MRP- md04

Hi Experts,
Material A was below its reorder point. MRP created a purchase req-ABC and latter converted to Purchase order-123xxx. Then I can see in MD04 that the Purchase Order-123xxx has an exception message 20 (cancel process). When the MRP background job run another purchase req was created because the stock is below the reorder point.
I am wondering why it creates another purchase req-DEF, MRP should still recognize the Purchase Order 123xxx. Therefore should not generates new PR.
How exception message generates? do you think it affects the MRP run?

You should chek if the receipt date for your PO covers your requirements. In many cases, SAP trigger an exception message for "manually" rescheduling some Elements (such as production Order or Purchase Order). If the Order is not rescheduled, the system suugest to cancel it and generates a new element (a planned order) with the "right" supply date and the proposal to reschedule. Let say:
Initial:
Today       Stock                           100
Today       Demand                       -400
Tomorrow  PO                              500            (must be rescheduledfor today)
After MRP Run
Today       Stock                           100
Today       Demand                       -400
Tomorrow  Planned Order               500           exception --> reschedule for today
Tomorrow  PO                              500            exception --> cancel process
Regards
Dario

Similar Messages

  • Scheduling agreement without usage in MRP / MD04

    Hello,
    i want to use a scheduling agreement which isn't relevant for MRP. I use the standard agreement type LPA (Scheduling Agreement). The storage location for this process is marked as u201Cstock excluded from MRPu201D and the Source list record is also not relevant to MRP. Although I set these parameters, the schedules appear in MD04.
    Is there any possibility like the requirement class in SD? In SD I can set the parameter "Transfer of requirements".
    Regards
    Andreas

    It wont be possible to exclude seperate document type from MRP.
    Excluding a Sloc wont work. MD04 list will show the Scheduling Agreement.
    You can use a Custom 'Z' Logic to supress the Scheduling agreement from MD04. the program can be written in ABAP Code.

  • MRP - MD04 table details

    Hi,
    We are in the process of configuring MRP system .  While doing so, the users are asking for a customised reqport which can throw the details of Planned order, customer order, qty required , No. of Purchase req. raised and PO raised and the status
    To meet this, we need to write a customised report . To do so, we need the table details where are all the data stored.  There are FM available which throws the latest one displayed in MD04 screen.
    We need the entire history and hence we need to understand the tables.  Request you to help us in identifying the physical tables where the data stored.
    M.Senthamil Selvan

    Try this BAPI :  BAPI_MATERIAL_MRP_LIST

  • Tables relevant to MRP, MD04  tcode and stock related tcodes

    Hello gurus,
                 table related to STOCK, MRP, AVAILAIBILYT CHECK AND TOR, MD04 Tcode
    Thanks in advance
    Sameer

    hi
    for stcok
    MARC, MARD,
    MSKA     Sales Order Stock
    MSKAH     Sales Order Stock: History
    for MRP
    MDIP     Material: MRP Profiles (Field Contents)               
    MDKP     Header Data for MRP Document               
    MDKPDB     Header Data for MRP Document               
    MDLG     Customizing: MRP Area Storage Location               
    MDLL     Customizing: MRP Area Subcontractor               
    MDLV     Customizing MRP Area               
    MDLW     Customizing: MRP Area Plants               
    MDMA     MRP Area for Material               
    availabilyt check
    TMVF     Availability Check Control
    TMVFP     Availability Check: Blocks
    TMVFT     Availability check control: Texts
    TMVFU     Scope of Availability Check (Default Values)
    TMW00     MRP Default Values per Material Type
    for MD04
    VBBE     Sales Requirements: Individual Records
    VBBS     Sales Requirement Totals Record
    UMD04     Default Values for Planning Table in Repetitive Mfg

  • MRP - MD04 and special stocks - how to manipulate exclusion in Avail.Stock

    Hello,
    I have the following question about the Avalable stock which appears in the MD04 trx. for a material in a Plant.
    This Stock Available normally includes stock "Unrestricted Use" and one can customize the inclusion of Blocked Stock, Restricted use Stock, and "Stock in transfer" in this Stock Available.
    My question is related to the other types of stock which appear in the MD04 as included in the Available Stock (Quality control, returns, Consignment, Valuated Stock at Vendor,etc.)
    Where can I manipulate theis inclusion or exclusion of these types of stock in the "Stock Available" in the MD04? Is this Config or do I have to activate a user exit?
    The stock Type "Material Packing - Lending" also can be excluded from the Available Stock in the MD04?
    Thanks for any reply,
    Aart

    Thanks for the replies,
    Maybe I did not state my question well:
    My Client uses "Stock in Consignment" and "Stock of Packaging in Lending"  (both in Unrestricted use) in a Plant.
    He does not want these stock types to play a part in MRP as available stock. In the MD04 trx. SAP estandard seems to include always in its Availbale stock these kinfd of stocks. Is there a way I can exclude them?
    Thanks for any replies,
    Aart

  • Log for schedule agreement  division created/modify/delete at MRP (MD04)

    Tables CDHDR and CDPOS were saved when the user changed data manually using the transaction ME31L and  ME32L.
    When the new schedule divisions  were create direct at MRP, the registries were not saved.
    I searched for any configuration to activated this registry though without succesfully.

