Dear Experts,
Please advise on the following:-
There are two products, like Product A - 2 Nos, and Product  B - 3 Nos, will be manufactured for a project order.
Finished product will be attached in the project structure and will be manufactured in house through PP module. Material planning will be done thorugh project MRP.
A sales order will be created with two line items, Product A - 2 Nos, and Product  B - 3 Nos.
Root level WBS element will be linked with sales order header level for milestone billing.
Is it possible to see the cost and selling price comparison of product A and product B through this settings, as they are different type of product and their selling price are different.
Can the system apportioned the cost of sales based on the selling price of the product A and Product B.
Looking forward to hearing from you.
Thanking you.
Best Regards,
Abdul.

Hi,
  This you can do it in two ways:
1. Make three header under top level....one Product A, 2nd Product B ( as Billing element) and third as Common expense ( only cost). Now 1st & 2 nd WBS, you have to have sales order linking with individual lint item, for third you will accumulate all the common expense till the period end then make a reposting of the same in desired proportion to both products WBS hierarchy
(This is if you want to have a track on the common expense as well.......like planning, budgeting & control)
After this reposting, run RA for individual billing element and hence you will all the complement detailing and control over Revenue and expense with respect to Product A and Product B individually.
2. If you don't want to maintain that kind of detailing the common expense and keep track of it through project, then have cost centers accordingly and make an assesment/ distribution with respect to expenses accumulated at those cost centers for the period to the respective WBS under each product. Then execute the period end processes for the project.
Or
You can try with have two more line items in the costing sheet as an overhead against common expenses with respect each product.
I hope this should help you.
Regards
Avisek Bhardwaj

Similar Messages

  • Production order from sales order with multiple line item(for one material)

    Dear Gurus,
    I am working in MTO scenarios. If there is several line item in a sales order for one material, multiple production order( same as no. of sales order line item) is getting created against each of the line item.My requirement is,since the material code is same in each line item and sales order is one, one production order should be generated for all line item. please tell me how to do it.
    (Here for one material, multiple line item is required for some specific reason)
    Regards
    Rajib Pathak

    Hi,
    This is not possible.
    In Std SAP will create one production order for one sales order. The stock is also allocated to thet particular sales order only. Because each and every sales order may vary in any one of the parameters. Considering this, SAP has designed like this.
    Regards,
    V. Suresh

  • Copying the item text in case of multiple line items

    Hi All,
                    I have a scenario where the sales order gets created in our SAP through a 850 idoc. The incoming idoc has only one item segment which carries the total order quantity ( for example say 1000). Since my company has contractual agreements with the end customer for doing multiple shipments , our sales department splits the total quantity into multiple line items in the sales order. Say splitting the 1000 quantities into 5 line items of 200 each.
    The problem here is that when the sales order got created , all  the related item text were copied only to the first line item ( of 1000 qty) and which is standard SAP. Since the order quantity was manually split, the related item text are not carried to the subsequent line items. The issue comes when an outbound (810) idoc is sent to customer . As I told earlier since only the first line item has the item text , the 810 idoc which was created for  the first line item only has the item text . The rest of the 810 which were subsequently created for multiple shipments/invoices on different dates didn't have the item text in the 810's. This is becoming a major problem as the 810 files are failing at our trading partners end because of missing text.
    Now my question is, Is there a way that I can make the item text copy automatically when multiple line items are created manually by business. Like is there a way where I can modify MV45AFZZ  to copy the item text in their respective segemnts ( z003,z004 etc) to "N" number of line items.
    Also please suggest if there is a better way of doing it. Suggstions are most welcome !!!.
    Regards
    Amrith

    Hi,
    First of all try to avoid doing select into corresponding fields. THis would improve the performance of the program.
    Try to do a single fetch from the BSIS table . fetch the hkont, belnr, dmbtr fields in to a master internal table. Manipulate and play with the data as required.  Don't hit the data base table more than once (unless it is required) . This would improve the performance of your code.
    Try to code this way.
    types: begin of ty_bsis,
                 hkont type hkont,
                 belnr type  belnr_d,
                 dmbtr type dmbtr,
              end of ty_bsis.
    data: it_bsis type standard table of ty_bsis,
             wa_bsis type ty_bsis,
    select hkont belnr dmbtr
              from bsis
              into table it_bsis
              WHERE HKONT IN S_RACCT
            AND PRCTR IN P_PRCTR
              AND MONAT IN S_POPER
             AND BUKRS EQ P_BUKRS
             AND GJAHR EQ P_GJAHR
              AND PRCTR IN S_PRCTR.
    Using the data availabe in the it_bsis, you can manipulate as required.
    Hope this would be helpful
    Regards
    Ramesh Sundaram

