IR created for Purchase order without accounting document

Hi all,
We have a peculiar situation where an IR (Invoice receipt) document has been created for a purchase order where the corresponding accounting document has not been generated. Can you please let us know how can we create accounting document for this IR.
We tried to reverse this IR by transaction code MR8M but it is throwing the error message "Reversal not possible, accounting document for the ref. does not exist".
We understand that there is some standard SAP utility which posts the accounting document and in case there is some configuration also for this, please let us know.
We would be grateful for any information on resolving this issue.
Regards,
Santosh

Hi,
Please refer to the below links:-
http://www.sap-img.com/financial/integration-of-fico-with-other-modules.htm
http://www.sap-img.com/materials/what-is-the-dataflow-of-mm.htm
Re: FI-MM(Valuation Class)
Rgds.

Similar Messages

  • Profit center for purchase order without account assignment

    I've requirement to include profit centers in purchase orders without account assignment category.
    The trouble is when there is no profit center maintained in material master.
    Is there a way to determine profit center in purchase order for such cases?

    Dear Abinash,
    Define substitution in GGB1 at line item level as shown below:
    Prerequisite : BSEG-WERKS = Maintain plant
    Substitution : BSEG-PRCTR = maintain profit centre as constant value
    After define it, assign to the co.code.
    Regards,
    Mukthar

  • How create a purchase order without imputation using bapi: BAPI_PO_CREATE1

    Hello Forum
    I have an request for purchase order with imputation K (cost center, EBAN-KNTTP). During the liberation of the request for purchase order, and using the Bapi: BAPI_PO_CREATE1, I want to create a Purchase Order without imputation (imputation empty or charge empty).
    The system displays the following error: The request for purchase order, item (position) 10, is attributed to another order...
    I imagine that is because the request for purchase order has imputation (charged) K and the purchase order will have no type of imputation (imputation empty).
    However, manually, Yes, I can create the purchase order. That is, I first release, the request for purchase order. Then I create the order of purchase using ME21 and with reference to request for purchase order, and when SAP returns the items of the request for purchase order, I manually remove the imputation K, and these items to become the purchase order.
    Please support me want to know how to resolve this case, why can not I create a purchase order without imputation to from the request for purchase order with imputation K, using Bapi
    Thank you.
    Greetings,

    Hi,
    In the item overview of the purchase order creation screen (ME21N), you have a column Purchasing Doc and next it item no.  You can give the existing purchase order number here with item no which will create a purchase order, and changes can be made wherever you require.
    Hope this helps.
    Thanks
    Krishna.

  • Ammendent to Purchase Orders without changing document Number

    Hi Experts,
    Can we issue amendment to Purchase Order without changing the Purchase Order  Number for change in any of the following parameters:
    (a) Quantity
    (b) Unit Price
    (c) Statutory Levies
    (d) Delivery Schedules
    (e) Technical Specifications
    Kindly advice me.
    Thanks in advance,
    Regards,
    Rounak

    Hi Rakesh,
    Thanks for your suggestion...........
    If incase there is a PO with 100 ton of Steel and after subsequent supply of 40 tons it has been found that some of the above mentioned parameters are changed, thre how can we do the changes/amendents so that we need not issue a seperate PO. also if the supply is over the said demand qty of 100 tons (say 125 tons) how do we account the same in tghe existing PO?
    Kindly advice....
    Regards,
    Rounak

  • LIV for Purchase Orders with Account Assignment

    Hi SAP Gurus,
    I would like to get your expert advice on this...
    I enabled total based invoice acceptance and reduction by performing the required configuration steps (define vendor tolerance group, set up the auto invoice reduction tolerance checks, assigned the tolerance group to the vendor). I was assuming that this would work for my purchase order which contains an account assignment. However, when I tested it out, instead of behaving as expected (create invoice and credit memo for the excess value), the system generated only 1 accounting document. The price variance was posted back to the account assignment assigned to the PO item.
    Did I miss out on any steps? or is this the way SAP treats account assigned (non-stock) PO items (i.e. no invoice reduction occurs). If so, can you explain to me why?
    Best regards,
    RiVeR
    Edited by: delo celo on Jul 14, 2010 6:16 PM

