Hi Experts,
We have a scenario where the client may use multiple plants to manufacture a component. The client will try to complete the project in one plant itself. But, the following conditions may happen;
Case 1. When there's no sufficient capacity or resources, the balance manufacturing process in project has to be completed in other plant.
Case 2: Few numbers of parts will be manufactured in one plant, balance will be manufactured in other plant
How can this be done, and how to account for costs...for two plants? How do we complete balance or remaining machining processes in other plants? Please advise.
Thanks & Regards,
Kabir

Hi Kabir,
Please try the following link :
http://help.sap.com/saphelp_erp60_sp/helpdata/en/ed/b7853488601e33e10000009b38f83b/frameset.htm
Thanks,
Dhruv Kumar Malhotra

Similar Messages

  • Multiple plant in one project

    Dear PS gurus!
    Want to know that can we create one project having multiple plant, if yes ? how we will do costing?How to customize?
    plz let me know the concept.
    Ansar

    you can have multiple plants in one project
    there is no customising for this - the plant would be set up as part of enterpise customising
    the costing will be based on the WBS object assigned
    for eg you can have a project where some work is carried out in plant A and some work in plant B - projects can be cross plant the cost will be assigned to the WBS based on the actual postings but the WBS can have different plant assignments

  • IDVD burning one project on multiple macs? where are project contents?

    How do I burn one project on multiple macs? I have a idvd project I created in keynote, added music to it in Garageband, exported to quicktime, and now is in iDVD burning just fine. However I have tons of these dvd's to make, I would like to put all my mac's to work.
    last night i tried to share the file, and it is just an alias when i drag it over from the macbook it was created on to my imac. the file says it is in use and locked, since the macbook that created it is burning it. If I wanted to brun on the imac, I had to wait until the macbook was done.
    is there a way around this? What if I copied all files I used to make the idvd project to my imac or any computer i wanted to burn on? woudl it hen allow two macs to be burning the same project?
    I figured I could do this just like on my PC, drag the file over and voila...no such luck, its like if i had dragged a shortcut over to another pc...if the first one is using the file, its locked. Basically how do i get to the actual contents of the project, so I can also bring them over and hopefully it will allow me to burn on multiple macs at the same time?
    my next solution if that didn't work was to start copying dvd's using popcorn on the other macs while the macbook continues burning through idvd.
    Any opinions on how i can duplicate a dvd fast...need alot of copies!

    Also as to where the files are.
    I-DVD project bundle: This is the file created when you save the project.
    • [user]/Library/iDVD/Favorites: This folder is located in your home folder.
    • [root]/Library/iDVD/Favorites: This folder is located at the root of your disk.
    • /Network/Library/iDVD/Favorites: This folder is on a network system specifically
    configured by your system administrator for this purpose. (This is not the same as
    having a server networked into your computer.)

  • One characteristc for multiple plants

    Hello All,
    In our project we have two company codes and two plants in each company code. In first company QM module is already implemented and we are doing roll out for second company codes. Major QM activities and batch charactristics are same as products are same. For characteristics selected sets are assigned along with plant one. Now I want to use same batch charactristics for the second plant and I maintained all selected sets for the second plant also. But how can I assign second plant in the charactristics valu tab page? There is only one plant field. I want to use same selected sets for the second plant also.
    Regards,
    Mayura

    Hello,
    Thanks for the quick reply.
    But how can I create same charactristic codes in second plant? Now client is saying that if same characteriscts are available in the system what is the use of creating new one? If we created with diff codes still description will reman same and it will show duplication in the syswtem.
    Please suggest other solution
    Thank you.
    Mayura

  • Multiple exams in one project and variable

    Hello captivators,
    How do I make a captivate project with multiple exams. And with variables (widgets) that I need in the whole project.
    In the intro of the project you can select a character. That selected person is the visual coach (different branding) for the course.
    The student needs to through an intro module, next he can choose 6 parts of the course.
    One part = intro,n * show me, n * practice me, 1 * exam.
    The student needs to follow 1 part to the end. And then return to the intro.
    1st option: one project
    I can’t seem to make multiple examns with multiple results
    2nd option: multiple CP’s
    Then I have problems with the variables that are only known in one CP (SWF)
    3th option: Aggregator
    Then I can’t make condition. And I can’t hide the captivate menu when exported. I need conditions.
    HEEEELP Please,
    Koen

    I've not tried something like this to advise on whether it's possible in Captivate natively...but you've seem to have looked at all options and not found it possible. If that's the case, then perhaps the best option is to make the 'aggregator' in Flash, where you load each related CP file as the condititions are met. It's definitely possible to do, as one of my colleagues always uses his own 'Flash Shell' for this sort of thing. Possible for you, and ok in the project constraints?
    Erik

  • During import, how to auto split one project into multiple albums based on date?