  • SRM 7 - defaulting values for multiple line items on shopping cart

    Hi,
    We are using SRM 7 - Employee self service - Punch out catalogues and describe requirements.
    Our scenario is this:
    - User is responsible for creating shopping carts for numerous cost centres/other users
    - Shopping cart will have multiple line items (but the cost centre/other user will be same for all line items)
    - Is it possible to define in a shopping cart that all line items will have a specific value?  E.g. all line items will be assigned to a specific cost centre?
    I know about assigning dedault values in PPOMA_BBP - but our situation is where user does not want to use this default value this time, but another value
    Any suggestions?
    Thanks

    Thanks Alex for quick reply
    To confirm, did you use the BBP_DOC_CHECK_BADI (in conjunction with the BBP_ITEM_CHECK_BADI) to look at different cost centres on the multiple lines on the shopping cart?
    Also - did you use the same BADI to give user opportunity to enter a default cost centre that is then automatically applied to all line items on the cart?
    Thanks
    Azam

  • Multiple Line Items in billing

    Dear All,
    I got one issue on production server,the scenario is like this,
    My client gives one Free of Cost (Item Category is TANN) On purchase of one material like XYZ(with item category TAN).
    And while creating Sales order it takes FOC automatically.
    And when i am trying to do billing it shows FOUR Line items instead of TWO.
    Can anybody help me to solve this problem...
    What should i check...?
    Its urgent...
    Thanks & Regards,
    Ullas Kumar

    Hi ullas
    As your requirement is in invoice VF01, you want to see multiple line items . that means, if you have entered 1line item then 1line item will be free so totally 2 line items will come in sales order with TAN&TANN item categories.But in invoice you want 4line items
    so go to VTFL and check the billing quantity feild as B and check the cumulative cost feild
    Reward if useful
    Regards
    Srinath

  • SNC5.1- How to Publish multiple line items in SNC Web UI (Supplier view)

    Hi Experts,
    I am working in SAP SNC Supplier Collaboration project. I have a scenario where i am trying to "Publish PO" for multiple line items in Web UI. I am able to confirm each PO line item and Save PO. But if i try to publish one line item at a time, then the system publishes the 1st line item and it does not allow me to publish the remaining PO line items.
    All i can do is, Confirm and Save all line items, and then "publish" it at the end. In this way,i can view all the confirmed line items (POA) in SNC. But how do I Confirm/Save/Publish each PO line item?
    Appreciate your help.
    Regards,
    dmohite

    Hi dmohite,
    As the POC standard process Supplier should give confirmation for all PO items after confirmation of all items it should allow to Published the PO at Header level.
    If supplier does not give confirmation for all items it should not allowed to Published the PO at Header level but you are able Published the PO at header level without confirmation of all PO items.
    You can implement note no: 1320445 (manual implementation is required).
    After implementation of this note without confirmation of all PO items it won't allow to publish the PO at header level.
    Please let me know for any clarification.
    Regards,
    Nikhil

  • IDOC to JDBC, problem with the multiple line items structure and mapping

    Hi,
    I have a scenario where the ORDERS data need to update the SQL table. for the idoc which consists one line item its ok but for multiple line item its just updating one line item. In the destination side we have only one table for purchase order which consists of lineitem as a field.(no different tables for Header data and Line item data)
    Can anyone suggest me how to create a structure for target side and how to map them.
    Regards,
    CJ

