NWDI in the XI Scenario - SLD

Experts,
I have created a track to transport the XI content.
We have two SLD servers in the landscape. The first is used by XI and contains all the required XI business systems and the second is used only by NWDI and contains only the SC definitions.
My question-
DOes the SLD for NWDI need XI system details???? According to my understanding, NWDI needs only the component information from the SLD.
Bascially, do i need to import the business system data into the SLD that is being used by NWDI???
thanks,
Vineeth

Did a little research and found that the SC information is sufficient for NWDI.

Similar Messages

  • NWDI in the XI scenarion, SLD

    Experts,
    I have created a track to transport the XI content.
    We are currently using 2 SLDs. the first for the XI which contains all the XI business system details and the second SDL only for NWDI.
    The SLD for NWDI currently has only the Software Component details and does'nt contain and system details.
    My question-
    DOes the SLD for NWDI need XI system details???? According to my understanding, NWDI needs only the component information from the SLD. The actual transport of the sources is done using the SDM. Am i correct??
    thanks,
    Vineeth

    that's true. You will require XI component information in NWDI only if you are maintaining any objects like modules, services for XI using NWDI.
    When coming to transports, you can maintain tracks to maintain the information for XI as well as NWDI seperately.
    Reward if helpful,
    sarath.

  • SRM to MDM Scenario -- Unable to Edit the Integration Scenario

    Hi Experts,
    I'm doing a scenario in XI/PI from SRM to MDM.
    I had downloaded all the related content from service market place and also established SLD connections as well.
    When I'm trying to import the Integration Scenario from Integration Repository to Integration Directory I'm getting the follwing error.
    Software component version with GUID 77891250-7da4-11d8-b240-e6890a114c15
    does not exist (SWC_NOT_EXIST)
    I'm unable to edit the integration scenario in IR even with PISUPER credentials which have all the access.
    I'm also unable to edit any of the other objects as well (e.g.,Message Interface,Interface Mapping etc.,)
    PFB the link where I pasted the error snapshot I'm getting when I'm trying to open the Integration Scenario in IR.
    [http://picasaweb.google.co.in/prajwal24/MyScenario#5492932473682114498]
    Can anyone please help me out on what can be done to edit the Integartion Scenario.
    Thanks and Regards,
    Pruthvi

    Thanks kaushik and Salvi for your valuable inputs.
    I have created a copy and now able to edit the Integration Scenario.
    But again a new problem came up.
    Now after editing the predefined scenario which has only SRM 5.0 and SRM 7.0
    I need to add SRM 7.0 application component here in this Integration scenario and this was done successfully.
    Now i need to add one send action and this send action is present in the SWC SRM SERVER IC 7.0.
    I had downloaded the SRM SERVER IC 7.0 content already and I'm able to see in Integration Repository also.
    But this SWC is not present in the application component SAP SRM (WITH SAP EBP) 7.0.
    Please let me know what to do now inorder to add this send action in that application component.
    Regards,
    Pruthvi

  • In solution manager system not showing all the system in SLD

    Dear Gurus,
    During the installation of solution manger sysyem i selected as a Central SLD as solution manager
    Later installed ECC 6.0 and EP systems selected SLD as solution manager system during the instllation.
    If i login in to http://hostname:50000/sld (solution manger system) and the screen also not showing all the options also. some options missing in the tab. Wat I need to do to see all the options clearly.
    It is not showing all the systems if i check in EP and ECC for SLDCHECK it is not givng any errror.
    But if i login into solution manger not  able to see all the system in SLD.
    Regards

    Thanks for reply
    it is not showing all the systems

  • Number of document created in th backend in the classic scenario?