    Hi Delo,
    Please find answers to your queries below in bold.
    1. I was just wondering why would SAP allow such transaction/s to happen? Wouldn't it compromise the integrity of the whole document trail (PO account assignment is different from the LIV)?  -
    There could be some business scenarios in some organisations, where in Procurement team uses generic cost centre (header), which is specific to particular department or group, to procure. But at the time of Invoice Receipt, AP team knows exact cost centre or order, etc  to post the amounts. To cover these kind of scenarios, SAP probably has provided the option to change acount assignment.
    2. Is there a way to edit the Account Assignment for a Purchase Order line item even if that item has been fully received and invoiced? -
    These field changes at various levels can be configured via t-code OME9.
    a) IR Changeable - This field if selected will allow to change the account assignment of a purchase order item at the time of invoice receipt.
    b) Acct. assg. changeable - This field is selected will allow to change account assignment for an item following goods receipt or invoice receipt.         
    Hope this clarifies your queries.
    -Ravi

  • GR for purchase order with Account assignment E

    Hello All
    I am having a scenario where in the BOM structure is as under: A->B->C--->D, D is the raw material, C is the component produced in-house, B is the material which we procure through subcontracting, in the material master of C SPK:30 is used for subcontracting, & A is in-house produced material with purely MTO scenario (20 - strategy).
    Once the sales order of A is there we run MRP for it, as per the master data settings described above we get purchase requisition for D & when I convert it to purchase order it is having account assignment as E.
    This is all well but the moment I try to save it, system throws an error stating: 'G/L account 20500100 cannot be used (please correct)". This G/L account is of raw material itself.
    Can you please guide me to overcome this problem.
    I am looking forward to listen from you soon.
    Regards,
    J K Tharwani

    Hi
    Check the OBYC settings for this transaction, assign the correct G/L for this transaction. Try to get the help from MM consultant to resolve this.
    Check in BSX Transaction for the invetroy posting.
    Check the G/L account it is exist for your company code.
    Take the G/L account which is coming in the error message and go to FS00 t code select tab Create/blank/interest , there you will have field status group just double click on that . It will take you to field status group display in that check the combination of the selection.
    Thanks
    S.Murali
    Edited by: S. Murali on Jun 26, 2009 5:07 PM
    Edited by: S. Murali on Jun 26, 2009 5:19 PM

  • Link between Customer Purchase Order and Accounting Document Number

    Hello all,
    is there a table in SAP that contains the purchase order number of the customer and the Accounting Document Number (belnr)?
    thanks in advance
    Anne

    Do this:
    SELECT awtyp awkey
      FROM bkpf
      INTO CORRESPONDING FIELDS OF bkpf
      WHERE bukrs = bsis-bukrs
        AND belnr = bsis-belnr
        AND gjahr = bsis-gjahr.
    ENDSELECT.
    This should give you SD billing document information.
    Rob

  • Is it possible to use IQS1 for purchase orders without material master?

    Hello,
    We are currently trying to come up with a way to send a notification on purchase orders which have GR's posted against them so that the purchasing team/requestor know that products have been shipped.  We have an office in Qatar where we would like to ship products to (which we are purchasing out of a catalog based in the US) and we need a way to track the shipment.  We are currently using T-Code IQS1 for any items which have been created as material master and are in stock within Qatar however we would like to utilize this t-code for products which are pulled in from a supplier catalog, which are not part of the material master.
    Is there a way to use IQS1 for non-material master products?
    Thanks,
    Katie

    Worked with my development team to locate the resolution.

  • Goods receipt for purchase order with account assignment 'K'

    Hello All,
    There are couple of purchase orders with acc.*** "K". On doing the GR for these PO's they have been done with mvt type 103 & mvt typ 105.
    I understand that material has been directly consumed to the respective cost center.
    How do track the internal movement for these materials??
    I need to view the stock for these materials at the cost center as in MMBE the stock is seen as ZERO.
    All these materials are with QM proc ACTIVE. So a goods receipt is done 105, then the inspection lot is cleared. However, in this case as the material is directly consumed, it is NOT displayed in QA32.
    Is the above procedure correct??? Is it better to receive stock against mvt type 101 & then do a 201 mvt ??
    Request your inputs.....
    Regards,
    Manoj Reddy

    Account assignment inventories are not maintained. To maintain a report for cost center receiving/issuing you need to make a customized report with help of ABAP.
    Other way is to pull report in MB51, with selection criteria COST CENTER and it will give you result of stocks available on cost center. For stocks received on cost center, you can pull report with cost center and movement 101.
    201 is used for goods issue to cost center from warehouse, the stock you receive from PO against 101 is directly charged to cost center, so no need to issue later to cost center.
    Edited by: Afshad Irani on May 17, 2010 2:17 PM

  • User exist for purchase order with account assingment

    As our org has gone with Project specific stocks. we are maintaing seprate "Z" table which conatisn datas like WBS element, material code & material price. And when we raise a P.O for a particular project with WBS element and when we enter material code first it should check whether the material code exist in "z" table. If material code exist it should allow or else it hould display a message that material dose not exist.
    Regards]
    Dinesh

