How to enter a specific vendor for  the delivery costs in purchasing order?

Now I want to create a purchasing order including planned deliver costs such as Freight, Coustoms ect, as the vendor of such planned deliver costs is different from the goods supplier, then How to enter a specific vendor for  the delivery costs in purchasing order? That means the partner for invoice partner will be two vendors at least in one purchasing order. thanks very much.
<i>
<b>No one would like to answer this question?</b></i>
Message was edited by:
        King Qi

hi, 
You can have vendor at each condition record level.
try it out.
cheers
Rav

Similar Messages

  • Selection of a price list based on the delivery date of purchase orders

    Description of requirement:
    One of our customers would like to have the price list selected on the basis of the delivery date of purchase orders rather than on the posting date.
    The customer wants to have this feature available by the date scheduled for their go-live, that is January 2nd 2008.
    Best regards,
    Emmanuel Ruellan

    Dear development team,
    Is it possible to have the above functionality in a future version?
    Best regards,
    Emmanuel Ruellan

  • Inbound idoc for updating delivery date of purchase order

    Hi All,
    Our vendor sends a delivery file consisting of delivery date and quantity(could be partial) for line items of a purchase order.
    I need to update the Purchase order line item with the delivery date and quantity sent from the Vendor. It should add a new confirmation line with custom confirmation category in the confirmation tab of the line item in the Purchase order.
    Each time we get a delivery file we need to add a new confirmation line in the confirmation tab of the purchase order line item.
    How can I get this working using inbound idoc processing? Which Idoc type should I use to solve my issue. Will ORDERSP work for my scenario?
    Thank you,
    Sonali.

    >
    sonali ashi wrote:
    > We have all EDI set up done for ORDERSP idoc in our system. Problem when I use this idoc type by default system is always adding confirmation catgeory 'AB' but we want our custom  category to be added instead of 'AB'.
    > Edited by: sonali ashi on Dec 23, 2010 9:47 PM
    Confirmation category used for order acknowledgement is define in configuation. You can change that from AB to your custom condition and EDI should pickup that.
    SPRO->Material Management->Purchasing->Confirmation->Define Internal Confirmation Category
    >
    sonali ashi wrote:
    > I have also noticed that 'AB' confirmation accepts only full quantity order acknowledgement through Idoc processing.
    > Manually I can add a "AB" confirmation for partial quantity but in the idoc processing it fails.
    > Edited by: sonali ashi on Dec 23, 2010 9:47 PM
    Check tolerance limit defined for confirmation category in 'Conformation Control' Node in SPRO at same level as above.
    Regards,
    Pawan.

  • How to scan a specific folder for the existance of a PDF before saving

    I created a folder level function for saving a file by passing it a name and a path.  The problem is I don't want to allow the user to overwrite a file of the same name.  I would rather want to append a version number to it's name so I can keep track of the evolution of the form.
    I'm thinking about a script to scan the folder for the occurrence of a file and returns something or throws an error.  I experimented with app.browseForDoc() but I don't want the dialog box to show.
    I would use a do/while loop to appends a version number and then look for the file until I get a specific return value or error indicating that the file is not present (or in my case that the name is not already used).

    I think I have just the answer, I still need to try it though.  I forgot about prompting the user for appending version numbers because it would mean he'd have to cancel a bPromptToOverwrite box for each version present in the folder.  That's way too many boxes.
    BUT....;o)
    I needed a way to prevent overwriting which is the first concern.  What I'm looking for is a way to:
    1-stop my save script before overwiting;
    2-Append version number if script stops and launch save script again;
    One way to stop the script is when an error is thrown.  I'm thinking about saving the file as a copy with the bCopy parameter and adding a DOS script to the folder that would monitor in real time the attributes of all files and turn it to read-Only.  That way, if I run my save function and reader tries to overwrite a file, it will throw an error.  I will modify my save function to return a boolean named successfulSave.  Using a try/catch handler, I will append a version number to the file name and call the save function again.  I will encapsulate this in a do/while loop until successfullSave is true.

  • Report for the changes made in Purchase Order

    Hi Friends,
    In my location, changes are made to the purchase orders as and when required. Is there any report which shows the changes made to the Purchase Orders?? I am aware of the Item changes option in the Purchase Order.
    Thanks in advance..
    Regards,
    Phani

    Hi,
    You have to develope an own ABAP report for this, based on the change tables CDHDR and CDPOS
    CDHDR - Header Change
    CDPOS - Item Change
    EREV - Version Change
    Check the link
    Purchase order change log
    Regards
    KK
    Edited by: Kishore Kumar Galla on Apr 5, 2010 1:16 PM

  • Is there a way to pay for the CC subscription by purchase order?