    Hi Rajan,
    The table structure is
    [PO_DATE]
          ,[VENDOR_NO]      ,[PAYMENT_TERM]      ,[MATERIAL_CODE]      ,ORDERED_QTY]      ,RECEIVED_QTY]                                 
          ,[UOM]       ,[RATE]       ,[CURRENCY]       ,[PO_EXCRATE]       ,[TAX_CODE]       ,[BASE_VALUE]       ,[TAX_VALUE]
          ,[TOTAL_VALUE]       ,[ADVANCE_PAYAMT]       ,[TOTAL_QTY]        ,[SNO]       ,[POLINEITEM]
    Datatype structure:
    PO_XI_MT_ORDERS05 1-1
    STATEMENT   1-UNBOUN
      TABLENAME 1-1
        ACTION   optional
        TABLE    1-1
        ACCESS  1-1
           PO_NO   0-1
           PO_DATE 0-1
    Correct me if im wrong.
    Regards,
    CJ
    Edited by: kuncjy on May 5, 2011 11:32 AM

  • URGENT: Delivery with multiple line items for a STO

    Hi Gurus,
    We ar ecreating deliveries using VL10b for a STO. Teh TSO has 40 - 50 line items. But the delivery is created with one line item only an dit creates a delivery for each line item. How cna we allow the inclusion of multiple line items in delivery?
    We are using delivery type NL an ditem categor is NLN.
    Geratly appreciate any help in that.
    Thanks,
    KHAN

    The problem you face is called 'Delivery split'.
    For the STO scenario, one common cause is different delivery dates (in the past) in the STO line items. If so, then you should refer to SAP Note 377501 (from where I quote below):
    You can implement the source code specified in the correction instructions in copy routine 301 (or a copy of this routine in the customer namespace). This correction ensures that when you transfer data form the preceding document, backlogged delivery dates or goods issue dates are set to the current date. This prevents the system form performing a delivery split.
    Then a rescheduling of the delivery occurs. Since forward scheduling occurs for backlogged delivery items (that is, the picking date or the transportation planning date is set to the current date), the manipulation of the delivery date or goods issue date in the copy routine does not affect the result of the scheduling.
    If the dates are not the problem, then this Note refers to other Notes which deal with this problem, and should definitely solve your problem.
    Regards
    Nikhilesh

  • Pass Idoc PO Multiple Line Items to file

    Hello All,
    we are using Message Type ORDERS and ORDERS1 as Basic type to pass PO and sales data. I have configured IDOC to File scenario. I'm able to successfully place a file in file folder.
    But my issue is some of the PO's have multiple line items and saved file has one first line item information. I have even tried unbounded for line item but no luck.
    <b>How do I pass all the line item values to the file ?.</b>
    The output structure should be
    1. PO Number
    2. PO ITem
    3. Material No
    4. Delivery Date
    5. Vendor Number
    the data type I created is
    Pur_Ord
    |__ EBELN
    |__ EBELP  0..Unbounded
    |__ MATNR
    |__ AEDAT
    |__ LIFNR
    the current output is
    <?xml version="1.0" encoding="UTF-8"?>
    <ns0:Pur_Ord_Out xmlns:ns0="http://PO_TO_FILE">
      <EBELN>0004500066</EBELN>
      <EBELP>00001</EBELP>
      <MATNR>000000000000010027</MATNR>
      <AEDAT>20051215</AEDAT>
      <LIFNR>0001005780</LIFNR>
    </ns0:Pur_Ord_Out>
    Im looking for an output with all line items
    Thanks in advance
    Praveen

    Praveen
    Try this
    Pur_Ord
    |__ ORDERS 0.. Unbounded
      |__ EBELN
      |__ EBELP
      |__ MATNR
      |__ AEDAT
      |__ LIFNR
    Here ORDERS is the parent node.
    KK
    Message was edited by: KK

