MS Project Resource question

Hello,
In MS Project i'd like to add resources to tasks, but this results in some problems
For example i have 1 person (Daan) scheduled on a task for 5%.
But i the resourcesheet MS project has scheduled him 40 hours a week for the first task.
Why does MS project schedule him for 40 hours in stead of the 2 hours a week (5%) i filled in?
With kind regards,
Erwin

Hi,
Which version of MS Project are you using? Is it connected to Project Server or standalone? Can you detail the exact sequence to reproduce the issue? Or screenshots?
Hope this helps,
Guillaume Rouyre, MBA, MCP, MCTS |

Similar Messages

  • Project Resource Calendars for onshore and offshore (different working hours)

    Advice please.
    As with many companies we use Project 2010 with onshore and offshore resources.
    Facts are as follows:
    Onshore resource – 09:00 – 17:00 – 35 hour week
    Offshore resource – 08:00 – 18:00 – 40 hour week
    These resources are in different time zones; however that element is not an issue.
    The problem seems to be with resource calendars.  Resource calendars are setup as per above and assigned to appropriate resources in EPM/Project Server 2010 - however could be local for same issue. 
    The problem is that work is reflected correctly in hours or days but not both.  
    So looking at Task usage table. 
    For example:
    Typing in hours for Onshore and Offshore resources on any task is correct. 
    So 7 for onshore and 9 for offshore.  However when you can the work view in options so that work is entered in days, its incorrect for offshore. 
    Same hours for both but incorrect days.  Basically the resource calendar does not seem to have an impact.
    The Plan default working times can be set to either schedule but either way one or the other type of resource is out.
    For instance :  Offshore resource 9 hours should equate to 1day. However it equates to 1.29 days. 
    Which would be correct if that resource was on an onshore cal.
    My assumption is as follows:
    Set the Project default hours to 08:00 – 18:00 – 9 hour days, 40 hour week.
    This allows offshore to work there hours as the project plan is effectively open for business.
    Onshore resources should then be restricted to their resource calendar meaning that they only work 7 hours per day regardless of the plan indicating 9 hour days.
    Hope that makes sense...
    Any thoughts would be much appreciated…..
    -CL.

    Hi,
    Everything you write is right, and your confusion only stems from the misunderstanding of how Project defined the "day" as a time unit.
    Matter of fact, Project uses for its calculations only ONE time unit which is the MINUTE.
    Of course, that implies the HOUR is a usable unit as well - an hour being 60 minutes isn't questioned by anyone.
    OTOH, your post illustrateds tha a definition for  day is not so obvious; Project's definition is that a day is always equal to an hour times the parameter "hours per day" in the options. So what a day is, is totally independent from any calendar, Project,
    Resource or Task calendar. Within that definition the values you see are "right".
    But the good news is that your other assumption,quote:
    Onshore resources should then be restricted to their resource calendar meaning that they only work 7 hours per day regardless of the plan indicating 9 hour days.
    That is true. Work is planned according to available working time in the appropriate calendar.
    My advice is to not use the day as planning unit in any view: the hour will better allow to understand how Project is planning the tasks.
    Greetings,

  • Project Management Question - timelines for Production system deployment

    Hi
    I need an expert advice on setting up timelines for establishing an Oracle Apps Production environment. We are implementing Oracle HR & Payroll at an organization.
    Our system architecture is a 2-node application tier and 2-node DB tier (RAC). RAC is configured by another party and we only have to prepare the application tier (2 nodes)
    We would be installing Oracle Apps R11i (11.5.10) with jserv load balancing on the 2-nodes
    Can anyone suggest how much time this should take to install/configure & patching of the application tier (on 2 nodes)?
    Regards
    Saira

    Duplicate post (check your other thread):
    Project Management Question - timelines for Production system deployment
    Re: Project Management Question - timelines for Production system deployment

  • Resource Assignment without Project Resource Management Module

    Hi Dina,
    We are implementing Oracle projects for one of our customers. The customer does not want to implement Project Resource Management module. Is it possible to assign resources to a project or create a new requirement using the Resources tab in Project screen (HTML page) without implementing the Project Resource Management module. Pls let us know.
    Regards,
    Sri
    Edited by: user12209290 on Nov 18, 2011 9:30 AM

