Mark confirmation warning as error at plant level

Hi,
Its a business requirement that when carrying out confirmation of production orders, over and underdelivery tolerance as specified in material master should be enforced. This can be done using transaction OPK4, selecting the plant and order type and setting the check for the appropriate message to error instead of warning. However, this has to be done for each and every order type within a plant. Is it possible to apply this at the plant level, i.e. flag the warning as an error for all order types within the plant at one go? Help is appreciated.
Regards
Edited by: Khan Awkhan on Oct 15, 2009 10:00 AM

Khan,
As you rightly saw, this is only possible for a Plant/Order Type combination(OPK4). There is no other option available to just define it a plant level and apply to all order types within the Plant.
Regards,
Prasobh

Similar Messages

  • Error in confirmation of Transfer orders at Header level (TC LRF2)

    Hello All,
    A transfer order has single item.  It has got confirmed at the item level for the full quantity.  The confirmation switchbox at item level is checked in by the system automatically.  But in header level the switch box is not checked in.
    While trying to confirm the Transfer order at header level, the error message shows that the Transfer order is already confirmed.  But the Transfer order still exists in LRF2.
    Thanks in Advance.
    Regards,
    Sasi.

    Hi Marcos
    Note 566995 is an old correction note, which is probably already implemented on your system but it describes the standard system design regarding confirmations posted in mass processing transactions:
    When you enter an operation confirmation via the order info system or the mass processing the system now sets the confirmation type to 'Automatic final confirmation' as well as the indicator 'Post open reservations'. Thus the system automatically generates a final confirmation when you confirm the whole planned quantity and the operation receives status CNF (finally confirmed) instead of PCNF (partially confirmed).
    System is designed that way because a mass processing transaction will be generally executed in background mode and a huge number of confirmations can be posted at the same time. Therefore, user will not be able to enter any value to the confirmation.
    If you don't want this behaviour you could use the BAPI
    BAPI_PRODORDCONF_CREATE_HDR to develop your own mass processing transaction to post confirmations.
    BR
    Caetano

  • System Warning and Error Messages in Plant Maintenance

    Hi All,
    Where can I find the list of system warning and error messages for Plant Maintenance?
    Thanks
    Andrew

    Hi,
    Follow the following path in SPRO. Some of the standard messages you will fond there:
    Plant Maint & Customer Serivces - Maintenanace & Service Processing - Maint. & Service Orders - Message Control.
    SM

  • Classification at Plant Level

    Hy,
    I want to make some restriction in Bacth Classification, but this is only for some selected Plants only.So is it possible to restrict the classification at plant level insted of client level?
    Recently I have read about Class type 022 (batch Class)which seems to be Plant level, but when I am going to create new Batch Class with this 022 Class type , system throws an error
    "Internal class type 022 cannot be used in class maintenance
    Message no. CL089"
    Pls Guide,
    Dhaval

    Hy,
    My requirement is,
    We have just started Batch Determination strategy, for which we have marked one characterstic as a Entry required.So that user gets an massage at the time of GR if he fails to maintain the value of characterstic in Bacth Classification.
    Now situation is this,
    We are plan to convert that warning massage in to Error but, problem is that it refelcts in all the other plants, where there is no such kind of reuirement and Batch class is commonly for all the plants.
    Thats why I am thinks about Classification at Plant level.I know it is now too dificule or almost imposible to change the whole data, but we can plan better for our upcoming Manufactring Plants where system is still not implimented.
    Thanks for all of your kind guidence.
    Dhaval

  • Info record mandatory at plant level

    We want to restrict info record mandatory at a plant level out of many plants.
      i could make it mandatory and price not editable in the po, but while creating sched agreement it does allow the changing the prices.
    Pl help.
    Haresh

    Hi,
    Either goto spro>MM>Procurement>Environment Data>Define attributes of system messages and make 06/341 as Error or Warning, as required.
    Or
    Make source list mandatory in material master.
    Or
    Source List mandatory at plant in Source List config.
    Or
    Remove the pricing condition PBXX from your prcing that means you will have only PB00 (Gross price) condition in your PO which is determine the gross price from Info or contract or SA or RFQ but can't allow user to enter the price at PO level w/o any source document
    Or
    Customer exit MM06E005-EXIT_SAPMM06E_012
    Regards,
    Ashish.

  • Availability check at plant level

    dear all,
    my issue is
    i maintain two storage location for raw material say 1 and 2. material is transported from 1 to 2 by 311 Mvt. as 2 is storage at shop floor.
    production storage location maintain in MRP-2 view of this material master  is 2 .
    our client require that while release of process order for its header material system should not give material shortage error .system should check availability of material in production storage location 2.
    on not finding sufficiet quatity in 2 it should check for storage location 1, and on finding sufficient qty to fill the remaining requirement shuld not give error of missing part.
    to check material availability at plant level i ticked the indicator-"No storage location Inspection" in OPJJ config. setting.
    on this config. change also, while releasing the process order system automatically pick storage location 2(production storage location maintain in material master) on checking the mateial page assigned for this order and give missing part on check availability.
    some of our raw material are active for batch management.
    here also on releasing order of there header material system assign production storage location 2 to that raw material assigned to that order and searh batch only in storage location 2. and on not finding any stock in storage loc. 2 give message insufficient batch assignment and not check the stock in stor. loc. even it available in 1.
    kindly explain ...what may be the reason,
    even on checking availability at plant level its not considering all the storage location assigned to that materila for this plant.
    thanks and regards.

