Launch specific BPC Excel Report/Input Schedule or BPF from Infoview

Hi all,
We would like to launch either a specific BPC for Excel report and/or input schedule, or link to a specific BPF from BOBJ Infoview (probably a Webi report).
Therefore is it possible to provide a url to Webi to do this?
This is BPC NW 7.5
Many thanks,
Andy

Hi you all,
we are dealing with the same problem in our project. Our customer is implementing BPC and wants the Excel input schedules to be launched from the same place where their current BI (BO) reports are stored. That's InfoView, or actually soon BI Launchpad 4.0.
Is it anyhow possible to launch a normal BPC Excel input schedule directly from InfoView/BI Launchpad? I tested a bit with OsCLD function with a published Input schedule, and using the link OsCLD returns as Launchpad hyperlink, it's possible to open the .xls file in Launchpad browser window. Of course, none of the BPC's own structures or functions are there so it's just a plain excel sheet, not an really input schedule... so I guess BPC for Excel must be running when opening them and that pretty much is the same as using them directly from the Excel UI. But it's not the solution the customer wants to use.
Their reason for using Launchpad is that they control user access to their current reporting with the InfoView folder structure and want to use the existing authorization this way for BPC planning too.
Any suggestions?
BR,
Andy

Similar Messages

  • Assymetric report(input schedule) in SAP BPC

    What I mean!?
    I want  place in row expansion two dimension. Connection between members of these dimensions i described on example 1.
    I would like to build report(input schedule) like in example in analytical systems it call assymetic report. By means standart functional I can achieve only example2.
    Any suggestions will be appreciable.
    Regards
    Example 1                            
    Division1 
       ---         Cost1 100
      ---           Cost2 200
    Division2  
    ---           Cost3 200
    ---            Cost4 300
    ---            Cost5 100
    Division3  Cost6 500
    Example 2
    Division1  
    ---Cost1  100
        ---        Cost2   200
        ---        Cost3
        ---        Cost4
        ---        Cost5
        ---        Cost6
    Division2   Cost1
         ---            Cost2
         ---            Cost3  200
         ---            Cost4  300
         ---            Cost5 100
         ---            Cost6
    Division3  Cost1
         ---            Cost2
         ---            Cost3
         ---            Cost4
         ---            Cost5
         ---            Cost6  500

    Vijay,
       you  can  achieve  this with a  single evdre saved  as  an  Input  schedule...
    couple of pointers
    1)if you  do not  want   to  have the  col  names  changing  with  a  change  in current  view......put a  NOEXPAND   for  the  TIme  dimension  in the  expansion  range(where  you  have  SELF,DEP etc)
    2)for  the report  part....use  getonlyrange    to  have it  pulled  from the  DB  instead  of  user  entering data...
    go to helpsite   for the  exact  usage  of NOEXPAND  and GetOnlyRange..play  around enough...i'm sure  you'll figure  it  out!!!!
    hope  it  helps....

  • How can BPC display the property in report input schedule

    When create a property, if the InApp is check, we can use the property in the MDX Query, however what is the best way to display the property in report and input schedule?
    Although we can use the EvPRO function, but according the definition of EvPRO
    "The EvPRO (Property value) function returns the value of a specified property for a specified member."
    for example =EVPRO("Finance","Sales","Currency") will returns USD, if the currency value for the member Sales is U.S. dollars., if I have a property group for account dimension, how could I display the value of group for all the account number?

    Hi
    you just use EVPRO like you mentioned:
    =EVPRO(Finance,$D20,group)
    In the cell $D20 your account number is displayed. You copy this function down for each account.
    -> just create an input schedule or report from a template, open the configuration panel. There you see this principle used for property High Level, Calc, ...
    D
    this method is perfect but you need to add the formula each time.
    I would prefer to use the formula using the after or before range in expansion options of evdre which would make it dynamic and you need not copy paste the formula to derive the property each time.
    Cheers
    Thanks and Regards
    Harish B K

