Re-allocating Actual Costs and Actual Work from one project to multiple projects
My company would like to track costs in one project and then re-allocate those costs to multiple projects. Example: An end user would submit a timesheet against a task named 'Analysis' for Project A. Once accepted and published, the
costs for those hours would be subtracted from Project A and 60% of those costs would be transferred to the 'Analysis' task for Project X and 40% of the costs for those hours would be transferred to Project Y.
We believe we can accomplish this through reporting, but before we go this route, we wanted to make sure there was not a logical, supported way in MS Project Server to complete these actions. Could a script be developed to accomplish this?
Thank you!
Tasha
Out of the box Project and Project Server do not support this. However with VBA anything is possible. You could also use PSI to work directly with project data in teh Server db but that would take much longer to develop. Check you can do what you want
in VBA then you can use the result to spec the server version afterwards.
Rod Gill
Author of the one and only Project VBA Book
www.project-systems.co.nz
Similar Messages
-
Project POC to determine actual cost and actual revenue
Dear all experts,
please help me on the following issue.
i am working on a project for sales.
the project actual cost and actual revenue will be determined by the project POC.
i have read the SAP help about project progress.
but it confused me.
my first question is how can i caculated the actual POC?
is there a standard predefined way to solve it?
please give me some hints or suggestions.
thanks a lot.
JudyHi,
Can anyone detail the steps involved in carrying out RA with Valuation Method 7 with progressive value analysis. Here, we can give a percentage of POC into the system as certified by the Engineers unlike Valuation method 3 where the POC is calculated on the basis of actual costs incurred.
In the case of valuation method 3, only revenue is analysed by the system with reference to the POC and necessary entries are posted as Revenue surplus or Revenue in excess of billings. Whereas in the case of valuation method 7, both the revenue and costs are analysed and necessary provisions are made both for revenue and costs.
Regards,
Judy -
PLM table for Internal Order budget, Actual Cost and Actual Hrs
Dear all
In cProjects version 4.0, we have integration with existing ECC 6.0. We create Internal Order manually and assign it to cProjects.
One cProject having one Internal Order.
Resource Planning part is managed in cProjects while Actual Time keeping(CATS with reference to Internal Order), budgeting of Internal Order, Material and Service Procurement which is done against Internal Order is managed in ECC. ECC and PLM are separate systems.
We have RFCs established to transfer actual hrs, budget and actual cost data from ECC to PLM.
Which is the ABAP table in PLM where we get linking of cProject with Internal Order and also actual hrs, budget and actual cost data in PLM system?
Thanks & Regards
Ashishactual hrs, budget and actual cost data in PLM system?
Its not there, actual hours can be found in DPR_Task but it needs to be transferred by running a report.
The planned cost etc is also calculated at runtime and passed on to Costing object in ECC (Int order/PS)
Actual hours will be in CATSDB in ECC
needless to say actual cost will also be there in ECC and not in PLM, PLM only displays at runtime based on RFC.
If you want to try, Break the RFC and try to check the Evaluation..
Niranjan -
Copy and Paste Formula from One Cell to Multiple (How?)
I am aware of the "autofill" function by dragging the bottom-right corner of a cell containing a formula.
However, I cannot possibly do this if I want to copy the formula and paste it into 10,000 cells.
If I specify a range of cells to paste the copied formula - only the first cell gets it. I have seen this problem in previous iWork for a long time but am surprised Apple has not improved it (or made it obvious enough for me to get it at first sight).
Thanks!Hello
It's really boring to read several times the same comments: +When I use Autofill on formulae to copy them into empty rows I end up with little red triangles saying it isn't a valid formula. In Excel and Lotus 123 I can just use Ctrl-C and Ctrl-V to copy and paste into as many cells as I want, why not Numbers?+
Here we are not Apple employees so you are loosing your time and also the time of all of us reading your posts.