    Dear,
    In MRP2 view you need to maintain the second storage location i;e production storage laoction from which you are taking batches for production. So it will get copied to the component details of order.
    When you will do the batch determination at that time system will select the batches as per availibility.
    So in your case you need to do the batch determination agian after the store persone transfer the material to the production storage loaction then system will take all batches available in the production storage location.
    Stock determination enables you to implement various strategies to withdraw material for goods issues and stock transfers. You configure these strategies in Customizing. Based on the material requirements entered, the R/3 system determines how and when the material should be withdrawn, and from which storage locations and stocks.
    Create sort sequence with ascending order
    Then create batch search strategy in MBC1 or COB1 transaction
    Give the sort rule there
    Give the no. of batch splits as much as you want or just keep 999
    Then try doing the batch determination & check if you are getting what you want
    If you don't use the Batch entry as 3 then COR6N you can determine batches here then it will get copied to order after confirmation.
    Revert if you want further clarifications
    Hope clear to you.
    Regards,
    R.Brahmankar

  • PO workflow - escalator at plant level

    Hi SAP people,
    do you know if it is possible to set the time for workflow escalator at plant level?
    I have implemented the PO approval flow but i want to define 2 different escalator...
    Thanks in advance
    Michela

    Hi,
    Either goto spro>MM>Procurement>Environment Data>Define attributes of system messages and make 06/341 as Error or Warning, as required.
    Or
    Make source list mandatory in material master.
    Or
    Source List mandatory at plant in Source List config.
    Or
    Remove the pricing condition PBXX from your prcing that means you will have only PB00 (Gross price) condition in your PO which is determine the gross price from Info or contract or SA or RFQ but can't allow user to enter the price at PO level w/o any source document
    Or
    Customer exit MM06E005-EXIT_SAPMM06E_012
    Regards,
    Ashish.

  • Message settings at Plant Level - reg

    Hi,
    Is it possible to set a message at Plant level. Means for one plant it should be an error message whereas for a different plant belonging to the same company it should be a warning message.
    If yes, please help us with the prerequisites and the configuration path to accompany this functionality.
    Regards,
    RitiG

    Hi
    I dont think this can be acheived directly using SAP standard customizing.
    But based on the application we can use certain user exits & change the Error & warning message determination.
    Thanks & Regards
    Kishore

  • Batch Management @ Plant level in ECC 6.0

    Hi,
        I want activate the Batch Management @ Plant level in ECC 6.0 and when select the Plant level and save it , i am getting the information error like " THIS Type of conversion is not Yet Activated" .
    So i needs to activat @ plant level , what i needs to do for further.........
    Thanks & Regards

    Defining Batch Level
    Use
    This transaction enables you to set the batch level for batch management. Three unique options for a material are available:
    u2022     At plant level
    u2022     At material level
    u2022     At client level
    Prerequisites
    If the material or client level for a material is chosen, check that no materials exist in stock. If a material exists in stock, the level may not be changeable.
    IMG Menu     Logistics - General >  Batch Management > Specify Batch Level and Activate Status Management
    Transaction Cod >> OMCE

  • Error in operation level result recording

    Hi,
    I need held; result recording of inspection type =03 (operation level Quality inspection)
    A product manufacture via three operations (10, 20, 30)
    All operation quality inspection active let operation no-10, all products reject and confirm as rework.
    Next operation level quality record is done but confirmation not allow Reason is operation -10, rework quantity, (Actual quantity is more than planned quantity)
    How to add the quantity after reworks for next operation quality inspection?
    Pl helps me finding the solution.

    Hi,
    As per your more clearence , As per Example  production order Quanity =1, passes 3 operation10,20,30
    Operation=10 require rework as per quality ,
    Operation =20 system raise the error message = Operation =10 rework .
    If want to operation =10 ok Quantity =1 then system raise error messges =Actual quanity more than planned Quanitity
    ( 1 Rework + 1 Ok ) .
    Supose rework order create and confirm then next 20 & 30 operation how complete .
    Real scenerio :- Rework on operation =10 then again Quality check then goes to 20 operation Quality check pass / Rework if rework then again quality pass then goes to next operation level
    I hope under stand my problem
    Need help- please

  • Error in MB31 level

    hi everybody
    i have an error at MB31 level
    This particular error occured while doing MTO scenario, system says "GR quantity is greater than Confirmed quantity for the last transaction" though i gave the lesser quantiy also system shows the same error, can anyone help in this regard
    thanks for all

    Check your production order (CO02, CO03), click on the blue status icon "i" to see the status and if it's TECOed. Only if the necessay confirmations have been done, can receipt be carried out.