    Transaction AUT10 display the execution process though it doesn't mention exact information was changed.
    Is there any configuration to change the behavior of this transaction or another transaction I could see the information was changed, deleted or inserted?

  • MRP MD04 - message 15 Postpone the process

    Hello Experts,
    In md04 it is falling into exception and postponing the planned lead time to  open sales order.... we want delivery date as per planned lead time ...i guess system is considering dependant requirements and pushing date to open sales order date
    But we want delivery date as per Planned lead time can anyone help me do the changes and resolve this please

    I have Ignored this warning and now process Chain is working fine.
    Thanks,
    Siva.

  • Open shipping notification in md04

    Dear Experts,
    Please suggest how we can handle the qty differences arising from the goods receipt or return delivery in case of using the goods receipt w.r.t inbound delivery in system.
    In MD04 the diffrential quantities are shown as open shipping notification, but our requirement is that the inbound delivery should have the status closed in case of partial GR or return delivery.
    In case of automotive goods receipt there is configuration for quantity difference profile, but for organization like us who are in manufacturing how to overcome the same.
    The main motto is that we do not want any open shipping notification in md04 how to achieve that.
    regards

    Hi
    There are no the standard ways to handle certain type of MRP elementt like the shipping notifications to be excluded unless you put them into a storage location excluded. (MRP indicator 1 in transaction MMSC).
    However, SAP delivered some BADIs to allow the customer write their own source code to control them, e.g. the BADI
    MD_CHANGE_MRP_DATA, it contains some methods below.
    CHANGE_MDPSX_MDBS     Change data when importing purchase order/ delivery sched.
    CHANGE_MDPSX_MDLA     Change data when importing shipping notification
    They are called in MRP/MD04 etc after reading the PO or shipping notifications then you can decide if they should be excluded or not by your own source code, please read the documentation of them in SE18 on how to implement.
    Leon
    Regards.

  • MD04 stock requirement

    Hi All,
    Im facing the following issue with the MRP - MD04.
    For a material I have and MRP Area and MRP Type PD "MRP". If I created a service order + sales order I cannot see the requirement on MD04 (like I spect to).
    Component material is with availability check 01 and on OVZ9, I completed the line with 01 and PM or SM. Inside OVZ9 I marked
    Incl.depen.reserva; Incl. planned orde and Incl. production order.
    So, someone knows what its missing ???
    Its possible to link in PM the checking rule to the order type ???
    Thanks,
    D

    Dear, In sale order - check the schedule line category in schedule line tab, is the schedule line category have req/Assembly tick in VOV6
    and also check the requirement type in procurement tab of sale order
    find the requiremnt class in OVZH  for the requiremnt type
    In OVZG fxheck the requirement class,  & is the requirement class have   tick in req. transfer?

  • MRP prompt cancellation for PR/PO due to demand changed

    Hi,
    I have many cases recently where my MRP ask me to purchase parts via Purchase Order. I have complete and firmed my purchase order. But the next day, i found that the MRP ask me to delete this order as there is no more demand required.
    Understand that there must be someone removed the requirement for the top parts and caused all components and raw material are now request to cancelled.
    Questions: In SAP, is there any way that we can know from MRP (MD04/MD05), which requirement is being removed and caused all this cancellation?
    What i can see now is that the MRP ask me to cancel the PO. But i do not know why this is being cancelled..
    Appreciated your prompt reply.. Thanks..

