ICPO PR adding lead time in supplying plant
Hello Experts,
I have a situation where Plant A (Purchasing Plant) is placing order for a material to Plant B (Supplying Plant) through ICPO (InterCompany Purchase Order).
The requirement for the material is put through PIR (Planned Independent Requirement) in plant A. The Planned delivery time in the material master in plant A is considered for calculating PR Release date after MRP.
This PR drives a Planned Order in plant B which calculates Order Start date through Lead Time Scheduling considering the PR release date from plant A as the Order finish date in plant B.
The issue with this is the material is ready in plant B much before it is required in plant A.
Example: -
Planned Delivery Time in Matl Master in Plant A - 60 days
Requirement date (thru PIR) in Plant A - 30/06/2014
After MRP, PR for the material is created in plant A with Rel Date 01/05/2014
In Plant B - Planned Order Finish date - 28/04/2014 (whereas i need the material in plant A on 30/06/14)
Planned order start date - 25/04/14
Thanks in Advance,
Deodatta
Hi,
thank you very much for your reply .here i have small clarification required the 1st part po date there is no prob. 2nd part h PR release date how to calculate.
functional is calculating like this.
1st step: entering in date perioed in release date (1st aug -20aug)in ytable to getting the all PRS.
2nd step: these prs from ytable enteing eban table some restriction like plant , deletion indicator etc here getting prs,podate po etc
3rd step: again all prs takking from eban table they are entering in ytable :here all pr date are getting
lead time = PO date from 2nd step- pR date 3rd step.
can you suggest me how to do 3rd step in bw reporting level or modelling level
Regards
Rk
Similar Messages
-
Different Lead times for supplier in MRP calculation
Dear All,
We have different suppliers for a material. Different suppliers have different lead times and Min.lot size. Our requirement is when we run MRP system should suggest Pld.Order quantity for the supplier and also take lead time accordingly. I have done splits for suppliers by using Quata arrangement but system is only taking planned delivery time from material master record.
I also defined info records for the vendor and define lead time but still system is taking Pld delivery time from materials master.
Please help
Majid Ali khan.Hi,
Go to OPPQ, enter your plant then click on External Procurement, there tick the check box Scheduling: Info Rec / Agreement.
This will ensure that the PDT is read from info-record if it exists.
Hope it clarifies.
Regards,
Vivek -
Different lead times for suppliers
Dear All,
We have different suppliers for a material. Different suppliers have different lead times and Min.lot size. Our requirement is when we run MRP system should suggest Pld.Order quantity for the supplier and also take lead time accordingly. I have done splits for suppliers by using Quata arrangement but system is only taking planned delivery time from material master record.
I also defined info records for the vendor and define lead time but still system is taking Pld delivery time from materials master.
Please help
Majid Ali khan.I also maintained plant parameter -- external procurement -- tick on planned delivery time from info records with this setting to make system to consider different planned delivery times.
-
Hello,
Do we have a standard transaction for mass change of lead time for material-plant level for all materials in a plant. This should also consider lead time for DC.
Regards
Prashant Kedare>
Prashant Kedare wrote:
> Hello,
>
> Thank you for the replies so quickly. But the planned delivery time is to be maintained only for materials from external vendors. How about receiving goods from a Warehouse which takes 1-2 days for receipt of material. Where do we set this parameter and how do we mass change it?
>
> Regards
> Prashant Kedare
In MASS, use Total RL time = MARC-WZEIT for updating total replenishment lead time and just update materials which are for external vendors.
Use GR Proc. Time = MARC-WEBAZ for updating Gr proc. time field records and you can give range of materials for which records needs to be updated or created. -
Report Supplier Lead Time - Days
Hi All,
Can anybody give me the characters, key figures, CKF's, RKF's and other fields that are usually used in Supplier Lead Time - Days Report in general irrespective of the requirement.....come up what ever you remember from your side.
Thanks All,Nevermind
-
Supplier Processing Lead Time with ASCP Unconstrained Plan
Hi All,
Is it possible for unconstrained plan to consider supplier lead time constrained which we define in ASL?
I have defined an Unconstrained Plan & the plan is not considering Item Level , ASL Lead times & generating the planned Orders to meet demand due dates by compressing the Lead time.