    Hi,
    I would recommend you to test BAdI ME_PROCESS_PO_CUST.
    Regards,
    Edit

  • Give rhe report program for 'Purchase orders without Purchasing Requisition

    please give me the report program and related tables

    report zrich_0003 no standard page heading.
    data: begin of itab occurs 0,
          ebeln type ekko-ebeln,
          ebelp type ekpo-ebelp,
          matnr type ekpo-matnr,
          txz01 type ekpo-txz01,
          menge type ekpo-menge,
          meins type ekpo-meins,
          end of itab.
    select-options: s_ebeln for itab-ebeln.
    start-of-selection.
      select * into corresponding fields of table itab
             from ekko
                 inner join ekpo
                    on ekkoebeln = ekpoebeln
    <b>                         where ekko~ebeln in s_ebeln
                               and ekpo~banfn = space.</b>
      loop at itab.
        write:/ itab-ebeln, itab-ebelp, itab-matnr,
                itab-txz01, itab-menge, itab-meins.
      endloop.
    Please remember to award points for helpful answers. Thanks.

  • BADI / User exit for Purchase order(ME21N) after saving the document

    Hi expert,
    I need the BADI / User exit for Purchase order(ME21N) after saving the document
    This is for email sending after create the purchase order so PO document number will be the import parameter
    pls help me
    point will be reward
    Regards,
    Ganesh

    Hi Ganesh,
    Could you please share your solution?
    Thanks.
    Hoops
    Edited by: Hoops on Jun 13, 2011 10:51 PM

  • Creation of Purchase order without Quantity

    Dear experts,
    Good Evening,
    My client requirement is to create a purchase order without any quantity but with price ,is it possible by any chance.
    Thanks
    Vijay rebala

    Sorry for not responding ,but business wants purchase order
    That's probably what is wrong with your scenario. Business shouldn't "want a purchase order", Business should want a process that works, irrespective of the transaction.
    It's up to the people that know how the ERP works, to tell the business how they should use it.
    If they are in the negotiation phase, they shouldn't be using a Purchase Order to do it, they are basically exchanging quotations.
    The Purchase Order should be used when you have already agreed to the terms. That's how SAP standard works,.

  • Purchase orders and sales documents

    hi what r the transaction codes for purchase orders and sales documents.

    Hi Mohan,
    ME2C  Purchase Orders by Material Group
    ME2J  Purchase Orders for Project
    ME2L  Purchase Orders by Vendor
    ME2M  Purchase Orders by Material
    ME2N  Purchase Orders by PO Number
    ME2W  Purchase Orders for Supplying Plant
    VA03  Ccreate Sales Order
    VA03  Change Sales Order
    VA03  Display Sales Order
    Regards,
      ok

  • Creation of Purchase Order Without Requisition

    Hi Experts iam new to this forum
    Can u please explain with navigation that how to create a Purchase order without requisition ??

    Navigate to purchasing responsibility.
    use menu --> Purchase order --> Purchase order form.
    This is a very detailed note on how to do that:
    How to Create Purchase Orders (Doc ID 168237.1)
    Regards,
    Paarthy

Maybe you are looking for

  • Problems with iTunes and Podcasts after upgrade to iOS 8.1.3.

    I upgraded my iPhone 5 to iOS 8.1.3, then I purchased some music on iTunes. While hearing the music, incomming call shut the Music player down. From that time on, cannot open neither Music, nor iTunes Store, Podcasts, Settings/General/About, (Nike) R

  • Session ejb 3.0 stateful and same instance

    Hello, I'm using OC4J 10.1.3.3 and EJB 3.0/JSP In a jsp I do two different lookup for a STATEFUL session ejb 3.0, and I want two different instances of the ejb, instead I get the same one... Please help. Thanks.

  • Mac Mail Setup

    I'm setting up a Mail account on my new Mac Mini (Lion).  I've set up everything like the Mail account on my original Mac, but I've got 3 problems: 1- The Incoming Mail Server setup box refuses to save the password I type in, even though I hit Save a

  • Mac Book Pro rebooting repeatedly...

    A Mac Book Pro used by a professor in our building has been rebooting spontaneously. Can't observe a pattern...not during a certain program, etc. Observed it once in between installations, user said it's happened frequently since then, even when comp

  • Mark indicator 'Via Delivery' in MIGO

    Hi, Their is a requirement where we want to always post the Return delivery (mvt 122) via MIGO with Delivery. For this in MIGO we need to select the option 'via delivery'. Is it possible to keep th field 'via delivery' mandatory so that it has to be