    Hi
    With Project Management you can assign resources to the work plan. Resources might be named people or generic resource by job.
    You can track planned hours by resource versus actual time worked, You can look at roll-up of planned hours across multiple projects for the same resource, or summarization of planned and actual hours using the RBS.
    However, you will not get the functionality of demand published to resource managers, and the search functionality for available person to join the requiring project.
    Dina

  • Project Resource Management

    Given all of the Oracle Project solutions out there (EBS, Primavera, Fusion, PeopleSoft), which of these is the best choice for a company that would like to do resource allocation, forecasting, etc? (taking Oracle's longterm vision in this area into perspective)

    Hi
    The module Oracle Projects Resource Management deals only with human resources, employees, contingent workers, candidates.
    This module is integrated with Oracle HRMS.
    Dina

  • Project Billing Question

    Hi All,
    I have couple of Project billing questions. Hope you can help
    1)A wrong customer was attached to project billing agreement, funding and base line also completed for the customer.
    Now we realized that its wrong customer and want to change it to correct customer.
    What are the options we have here?
    Can we delete or end date the billing agreement?
    will the funding be release from the wrong customner after deleting or end dating the billing agreement?
    2) Wrong customer attached to a project..agreements,funding,baselining are NOT done.
    How can we delete this customer and add the correct customer?
    The option to change the customer is grayed out.
    Appreciate if you can help.
    Thanks

    Hi
    On your first question you said the agreement was created for wrong customer. Since you already baselined the funding, I assume you have that customer linked to the project.
    You can go the Agreement form and  enter a negative funding line allocated to the same project. The total allocated amount will be zero. The agreement is now not allocated and free to be allocated to another project. If it is a wrong agreement you may update the agreement amount to zero.  Now create a new agreement for the right customer.
    The open issue is with the project. You have a wrong customer associated with that project. However, system will not allow you to remove the customer - project record.  Solution depends on the way the project was setup. Did you enable customer at top task? if so, end date the top task and create an alternative top task with the right customer.
    If the project has been set with a single customer you better close the project and start a new one.
    However, if you need an alternative solution, I can suggest a custom method. Go to Help > ..> Examine and change the existing customer of the project to zero contribution.
    Now you will be able to add the right customer to the project and have 100% contribution on it.
    Dina

  • Project Resource Cost

    We are not implementing Project Resource Management here.
    What are the possible ways to enter the Cost incurred on an Employee (Salary) against the Project.
    This cost has to be there on projects subledger as it will be considered to calculate the Project Revenue & Invoice using Cost/Cost Dist. Rule.

    You don't need project resource management for this.
    There are two ways to use the employee salary as project cost: -
    1. You can use the organization rate schedule and enter employee/resource payroll/salary rates.
    2. using labor costing extension, you will be able to pick up the payroll salary information from employee assignment element entry.

  • C- project certification question and material

    Hi Gurus,
    I want to know is there any cretification for  SAP C- Projects  could you please let me if any one has SAP done c-project certification questions, or any relevant sites wherein I can get the same.
    Thanks in advance for your help,
    Thanks
    Ashish

    Hi Ashish,
    cProjects being a part of the PLM package, you would need to undergo SAP PLM certification. As per my knowledge, there is no separate cProjects suite certification available.
    However, there are training programs conducted by SAP for cProjects and xRPM. You may get the details regarding these from the marketplace. Please refer https://websmp101.sap-ag.de/partnerportal/apj/home
    Let me know if this helps.
    Regards,
    Vivek Pandey

  • Which configuration to include another project resource ?

    What configuration should I do in order that a project resource uses another's
    project resource referring it to by its project root web context?
    Example:
    in Project1.jpr, file1.xsl includes Project2.jpr file2.xsl stating <xsl:include href="/project2/file2.xsl">
    or
    in Project1.jpr, file1.jsp includes Project2.jpr file2.jsp stating <%@include file="/project2/file2.xsl">
    (Of course I do not want to use an absolute URI which includes the server name)

    You would need to configure both projects to have the same "HTML Root" directory in their project settings.
    In JDev, we have so far used the concept of each project representing a separate WAR structure, so by default projects have separate "HTML Root" directories. Since jsp:include operations and jsp:forward operations are not allowed to cross a WAR file boundary (per JSP 1.2 spec, section JSP.2.2.1), the only way to have jsp:forward and jsp:include to work is to put the two JSPs in the same WAR structure. In JDev this means having both JSPs in the same project, or having the two projects share the same HTML Root directory.