Constraint option is not checked in plan options.
Appreciate your advise on this issue.
Regards,
Pranay SaxenaHi Pranay,
An unconstrained plan cannot have ANY constraint.
So it is not possible to have just the supplier lead time as constrained.
Alternatively, if that is what is your requirement, you may run a constrained EDD plan with just the material constraints enabled and the "Enforce Purchasing Lead Time" Flag checked.
If the supplier capacity is NOT set.. it will be treated like infinite..
This way you will force the engine to respect the lead times from ASL and acheive a near unconstrained plan.
Another alternative is use constrained plan as explained above and set the profile MSO: Lead Time Control to Do not Violate Minimum processing LT... in this case even the processing LTs for the MAKE items are also respected.
Hope that helps.
Regards,
Mohan Balaji
NOTE: Please mark the post as Helpful or Answered if the update has really helped you. This would also bring the thread to logical conclusion and will be helpful for the viewers. -
Can I get supplier actual lead time in system?
can I get supplier actual lead time in system?
suppose if oyu have created PO and as per your inforecord lead tine 15days but you really want the actula time based on the vendor promice
either you have to activate the ASN functionality or order acknowledge function
to do that when you create PO go to confirmation tab and select the order ack and/or shipping notification and make conf reqd filed checked that means prior to GR you need confirmation from vendor about the date, and qty atleast
you can receive the confirmation via EDI also but in this case you and vendor both should EDI funcitonality
once oyu receive the confirmation then you have to createin the system using VL31N tcode then it will be populated in your PO. -
Hi Guys,
We have an issue - i.e. when we create STO manually in ECC 6.0 it always add extra one day to the good issue lead time. I have checked and we have no plan delivery date on the material master, 'pick & load' at the shipping point is standard 1 hr, no lead time on the route. Also as this is intercompany STO so we do not use PIR.
Any ideas where can this one day extra lead time comes from?
Thank you.Thanks girang. I have checked the Shipping point configuration and it is standard 1 hr for 'pick & load'. The funny thing was we tried creating STO from the same supplying plant to existing plants in SAP and they worked fine; but this problem occured when we created STO to the newly added plants into SAP. Can't figure out what is the problem...
-
Lead Time Calculation in SNP Heuristics
Dear All,
Please let me know how the lead times are determined in SNP heuristics?
Ex: Distribution Center to Production Plant and
Production Plant to Supplier.
Thx,
Ram.Hi,
Please check the below link for help: [Scheduling|http://help.sap.com/saphelp_scm70/helpdata/EN/05/f8923945b12c4de10000000a114084/frameset.htm]
Best Regards,
Ada -
Reg: lot size and replenishment lead time
1. please explain about lot size and replenishment lead time.
2. please also explain about consumption based planing and in steps explain how to perform manual and automatic reorder point(transc code please)You use the lot-sizing procedure to determine how the system is to calculate the reorder quantity in the planning run.
A lot size defining the lot-sizing procedure is assigned to every material master record applicable to materials planning.
The lot size is defined in Customizing by the combination of the lot-sizing procedure and the lot-sizing indicator.
Three procedures for lot sizing are available:
o static lot-sizing procedures
o period lot-sizing procedures
o optimizing lot-sizing procedures
You use the lot-size indicator to define the procedure.
The following parameters are also available for controlling the lot-sizing procedure:
o Short-term and long-term lot size
You can split the lot-sizing procedure into a short-term and a long-term period. This means that you can select one lot-sizing procedure in the near future and a different one in the distant future.
You define the periods in the section of the screen entitled "End of the short-term period/start of the long-term period".
The valid from date of the long-term lot size area is defined via:
- a periodicity
- a number of periods
The beginning of the long-term period is calculated by taking today's date and adding the number of periods in the future; the long-term planning period then starts on the next complete period.
Note
For materials that are planned using the short and long-term lot size,
it is recommended that you define a maximum MRP period. Defining the
MRP period has the effect that materials after a certain period are
included in planning even if no changes relevant to the planning run
have occurred. This avoids a situation where order proposals created
with the long-term lot size move into the short-term period because no
changes relevant to MRP have occurred for the material.