Of course we may let them unread. But as old helpers, we always assume that when someone post something, it's to ask a question to which one of us may give a answer.
Your flames are perfectly useless.
If you wish that Apple take care of your opinion, go to "Provide Numbers Feedback" in the "Numbers" menu and describe your wishes.
Happily, one poster make me laugh when he wrote that "this anomaly is a long time one in iWork".
I really don't understand how an application which is in version 1.0 or 1.0.1 may contain a "long time" anomaly !!!!
And the only responce I may give to all of you is: *if you can't live with this feature, stay with E…l.*
*We will not miss you !!*
Yvan KOENIG (from FRANCE samedi 20 octobre 2007 19:47:45) -
Joining Actuals and Planned Work from Project Server
Hi,
I have an SQL based query which returns Actuals and Planned work from Project Server; however a number of records (generally generic resources based on the ResourceIsGeneric column) are excluded. I believe this is because my Actuals query does not return
generic resources as we are joining both sides of the query on ResourceUID. I have included a snippet below - is there a way to join Actuals and Planned work so I can return all Resource data?
Thanks
SELECT tl.ResourceUID
,tl.ProjectUID
,tl.ResourceName AS [ResourceName]
,CASE
WHEN tl.ProjectName = 'Administrative'
THEN tl.TaskName
ELSE tl.ProjectName
END ProjectName
,ruv.RBS AS [RBS]
,Sum(ta.ActualWorkBillable) ActualWorkBillable
,Sum(ta.ActualWorkNonBillable) ActualWorkNonBillable
,Sum(ta.ActualOvertimeWorkBillable) ActualOvertimeWorkBillable
,Sum(ta.ActualOvertimeWorkNonBillable) ActualOvertimeWorkNonBillable
,CASE
WHEN Sum(ta.ActualOvertimeWorkBillable) > 0
THEN Sum(ta.ActualOvertimeWorkBillable)
END [HOURS]
,DATEPART(year, ta.TimeByDay) AS [Year]
,DATEPART(month, ta.TimeByDay) AS [Month]
,DATENAME(month, DATEADD(month, DATEPART(month, ta.TimeByDay), - 1)) AS [MonthName]
,puv.[Project Status] AS [ProjectStatus]
,ruv.[Primary Role] AS [PrimaryRole]
,ruv.[Resource Department] AS [Department]
,ruv.ResourceIsGeneric
,ruv.[Cost Category] AS [ResourceType]
,puv.[SAP Project Code] AS [SAPProjectCode]
,CASE
WHEN tl.ProjectName <> 'Administrative'
THEN NULL
ELSE tl.TaskName
END TaskName
,puv.[Project Plan Type] AS [ProjectPlanType]
,puv.[GEM Project Manager] AS [GemPM]
,ruv.[Rate Code] AS [RateCode]
,ruv.[Cost Centre] AS [CostCentre]
,ept.EnterpriseProjectTypeName AS [EPT]
,puv.[I DO Phase]
,puv.ProjectOwnerName AS [ProjectOwner]
FROM dbo.MSP_TimesheetActual_OlapView ta
INNER JOIN dbo.MSP_TimesheetLine_UserView tl
ON ta.TimesheetLineUID = tl.TimesheetLineUID
INNER JOIN dbo.MSP_EpmResource_UserView ruv
ON ruv.ResourceUID = tl.ResourceUID
LEFT JOIN dbo.MSP_EpmProject_UserView puv
ON puv.ProjectUID = tl.ProjectUID
LEFT JOIN dbo.MSP_EpmEnterpriseProjectType ept
ON ept.EnterpriseProjectTypeUID = puv.EnterpriseProjectTypeUID
WHERE ta.TimeByDay >= @xDate1
AND ta.TimeByDay < @xDate2
AND tl.TimesheetStatus IN (
SELECT ParamValues
FROM @ParamTable
AND ta.ActualWorkBillable > 0
GROUP BY ...
