Planned price in material master default in valuation price in PR

Hello,
I want to default planned price  of material master in valuation price of Purchase requisition,
Currently MAP is defaulted in valuation price field in Purchase requisition.
Is this possible by using any user exit?
Regards

Yes this is possible .you have to use the BADI    ME_PROCESS_REQ_CUST  and method PROCESS_ITEM  if the PR created manuallly or through MRP. Try this User exit also MEREQ001
If the PR created through sales order you could use user exit in sales order   program name:SAPMV45A and subroutine : USEREXIT_MOVE_FIELD_TO_ME_REQ in the include MV45AFZB.
Appreciate if it is helpful

Similar Messages

  • Material Master Default Values

    Dear All
    Whenever we create a material, we want to have the same value as default for a particular field in one of the Material master views.
    Is this possible and how can it be done?
    Regards
    Hary

    Hi Hary,
    Discuss with an ABAP consultant & find the user enhancement for the material master screen & then get the user exits  for the fields.
    Give the list of fields you need to have default values, then it can coded in the include program.
    To find a user exit use T.code SMOD.
    For further coding use T.code CMOD.
    Regards,
    Senthilkumar SD

  • MRP TYPE for  Periodic planning in the material master.

    Dear gurus,
    i need planned the materials in the periodic modality, are there the type MRP in the material master for create the planned file ( table MDVM) one once a month or in the specific period chose ?
    Example :
    I need that the material master don't create a file planned ( MD20- TABLE MDVM) for a change of the requirement situation new , but i would like that the flag in the table ( MDVM) or file of the planning MRP created when the today date is in the period specific.
    31.3.2011  (or period 1.4.2011- 10-4-2011)Date for the create a file MRP and after when run MRP planned the material, for others scenary the system must not planned the material.
    Are there the MRP type for my problem? Or the customizing setting?
    Thanks a lot
    Dani

    Dani,
    Not sure if MRP type or customizing can help here. And even if we are able to achieve this requirement it will be applicable at plant level.
    However, try exploring option of periodic lot size (weekly, monthly, etc). This will work according to period you've set and should give you the results you are looking for.
    Regards,
    Himanshu

  • Activating split valuation in material master (autom. batch valuation cat.)

    I want to activate the split valuation (automatic batch) in several materials. These materials have purchase orders, schedule agreements or production orders, etc...
    Is there any way to activate the split valluation without deleting all the related documents?

    Hi,
    You want to activate batch management on materials that have stock and
    transactional data like PO's production orders etc.
    Refer note - 533276 , which makes a mention of report -
    RVBCONVMAT2BM.
    This report can activate batch management without the necessity of
    manual preliminary works such as the posting of the stocks or the
    completion of open documents.
    If this report does not exist on your system then SAP will provide the report as a different tool and will charge for it.
    Hope wil help u.
    Deepak

  • Planned price in process order

    Hi Gurus,
    We have a problem with planned cost for the BOM in process order
    We are not getting planned price for in-put materials, where as we are getting actual cost for the in-put materials
    We have maintained price in material master.
    Split valuation also maintained for the materials.
    How to get the planned price for those in-puts.
    please any body suggest me in this.
    waiting for the reply
    regards,
    anand.M

    Hi,
    Please find the link
    Difference between Planned cost..........
    Thanks and regards
    E.Rambabu

  • Material valuation with respect planned price 1 in material master

    Dear All,
         The costing variant PPC1 has been used for released cost estimate. In my scenario I want to create one more variant say ZPC1 where to calculate the value of the material from the planned price 1. In this case
    1.     What should be the validity date mentioned in the material master for valuation
    2.     The variant has been configured as
    a.     Costing Type – 12 Mod Std cost Est
    i.     Price Update – No Update
    ii.     Save Parameter – With Start of Period
    iii.     Misc – Cost Sheet
    b.     Valuation Variant – 001 Planned Valuation
    i.     Material Valuation - Planned Price
    ii.     Standard Price
    c.     Date control
    i.     From Date : Start of Current Posting Period
    ii.     To Date : End of Current Posting Period
    iii.     Qty Struc Date : Current Date
    iv.     Val Date : Current Date
    d.     Qty Structure Control (As PPC1)
    3.     When I run the standard cost estimate with variant ZPC1 the system calculates the standard price of the material even when the price is mentioned in the planned price1. 
    How the variant should be created to capture the planned price for calculation when using the variant ZPC1.
    Kindly help me in this regards
    Regards
    Vasantha

    HI,
    The requirement is to execute the cost estimate quaterly for planned price 1.
    So we are planning to create separate costing variant to pick the planned price 1 of RM.
    Clinet has the Excel file with the details of RM and Price combination but the prices are not available in SAP.
    We are looking for the Mass transaction to upload the prices in Planned price 1.
    Kindly help.
    Thanks,

  • Inter company PO is not pulling the valuation price from Material Master

    Hi Experts,
    We have a scenario, Inter-company PO with pricing procedure which pulls Material Price from Material Master (Std Price), similar to intra company PO
    Even after maintaining the std price in the supplying plant , system is not pulling the Valuation price from Material master only for a particular Material
    I checked the Plant level attributes ( for ex: Plant Mat status, client level status and everything looks fine )
    Could you guys please mention what would be the issue ?
    Thanks in advance
    Illayaraja

    Hi,
    Is there a routine which pulls the value? then you need debug with ABAP help for that routine where its failing to pull
    Thanks
    Diwakar

  • *How to change the Valuation Category & Price control in material master*

    Hello SAP Gurus,
    I have a requirement to change the valuation category from 'X' to '  ' in accounting view of material master.
    -> I have cancelled all the open PO's & SO's for the material
    -> I have ensured that there is no stock for the material in that valuation area.
    But still I get an error message that batch already exists for the material. When I check entries in MCHB I find that there are previous entires in MCHB with zero stock.
    I have gone through the SAP note 155874 which recomends the archiving the effected objects.
    Please let me know is there any work around to change the valuation category from 'X' to '  ' & price control 'V' to 'S'. I also need to change from '  '  to 'X' for a few materials.
    Thanks for your advise.
    Best Regards,
    Narayan.

