
    Regards,
    Manthan

  • How to change duration of multiple photos

    Greetings - I'm trying to change the duration of multiple photos in iMovie. Basically, I'm trying to change the duration of about 300 images (to make a time-lapse movie), but can't for the life of me figure out how to do it.
    I need to change the duration of every photo to 0:03, but when when I do so, it automatically imports the photos with a duration of 9:29, and I can only change the duration of individual photos after import. I made a time-lapse move a while ago but can't remember how to do it. Any thoughts?

    Select a group of your stills in the time line. (I would do maybe 30 at a time, because to do the whole 300 at once might overwhelm the machine -- though you could try.) Then go to Media > Photos > Show Photo Settings. In the Show Photo settings dialogue box, set your duration to 0:03, and then hit Update. The selected photos should all update to 0:03. You may need to remove the transitions first.
    Another way would be to set your duration for 0:03 on the first photo that you import into your timeline. Then all other photos that you import afterwards will have that same duration.

  • How to change duration of music on menu?

    Adobe Premiere Elements 7.0 - Windows Vista 64bit
    I'm getting there. (Thanks to your help!)
    I started from (almost) "scratch" so I'd have a nice "clean" video to burn to a DVD. I've reset all my chapter markers. Perfect, in Preview. I've chosen my menu and adjusted the motion scene selection buttons. Gorgeous, in Preview. I don't like the "default" music that comes with the menu I chose. I read some old threads here and found there is a 30 second limit, so I used Audacity to cut a WAV clip that's 16.23 seconds long to use as a loop. Here's the problem:
    I clicked "Browse" and selected the same music clip for the Main Menu and each of three successive Scene Selection pages. Works fine on the Scene Selection pages, but the Main Menu won't play past 13 seconds for some inexplicable reason. I tried manually adjusting the "duration" to 16.23, but it snaps back to 13 as soon as I hit Preview.
    I've closed the program, restarted my computer, made a new (identical) music clip (just in case the Main Menu didn't want to "share") but it still won't take it. It plays the first 13 seconds then abruptly loops back to the start, which is NOT a *smooth* transition - but it would be, IF it would play the whole 16.23 seconds like the other menu pages do without any problem.
    I'm open to suggestions, but I sure hope I don't have to start over again. Oh, BTW - I tried switching to a totally different Disc Menu, just out of curiosity, and that one played the whole music clip on the Main Menu page without a problem... but I don't like the look of that menu, I want the other one - the one that's giving me grief (of course). Don't understand why it would work on one and not the other.
    Please advise. Many thanks in advance. Cheers, Val
    To answer a question one of you (Bill?) asked on the previous thread about my source material --
    It was originally a PAL video cassette, converted to NTSC DVD. It's all on my computer now - four VOB files: three @ .99GB each, and one @ 691 MB. It's a one-hour Peter Allen TV Special broadcast in Australia. I am removing the advertising and making a menu that will allow selection of each song individually. I want more of a "concert" and less of a "TV show" as the finished product.

    Here are the results of my test of the Broadway Menu Set and the exact steps that I used. It starts a bit before the work with the Video and Audio, but this might be useful to someone creating a Menu Set for use with PrE.
    I got the Standard (4:3) PSD’s for the Broadway Menu Set, both the Main Menu (mm) and Scene Selection (ss), plus the MPG and the MP3 files. To get these Menus to display in PrE’s Create Menus selection area, I Opened the PSD’s in Photoshop, and created the PNG “thumbnails” for them, using the naming convention of the other PNG thumbnails as my guide. I first resized each PSD to 160 x 128 pixels, and then did a Save_As_PNG-8, using the correct naming convention, used elsewhere. These were placed into a new “(V) Broadway” folder with the PSD’s, the Motion Asset MPEG and the Audio MP3 file. All displayed fine in PrE 4.
    In a PrE Project, I took the original Broadway MPEG and used TimeStretch to increase its Duration to the 29;20, that I had used before (that would match my Audio file from earlier tests), and did a Share, choosing MPEG. This resulted in an m2v, but that worked fine.
    In PrE’s Create Menus Panel, I chose the new, stretched m2v, and the Duration changed to match the 29;20 Duration of the Motion Asset. Next, I linked to the previous SmartSound WAV, that was edited to have a Duration of exactly 29;20. The Duration for that Asset changed to 29;20 instantly.
    I previewed and the searchlights were now slower (as was to be expected) and the limo was also slower pulling in and out. The Menu’s Motion Background was smooth, but slower. The new Audio with Fade-in and Fade-out, played perfectly, and the Menu Looped very nicely. Actually the Looping was now better than with the original MPEG and MP3 Assets! This was a nice surprise, as there was a bit of a jolt, when the original Audio Looped. Not sure what could be done to eliminate that, but think that it would be easily accomplished in Audition, or Audacity. Maybe a test for another day.
    I burned a DVD RW and the Menu worked perfectly. I did not complete the test by altering the Scene Selection Menus (in my test Project, I needed three of these), but feel confident that they would function the same way.
    In conclusion, if one needs to use other Audio source files, this can be done, so long as one takes two things into consideration: the Video Motion Asset will determine the Looping/Duration, and the Duration must be < 30;00. I chose 29;20 to give myself a bit of headroom. Now, one needs to consider the visual effect of using TimeStretch to modify the Duration of a Background Video - here, it was fine. The Audio needs to match perfectly, or be ever so slightly shorter (I’m talking about a few Audio Units here - slight indeed), than the Video Asset.
    Now, one is still limited to the 30;00 Duration limit, in PrE, but up to that point, the chosen Audio can be just as long as the Video.
    I strongly recommend using a short Fade-in and Fade-out on the Audio, so that there is a lead-in/lead-out that will keep from having harsh jumps with the Loop.
    Hope that this helps someone in the future.
    Hunt