    I don't get your questio clearly.....
    But as per my understaing of your que
    The PR generated from MRP or Manual creation-- when you convert the PR to PO system will pickup the price from inforecord and info record can not be created automaticaly by the system for psicing
    the inforecord will be cretaed first time when you create the PO from PR but it will not have pricing it is just updating the PO number in the info record
    so you have to create the info record.
    now suppose you want to copy the PR price to the PO than there is a funcitonlaity you have to activate
    tcode is OMET
    go here and check the adopt price check box than system will populate the button in the PR on valuation tab where you can select as gross price or net price than system will take this price in the Po.
    in you case if suppose system is copying the last PO price to new Po becuse in your system the setting for defualt value for buyers is active that;s the reason you see that system copy the last po price.
    if you dont want this than go to
    SPRO-MM-Purchasing-environment data-defien defualt value for buyer
    here on Price adoption tab you will see always copy
    now if you dont want than copy the 01 to blank value and remove the always copy
    Now use of PR release is not for the pricing but there is many other reqs for release procedure
    noramly the PO would have release process activated if you have concern for pricing.
    hope this will give you a clear picture

  • Sales Order Stock in MD04

    Hi,
    I would like the sales order stock to be visable in the MRP/MD04, how to do that without including all other block stock?
    BR,
    Christian

    Hi Christian
    Sales order stock is always visible in MD04... Can you elaborate your requirement little more ?
    Regards
    Bala

  • After PO , PR again Generating through MRP.

    Hello To All.
    I have Problem that, We have done our PR from MRP (MD51).
    PO is Creating from that PR.
    But when we once again run the MRP, system again generating PR.
    Please reply.
    Regard,
    Riten Patewl

    Riten,
    MRP will review the entire supply/demand situation and will generate proposals (purchase requisitions in your case) based on the configuration you are using.  You have not given enough information to enable anyone to determine what is the problem.   According to the symptoms you are describing, If the Purchase req was converted in its entirety to a purchase order, including dates, then either the demand situation has changed, or you have a rescheduling horizon conflict that does not allow MRP to consider the newly created PO.  You can tell this by reviewing the exception messages.
    A couple of other thoughts that may also be contributing to the issue.  A common mistake that people make is that they believe that a Pur Req is deleted when converted to a Purchase order.  In most cases, the purchase req is not deleted, but is instead treated by MRP/MD04 as 'replaced' by the Purchase order.  In addition, it is also marked as 'fixed'.
    If you convert a PR to a PO, but not the entire quantity, the PR will still show on your MRP listings for the balance.  If you later delete the purchase order, then the original purchase req will reappear in the MRP listings, as 'fixed'.  If you create a Purchase order manually for the same quantity (not convert), then the purchase req will remain (but unfixed) until the next MRP run.
    Regards,
    DB49

  • Std Reports in MRP & SFC

    Hi,
    Could anyone provide me Std available SAP Reports in MRP & SFC
    Regards

    Dear Srividya,
    Enter the T code SAP1 only when you are in SAP easy access screen.when you are working with some other T code check
    with /osap1.
    Importatant reports for MRP
    MD04                 Display Stock/Requirements Situation
    MD05                 Individual Display Of MRP List
    MD06                 Collective Display Of MRP List
    MD07                 Current Material Overview
    MD08                 Reorg. MRP Lists
    MD09                 Pegging
    MD45                 MRP List Evaluation
    MD46                 Eval. MRP lists of MRP controller
    MD47                 Product Group Planning Evaluation
    MD48                 Cross-Plant Evaluation
    MD4C                 Multilevel Order Report
    MDLD                 Print MRP List
    SFC Reports
    MCP1                 SFIS: Operation Analysis Selection
    MCP3                 SFIS: Material Analysis Selection
    MCP5                 SFIS: Material Analysis Selection
    MCP6                 Goods rcpt analysis: repetitive mfg
    MCP7                 SFIS: Work Center Analysis Selection
    MCP8                 Goods rcpt analysis: repetitive mfg
    MCP9                 SFIS: Select Run Schedule
    MCPB                 Operation analysis: Dates
    MCPD                 Production order analysis: Dates
    MCPE_CUS             Commodity Pricing Customizing for MM
    MCPE_DOC             Commodity Pricing in MM Documents
    MCPE_FA_ACC_SEQ      Access Sequence for Formula Assembly
    MCPE_FA_COND_TYPE    Condition Types for Formula Assembly
    MCPE_FA_CT           Cond. Tables for Formula Assembly
    MCPE_FA_DET_PROC      Det. Procedure for Formula Assembly
    MCPE_FA_FC           MM Field Catalog
    MCPE_FA_GCM           Formula Master Data Maintenance
    MCPE_MD              Commodity Pricing Master Data for MM
    MCPE_WB              CPE Formula Workbench for MM
    MCPF                 Material analysis: Dates
    MCPH                 Work center analysis: Dates
    MCPK                 Operation analysis: Quantities
    MCPM                 Production order anal.: Quantities
    MCPO                 Material analysis: Quantities
    MCPQ                 Work center analysis: Quantities
    MCPS                 Operation analysis: Lead time
    check and revert.
    Regards
    S Mangalraj.