) TimesheetActual
FULL JOIN (
SELECT ruv.ResourceUID
,puv.ProjectUID
,ruv.ResourceName
,puv.projectname AS ProjectName
,ruv.RBS AS [RBS]
,Sum(abduv.AssignmentWork) AS [PlannedWork]
,DATEPART(year, abduv.TimeByDay) AS [Year]
,DATEPART(month, abduv.TimeByDay) AS [Month]
,DATENAME(month, DATEADD(month, DATEPART(month, abduv.TimeByDay), - 1)) AS [MonthName]
,ruv.ResourceIsGeneric
,puv.[Project Status] AS [ProjectStatus]
FROM dbo.MSP_EpmResource_UserView ruv
INNER JOIN dbo.MSP_EpmAssignment_UserView auv
INNER JOIN dbo.MSP_EpmAssignmentByDay_UserView abduv
ON auv.AssignmentUID = abduv.AssignmentUID
AND auv.ProjectUID = abduv.ProjectUID
ON ruv.ResourceUID = auv.ResourceUID INNER JOIN dbo.MSP_EpmProject_UserView puv
ON auv.ProjectUID = puv.ProjectUID
AND abduv.ProjectUID = puv.ProjectUID INNER JOIN dbo.MSP_TimeByDay_OlapView tbdov
ON abduv.TimeByDay = tbdov.TimeByDay WHERE abduv.TimeByDay >= @xDate1
AND abduv.TimeByDay < @xDate2
AND ruv.ResourceName <> 'Unassigned Resource'
AND ruv.ResourceName IS NOT NULL
AND abduv.AssignmentWork > 0
GROUP BY ruv.ResourceUID
,puv.ProjectUID
,ruv.ResourceName
,puv.projectname
,ruv.RBS
,DATEPART(year, abduv.TimeByDay)
,DATEPART(month, abduv.TimeByDay)
,ruv.ResourceIsGeneric
,puv.[Project Status]
) TimesheetPlanned
ON TimesheetActual.ResourceUID = TimesheetPlanned.ResourceUID
AND TimesheetActual.[Year] = TimesheetPlanned.[Year]
AND TimesheetActual.[MonthName] = TimesheetPlanned.[MonthName]Hi,
you pasted just part of your query, e.g. is declaration of @ParamTable missing. Without complete query, it is difficult to see, what you are trying to do.
Could you please provide complete query?
Barbara
To increase the value of this forum, please mark the replies that helped to solve your issue as answer. If you find answers to questions from other forum participants to be helpful, please mark them as helpful. Your participation will help others to find
an appropriate solution faster. Thanks for your support! -
Actual costs and Planned Costs
HI Friends
I want to know the Main Tables from which i can get the <b>Actual costs and Planned Costs</b> for the given Cost element or object number
I tried with table COEP and i got actual costs up to all cost elements in the given controlling area and in given cost center , but for some cost elements, this tables does not have any entries...
So is there any other way to get these Actual costs and
from where i can find the Planned Costs
Reagrds RkHi
I already checked these tables but i didn't get the exact data
for actual costs i checked COEP but some costs are missing there
and i could n't find the field BENKZ in coep table
I am comparing these values with the standard transaction <b>S_ALR_87013611 </b>
but not getting exact details in my program
can you please help me in this regard..
Does anybody worked on this transaction <b>S_ALR_87013611 </b>, then please explain me the logic how it is getting the actual and planned costs
Regards Rk
Message was edited by:
Rk Pasupuleti -
WBS Element Actual Cost and 'Detailing the Value Type ' issue
Hello BW Experts ,
I want to extract the WBS Element Actual Cost and Revenue.
I have selected the data source 0CO_OM_WBS_6 .
In this data source there is a field Detailing the value type ' 0VTDETAIL.