  • How to assign sampling procedure at plant level.

    Hi Team,
    Pls suggest me "How to assign sampling procedure at plant level."
    Error message is  -  You can not use sampling procedure here.
    Not all sampling procedures can be used in this context.
    Example:
    Only the sampling procedures for an attributive inspection based on the
    number of nonconforming units are allowed.
    However I have assigned 0.05% sampling procedure in IDES system plant, which is accepted. However I am not allowed to assign this in client system..
    Pls suggest me solution.
    Thanks

    Hi,
       During creation of inspection plan you can assign SP at plant level, IP always at plant level
    Q.Error message is - You can not use sampling procedure here.
    ---> pl check the MIC where Sampling procedure in clicked or not
           pl revert
    Cheers,

  • Message CO347, warning to error

    Hi Experts,
    Where we can change message CO347 from warning to error.  I checked in OPJB but did not find.  The message is there in SE91 transaction. 
    Pl help me to change this message.
    Thanks & Regards,
    Vikas

    Vikas,
    Not all messages are allowed to be converted to the way we require. In this case, i would suggest you define for system Status "PCNF", Business transaction  "Deletion Flag setting" - Forbidden, this has to be done in transaction BS22. Please note this is at client level so other applications which are using this status also would have the same effect(Like PP-PI).
    OR
    Use Enhancement "PPCO0002" - user exit "EXIT_SAPLCORE_001" or "EXIT_SAPLCORO_001" - Here you use your code to check the condition you want.
    Regards,
    Prasobh
    Edited by: Prasobh Karunakaran on Sep 7, 2009 1:14 PM- Additional data on CMOD added

  • Error:ID=2011;LEVEL=1] InhouseDocReader doSyntaxCheck() offset[239]

    Dear SAP experts,
    I am getting this error in my File Sender Communication Channel,
    Error: javax.resource.ResourceException: --- Conversion of synchronous request from module chain ended with errors ---[Error:ID=2011;LEVEL=1] InhouseDocReader doSyntaxCheck() offset[239]: message structure error : segment CTA is not on the right position. DESCRIPTION: InhouseDocReader Warning: A Segment whitch does not match with the inputstructure was found during the syntax check and no other segment with a small error was found.
    The message is a D96A_SLSRPT edifact message.
    Are there any error in the message structure?
    Kindly advise.
    Fred

    Hi Fred,
    I refered your problem in the sites,as i got this answer:
    Read it,may it helps you to solve the problem
    although the SAP note tells that you only need to install the plugin till R3 4.6 you must install it for a 4.7 R3 as well.
    It is only automatically available with WebAs 6.40 R/3 systems.
    We had the same problem with our 4.7 R3 but after installing the WP-PI 6.00 everything worked fine.
    Be sure that users which should have access later to the UWL have sufficient backend rights. There are several RFC rights they need to have. (e.g. RFC rights for function groups SYST and SWK1)
    Reward points if this helps
    Regards
    Vani.

  • MM01 material copy from at plant levele

    Hi,
    I have a simple but very important question to ask about MM01 material "copy from" function.
    When you copy a material at an organisational level other than general data (at plant level for exemple), SAP copies some data and left some others blank
    For exemple, in "Work Scheduling" material views, it copies "Prod.Sched.Profile" data but not "Unit of issue" nor "Prod.stor.loc."  data.
    What make the difference between these data ? Why all isn't copied ?
    Thanks for help
    regards
    Morgan

    storage locations are plant specific customizing.
    SAP cannot assume that the second plant would use the same keys like the first plant.
    If SAP would copy the storage location, then it would result in an error if it is not customized for the target plant - better not to copy it.

Maybe you are looking for

  • Access wireless set-up program for HP 3050 printer

    I'm trying to connect an HP Deskjet 3050 J610 printer to my wireless network.  It's an older model so the CD that came with it is not compatible with OS X 10.9.1, but the printer driver is already loaded in the operating system.  So I'm able to print

  • Droplet for animated giff in Photoshop?

    Is it possible to set up a Droplet for Photoshop that could receive multiple files and export them out as one animated gif? I am trying to place three files into a Droplet I have made for Photoshop with the Actions set so that it converts them into a

  • HT201210 Having two iPhones on one account

    How can you whipe an old iTunes account for a different iPhone??

  • Display of Particular Purchase order not to be shown

    Dear Experts How to stop the display of for some particular  purchase order on the same user id. i want to restrict some user not to be display some specific Purchase order , condition is that we cant change doc type or also cant change purchasing gr

  • Migration Assistant hangs when transferring data from Windows 7 to mac

    My PC is a Windows 7 64 bit.  When I run Migration Assitant, I get as far as the screen that has my Windows Name and my Windows Account Name. Those are filled in automatically.  When I click "Continue", nothing happens. Any ideas?  Thanks.