    Dear Experts,
    Could you please tell me the number of document and its details created in the ECC backend in the below cases?
    1. Case 1:
    Define backend objects:Purchase requistion created if no stock available.
    Is it correct that the system will create two documents here? The first document will be Purchase Requisition
    ( from the classic scenario) and then a purchase order has to be triggered manually from the PR?
    2. Case 2:
    Define backend objects: Purchase Order if data complete, otherwise Purchase requisition.
    Here, if all the data are complete and the system directly creates Purchase Order in the ECC backend system. From the shopping cart in SRM, one can see only ECC backend purchase order, no purchase requistion. If i check the Purchase Order in ECC backend system, I donot see any purchase requistion with reference to the Purchase Order.
    Could you please help here? What are the number of documents created here? It is one or two (both purchase requisition and Purchase Order).
    Is it not a violation of standard classic scenario if only one document is created?
    Thanks and regards,
    Ranjan

    Hi,
    In other words in the shopping cart is approved
    1) If the source is assigned  -It will create a P.O in  the backend  (Classic)
    2) If the source is NOT assigned  -It will create a P.R in the backend (Classic) .. you have to assign a  source
    Regards
    G.Ganesh Kumar

  • What are the major scenarios to customize DAF pipeline ?

    Hi,
    In which purpose DAF pipeline need to be customized.
    Please tell me what are scenarios to customize the DAF pipeline.
    Thanks In Advance.

    Some of the probable scenarios where we might want to customize the DAF pipeline: autologin based on a custom logic; implementing SSO; to set some request attributes based on request URI and/or parameters which can be used by the subsequent servlets/filters or other components; detect device type based on user-agent and other parameters/attributes; trigger a custom event on some action like page view etc.

  • How to deal with BRS for the below scenario?

    Hi,
    I would like to know the solution for the below scenario for BRS:
    I have a customer who was maintaining their accounts with Tally software for their previous Financial Year. This year they have shifted to SAP B1 2005B. They have issued few cheques for their vendors in the month of march 2008 which has been realised in the month of April 2008. As per Tally, the closing balance of their bank is 8 Lakh but as per the bank statement, their closing balance is 23 Lakhs. In SAP, the opening Balance for the bank is considered as 23 Lakhs. Now there are 15 Lakh worth cheques which were not realised for the month of March 2008.
    Example:
    abc a/c - 3Lakh
    def a/c - 5lakh
    xyz a/c - 7 lakh
    How do i reconcile for this scenario and what procedures do i follow in SAP?
    Thanks and Regards,
    Kaushal

    Hi Kamlesh,
    Thanks for your response.
    Actually, In the "Process External Bank Statement" window, i see that there are few entries which is for the previous year and which has not been reconciled. I have never worked practically on BRS and hence, i am scared to make any changes in the clients database without being confident on what i am doing. I need to reconcile for one of their Bank a/c for the month of April '08. I have the copy of the statements for the month ending 31st Mar 08 and 30th Apr 08. The closing balances are as below:
    31/03/08 - 2300000.00
    30/04/08 - 3100000.00
    Now my OB for Bank a/c for April '08 in SAP is 2300000.00 Dr.
    When i go to External Bank Reconciliation - Selection Criteria Screen (Manual Reconciliation), here are the detail that i enter:
    Last Balance: INR -7,000,000.00000 (Grayed out by the system)
    Ending Balance: INR -3,100,000.00000 (Entered by me)
    End Date: 30/04/08 (Entered by me)
    "Reconciliation Bank Statement" Screen opens up and shows the below balances in the screen:
    Cleared Book Balance: INR -7,000,000.00000
    Statement Ending Balance: INR -3,100,000.00000
    Difference: INR 3,800,000.00000
    As per the Bank statement, i have found all the transactions listed out here for the month of Apr '08 but, i also found that the open transactions for the previous month from April '08 have been lying in "Process External Bank Statement" window.
    Could you please help me solve my issue as to what needs to be done or could you also get me some links from where i can get few documents for processing External Bank Reconciliations?
    That will be of a great help for me. I need steps as to what needs to be done first and then the next so that i can arrive at the correct closing balance for the month April '08.
    Thanks in Advance....
    Regards,
    Kaushal

  • Can anyone tell me the field name, table name for the following scenario?

    Hi All,
    Can anyone tell me the field name and the respective table name for the following scenario's?
    1. A report to list all the materials to which Invoice is done and delivery is pending.
    2. A report for Order tracking.
    3. A report, which gives PO(Purchase Order),  Pricing details.
    4. A report, which calculates the MATERIAL COST. It will select all the material issued for the entered service order number from  stock.
    Thanks & Regards,
    P.Gowrishanker
    Edited by: Gowrishanker pari on Jun 1, 2008 8:58 AM

    I believe that OmniVision Technologies has the contract for the 3gs.