As per SAP BI Help if the value of this field exists between 1 to 4 then it is actual cost of WBS ( also Key figure Category 0METYPE should be 1000 for actual cost and for revenue it is 1001).
value 4 of 0VTDETAIL means CO Activity Allocations.
When I see the data from this data source in RSA3 , I could not get any WBS whose 0VTDETAIL is 1 to 4 and Key Firgure Category as 1000, value type = 10.
Is there any other data source I should select in order to get actual cost for WBS ?
I can see the settelment cost whose 0VTDETAIL = 5 through this data source in RSA3.
But I want to see the data for the Actual Cost whose 0VTDETAIL = 4 .
What could be the reason ?
Thanks in advance .
Amol.Dear Oscar,
Thanks for your response,
The Actual Cost posted by our Functional Consultant is USD 250, but i am getting the Total Actual cost is ZERO (Sum of -250 +250) as i shown above.
the posted actual cost is +250, finally we need this figure only,
if i do restriction on Sender receiver Indicater field with S than i will get Actual Cost 250, but in SAP standard RKF for Actual Cost there is no restriction on Sender receiver Indicater field (S & H)
I hope you got my point now.
Thanks
Amar Reddy -
In which table production order planned cost and actual cost i can see?
Dear PP Guru,s,
from which table i can see productuion order planned and actaul cost. i checked following tables AUFK, AFVC, AFVV, CAUFV, AFRU, AFKO, AFPO. but i did not found planned cost and actual cost field. is there any other way to get this data with respect production order?
Regards,
sreeDear,
Planned and actual costs of prod order from COEP, COSS, COSP S027 tables
production order shows the planned cost based on the quantity structure.
Please refer my reply in this thread for details,
Re: Actual Halb Material Cost
Regards,
R.Brahmankar -
Function Module to find Planned Costs and Actual Costs against WBS element
Dear All,
We have a requirement where we need to find out the Planned Costs and Actual Costs booked against a WBS element, in a year. The costs can be against all the plan versions or on individual plan version.
Are there any function modules to retrieve this value?
Thanks for the help.
Warm Regards,
JudithHi,
The easiest way would be to get the OBJNR for all WBS elements from PRPS and look up RPSCO and summarize for Value type (RPSCO-WRTTP) 1 for planned cost and 4 for Actual cost.
Please let me know if this helps.
jibat -
IW32 needed Plan Cost and Actual Cost table name
Hello ,
In IW32 transaction Plan Cost and Actual cost in cost tab ---Table Name.
Req: needed plan cost & actual cost table names for particular order number.( For New Report )
Can you please let me know where Plan cost & actual cost get stored in IW32 in Cost tab ( table name / function module name ) or how its get calcualted for particular order number.
Thanks in advance !
Regards
Rahulhi ,
i too had same issue , i wrote following FS for that :
Actual and planned cost from PMCO-WRT00 to WRT12(the sum of values should be considered for actual as well as planned ) for PMCO-OBJNR taken from CAUFV -OBJNR for order number AFIH-AUFNR and also currency from CAUFV-WAERS .
Actual cost will have valuation type PMCO-WRTTP = 4 and planned cost will have valuation type PMCO-WRTTP = 1 , which will be placed in different column
hope this helps
regards
satish -
Hi All,
When is the target cost and actual cost gets populated and from where does the data comes from liek labour,machine,overhead cost comes?
Thanks in advanceDear Friend,
speaking from controlling point of view, target and actual costs will be flown from "costing variant planned" and "costing variant actual" respectively.In above mentioned varinats, whats the process has to be followed to calculate material costs,activty costs,overhead costs etc will be defined. These variants will be assigned in order type dependent parameters OPL8.
Target Costs - In standard cost estimate(ck11n),target cost will be calculated in the following way
-material cost from material master and BOM
- activity costs from routing( for this u need to plan the activity costs in KP26)
- other costs from the definitions of planned costing variant.
- after running the standard cost estimate,u need to mark n release(ck24).