  • Setting the value of a single attribute for multiple line items

    Hi all,
    I am working on a Web Dynpro application, I have created this applicaion for an accounting document so it has header data and multiple line item data. As per the requirement I have to put the following logic:
    1. When a user enters a value in the field KBLNR on the line item, all the other fields like cost centerm fund, functional area should populate from a database table based on the value of the KBLNR. to get this I have put the following code:
    TYPES: BEGIN OF t_kblp,
              fipos     TYPE kblp-fipos,
              kostl     TYPE kostl,
                      END OF t_kblp.
      DATA lv_kblnr TYPE wd_this->element_t_bseg-kblnr.
      DATA: lt_kblp TYPE STANDARD TABLE OF t_kblp,
            wa_kblp LIKE LINE OF lt_kblp,
            lt_bseg              TYPE STANDARD TABLE OF bseg,
            wa_bseg              TYPE bseg.
      DATA lo_nd_t_bseg TYPE REF TO if_wd_context_node.
      DATA lo_el_t_bseg TYPE REF TO if_wd_context_element.
      DATA: ls_t_bseg TYPE wd_this->element_t_bseg,
            lo_api_controller    TYPE REF TO if_wd_controller,
            lo_message_manager   TYPE REF TO if_wd_message_manager,
            lo_nd_tbseg          TYPE REF TO if_wd_context_node,
             lo_el_tbseg          TYPE REF TO if_wd_context_element,
             lt_el_tbseg          TYPE wdr_context_element_set,
             lv_bseg              TYPE bseg.
      lo_nd_t_bseg = wd_context->path_get_node( path = `ZDATA.CHANGING.T_BSEG` ).
      lo_api_controller ?= wd_this->wd_get_api( ).
      CALL METHOD lo_api_controller->get_message_manager
        RECEIVING
          message_manager = lo_message_manager.
      lo_nd_tbseg = wd_context->path_get_node( path = `ZDATA.CHANGING.T_BSEG` ).
      lt_el_tbseg = lo_nd_tbseg->get_elements( ).
      LOOP AT lt_el_tbseg INTO lo_el_tbseg.
        lo_el_tbseg->get_static_attributes(
                               IMPORTING static_attributes = lv_bseg ).
      IF lv_bseg-kblnr NE ' '.
          SELECT belnr
                 fipos
                 kostl
                 PSPNR
                 geber
                 saknr
                 fkber
                 grant_nbr
                 gsber
                 FROM kblp
                 inTO corresponding fields of wa_kblp
                 WHERE belnr = lv_bseg-kblnr and
                      saknr = lv_bseg-saknr.
            ENDSELECT.
    lo_nd_t_bseg = wd_context->path_get_node( path = `ZPRELIMINARY_POSTING.CHANGING.T_BSEG` ).
    * get element via lead selection
            lo_el_t_bseg = lo_nd_t_bseg->get_element( ).
    lo_el_tbseg->set_static_attributes(
                               EXPORTING static_attributes = wa_kblp ).
       CLEAR: lv_bseg, wa_kblp.
      ENDLOOP.
    everything is working fine but now the problem is couple of fields that I have in wa_kblp are with different names in bseg table and hence they are not updating... I tried putting the following logic within the loop :
    lo_el_t_bseg->set_attribute(
        name =  `PROJK`
    value = wa_kblp-pspnr ).
    but it's only setting the value of the first line item and not working for the multiple line items, can you please tell me how can do this?
    Thanks,
    Rajat Garg
    Edited by: rajatg on Jun 24, 2011 5:09 PM

    Hi Chris,
    I tried your code and it worked fine but after I put this code I am getting another issue. within the loop I had a code to make the fields non modifiable on the screen and was working fine but now what's happening is it's making the all the lines uneditable except the one with data on it (which is completely opposite), this is what I have coded:
    LOOP AT lt_el_tbseg INTO lo_el_tbseg.
        lo_el_tbseg->get_static_attributes(
                               IMPORTING static_attributes = lv_bseg ).
    IF lv_bseg-kblnr NE ' '.
      SELECT belnr
                 fipos
                 kostl
                 PSPNR
                 geber
                 saknr
                 fkber
                 grant_nbr
                 gsber
                 FROM kblp
                 inTO corresponding fields of wa_kblp
                 WHERE belnr = lv_bseg-kblnr and
                      saknr = lv_bseg-saknr.
            ENDSELECT.
    move: wa_kblp-belnr to wa_bseg-kblnr,
    wa_kblp-fipos to wa_bseg-fipos,
    wa_kblp-kostl to wa_bseg-kostl,
    wa_kblp-pspnr to wa_bseg-projk,
    wa_kblp-geber to wa_bseg-geber,
    wa_kblp-saknr to wa_bseg-saknr,
    wa_kblp-fkber to wa_bseg-fkber,
    wa_kblp-grant_nbr to wa_bseg-grant_nbr,
    wa_kblp-gsber to wa_bseg-gsber,
    lv_bseg-dmbtr to wa_bseg-dmbtr.
    append wa_bseg to lt_bseg.
    lo_nd_edit_property = wd_context->path_get_node( path = `ZPRELIMINARY_POSTING.CHANGING.T_BSEG.EDIT_PROPERTY` ).
          get element via lead selection
          lo_el_edit_property = lo_nd_edit_property->get_element( ).
          lo_el_edit_property->set_attribute(
            name =  `EDIT_FIELD`
            value = 'ABAP_TRUE' ).
          lo_el_edit_property->set_attribute(
            name =  `EDIT_WBS`
            value = 'ABAP_TRUE' ).
    endif.
    endloop.
    o_nd_t_bseg = wd_context->path_get_node( path = `ZPRELIMINARY_POSTING.CHANGING.T_BSEG` ).
    get element via lead selection
            lo_el_t_bseg = lo_nd_t_bseg->get_element( ).
      CALL METHOD lo_nd_t_bseg->bind_table
        EXPORTING
          new_items            = lt_bseg.
    Can you please see what I am doing it wrong here....