  • Provide the java code for the following scenario.

    Hi Experts,
    I have tried with all the combinations for this scenario. As per my understanding i require java code for the following scenario
    so that it becomes easy........
    I require a Message mapping for this Logic.
    In the Source there are 4 fields and, the Target side, the fields should appear like this.
    Source Structure- File
    Record
    |-> Header
    Order_No
    Date
    |-> Item
    Mat_No
    Quantity
    Target Structure-IDoc
    IDoc
    |-> Header
    |-> Segment
    Delivery_Order_No
    Recv_Date
    |-> Item
    |-> Segment
    Delivery_Order_No
    Material_Num
    Recv_Quantity.
    The Logic is for every Order number an IDOC is generated.And if the Material num matches then the quantity should be added. and important note is that the material numbers are different for every order number. That means if a material number is 2 in the order number A. Then the material number can never be 2 in any of the order numbers.Here is the following with an example for the above scenario.
    For example:-
    we have
    Source Structure- File
    Order-no Date Mat_No Quantity
    1 01/02/2011 A 10
    1 01/02/2011 B 15
    1 01/02/2011 A 10
    2 01/02/2011 C 10
    2 01/02/2011 C 10
    3 01/02/2011 D 20
    3 01/02/2011 D 10
    3 01/02/2011 E 25
    Target Structure-IDoc
    Delivery_Order_No Recv_Date Material_Num Recv_Quantity
    1 01/02/2011 A 20
    1 01/02/2011 B 15
    2 01/02/2011 C 20
    3 01/02/2011 D 30
    3 01/02/2011 E 25
    So for this example total of 5-Idocs created. That means for this example if Order_No is 1 When the Mat_No is A the quantity gets added. For this Scenario 1 IDoc with four Fields 2 in Header(Delivery_Order_No, Recv_Date) and 2 in Item(Material_Num, Recv_Quantity) is generated by adding the quantity field in the Target Side. Similarly if Order_No is 1 when the Mat_No is B then separate IDoc is generated with four Fields 2 in Header(Delivery_Order_No, Recv_Date) and 2 in Item(Material_Num, Recv_Quantity) in the Target Side. Similarly, if Order_No is 2 when the Mat_No is C, an IDoc is generated with four Fields 2 in Header(Delivery_Order_No, Recv_Date) and 2 in Item(Material_Num, Recv_Quantity) by adding the quantity field in the Target Side. ike wise the process goes on upto 3.Kindly do the needy..
    Kindly provide the java code.
    Thanq very much in advance..

    what i have understood from ur example is that u want to generate an idoc for unique combination of  Order-no and Mat_No
    if yes then chk the below mapping..
    change the context of Order_No, Date, Mat_No and Quantity to Record (right click-> context)
    1)
    Order-no
    ----------------------concat[;]---sort----splitbyvalue(valuechanged)-----collapse context---IDoc
    Mat_No
    2)
    Order-no
    --------concat[;]---sort----splitbyvalue(value changed)---collapse context---UDF1--splitbyvalue(each value)--Delivery_Order_No
    Mat_No
    3)
    Order-no
    -----------concat[;]---sortbykey----------------------- \
    Mat_No                       /                            \
    Date--------------- /                                       \
    ----------------------------------------------------------FormatByExample-----collapsecontext---splitbyvalue(each value)----Recv_Date
    Order-no                                                 /
    -----------concat[;]---sort----splitbyvalue(value changed)
    Mat_No
    4)
    Order-no
    --------concat[;]---sort----splitbyvalue(value changed)---collapse context-UDF2--splitbyvalue(each value)--Material_Num
    Mat_No
    5)
    Order-no
    -----------concat[;]---sortbykey
    Mat_No                       /
    Quantity --------------- /
    ----------------------------------------------------------FormatByExample-----SUM(under statistic)----Recv_Quantity
    Order-no
    -----------concat[;]---sort----splitbyvalue(value changed)
    Mat_No
    UDF1:
    String [] temp= a.split(";");
    return temp[0];
    UDF2:
    String [] temp= a.split(";");
    return temp[1];