    I believe I've done enough aperture reserach to get all my terminology right, so here goes...
    I've created a file structure within the aperture inspector the the tune of: 
    Year [folder], Type of event (Occasion, special occasion, holiday, vacation) [folder], Project (Wedding), Album (i.e. Day 1, Day 2 or Pre wedding week, event, honeymoon).
    I also have entire months with 7 or 8 pictures each day, that are of the same type/project (random dog pictures) but are distinctly different days (albums - day in park, in bed at night, watching movie). 
    My question is, can I import one project with multiple albums already created based on the date they're taken.  As I can see it, all I can do is split individual projects automatically by date.  But what if one project is over one month, but has multiple distinct days that would be ideal for albums?  One more example.  We did a trip to San Fran.  One day was touring the city, one day was a concert, another day was touring the city.  All one project, but 3 different albums (in my mind).  I had to import as one project, then separately go in and make albums.  I would like that done automatically.
    My suspicion is that I can not natively do this within aperture, and that I would need something called an "applescript."  I haven't done any reserach into that area, so if that's the case and you know where I can find a script that would do this, I'd appreciate the help. 
    Sorry for the wordiness, just wanted to be clear.  Thanks for any and all help!

    Hi,
    You need to create a new requirement in tcode VOFM for that, together with your ABAP consultant. This requirement will be used in copy contol.
    http://saptechsolutions.com/pdf/VOFMCopyRequirementRoutines.pdf
    MdZ

  • Best way to have multiple arrangements in one project file?

    Hello everybody,
    I am trying to figure out a smart way of having multiple arrangements associated with one project. More importantly, this would allow me to have multiple arrangements associated with the same pool of audio files in one audio window -- without needing to import/export audio.
    In DP this is achieved with multiple "sequences". I am aware this feature is not in Logic. However, perhaps there is a way to achieve a similar process?
    I guess a not-so-elegant approach would be to simply save a new song; however, if I want to use new song audio files in the old song, i'd have to import the new song audio files to the old song. Not a big deal, I guess.
    Thanks,
    D
      Mac OS X (10.4.5)  

    Thanks for responding Justin & David,
    Let me to try to better explain what I am trying to achieve.
    (Currently my problem is that I am thinking in the "workflow language" of DP, trying to figure out an analogous "translation" in Logic. For those familiar with DP, I am simply wanting to create a new sequence, within the same "song" file.
    Let's say I create a bunch of audio tracks, and compile them into arrangement A. I would like to work on a new idea that may be part of the final piece; So, I would like to have a clean, new arrangement page where I can put some of the previous audio files generated & used in arrangement A, as well as make some new ones. I'll call this arrangement B. So, in other words, arrangement B is a fresh new arrangement page that uses audio files from arrangement A as well as new ones.
    If any previous/current DP users know the best way of approximating DP's use of multiple sequences, I'd love to know what you do.
    I will explain what I am able to do if I were in DP (for the sake of communicating my problem, but not intended to begin a DP vs. LP thread).
    I will use Logic terminology, but DP concept:
    In DP, one can have multiple Arrangement windows that share a pool of audio files from one Audio Window. This allows one to try different arrangements, without keeping track of new/old audio files; and without needing importing and exporting them between songs.
    I have been reading the Project Manager section in the Logic manual. (By the way, I am not seeking a DP functionality in Logic; I am seeing how one achieves a similar workflow approach in Logic.)
    I realize I cannot even explain myself well. Perhaps I should consider the concept of sub-arrangements, and master arrangement. I guess, sub-songs, and work-in-progress master song. The master songs should have all audio files, and sub-songs have whatever audio files were created while working on that particular sub-song. So, with this, whenever I want to go back to master song, I've got to import the audio files from the sub-song.
    This may make sense - & may work smoothly. I've got to try it out.
    (Btw, David, I captured a screen shot, but I don't know where/how to post it.)
    A major thanks to all who have the patience to read so many words for a one word sentence.
    Thanks,
    Danny

  • Move multiple Web dynpro projects to one DC

    Hi all,
    I have got around twenty local web dynpro projects. Now i want to move them to a DC. I have created the domain,track,imported the Development Configuration and created the DC. Now i want to move the local projects which are there in the NWDS to the new DC. I could move one project. But how can i move multiple projects??
    regards
    Shyam.

    Hi,
    well though I would not recommend to move 20 projects into a single Dc you can still do it. Just create the DC and then goto the file navigator and copy everything from the src/packages folder from the local WD project to the src/package of the DC project. After that you should do a Reload on the DC project.
    rgds
    David

  • Multiple plants creation is possiable with one Tcode in MM?