  • Single/ Consolidated  GR/IR entry for a PO having multiple line items

    Hi,
    In a PO there are couple of line items for materials of similar type and class. While making the Goods Receipt, the Accounting Document is making two no of line items for GR/IR accounts as credit and two no of inventory accounts as debit. Same is happening to GR/IR account while making Invoice Receipt document also.
    Informatively, both the materials above have been assigned to one GR/IR account in the OBYC table.
    My question is, is it possible to consolidate the value of both these materials and post one line item for GR/IR account. This is required as in our case in a PO, normally, we do have multiple line items and hence it is resulting multiple no of GR/IR and inventory accounts in a single accounting document. As we are getting details of the line item from PO history, we do not require it in the accounting document.
    Requested to kindly help.
    Regards
    B.Mohanty

    Hi
    This is not possible (you will compleet los the link between the Invoice and GR)
    The reason is that when you receive an invoice that this is based on a G/R line and the way arround when you receive first the invoice(s).
    The system need this for the automatecly clearing from the  G/R - I/R account, that is based on PO an PO line item number.

  • MM: PO Not Picking up PR Having Multiple Line Items

    Hi All,
    When Creating PO with Reference to PR Having multiple line items, not picking up the line items and also the vendor and also the where in we  have to select  input tax code.
    CASE1: Created PR 760001340 with single line item and also could able to create PO.
    Case2: Created PR 760001341 with multiple line items, When creating PO with reference to PR the line items and Vendor are not picking Up.
    Plz. Advise a solution.
    Thanks in Advance.....
    Regards
    Sudheer

    HI SHWN,
    Thanks for prompt response.
    ERROR Message: When referencing a requisition, please also enter a requisition item no.
    Regards
    Sudheer

  • How to Restrict Single Delivery Date for PO with Multiple Line Items

    Dear Experts,
    How to Restrict Single Delivery Date for PO with Multiple Line Items.
    System needs to through Error Message if User Inputs Different Delivery Dates for PO with Multiple Line Items in ME21N Tcode.
    Can we achive this by Some Enhancement in SAP or Not ???
    If so how to do it.
    Any Inputs is highly appreciated.
    Thanks and Regards,
    Selvakumar. M

    Hi Selvakumar,
    we can resrict the PO to have a single delivery date in all the line items by means of giving a error message or overwiting the delivery date keyed/determined in the line item.
    You can use the BADI -> ME_PROCESS_PO_CUST. In which you need to implement the method PROCESS_SCHEDULE.
    (for technical aid - This method will be called for each and every PO line item, From the imporing parameter im_schedule we can get all the details of current PO line, even we can change the data in the current PO line. )
    Regards,
    Madhu.

  • Creating a PO Using BAPI For Multiple PLants Or Multiple Line Items

    Hi All
        Can you please suggest me how to create a Purchase Order Using BAPI_PO_Create1 for Multiple Plants Or for Multiple Line items. The Requirement is like the PO is for single material for single vendor but for mulple stores i.e plants
    NOte:  Suggest me the  Creation of PO for MUltiple Line items or for multiple plants Using BAPI . Hope you people will give me the needful.
    Regards
    Shivakumar Bandari