    I work for the NHS and I can only see the option for card as a payment option.
    Is there a way we can arrange to invoice and raise a purchase order?

    Who would our reseller be? We previously used a contract supplier called trustmarque but the old Adobe agreement had indeed expired back in March. GPS and Adobe were talking about another extension however in this instance no middle ground could be found. Adobe and GPS are in discussions for a replacement however this isn’t likely to be until the end of the year really.
    It doesn't seem very straight forward for businesses to come directly to Adobe to order.

  • Auto Population of SC vendor details in delivery tab of Purchase Order

    Hi friends,
    I want to buy material 123 from X vendor and deliver to vendor Y.
    How can I automatically populate the Vendor Y and tick SC Vendor box in the delivery address tab in the Purchase order other then maintiang Outline agreement. Is it possible to get this by Info Record ?Please confirm.
    Regards
    Madhavan

    Hi,
    No this is not possible using info record , you need development for this use BADI ME_PROCESS_PO_CUST
    To put a logic based on PO document type and item category combination or vendor item category combination
    Thanks
    Diwakar

  • Freight not to be loaded on the Material Cost in Purchase Order

    Hi,
    For Purchase Order, we want to configure a scenario where in we want the freight not to be loaded on the Material Cost.
    Where need to change in the configuration do achieve the same.
    Please guide.
    Regards,
    PK

    HI PK,
    1. New condition type to be created by copying the standard condition type FRA1/FRB1/FRC1
          New condition type ZFR1 created by copying FRA1 - M/06.Accrual flagged in this condition type same as FRA1 and Condition category of the new condition type should be Blank and maintain X-Negative value in the plus/minus field. Accrual must be flagged.
    2.New account key ZR1 created
    OLME -- >conditions -- >Define pricing Determination process -- >Define Transaction/Event keys
    3.Assign this condition type to pricing procedure - M/08 .Also assign transaction key ZR1 .
    80     1     FRA1     Freight %     70             X                              FR1
    80     2     ZRA1     Freight  in spl GL     70             X                         FRE     ZR1
    4.GL account maintained in OBYC for this new account key -ZR1
    Maintain same conditions for FRA1 and ZFR1.
    5. Goods receipt debits freight amount to separate account
    Inventory Acct -  100 Dr
    GR/IR - 100 Cr
    Frght Clr Acct - 20 Cr
    Frieght payable - 20 Dr
    6. At the time of MIRO
    Vendor - 120 cr
    GR/IR - 100 Dr
    Frght Clr actt - 20 Dr
    Hope Help U !
    Regards,
    Pardeep Malik

  • Paying the vendor for the packaging material

    Hi,
    I have a scenario wherein I want to pay the vendor for the packaging costs incurred for the packaging item created automatically in the delivery. My packaging vendor and transporter are different. I have shipment as well as shipment cost associated with the delivery.
    How do I pass on the cost incurred on packaging from the delivery so as to pay the vendor?
    Thanks.

    Hi,
    The transportation costs can be calculated on different bases, for
    instance on base of the handling units (C), Per handling unit (E) or
    Shipping unit including delivery item (F). In all cases the handling
    unit must be part of the transport, to become calculation base for the
    transport cost calculation.
    Note 700512 will also helps to you.
    Good luck,
    david

  • How to create an address code for PO delivery address?

    Hi Guys,
    How to create an address code for the delivery address in the purchase order? Please explain me with details.....
    Thanks
    Raja

    delivery adress records can be created with transaction MEAN.
    the number is purely internal.
    In ME21N you can then search by name (you will certainly not know the number)

  • How to make the delivery cost changeable after cancellation of GR?

    Create a PO (with Delivery cost), then GR (101) , then cancel the GR (102), but the delivery cost still cannot be modified eventhough the GR has been cancelled - how to make the delivery cost changeable after cancellation of GR?