You define the maximum MRP period in the step, "Define maximum MRP
period". A material that is planned on a regular basis should also be
provided with an MRP type that contains the indicator for regular MRP.
o Scheduling indicator
For period lot sizes, you can use the indicator for scheduling to
determine whether the availability date;
o is to be set to the first requirements date in the period
o or is to be set to the beginning of the period
o is to be set to the end of the period
o or whether the period start represents the beginning of the planned
order and the period end represents the availability date (repetitive
manufacturing)
Interpretation of the delivery times
For the lot-sizing procedure, you can also define whether the period
start is to be interpreted as the delivery date or as the availability
date using the indicator, "interpretation of the calendar times".
NOTE
The indicators, Scheduling and Interpr.deliv.times are mutually
exclusive.
Indicator for the splitting quota
For the quota arrangements, you can determine whether the requirements
quantities are to be distributed to several items, that is, whether
they are to be split. With the splitting quota arrangement,
requirement quantities are not simply allocated to the smallest quota
rating. Instead, they are distributed among various sources using the
following formula:
Quantity for source of supply X = Quota of source X * reqmts quantity
Sum of all quotas
Overlapping indicator
The overlapping indicator along with the cycle time in the material
master record are used to split the planned orders into several
partial quantities whereby the in-house production time overlaps by
the cycle time.
Lot-sizing procedure for make-to-order production
In make-to-order production, you can use the indicator, Lot size for
make-to-order production to determine whether,
the order quantity is to be calculated using the exact lot size
the order quantity is to be calculated using the exact lot size and
the system is also to take the rounding quantity or the minimum and
maximum lot size into account
the order quantity is to be calculated using the lot-sizing procedure
defined for the short-term area
Maximum stock level variant
The system only displays the Maximum stock level variant field in the
lot-sizing procedure, Replenishing to maximum stock level. The
indicator only has an effect in connection with reorder point planning
taking external requirements into account and in connection with
material requirements planning and controls how the system calculates
lot sizes. -
Product Specific Transportation lead time
We need to maintain different sourcing lead times for different products in the "Transport duration" field of the "Means of Transport" of the transportation lane. The transportation lane exists between the Supplier and the DC. A single vendor would supply different products which may have different lead times.
Could anyone kindly give us pointers as to how this could done in the TL ?
Best Regards,
MukundanHi
as well as Sanjog's answer another option is to keep just one TL MOT record and instead use the Goods Issuing time on the product Location record to account for the different leadtimes of product from a supplier. This time is added to the transportation time on the TL. It is the "GI Processing Time" field on the GR/GI tab.
Which method you use depends on the amount of different leadtimes you have from a supplier (a few and I would use Sanjog's method, more and I would use the GI time). The GI time can also be integrated in with the transportation planning of deliveries in the ERP system as well to give better visibility of milestones in the delivery tracking. (e.g. you have a planning point when the goods should be ready to ship as well as when they are due).
Regards
Ian -
Lead Time for Procurement Materials
Hi Gurus,
Can you elaborate on hierarchy for procurement lead time materials. If there is lead time given in Material Master as well as Info record and Source List. Then which lead time will be considered by the system for procurement?
Also clarify what is the significance of Source list for Material Master?
Regards,
PradeepHi
System takes more priority for lead time mainatained in Info record ahead of material master's planned delivery time. Along with planned delivery time, purchase processing time maintained in OMEW and GR processing time in Material master.
Source list defines the vendor/list of vendor who supply material for a plant in the given validity period. A vendor can be fixed or blocked. FIxed vendor makes MRP to create source assigned PO. later it can be made as PO automatically.Scheduling agreement with sourcelist and MRP relevency indicator 2 can give automatic schedule line.
Regards
Antony -
Lead time from catalog does not consider factory calender
Hi,
we are working with SRM 2.0 classic scenario. I have following problem:
We take over lead time from a supplier catalog via OCI in EBP. This works but the lead time does not consider holidays and weekends. How can I activate the Factory Calender?
Thanks ThomasHello,
I just sniff arround and found out that EBP 3.0 does not support factory calendar.