  • What is the appropriate data expiration / eviction scheme for the following scenario

    We currently have an expiration scheme through which data entries in cache-A get expired after the cache hits a certain size. The LRU entries are expired after the max threshold is reached. But the issue is that certain entries in the cache are rendered meaningless without the other entries. There is a virtual grouping of entries in this cache.
    Is there an expiration scheme that can be defined through which a group of entries can be deleted in one shot, and how can this policy be enforced.
    The other way i would percieve this to work is to separate the currently virtually grouped entries into their own individual caches. This seems the logical thing to do, except for the issue being that we would still like to keep all these caches in the same service, and have an eviction policy defined at the service level instead of at the cache level.
    Is it possible to define an eviction policy at the service level, for example to satisfy the below scenario.
    Service-A has 10 caches in it [cache-1, cache-2, ....., cache-10]. And there is a limit of 10GB defined on the service. So, if the total utilization of all the caches in Service-A reaches 10GB, an entire cache from amongst [cache-1, cache-2, ....., cache-10] will need to be cleared and the memory be made available. Which one of the caches to be cleared will depend on which cache satisfies the LRU condition. So, maybe the entire cache-5 should be deleted if the entries in this cache was the oldest used.
    Please let me know if the above scenario can be implemented.
    Thanks
    Sumax

    Ricardo Pedro Rodrigues Ferrão wrote:
    > Hi Eugene,
    >
    > I’ll try to explain it better.
    >
    > For example the business unit A is “portable pc” and I have this business unit in both companies and what I want in management consolidation is to consolidate data by the business unit “portable pc” joining data from both companies.
    >
    > Thanks.
    Ricardo,
    I had similar business scenario in my earlier project and the expectations were almost same.
    I created one consolidation area (legal consolidation) under one single data basis and assigned business area as sub-assignment. All the consolidation functions are executed by the business users based on legal cons requirements purpose, while the reports can be generated for both legal and management consolidation.
    In management consolidation reporting, your expectations can be met easily. The header will be business area, while line item data will be companies wise (if you would like the data to display that way).
    For more information, you can check the threads created by me.

  • What are the business scenarios used in plastic industry

    Hi Experts,
    Could you guys please tell me what are the business scenarios (in sap sd) i should use while implementing in plastic industry (as if someone already worked on implementation project at plastic industry).....
    As per my knowledge i would use:
    MTS
    Batch management
    Third party etc....
    but in addition to these (if anyone already worked on the implementation project in plastic industry...then what are the business scenario used for......please suggest.....)
    If have any idea please suggest........ would be a great help.......
    Thank you in advance...........

    it depends which part of the value chain you are working at e.g. your company is B2B, supplying ingredients to Plastic industry manufacturer or you sell to wholesellers.
    Below are the processes you - may - do in Plastic industry -
    - Inter-company stock transfer
    - Subcontracting
    - Contracts
    - QM inspection during delivery process
    If you require business scenario descriptions (in brief) for the above processes, then please convey.
    Edited by: Typewriter on Jul 11, 2011 11:30 AM

  • Need best Architecture design for the following scenario

    Hi Experts,
    I need best architecture design for the following scenario:
    Sender: Mail
    Receiver: if sender body contain u201DApproveu201D, then call SOAP adapter, If SOAP adapter execute successfully, then  send Mail(SOAP adapter executed successfully) and SMS .  So receiver is SOAP, Mail and SMS.
    My current approach issue:
    Three message mapping:
    Mapping1: mail to SOAP
    Mapping2: mail to Mail
    Mapping3: mail to SMS
    In interface determinant>u201DSelect all three operation mappingu201D> u201Cselect order at runtimeu201D.
    Issue in current approach: For me first SOAP adapter should complete successfully, after that only my Mail and SMS operation mapping should execute:
    But problem is before success of SOAP adapter engine, Mail and SMS mapping completed or integration engine executed.
    Note: There is possible to fail the SOAP request in adapter engine.
    Kindly help me --> u201CAm I going correct way or want to change the architectureu201D?
    Thanks for advance!!
    Regards, Kumar