  • BPC 7.5 Input Schedule in Excel 2010 - Expand time dimension dynamically

    Hi BPC experts,
    My project dimension has two properties, one for startdate and one for enddate of the underlying project. Example: Project XYZ, startdate: 2010.APR, enddate: 2011.JUN
    In my input schedule I need the timespan to expand on month level from 2010.APR up until 2011.JUN. In this case it needs to expand 15 months where each month is displayed per column.
    The issue is that all projects have different start and end dates and the expansion on month level needs to adjust accordingly. There is no maximum project time frame but if it helps I can live with a maximum expansion of for instance max 100 months.
    I have another dimension for time with a hierarchy year - quarter - month (month being the basemember).
    Every tipp highly appreciate!
    Regards
    Sven

    Hi,
    1) i use EvMBR for list values the CEBE necesaries.
    2) Define ListBox by source list the EvMBR
    Is necesary use Index() for get value the indice returned by Listbox when is selected the value.
    3) Use EvGTS() linked to value getting by Index()
    4) This is code in EvGTS:
    =SI(EVGTS($N$11;1;"CEBE:CI1CA001";$N$14;"CUENTA:ZACB0001";$N$16;I28;"MONEDA_PPTO:USD";"PARAMETRO:NA";$N$20;$N$21;"SUCURSALES:NA";$M$27;$N$24)="#NODATA";"";EVGTS($N$11;1;"CEBE:CI1CA001";$N$14;"CUENTA:ZACB0001";$N$16;I28;"MONEDA_PPTO:USD";"PARAMETRO:NA";$N$20;$N$21;"SUCURSALES:NA";$M$27;$N$24))

  • BPC 10.0 Input Schedule refresh : investigating performance issues on frontend side

    Hello,
    We are running SAP BPC NW 10.0 SPS8.
    We recieve a lot of complaints regarding performance issues.
    More specifically BPC Input Schedule refresh takes ages (11 minutes actually)
    I am a SAP Basis Administartor with some solid BW experience, but very linited BPC knowledge.
    So raf we have tried the following :
    * BPC Full and light ptmimize of the BPC Cubes.
    * Updating Oracle Statistics
    * Activating ABAP/SQL traces*
    * Checking USJTAT Logs
    Then it rutned out that the perfromance problems werre not caused by the backend SAP BW server (only 9 seconds of bakend  processing are displayed in UJSTAT).
    The overwhelming majority of the processing is spent on the frontend side : on the computer of the user.
    We really would like to know what is happening on BPC Frontend side, but are really lacking any investigative method .....
    other that  checking memory/CPU usage o nthe frontend computer.
    From your experience, is there any tool/method to allow to conduct some investigation on what is going on the frontend side, when a BPC Input Schedule is refreshed ?
    Thank you for your attention.