You should use BBP_DOC_CHECK_BADI or BADI BBP_CATALOG_TRANSFER and call within this BADI the function modules requesting the factory calendar data via RFC on the backend.
i.e.
get the target system of the follow-on document
SELECT log_sys from BBP_DET_LOGSYS INTO wa_logsys-log_sys
WHERE CATEGORY = ls_item-category.
ENDSELECT.
read table T001WK
CALL FUNCTION 'META_READ_TABLE'
EXPORTING
query_table = 'T001W'
logical_system = wa_logsys-log_sys
TABLES
options = options
fields = fields
data = tabcont
EXCEPTIONS
OTHERS = 1.
fill the internal table xt001w
LOOP AT tabcont INTO la_tabcont.
MOVE la_tabcont-content+3(4) TO la_xt001w-werks.
MOVE la_tabcont-content+61(2) TO la_xt001w-fabkl.
APPEND la_xt001w TO xt001w.
ENDLOOP.
SORT xt001w BY werks.
get the fabric calendar related to the plant
READ TABLE xt001w INTO ma_XT001W
with KEY werks = ls_item-BE_PLANT.
check if delivery date is a working day
CALL FUNCTION 'DATE_CONVERT_TO_FACTORYDATE'
DESTINATION wa_logsys-log_sys
EXPORTING
DATE = ls_item-DELIV_DATE
FACTORY_CALENDAR_ID = ma_XT001W-fabkl
IMPORTING
WORKINGDAY_INDICATOR = W_IND.
get an error message if delivery date is not a working date
IF W_IND = '+'.
CLEAR ls_message.
ls_message-msgty = 'E'.
ls_message-msgid = 'ZBBP'.
ls_message-msgno = 'xxx'.
ls_message-msgv1 = 'error message text, e.g. delivery date not
working date'.
ls_message-item_guid = ls_item-guid. "assign message to item
APPEND ls_message TO et_messages.
ENDIF.
endloop. -
MM Report for Reorder and lead time
Hi,
Can anyone suggest me a report that can show information by materail such as min./max. quantity, re-order or safety stock, and replensihment lead time.
Thanks
Atifyou can create the query using MARC or just go se16 adn enter the MARC table and pull the data.\
Displayed Fields: 8 of 8 Fixed Columns: 2 List Width 0900
Material Plant Reorder Point Safety stock Min. lot size Max. lot size Total RL time Min SafetyStock
MATERIAL Z001 0.000 0.000 5,000.000 350,000.000 0 0.000 -
Product is not defined in Supplying plant in demo system
Hi Experts,
I am doing initial load in demo system. While doing Material transfer I am facing Product is not defined in supplying plant issue.
Though I am transferring master data 1st time to the plants, how can i extend product to the supplying plant first.
please advice.
Thanks,
Bala.Hi Bala.
Are you using special procurement key for Production in Another Plant? If yes, perhaps you can try to send first the material at production plant and only then send it at planning plant to APO. I've never had this issue, so this is just an idea/educated guess.
Also, what support packages are you on?
Regards,
Tiago
Maybe you are looking for
-
Have had a kernal panic issue with this machine since it was purchased. Apple has replaced the motherboard, HD, graphics card and display, run every hardware test imaginable, but the panics persist. Panics are now they are down to once or twice a w
-
Hi experts In our development system - T-code:CA03 after entering when we clicking header icon dump error is coming. All other icons are working fine. Our ABAPer also checked screen 1200 is active. what can be the other possible reasons.? Regards, sr
-
NetConnection.Call.BadVersion - Channel disconnected
I am facing NetConnection.Call.BadVersion error when I run flex based application with BlazeDS on S64 with Weblogic application server. At application start up, it makes 4 calls to server and get appropriate data. However once the application is up a
-
Question about SOA suite installation After RCU setup creates tablespace for Identity Manager and SOA- question: how does SOA install connect or know about the tables created by RCU. Because in the SOA setup process there was no configuration for Dat
-
Photoshop and Mac sleep problem.
Hi everyone, I have a MacBook Pro Retina, intel i7, 8 GB of RAM, SSD, I've installed the Photoshop CC (2014) trail version, because i'm interested to buy the complete version. The problem is that if my mac goes in stop, only after the installation of