  • How to avoid item suppression in multiple item PM strategy plan

    Dear gurus,
    we have ONE plan, which have two items.  First item is linked to a task list which has 1M package, Second Item is linked to a task list which has 1M,1Y pack.
    I have scheduled the task and i am not receiving a work order for the first item's 1M task, during second item's 1Y task is due.
    How to over come this item suppression
    PLAN:01-ITEM-01-TASK LIST-01-Pack 1M
    PLAN:01-ITEM-02-TASK LIST-02-Pack 1M, 1Y
    ITEM01:    1M 1M 1M -
    1M 1M 1M
    ITEM02:    1M 1M 1M 1Y 1M 1M 1M
    Thanks in advance
    Edited by: ERP_YN on Mar 22, 2011 12:56 PM

    Hi ERP,
    I feel it is a short-coming in SAP when using multiple Items with different Package sets.
    This does not work for the selected combination, that is one TL Monthly Package & othet Monthly & Yearly when you have different Heirarchy for the Packages.
    Try making the Heirarchy as same for both of them and try creating a new plan, not the old one. But not sure on the result.
    Regards,
    MLN Prasad

  • Preventive maintenance by production

    I have this question raised by the user as in how we can separate the preventive maintenance by production?

    Hi Pallavi
    Thanks for showing interest in my solution to your problem.
    See For plant maintenance activity we always need tasklist. You can have the one common tasklist for the activity executed by the Plant maintenance team as well as Production team. The change you need to implement is you need to create the work center for production & assign that to the task which is executed by production person. You can also assign the persons to work center so that youcan track who are involved from your production department to execute the maintenance activity as well as you can  like ways we do in TPM activities you need to do the following actiuvty.
    1. Create work center from production team & assign the persons doing maintenance activity to work center so that you can assign a person to that activity.
    2. Then create the task list (either general if you want to general activity or Equipment related if you want production person doing eqpt related maintenance activity) & assign production work center to each task which will be executed by production team.
    3. Prepare the maintenance plan(you can have either one single plan for both or can have seperate plan for production person)
    4. Scheduled the plan & will have Maintenance work orders as planned activities will be due.
    5. Execute it & update the details in maintenance orders as maintenance team will do for their work.
    This will give you good track for production people's involvement in maintenance work (TPM). If possible i will prepare the document & will send to you. or link it with the message.
    Regards
    Makarand

  • How to change Unit for Breakdown Duration in Maintenance order.

    Hello,
    In cuni, somebody created Unit "TST" by mistake, system can not convert it to "second" for calculation automaticlly.
    "TST" make no sence. So if maintain "TST" as Unit for Breakdown Duration in a maintenance order, dump will happen. However there is a maintenance order maintained Unit for Breakdown Duration as "TST" saved by mistake, Dump will happen when I try to access to this order by IW32 to change the Unit for Breakdown Duration. Is there any way to change the Unit for Breakdown Duration"TST" to "H" so that I can access to this order by IW32.
    Thank you.

    Hi,
    You could temporarly adjust the CUNI definition for TST so that it can be converted to seconds. Adjust the notifications to set a valid unit of measure.
    The alternative would be to update the field MAUEH in table QMIH with a valid breakdown unit of measure.
    -Paul

  • Changing basic finish date in Preventive maintenance orders

    Hi Experts,
    My requirement is to block PP work centre when maintenance schedule the equipment for preventive maintenance. I am making system condition as zero in generated preventive maintenance order but basic finish date is not changing in the order automatically. Can anybody please explain how to bring this? Finally my requirement is system should change basic finish date and time as time given in operation of task list.
    Thanks in advance.
    best regards,
    Srinivas M

    Hi Praveen,
    I have done all setting and tested but there is no change.
    My client requirement is like this - whenever maintenance plans are scheduled, for the scheduled dates, production capacity should not be considered by production. We could do this for breakdown orders but not happening for PM orders unless we change the finish date.
    The issue is to get the finish date automatically when scheduling maint.plans with respect to values given in operations. Please suggest how to get the  basic finish dates automatically.
    best regards,
    -Srinivas