  • Project Resource Rates

    Hello
    we're using EPM 2010 and soon 2013 to manage our clients' projects.
    we are using a centralised resource pool and people will enter Timesheet for project tracking.
    one particularity is that every project is having a specific agreement on a rate for resources.
    I know that we have 5 rate tables in EPM but I see this as a limitation because someone in his life will surely be assigned to more than 5 project and starting to play with talbles AND effective dates leads to management nightmares.
    so my question is : do you see a way we can edit the resource rate per project?
    do you see any other alternative for our use case?
    regards
    Jérome

    Hello Jerome,
    I've written a utility that allows you to define ratecards externally to your project, and then apply them as and when required. So say you had a rate card per customer, you could build that ratecard once, and then use the ratecard import utility to apply
    those rates to each project you are executing for that customer.
    It's not open source, but it is freely available within our MS Project add-on. See the middle section of this webpage ("Rate Card Utilities") for a description:
    http://www.eversight.co.uk/#!dataimport/cuqb
    Get in touch if that would be helpful,
    Andrew
    Andrew Simpson
    Founder – Eversight Ltd
    E: [email protected]
    W: www.eversight.co.uk
    Download Eversight for MS Project — a free add-on which helps users build high quality schedules with MS project.

  • Project resources with different working weeks

    Hi All, 
    I have a project with resources in different locations (Australia and the Middle East) who have different work weeks. 
    Australia (Monday-Friday)
    Middle East (Sunday-Thursday)
    Basically, common work week is Monday-Thursday, while the Australian resources do not work Sat/Sun, and the Middle East resources do not work Fri/Sat. 
    I need to be able to schedule work for both resources, but I can't find a way to allocate work weeks in this way as it appears that work weeks is a global setting. Is there a way around this with holidays that i'm not seeing? Anyone have a solution to this,
    I can't be the first person to run a project in this manner. 
    Help very greatly appreciated, 
    Ryan

    RyanBaker --
    This is a really excellent question, by the way, because it gets at the heart of how Microsoft Project really works.  Remember that Microsoft Project is a scheduling tool.  You give it the correctly scheduling information and it will figure out
    the correct schedule for every task in the project.
    To resolve your situation, begin by creating two new Base Calendars:  an Australian calendar and a Middle East calendar.  On the Australian calendar, set the work week to Monday - Friday.  For the Middle East Calendar, set the work week to
    Sunday - Thursday.  On your Standard calendar, leave the schedule set to Monday - Friday.
    Next, assign the correct Base Calendar to each resource in the project.  For resources from Australia, set the Australia calendar as their Base Calendar.  For resources in the Middle East, set the Middle East calendar as their Base Calendar.  This
    will ensure that Microsoft Project schedules tasks correct when you assign resources to them.
    Leave the Standard calendar set as the Project and Nonworking Time calendars in the project.  Even though it will only show work from Monday through Friday, it will not matter.  When you begin assigning resources to tasks, Microsoft Project will
    reschedule the task, if needed, using the schedule shown as the Base Calendar for each resource.  For example, you have a 5-day task with no resources currently scheduled to start on a Monday and finish on Friday.  If you assign an Australian resource
    to this task, the schedule will not change.  But if you assign a Middle East resource to the task, the schedule of the task will change automatically to reflect the working schedule of this resource.
    Hope this helps.
    Dale A. Howard [MVP]

  • CUA Project Propsal Questions

    Hi Experts,
    I am doing research on CUA and have been asked to provide answers to the following questions.  If you have been though a CUA Config/implementation recently, I would appreciate your feedback.  We are a company of 10,000+ SAP Users (approx. 1500 dev/QA users we would be using for CUA)
    •Will Security save time by making Central Changes to user masters?
    •Cost savings?  Other benefits?
    •How much time to configure each system? 
    •How much Basis involvement?
    •Any other resources required? 
    •Will users benefit from Single Sign On with CUA?
    •Will Basis have more work after system refreshes?
    •What is Virsa's role/how does it integrate with CUA?
    •Are there any known showstopper functionality deficits with CUA that would prevent us from using it
    •We will use ourSolution Manager server for this project and for eventual production usage.  Any suggestions or feedback regarding this?
    •Hours the project would take?
      1.BASIS
      2.Security
      3.Change Management
    •Will a Refresh schedule be changed because CUA is implemented?
    •Have you come across any issues with refreshes?
    There are alot of questions and I will be more than happy even if only one question is answered.  As always, thank you for your expertise and advise.
    Teresa Wilson