    Hi All,
    Is there any way to Create multiple Plants at once...  like creating 500 Plants with one transaction code in MM? Don't want to use upload programme like LSMW.
    Thanks in advance.
    Shah Yan

    Hi,
    I dont think its possible to create multiple plants using a single T.Code. Since creation of Plant includes the maintenance of Address details.
    Hence the only option you have is upload tools/programs such as LSMW.
    Hope its clear.
    Regards,

  • Multiple Delivery from one project

    Experts we need inputs on this process,
    Presently we are trying to map the production/Assemble through Network with out PP module,
    but if we have multiple products (sections) delivery needed through one project.
    Thanks

    Hi PSR,
    Thanks for your response,
    Yes we will assign required material through BOM transfer with header (-ve) as final product,
    But requirement is to complete one product we may have 10 or more sections, so if we assemble only it will become final product in project site , now each section we need to show in SAP as deliver from project .

  • Multiple Developers on one Project

    Hi,
    I would like to know if there is a way that multiple developers on one project can work separately and later merge work into the main project?  I am thinking about the concept concurrent development.

    Hi Oumar,
    Use the NWDI to acheive this.
    Thanks.
    Sushil

  • How can a Multiple Projects in P6 can be linked to One Project in Unifier

    Hello Team,
    Can anyone help me with some solution to link Multiple Projects in P6 to a One Project in Unifier
    Regards,
    Avinash

    Hi Avinash,
    Hope you well.
    Not sure if this is answering your question correctly but you can set each P6 schedule to link to a specific Unifier schedule sheet in a Unifier project. You can have a number of schedule sheets in a Unifier project however only one schedule sheet can be the master schedule sheet.
    Hope this helps.

  • Re-allocating Actual Costs and Actual Work from one project to multiple projects

    My company would like to track costs in one project and then re-allocate those costs to multiple projects.  Example: An end user would submit a timesheet against a task named 'Analysis' for Project A.  Once accepted and published, the
    costs for those hours would be subtracted from Project A and 60% of those costs would be transferred to the 'Analysis' task for Project X and 40% of the costs for those hours would be transferred to Project Y. 
    We believe we can accomplish this through reporting, but before we go this route, we wanted to make sure there was not a logical, supported way in MS Project Server to complete these actions.  Could a script be developed to accomplish this?
    Thank you!
    Tasha

    Out of the box Project and Project Server do not support this. However with VBA anything is possible. You could also use PSI to work directly with project data in teh Server db but that would take much longer to develop. Check you can do what you want
    in VBA then you can use the result to spec the server version afterwards.
    Rod Gill
    Author of the one and only Project VBA Book
    www.project-systems.co.nz

  • Handling Multiple DVD as one project?

    Hi all,
    I am new to Encore. I got a chance to play with Production Studio CS3 (retail) before buying, and here is what I'd like to do to test my usual workflow:
    I have approx., 6 hours of video in PP CS3 (both DV and HDV) in one project.
    I'd like to create 3 DVD-Video disks from this. Is it possible to handle more than 1 DVD in Encore Project at once?
    If not, what is the best workflow for this?
    Should I split PP project to 3 separate ones, one per DVD, before export?
    Or is it possible to export only part of PP project to Encore (say, 1 sequence)?
    How do you usually handle multi-DVD workflow?
    Thanks,
    Vlad

    Welcome to the forum.
    The answer would be the same, even with CS5.
    Now, there is a recent thread on a user with multiple Projects, that have a common structure and many common Assets. I offered a workflow, that I have used for building a "template" Project, where one just Imports the unique Assets, edits the Menus, and then Burns that segment of a series of discs. In my case, I had 17 discs, in a set, and used that for all common items.
    If I can find that thread, I will post a link to it, however, if you do not have all those common assets, it will likely not be a useful workflow for you.
    Hunt

  • One customer to be delivered through multiple plants

    hi,
    sap gurus,
    one customer has to be delivered through multiple plants
    instead of one/single plant.
    where the configuration settings lies
    please do the need ful
    regards,
    balaji.t

    Hi there,
    When determining the plant system 1st checks in customer material info record. If not found then it will check in customer master. If not found then in material master.
    So in your case donot maintain the plant in CMIR or customer master. Just maintain in the material master.
    Also in a sales order you can change the plant manually. So change it manually.
    But make sure that all the required plants are assigned to the company code & sales org / dist channel combination. Only then you can manually change the plant. Also material should be extended to all the required plants.
    Apart from this, if you want to automatically propose plants, then you need to write a customized code in teh user exit in MV45AFZZ.
    There you have to define the conditions under which the system should automatically propose another plant. Check with your ABAPer if you want to go by the automatic method. But that is not advised as it is very complicated since it involved many scenarios to code for auto swap.
    Regards,
    Sivanand