Actual Costs - material costs frm goods issues (via goods mvmts thru MBIA,MB1B etc) against
production/process order.
- activity costs(as per the price u plannned in KP26)through operation confirmation in
COR6N/CO11N.
- any other costs like overheads,cost center issues etc as per the process defined
in 'actual costing variant'.
Hope this will clear your doubt.
Rams. -
Dashboard content is not populated with Planned Cost and Actual Cost
Hi
We are working in cProjects 4.0 + ECC 6.0 implementation. I could not get the data for columns in Planned Cost and Actual Cost in cProjects Project Dashboard. I have properly mapped the config settings and created and assigned a Project in PS
Has anybody got this data in the Dashboard?
Kindly suggest the solution
with regards,
K Rama Krishna
9394712743Hi Rama,
It is difficult to say, where the problem is.
but typically, the causes of the problem are
customizing is set incorrectly or the evaluation is not carried out.
You can run the the evaluation DPR_EVE_BATCH_DPO additionally, please untick the flag 'check the last changed date'.
Hope, it helps.
Kind regards,
Zhenbo -
In IW32 no Planned Cost and Actual is showing Zero
hi,
In IW32 no Planned Cost and Actual is showing Zero,since activity type is mentioned.
how it could be displayed.
ThanksDear Sharma,
1. This is regarding Maintenance order, frist you confirm by clicking on the operations tab-> double clicking on the work center->click on costing tab, check here activity type, activity unit is maintained.
2. then in in KP26 check the activity price in the current period.if it is zero u will get zero
3 then in the order click on components, if components are consumed also check the component price in material master.
this will resolve your issue
sree -
Service Order Actual costs and revenue
Hi,
Can you please let me know how to find actual costs and revenue related to service orders?
what tables to go to?
We are planning on going back to a service order from the billing document and get the actual labor costs.
Thanks,
MSHi Mahesh,
Thank you very much for that quick response.
EKKO is for purchasing documents. Can you please let me know how to use it for my service order?
Thanks,
Maulik Shah -
Target cost and actual cost not picking in production order
Hello,
The target cost and actual cost is not updating in production order when I display it in CO03 in cost analysis.
Even though we have maintained planned price in KP26.
Please suggest how it can be populated.
Best Regards,
TapanHi Tapan
For Target cost
1. Your std cost must be released before Goods Receipt
2. There must be goods receipt posted on the prod order
3. You must calculate variances in KKS1/2
For Actual Cost
1. Post Goods receipt and Goods issues
2. See if any mat movements are pending in COGI
3. Ensure that operation is confirmed in PP and no entry is lying in COFC
Regards
Ajay M
Maybe you are looking for
-
How can I move mail from the offline folder inbox to a local folder?
I have an IMAP account and my provider lost all but the last week of my emails. I still have them in the offline folder in Thunderbird so as long as I stay offline I can see the emails but I want to move them to local folders so I can go back online
-
Transferring photos from iPhone 3GS to Computer
I know this has been asked probably many times and I tried to click on the link that tells you how to do this. it wont come up and I have scrolled thru many posts. I cant find the information. I need to transfer my pictures from my Camera Roll on my
-
Elements 13 will not open slideshows from Elements 11
Upgraded to Photoshop/Premiere Elements 13 and when I try to open slide shows created in Elements 11 and edit them I get a message "Please select some media." Slideshows still open and work in Elements 11. Thanks
-
External Midi Plugin and Midi Output Delay
This one is fairly esoteric but has anyone run into the following problem or have a workaround? I'm trying to incorporate the External midi plugin into my setup so I can use the new midi plugins, but I cannot correctly calibrate my system when using
-
Align JLabels and JTextFields vertically in different areas
I like to have 3 TitledBorders for 3 different areas of my frame. Each area has its own components - JLabels, JTextField, etc. How to align JLabels and JTextFields vertically in different areas? e.g. for the following test program, how to configure l