    Hi Teresa
    > &#149;Will Security save time by making Central Changes to user masters?
    Yes if you have a broad landscape - i.e. lots of clients and systems
    > &#149;Cost savings?  Other benefits?
    User admin will be easier, CUA landscape monitoring will take additional overhead.  Personally I would use say you could save 25% of time when administering users if your landscape is conducive to using CUA. 
    > &#149;How much time to configure each system? 
    Once you have done one, it should take no longer than an hour for each system (less once you get the hang of it)
    > &#149;How much Basis involvement?
    Not much - maybe get them to set up the RFC destinations (specific CUA ones are good, but watch out for people trying to use them for remote CATT execution etc).  Basis may want to schedule the job which processes the userclone idocs in the target system.  It depends how you do things in your place.
    > &#149;Any other resources required? 
    No
    > &#149;Will users benefit from Single Sign On with CUA?
    I will defer to the far more knowledgable Mr Alsop on this one as I haven't a clue
    > &#149;Will Basis have more work after system refreshes?
    Usually limited to removing, re-adding in the CUA system.  It may save them time as the users can be pushed out of the master again if required (though will need to reprocess loads of failed idocs when they get locked)
    > &#149;What is Virsa's role/how does it integrate with CUA?
    What do you mean by Virsa? company doesn't exist any more.  If you use compliance calibrator then has no impact at all.  If you use Access Enforcer then there might be, but without knowing what you are doing, it's hard to say.
    > &#149;Are there any known showstopper functionality deficits with CUA that would prevent us from using it
    It can be a bit flakey, though has improved over the years.  It is not a magic pill which will solve all your problems.  You will get frustrated with it.  You have to do change reporting out of the CUA master otherwise you will only get change logs by the idoc processing batch user ID.  You need to keep on top of the idocs and log monitoring.  If you have a simple setup with few clients then might not be worth it.
    > &#149;We will use ourSolution Manager server for this project and for eventual production usage.  Any suggestions or feedback regarding this?
    I would recommend 3 separate CUA's - one for dev, one for test, one for prod.  Do not have one covering all because if the CUA master goes down for whatever reason then you have extra work.  Assuming R/3 is your main system (with lets say a BW and an APO) then I generally prefer to set the R/3 system as the master as there are usually fewer problems when doing role admin for that client.  That is only a personal preference though & lots of different parties recommend different things.
    > &#149;Hours the project would take?
    >   1.BASIS
    >   2.Security
    >   3.Change Management
    Impossible to say without knowing all details of your landscape.  Basically, you should be able to set up and test a reasonably complex CUA in less than a day.
    > &#149;Will a Refresh schedule be changed because CUA is implemented?
    I don't think so, though CUA should be taken into account as part of the activities
    > &#149;Have you come across any issues with refreshes?
    Yes, BASIS people messing up the CUA config or not doing the post refresh steps they were supposed to do.
    Good luck.  It can be very useful and very frustrating at times.  There are loads of installation guides out there.  As I have said earlier, it will not be the answer to all of your problems and does require extra monitoring.  In a project rampup situation where you have lots of users setup/changing in different clients then it can really help take a bit of the manual processing burden.
    Hope that helps
    Cheers
    Alex

  • Microsoft Project - Resource Pool Major Issues (continuation)

    Hi All,
    I have followed the the very helpful discussions in this forum under "Resource Pool Major Issues". I have read all the other related discussions as well.
    I still have a question on the Resource Pool:- I am using a stand-alone version of Project Professional 2007
    I create a Resource Pool; a Master Schedule and then insert several different Project Schedules into the Master. 
    I have gone through the motions of harmonizing the calenders and all the other good stuff recommended in the blog. 
    I then share the resources from the Pool.
    When I open each activity to load the resources, I cannot see the shared resources except at the Project level (but not at the task level)
    The only way I can pull the resources into the tasks is
    if I break the links of each inserted Project. (incidentally the inserted tasks are automatically linked option is de-selected)
    Even then, I get an irritating message pop-up saying that the calender does not exist.
    Has anyone had this experience, is it the correct way to share the resources; and do you have any thoughts, suggestions on this matter?
    Thanks
    FK