    What do you mean by successful execution of soap call?  Are you talking about Successful response (happy flow) from the soap call instead of application error ? Then based on the response you want to decide sending mail and sms.  How big call is your soap ?  If your soap interface is very simple I can give the other possible way.
    Sender sends the message, use mapping  to read the content and then do soap call in the mapping itself and after seeing the soap response decide about two receivers (mail and SMS).  If your soap call is very simple one, you can go for it. Otherwise I would not recommend this. The reason is you loose some visibility regards to monitoring during soap call in the mapping.
    Other option is go for CCBPM.  Here you receive the message, use send step to soap interface which is sync step. Then after seeing the response create another block with fork steps each for two senders mail and sms. If response bad then dont proceed or execute the next block. Simply use exeception or control step to jump out from the block,

  • Error in Master Data Out-of-the-box Scenario Customer

    Hi Experts,
    I set up a normal out of the box scenario of master data that is supposed to sincronize just Customers, but when I create a supplier It also creates it in my subsidiary company.
    I read the documentation Config_Guide_SAP_Business_One_Master_Data_Distribution_EN.pdf and it´s clear when it said that this scenario is only for Customers. Even in the appendix the card type it´s supposed to be mapped with the fix value cCustomer.
    I checked the xsl file and the cardtype is also mapped as it comes from the sender so I do not understand exactly what it does.
    I continued with my testing and when trying to update any field in a supplier an error appears.
    So, if it´s only for customers why does it create the suppliers?
    and if suppliers are also sincronized why cannot update any field?
    Thanks in advance,
    David

    Hi experts,
    I found the field that caused the error when updating suppliers. This field is
    <OtherReceivablePayable>
    <xsl:value-of select="BO/BusinessPartners/row/OtherReceivablePayable"/>
    </OtherReceivablePayable>
    If this field is not mapped the scenario works ok for suppliers also.
    I do not understand why in the documentation this scenario is supposed to be just for customers because is for all IC.
    I suppose is an error but if someone could confirm it would be perfect.
    Thanks anyway,
    David

  • How to test the B2B scenario ?

    How to test the B2B scenario ?
    Because the client may not give permition to test, then i heard  one thing in RWB we can test the data, how and where we can test the data ?

    Venkat,
    Follow the below procedure.
    Go to RWB, choose Component Monitoring , click Click Display
    Expand Integration Server node -Click Integration Engine .
    In the bottom of the page go to TestMessage tab.
    In the Service/Interface/InterfaceNamespace enter the Sender Service & Outbound Interface details
    Enter your username & pwd and choose the qos.
    Paste the payload in the payload area.
    Now click SendMessage .
    Done!
    raj.

  • How to map the permits Scenarios

    Dear Experts,
    Good Morning  to Every to Body.
    I am confusing to map the permits scenario . In my client place they raise the Work permit request to the Safety Officer for getting the approval for doing their work.
    Based on working condition safety officer checks the safety precautions , after verification he approved it and handover to the workperson. if safety officer not satisfied with safety precaustions he deny to give the approving for start the work. this is one scenario. and this work permit valid only for that approved day only. if its not complete that day , next day again workpermit was raised by work person or incharge of the work.
    2. scenario : for any corrective action on running machine or predictive maintenance time , maintenance people gets the work approval from the Relevant department or Concerned persons. Ones relevant department head gives approved , then only maintenance people will start the work.
    i am requesting you please guide me how to map in sap with out complexity. i am waiting for you people response.
    please suggest me.
    thanks & regards
    Jalu

    Hi,
    There are 2 different type of permits.
    1. Safety Permit
    2. Work Permit
    Safety permit will be approved by Safety officer. This is your first scenario. Work permit is approved by Maintenance officer, that is your second scenario.
      IWO10007 Maint.order: Customer enhancement - permits in the order
    As permits are approved in IW32, through above mentioned User Exit, you can develop some logic to restrict the authorisation between Safety officer in case of safety permits & Maintenance Manager in case of work permits.
    Regards,
    Maheswaran.