    Hello Vadim,
    We still need to get confirmation from the external consultants who developed the BPC solution, but as far as I can understand it :
    We do not use use member formulas
    We are indeed talking about EPM (without EPMRetrieveData functions)
    The perfromance  problems occur in DEV and QAS , after a restore of the BPC environment (backup from PRD)
    We already had the problem in the past, but we never knew precisely how to solve it, it is as if there was some missing links between the restored BPC environment from PRD and the DEV/QAS system
    One additional information, we checked the EPM CLient Log , and here are the errors displayed while refreshing the input schedule :
    The thing is that I have no idea what it means ...
    ?FILE_TYPE:DAAA96DE-B0FB-4c6e-AF7B-A445F5BF9BE2
    RECORD_SEPARATOR:35
    COLUMN_SEPARATOR:124
    COLUMNS:Time|Severity|Category|Method|User|DSRRootContextID|DSRTransactionID|DSRConnectionID|DSRCounter|Thread|Text
    SEVERITY_MAP:DEBUG|Debug|INFO|Information|VERBOSE|Verbose|WARNING|Warning|ERROR|Error|FATAL|Fatal
    HEADER_END
    2014-04-18 08:41:17,446|ERROR|ReportManagement|FPMXLClient.Office.EPMExcelReportManagerRepository.GetReportManager|BPCUSER|||||1|Unable to get the Object property of the OLEObject class#
    2014-04-18 08:41:18,613|ERROR|ReportManagement|FPMXLClient.Office.EPMExcelReportManagerRepository.GetReportManager|BPCUSER|||||1|Unable to get the Object property of the OLEObject class#
    2014-04-18 08:41:18,630|ERROR|ReportManagement|FPMXLClient.Office.EPMExcelReportManagerRepository.GetReportManager|BPCUSER|||||1|Unable to get the Object property of the OLEObject class#
    2014-04-18 08:41:18,648|ERROR|ReportManagement|FPMXLClient.Office.EPMExcelReportManagerRepository.GetReportManager|BPCUSER|||||1|Unable to get the Object property of the OLEObject class#
    2014-04-18 08:41:18,731|ERROR|ReportManagement|FPMXLClient.Office.EPMExcelReportManagerRepository.GetReportManager|BPCUSER|||||1|Unable to get the Object property of the OLEObject class#
    2014-04-18 08:41:37,171|ERROR|ReportManagement|FPMXLClient.ReportManagement.DynamicReport.Load|BPCUSER|||||1|bytes = 1#
    2014-04-18 08:41:39,348|ERROR|ReportManagement|FPMXLClient.ReportManagement.DynamicReport.Load|BPCUSER|||||1|bytes = 0#
    2014-04-18 08:41:39,474|ERROR|ReportManagement|FPMXLClient.ReportManagement.DynamicReport.Load|BPCUSER|||||1|bytes = 0#
    2014-04-18 08:41:39,536|ERROR|ReportManagement|FPMXLClient.ReportManagement.DynamicReport.Load|BPCUSER|||||1|bytes = 0#
    2014-04-18 08:41:39,597|ERROR|ReportManagement|FPMXLClient.ReportManagement.DynamicReport.Load|BPCUSER|||||1|bytes = 0#
    2014-04-18 09:00:22,088|ERROR|Dataservice|FPMXLClient.BPCProxy.MetaData_Data.DataServiceHelper.ExecuteReportAsStream|BPCUSER|||||ServerCallThread_666f378d-d824-4a8a-bf38-0da8493e2382|An error has occured on the server#
    2014-04-18 09:00:22,252|ERROR|BPC10Connection|FPMXLClient.Connection.RESTConnection.ExecuteReport|BPCUSER|||||ServerCallThread_666f378d-d824-4a8a-bf38-0da8493e2382|An error has occured on the server#
    2014-04-18 09:00:22,268|ERROR|OfficeWrappers|FPMXLClient.Office.EPMReportManager.ExecuteReport|BPCUSER|||||1|An error has occured on the server#
    2014-04-18 09:00:22,317|ERROR|OfficeWrappers|FPMXLClient.Office.EPMExcelReportManager.RefreshReports|BPCUSER|||||1|An error has occured on the server#
    2014-04-18 09:00:22,447|ERROR|AnalyzerOne|FPMXLClient.AddIn.RefreshSheetWithScan|BPCUSER|||||1|Execution of Report Default Report failed : #
    2014-04-18 09:00:22,537|ERROR|Automation|FPMXLClient.EPMAddInAutomation.RefreshActiveSheet|BPCUSER|||||1|Execution of Report Default Report failed : #

  • Update microsoft word report from bpc excel report.

    Hi experts,
    I'm using BPC 7.5 microsoft version.
    I have an assingment to do. I have a excel report (EVDRE) and I would like to link this report to microsoft word file. So when I change POV of my excel report, my word file should be change when open it. How can I do this?
    Thanks!

    Hi sushant,
    I have an excel report located inside bpc server. To access to this file I have to log in BPC Excel Addin --> Open Dynamic Templates --> Company --> eExcel --> Reports--> Mydocument.xlt
    My requeriment is that: when "Mydocument" was updated (for example with another Point of view), I would like to open a word document and see Mydocument Updated.
    I would like save this word inside BPC server (log in on BPC for Word and inside of "Open Dynamic Documents")
    How can I achieve this? I think that EvHot is to use in excel...but I want to update on word.
    Thanks!