    Hard Core,
    You indicate you have Project 2007 but you didn't tell us if you have SP3 installed. If not, do so.
    Since you indicate that you have "read all related discussions" I will assume that you are aware of the tenuous nature of linked structures in Project and that they are prone to corruption.
    Please clarify something. What exactly do you mean by "open each activity" and "I cannot see the shared resources except at the Project level"? Also, which links are you breaking?
    We can't really tell you if what you are doing is the correct way, (probably not if you have to break links for it to work), until we understand exactly what you are doing.
    John

  • IDCS5 Mac - Resource question

    My current project may open up as many as 194 documents in a session before it starts telling me that it is unable to open up the next document in line because it is "damaged."  Yet when I get out of InDesign, return, and open the documents that were reported as damaged, they open just fine.  Additionally, the plugin that was being used to open all these documents will open the documents just fine and do what it is required to do.
    BTW, if I process a lesser number of documents through the plugin in question in the Debug version, no leaks are reported when I exit InDesign.
    Is there a resource limit involved here that I should know about?  And if there is, is there any way around it?
    Please be advised that I am using ProcessScheduledCommands() to ensure that a document is really closed once I tell InDesign to close it.

    macinbytes wrote:
    If only I could do that with my keys, I'd have as many points as Peter.
    I'd gladly give you a few, but there's no way to do it.  And I still don't have the t-shirt...

  • Confuesed about Project resources : Stock / PR / PO

    Hi guys,
    I use IDES to run an demo project, set collect WBS , and assign material A to 2 options:
    option 1  needs  A   5 pcs
    option 2  needs  AB   10 pcs 
    After running MRP, I have 2 PRs for the material A and both belongs to  the same WBS Code .
    PR1 , A  5pcs, special stock flag Q, WBS code: P-1
    PR2, A  10pcs, special stock flag Q, WBS code: P-1
    And then I convert PRs to POs,
    PO1 , A  5pcs, special stock flag Q, WBS code: P-1
    PO2, A  10pcs, special stock flag Q, WBS code: P-1 .
    Now, I change the qty in the WBS to
    option 1  needs  A   10 pcs
    option 2  needs  B   5 pcs
    Run MRP again, I have a new PR
    PR3 , A  5pcs, special stock flag Q, WBS code: P-1 .
    That confused me, if the special stock flag links with WBS code P-1 , why the resources can't share ? I mean the total qty of A for P-1 is 15, it’s enough. I test again after GR to stock , still generate PR3.
    And then I found the material docs of GR shows the resources (stock) belong to WBS and NETWORK .
    How to configure to share the resources under the same WBS code (special stock) ? I don’t want another PR3 .Thanks all !
    Wayne

    Sorry, made some copy mistake .
    The Question should be :
    I use IDES to run an demo project, set collect WBS , and assign material A to 2 options:
    avtivity  1 needs A 5 pcs
    avtivity  2 needs A 10 pcs
    After running MRP, I have 2 PRs for the material A and both belongs to the same WBS Code .
    PR1 , A 5pcs, special stock flag Q, WBS code: P-1
    PR2, A 10pcs, special stock flag Q, WBS code: P-1
    And then I convert PRs to POs,
    PO1 , A 5pcs, special stock flag Q, WBS code: P-1
    PO2, A 10pcs, special stock flag Q, WBS code: P-1 .
    Now, I change the qty in the WBS to
    avtivity  1 needs A 10 pcs
    avtivity  2 needs A  5 pcs
    Run MRP again, I have a new PR
    PR3 , A 5pcs, special stock flag Q, WBS code: P-1 .
    That confused me, if the special stock flag links with WBS code P-1 , why the resources can't share ? I mean the total qty of A for P-1 is 15, it’s enough. I test again after GR to stock , still generate PR3.
    And then I find the material docs of GR shows the resources (stock) belonging to WBS and NETWORK .
    How to configure to share the resources under the same WBS code (special stock) ? I don’t want another PR3 .Thanks all !

Maybe you are looking for