    Hi
    "You are not allowed to add new delivery costs in a purchase order once goods receipt has been carried out as these would then be proposed in the invoice verification. The related posting to the clearing account for goods receipt and invoice receipt would not then balance, if no further goods receipt took place.
    After the invoice has been received successfully, it is not possible to change the delivery costs in the order. This is because information necessary for problem-free operation is no longer available for the delivery costs that have already been posted for subsequent reversals or invoices, or the operation can no longer be done without errors.
    It is also not possible to change delivery costs for stock transfers with SD shipping after goods have been successfully issued, as this can lead to errors during cancellation."
    I think you have to delete the line item and create a new line item with revised delivery conditions..
    MRao

  • How to execute availability check against delivery date in purchase order

    Hi all
    In MD04, I know that "available date = delivery date in purchase order + GR processing time" & "GR date = delivery date in purchase order". When I execute availability check in production order, I will get material's committed date = available date. But I hope to get material's committed date = GR date in purchase order.
    For example. delivery date in purchase order is 2012/02/06 and GR processing time is 2 days. After ATP in production order, I will get committed date 2012/02/08. But I hope it show 2012/02/06. How to customize it.
    (The GR processing time must be set 2 days for MRP calculation. it can be changed to 0.) Thanks!!

    Hi Rita,
    One Doubt, If you say that material commited has to be the GR date and you do not wish to wait for GR processing time, then why do you have the GR processing time in first place.
    For ex. My client, we get the stock as per GR in Quality inspection and so we have GR processing time considered for available time in MD04. But since the business considers the Inspection stock as avialble, The stock gets reflected in avialibility check the moment GR is done.
    So please explain your requirement in detail. There could some way to do so. If not the raise an issue with SAP.

  • Error doing ERS for planned delivery costs

    Hello!
    We post the freight for STOs via the FRB1 condition as our delivery costs. The freight vendor is of course, different from the vendor in the STO itself which is the plant. The freight vendor is marked for ERS settlement and the ERS works fine for it from the shipment cost documents of sales orders. However, while doing the ERS in transaction MRRL for the same freight vendor for planned delivery costs, nothing comes up in the list to settle. The delivery has been goods issued and freight accounted for. What could be going wrong here? What do I need to check?
    Thanks!

    OK, I got this issue resolved...don't know what was wrong and I didn't change anything but it is working now Freaky. But I do have one more related issue - hopefully someone can shed some light on it. For the freight vendor, we have a different PI partner in the vendor master set up by the plants - when I do the ERS, it is not creating the A/P against that different Invoicing Party (PI) - it is creating the A/P for the same freight vendor code...any clue what is needed to make it create the A/P for the different Invoicing Party that we have set up?
    Thanks!

  • Create a custom pop up text (warning) while entering a specific Vendor.

    Hi all,
    I would like know the steps to create a custom pop up text (warning message) while entering a specific Vendor number in the ME51 or ME51N screen. This test would be an instruction or a text for user to be aware off.
    Is it even feasible?...if so can someone please provide me with some steps or instructions on how to proceed?
    Thanks,
    El Matador.

    >
    matador wrote:
    > Hi all,
    >
    > I would like know the steps to create a custom pop up text (warning message) while entering a specific Vendor number in the ME51 or ME51N screen. This test would be an instruction or a text for user to be aware off.
    >
    > Is it even feasible?...if so can someone please provide me with some steps or instructions on how to proceed?
    >
    > Thanks,
    > El Matador.
    Hi
    In PR Vendor is not a mandatory to enter and even you can add warning message Go to SE91 and select appropriate message and activate for PR

  • How to enter a credit memo with the funds returning to the PO

    Hi Guys,
    This is my first post on here, not sure if I am posting this question in the correct area however hope you can help.
    I have a number of credit notes from a vendor which need to be entered, we usually enter these in MIRO which is fine but what I am after is how to enter these credit notes so the funds return to the Purchase Order for further use.
    For example, say the limits on the PO looked like this:
    Overall limit: 10,000
    Expected Value: 10,000
    Actual Value: 10,000
    So we have had invoices for the entire 10,000. Is there a way I can enter a credit for say 5,000 so the limits would then look like:
    Overall limit: 10,000
    Expected Value: 10,000
    Actual Value: 5,000
    We are hoping there is a way so we can avoid having the PR/PO increased, which has also gone above the contract ceiling.
    Usually with credits we would enter them as a credit memo if we wanted to change the qty and price, and a sub credit if we just needed to amend the price leaving the qty as is. By doing it this way the funds don't actually return to the PO like in the example above, what does happen is when we pull up the PO in MIRO we can access the "credited" funds at that time. We would like to see the funds back on the actual PO, not sure if this can be done though, any help or suggestions would be appreciated.
    Thankyou

    Hello Pistol,
    This question is related to PO's then it belongs in one of the FI forums.
    This is the forum for SAP Solution Manager which is the software SAP's support strategy is based upon.
    You have posted in the wrong forum.
    I would recommend closing this thread, and looking for a more appropriate forum to raise this question.
    I hope this is helpful.
    Regards,
    Paul