    Hi,
    Here is the sample code to do that...
    *---> po header data
      wa_poheader-vendor    =  your vendor..
      wa_poheader-doc_type  =  Your doc type..check with Functional contact....
      wa_poheader-purch_org =  Purchasing Org..
      wa_poheader-pur_group =  Purchasing Group
    *---> po header data (change toolbar)
      wa_poheaderx-vendor    =  'X'.
      wa_poheaderx-doc_type  =  'X'.
      wa_poheaderx-purch_org =  'X'.
      wa_poheaderx-pur_group =  'X'.
    *---> poitem data
    data: item like ekpo-ebelp.
    item = '0010'.
    loop at t_parts.
      it_poitem-po_item  =  '00010'.
      IT_POITEM-PLANT    =  Plant..
      IT_POITEM-STGE_LOC =  Sloc...
    *---> poitemx (item data change toolbar)
      it_poitemx-po_item  =  '0010'.
      it_poitemx-po_itemx  =  'X'.
      IT_POITEMX-PLANT    =  'X'.
      IT_POITEMX-STGE_LOC =  'X'.
    *---> add record's to internal table
      APPEND:  it_poitem,
             it_poitemx.
    endloop.
    *call bapi_po_create1
      CLEAR v_ebeln.
      CALL FUNCTION 'BAPI_PO_CREATE1'
        EXPORTING
          poheader         = wa_poheader
          poheaderx        = wa_poheaderx
        IMPORTING
          exppurchaseorder = v_ebeln
        TABLES
          return           = it_return
          poitem           = it_poitem
          poitemx          = it_poitemx.
    *---> check the return table for error message
      READ TABLE it_return WITH KEY type = 'E'.
      IF sy-subrc NE 0.
        CALL FUNCTION 'BAPI_TRANSACTION_COMMIT'
          EXPORTING
            wait = 'X'.
      endif.
    Thanks,
    Murali

  • Partial goods receipt for PO with multiple line items

    Hello All,
    While doing MIGO, for a PO with multiple line items, if one line item is having error, will we be able to go ahead with goods receipt? Or entire material document is blocked for doing MIGO?
    We will be doing a development - in case if there is problem in goods receipt (checking of any parameter, and if it is missing - we will be posting error message)...is it possible to ahead with next line item and still post the material document?
    If partial goods receipt if possible for PO with multiple line items, how do we do it?
    Regards,
    RJS

    Hi
    While doing MIGO, for a PO with multiple line items, if one line item is having error, will we be able to go ahead with goods receipt? Or entire material document is blocked for doing MIGO?
    No. You cannot post the MIGO, if even one of the PO line item is having problem or giving error.
    We will be doing a development - in case if there is problem in goods receipt (checking of any parameter, and if it is missing - we will be posting error message)...is it possible to ahead with next line item and still post the material document?
    If you skip a line irem and do GR with next line item, how will you match quantity & value with the vendor Invoice at LIV ?
    If partial goods receipt if possible for PO with multiple line items, how do we do it?
    Partial goods receipt is possible for PO line items. That means, if PO has 100 qty for line item 1 then you can do GR for 50 now and 50 later depending on the vendors delivery.
    Hope this is what you mean by "Partial Goods Receipt".
    Edited by: Arun R on May 10, 2010 2:03 PM

Maybe you are looking for

  • Windows Update Error Code C8000654

    Hello, I am getting error C8000654 when checking for updates. How can I fix this? Thank you.

  • Time Machine Backups after using a clone?

    I have had to revert to a clone of my MacBook Pro as a piece of software broke something. I have all my data and everything works fine except TM thinks the last backup it did was two weeks ago, when the clone was made. So now Time Machine wants to do

  • Can I re-download songs that I've already paid for?

    I lost my harddrive with my main iTunes library and my backup was a couple months old (I know, I know, stupid move). Anyway, can I re-download the songs that I'm missing that I've already paid for (and still have the elecronic receipts)? Thanks in ad

  • IDOC_ADAPTER.SENDER_BSI_INCORRECT

    Hi,   I get the following error message. Can anyone help on this? I have imported the metadata using transaction IDX2. Also the cache displays the logical system for the receiver system. My sender system is a third party and not an SAP System. Do I s

  • Changing size of standard data element.

    Hello here, I need some clarification. I have standard data element TIDNR - Technical identification number (Used in PM tables). It has Data Type - CHAR and Length  25. Is it possible to increase his length to 35? Maybe, it is possible to create new