  • Subcontracting Material MRP.

    Hi friends,
    Here is my issue,
    We have a material 'A' which is a subcontracting material and its subrequired material is 'B'.
    when we run MRP (MD04) for the material 'A', here it generating the PR's as required. but when we run
    the same for material 'B' it is generating the Planned orders (pldOrd). but this material is not in-house
    produced one..
    Why it is generating the pldOrd for the material B
    Please explain why it is happening and how it should be corrected.
    Regards,
    Mohan.

    Hi,
    Check the below settings
    1. For Matrl A Ensure the MRP2 , Procurement key is F and spl.proc.key is 30
    2.For Matrl B ensure the MRP2 has the Proc key F if you are buying this product externally
    Hope you would have maintained BOM as Matrl A header and Matrl B as lower material
    3. If you need PR to be generated, Put MRP relevant indicator as '1' in source list by giving proper vendor
    4. If you need Sch lines to be created,enter the Sch.agrmnt # in the source list and give MRP relevant
    5.Run the MRP for Matrl A in MD03,give the below MRP Control Parameters
               Processing Key NETCH
               Create Pur req    1
               Delivery Sch       3
               Create MRP       1
               Planning mode   3
               Scheduling         2
    6.By this MRP run,the lower level material also will get run automatically.
    7. If not,run MD02 with the above MRP control parameters 1,3,1,3,2

  • MRP & schedule margin key issue

    Hi All,
    My client is running MRP on daily basis they have maintained schedule margin key 001 with opening period as 0010.but while running MRP & MD04 they
    found below are the issues.
    We have tested many times using SMK as 000 & 0010 but every time system displayed below errors.
    Some times they are not getting the purchase requisition created in time (System should drop the purchase Requisitions according to parameters maintained in material master).
    Some time system creates planned order instead of Purchase Requisition (Their requirement is to create purchase requisition always)
    They get the exception message past due planned order
    As per my understanding there will be problem in buffer period.How can we avoid these exception messages & how can we create always PR instead of pl order.
    I will appericate if anybody suggest me how can we rectify above mentioned causes.
    Thanks,
    Ravindra.

    Hi Caetano /Ram
    Thank you for replies.I have following doubts on your reply
    I understood if I create Variant including only PR system will display always PR in MD04.
    1.If I run MRP using option 2 PR in opening period in this case system behave like same or do I need to include this parameter in variant
    2.How can I avoid exception message"Past open due" for Ex :- 10,20,30 etc... permentaly in MRP run?
    I have not tested solution yet I hope if I create MRP group & during background MRP run if I create variant with parameter 1 (PR only) it will create PR.
    Can you pls assist on SMK? For your clarification check below is my actual scenario
    if I assigned SMK with 000 (All periods like opening period,FAP,FBP & release period is 000) then what happen in MRP run if I made your suggested setting is system means it will always create  PR.
    If I assigned SMK with 001(opening period 0010,FBP 5,FAP 2 ,release period =5) also
    if I maintained GR time= 2 days,
    Pl.delivery time =10 days  in this case will above setting  work? if i run MPR using opening Period as well as PR only.
    Kindly correct me if i am wrong.
    Thanks,
    Ravindra

Maybe you are looking for

  • Listing of Channels in a container

    I am having some truble and need some help... I want to make a JSPProvider channel that can display all of the channels that are located in another Container. For example I have a TableContainer that contains a JSP channel and another Table Container

  • The IP Routing Process for VLAN's?

    I have the CCNA Study Guide third edition. Chapter five, page 254 has a description of the ip routing process.  It descripes the ip routing process using two nodes on different subnets and a router. We've recently deployed VLAN's, so I'm asking if I

  • How to enable Ultra DMA Mode 6?

    I've a Seagate Barracuda 7200.7 Serial ATA HD. The highest mode I can achieve is Ultra ATA-100 (mode 5) and not the maximum support by Barracuda the Ultra ATA-133 (mode 6). How can I enable mode 6 in Windows XP?

  • Date to be setted as dynamic radiobutton

    Hi, In my requirement, I'm actually using the LDB's and getting a desired selection screen. But i need to addd one more field in the Sel. screen. ie., date. I want tht date to be setted as dynamic radiobutton . parameter for presentation server filen

  • I've created a movie but at the end there is an invisible audio clip that keeps playing. How can I select it and delete it?

    Hello everyone, This is Karie Garnier in British Columbia, Canada. I'm new to FCPX. I've created a 20 minute movie, but at the end of the movie, there is an invisible audio clip that keeps playing. How can a video clip be playing and making sounds, w