  • Error in BPC Excel report

    Hello Experts,
    I am useing BPC 5.0,
    I am trying to create a EvDRE Grid report (Drag & Drop report in BPC Excel)
    I am Faceing an error as "EVDRE encountered an Error reteiveing data from the Web server".
    Thanks a lot for help.
    Cheers,

    Hi
    refer the pdf at Page 19 , may get somme help
    https://www.sdn.sap.com/irj/scn/go/portal/prtroot/docs/library/uuid/9016a6b9-3309-2b10-2d91-8233450139c1
    Regards
    Abhishek

  • Displaying current work status in BPC Excel report

    Hi All,
    Could any of you tell me how do we retrive the current work status that has been set for a particular application on to a Excel?
    We would get this in BPC WEB reports, but we are lookin gto display it in excel itself.
    Does EVLCk function have any link with this?
    can any one share the details of list of EV functions that can be used in BPC 7.0.
    Regards,
    Swetha

    Hi Swetha-
    SAP Note 1348997 "BPC NW 7.0 SP03 Work Status Explanation" provides a detailed PowerPoint deck that explains the specifics around Work Status.  Please note slide #39 and the mention of EVLCK.
    A few additional notes that may be of interest:
    EVLCK became available to SAP BPC 70 NetWeaver with SP02 (pls review SAP note 1310443, as well as the "BPC 7.0 SP03 NW Documentation Updates" in Note 1349538).
    Regards,
    Sheldon

  • BPC Excel Reporting

    Hi all,
    I want to plan for 2010 comparing 2009 actual.  My understanding is using evdre function.
    1.  So 2009.MONTHs ACTUAL vs 2010.MONTHs PLAN
    2. As 2009 data is actual, it would be brought from BW so the datasrc would be UPLOADED DATA. Whereas 2010 plan would be manual planning (datasrc u2013 MANUAL).
    How to integrate both?
    Thanks
    BSV

    Hi Bharath,
    You can have Datasource included in your expansion. For example, if you want compare 2009.MONTHs, UPLOAD with 2010.MONTHs, MANUAL what can be done is to have COL expansion for Time, Datasrc. Specify Memberset for Time as BAS(2009.TOTAL),BAS(2010.TOTAL) and for DataSrc as UPLOAD.
    Expand and then manually change the DataSrc for 2010.MONTHs as MANUAL. After this make the evdre static.
    Hope this helps.
    Regards,
    Shoba

  • BPC Input Schedule: DELETE button erase background color

    Hi,
    Can anyone help on the following problem:
    I have an input schedule (either with nested rows or simple) and BPC by default marks all changed cells with red color. But when [DEL] button key is pressed in a cell all other marked cells on the same row loses their red color and became white again. It's undesirable behavior.
    I've searched the forum and internet but nowhere this topic arise, maybe i'm doing something wrong. The one idea is to write a VBA macros which automatically recognize modified cells and then restores their previous backgrounds. Is there another solution?
    Thank you!
    Ivan

    Hi,
    When you create a report/input schedule using standard formating option system will generate with [multiple format|http://help.sap.com/saphelp_bpc75_nw/helpdata/en/87/2e5940a305405f957eb987daf30d5b/content.htm] .When you change the value it will turn to Red beacuse it defined under format range with criteria CHANGED and format with Red color. But system will not recognise DELETE as change. That is why if you want to delete a specific value you should make that value as 0 then only system will consider that as change other wise system would prompt you a message "There is no data to refresh".
    I think you have to write your own macro if you really want to use DELETE function,instead of zerorise the values.
    hope it helps...
    regards,
    Raju

  • How to reduce the size of Input Schedule (Excel Template)

    Hi,
    I am preparing Static Input Schedule (Due to complexity, I am unable to use EvDRE). Due to many EvSND's and Formulas used in the template, the file size is almost more than 10 MB.
    So it takes a lot of time while opening the template. So is there any way to reduce the size of the excel file (Input Schedule template).

    Here are some suggestions on ways to reduce the size of your static input template, which sounds to be rather large.  Please note that these suggestions are not in any order with regards to being the most effective in reducing the template, but overall should help in reducing the size.
    -  Make the EvSNDS as dynamic as possible.  Even though it is a static template, try not to use an EvSND formula which contains a reference to each dimension you are loading to.  I'm not sure how many dimensions you have in you application, but if you are referencing 12 dimensions in each EvSND, and you have thousands of EvSNDS, that takes alot of size.  So, if you are doing this, see if there is any commonality with any dimension with the input schedule and hardcode that dimension's member in the control panel.  For example, if all the evsnds are going to the same Category (i.e. BUDGET), you do not need to reference the cell with memberid BUDGET in each evsnd cell, but instead be sure it is set in the Control Panel of the Template correctly.
    - Only have base level members in the input template.  Many input templates are built so that after the data is sent, the summary level (or parent level members), are retrieved in the template so users can see summarized results after a send.  If possible, build the report with base level members only, and build a report to view summarized report.
    - Keep the number of Woksheets in the template to a minimum.
    - Make the layout of the report as simple as possible.  Try to keep the Conditional Formatting to a minimum.
    - With regards to the formulas in the template which you mention, I'm not sure if you are referring to Excel calculation formulas, or something else, however you do want to keep the use of formulas to a minimum.
    I hope this information helps.

  • Performance testing of Input schedule and report

    Hi All,
    We are checking the time taken for a template to expand and refresh,
    In a scenario, a report with 18000 rows expanded in 80 seconds,
    But in BW backend system it shows,
    SQE Query read: 5 seconds
    It means remaining 75 seconds are required for front end, Is it possible to split up this time like where it takes more time.
    Thanks & Regards,
    Ramanathan

    Hi,
    Dynamic EvDre with formating on degrades  report / input schedule performance.
    Please check whether your input schedule with formating or not?
    Thanks,
    Raju

  • Moving a template or input schedule from one environment to another in MS

    Hi team,
    Can anyone let me know how does any template or input schedule is moved from one environment to another in MS version?
    Please give me steps.. Appreciate your great help....
    Thanks,
    Chandrakanth.K

    Hi Chandrakanth,
    if you want only the template the easiest is just copy the xlt file from the same folder from one server to the other.
    If you want to copy all the environment (even data) you can use backup and restore from the server manager (appset\server backup save the zip file on the destination environment and restore it).
    From the BPC MS 7.5 SP06 and 10.0 SP01 even the SAP Enhanced Change and Transport System (CTS+) is enabled, for this please see http://www.sdn.sap.com/irj/scn/weblogs?blog=/pub/wlg/25924
    Kind regards
    Roberto

  • How to kill/stop a report from InfoView/CMC ?

    Hi All,
    I have CRS2008 v1 environment running reports against Sybase database. Users run reports from Infoview. I would like to know what the best way to kill or stop a report that has been triggered from Infoview? Kill the spid from sybase or is there a way to kill it from Crystal?
    Thanks
    Ajith

    I want to kill reports run by users if they affect the system performance due to large volume. In that case the stored procedure that the report uses to select data might run for longer periods and I want to able to kill that process. So the question is which is better ?
    1. Kill the spid for that report stored procedure in Sybase
    2. Stop/delete the report instance from crystal if it is possible.

  • BPC for Excel Input Schedules

    Hi
    With Input Schedules in BPC for Excel, is there an easy way to see which cells get uploaded ?, for example, if I open a report written by another person, how can I easily see which cells get upload when MNU_ESUBMIT_REFRESH runs ?.
    Thanks in advance for your help.
    Kind Regards
    Gavin

    HI,
       There is no specific way (something like a menu command). You can define a specific colors or format for the cells(or some formulas which change the format of the cell), but this is related to the input schedule design.
    Best regards,
    Mihaela

Maybe you are looking for

  • Automatic creation of PO's from Requisitions

    Hi I'm trying to get a grasp of what's needed to automatically create approved PO's upon approval of a requisition. There seems to be two ways to do it, a release program under a Contract Agreement, or using workflow with a Global BPA. Under either m

  • Erorr in JDBC Receiver Adapter ..

    Hi All, I am getting error in jdbc receiver adpt. I am using SQL Server 2000. My input file is .. <?xml version="1.0" encoding="UTF-8" ?> <ns6:MT_SALETARGET_REQ xmlns:ns6="urn:ters.com"> - <STATEMENT> -  <TABLENAME ACTION="SELECT">    <TABLE>Saletarg

  • Mybt history disappeared, duplicate profiles and a...

    Anyone else having problems with their account holder status. got in touch with online chat more than 2 weeks ago, no longer the primary account after hours trying to fix another problem with my account. Pin doesn't work, spent another hour trying to

  • Problem in consignment fill up

    in consignment fillup will i do PGI or not.....

  • Redirect to another page and set the error or success message from process

    I have a process that runs when a page is submitted. In the process I am catching an exception and if an exception occurs I want to redirect to a different page and display the error message of the exception. How can this be done? Below is my code. T