    Note 155874 cleary describes what has to be done to be able to change.
    There is no workaround, and if you change anything in the tables directly, then this will cause inconsitencies, as described in this note as well.

  • Set default value for price unit when creating material master data

    HI: Every
    could you tell me how to use user-exit or else ways to set default value(such as 1000) for field "Price unit" (MBEW-PEINH) when creating material master data(MM01)?
    I have try to use Exit:EXIT_SAPLMGMU_001. However, this way cannot respones it.
    thanks
    Henry

    Hi: Ihave find out a solution
    Use BADI: BADI_MATERIAL_REF
    SPROlogistics general enhancement supplement or change default data (industry)
    And then creating a Implementation Name
    Double click method: CREATE_MATERIAL
    And then write code as below:
    method IF_EX_MATERIAL_REFERENCE~CREATE_MATERIAL.
              c_mbew-peinh = '1000' .
    endmethod.
    However, SAP still store '1000' in database evenif we change the default value such as 100 when we use TCode MM01.
    in additional, we still use MM02 to change the default value such as '100'
    can anybody tell me how to do?
    thanks
    Henry

  • Material master valuation price from S to V

    Hi,
    is there a way to change from price S to V in material master ?
    How can I do it if FI department decide to change valuation from S to V ?
    Regards

    is there a way to change from price S to V in material master ?
    How can I do it if FI department decide to change valuation from S to V ?
    Hi
    First you can do your stock for that material as zero.
    And also close or delete all the respective documents like PO,GR...etc.
    Then only you can able to change the price from S to V
    Regards,
    Rahul

  • Default costing lot size and price unit as 100 in material master

    Hello,
    The costing lot size and price unit is "1" by default in material master. Due to this in CK11N the costing lot size is coming as 1.
    Then we go to MM02 and change the master by making costing lot size as 100 and price unit as 100.
    Please advise how can we make this default as 100 instead of 1 in material master. So that everytime we don't need to change.
    Is it coming from BOM?
    Please suggest.
    Regards,
    Tapan

    Hi Tapan
    No doubts, it is ABAP's responsibility to develop it.. It requires ABAP code to be written
    The functional specifications need to be given by you.. This BADI is called during Mat Master Creation/Change.. Your Func Specs should cover
    1. Which Mat types it should be used for
    2. The costing lot size and price unit to be defaulted...
    I used it to check Plant = Profit Center and it worked... For whatever checks and validations required during Mat Master creation, this badi needs to be used
    Regards
    Ajay M

  • How to reset planned price in material master

    Hi Gurus,
    Can anyone tell me how to reset planned price in material master.
    my user has run ck40n with wrong values, but i am not able to reverse costing run by using ckr1 or ck44. what could be the reason behind this.
    even after executing tcode ckr1, i can still see the standard cost in material master.
    how to reverse the costing run.
    Thanks in advance
    Suresh

    Hi,
    If you want reset you can delete the cuurent planned price in the material master for the cuurent period,
    Use t.code CKR1,  you have to enter comapny code, plant,material
    In control parameters you have to choose radio button Current Standard Cost Estimates
    Current Standard Cost Estimates
    If you set this indicator, the system will select the current standard cost estimates for deletion.
    If you also set the Additive cost estimates indicator, then additive cost estimates will be selected for deletion.
    Regards,
    Rama Mohan Bangaru

  • Remove planned price from material master

    Hi,
    By error we have a price in the planned price field MBEW-ZPLP1 , i have noticed on mass change MM17 there does not seem to be ZPLP1, does anyone know how we can remove this price from the material masters without going in each material individually?
    Thanks
    Frankie

    Hi Frankie,
    PLease read the note 323892 which explains the reason why this field can not be mantained with MASS transactions.
    Best Regards,
    Arminda Jack

  • Defaulting values in material master creation

    Hi,
    I want to have some filed values to be appeared as default in all the views while creation of material master.
    By user settings, I can restrict Org level values such as C Code,S Org Distribution Channel etc etc.
    But how to make field values such as account assignment grop,division,valuation class,price control,transport grp,loading grp etc appearing default so that user does not have to think.
    Regards,
    manOO

    Hi,
    You can set values for Parameter IDs of the fields that you want to default.
    Set values in system -> user profile -> own data under parameters tab.
    For example Disision's parameter id is 'SPA'. You can set a default value for division by giving proper value for SPA under parameters data in own data.
    Hope this will help.
    Regards,
    Naveen.

  • Price update from Original Material to copied Material Master

    I have a scenario,
    We are selling Raw materials to outside companies who have shortage of materials on Loan Basis. Once they have materials, they will return the materials within a time period. If they don't have the materials and unable to return within the said time, they will make the payment.
    We will follow the normal sales process to sell the item to the customer.
    1. creating sales order,
    2. Outbound Delivery, and
    3. Billing
    Return process when receiving the materials from the company.
    1. Billing Cancellation
    2. PGI Cancellation
    Since this is not an actual sale, hence we need to maintain selling price same as the purchase price.
    We are planning to extend the Raw Materials to Sales View in the material master. However, we came to know that this will be Violation of Act. Hence we are planning to create a new material by copying the existing Raw Material master but the Material type will be Issue on Loan. This material will have sales view and purchase view.
    This material will have a separate Valuation Class. Price control indicator will be V, since the item should be valuated at Purchase Price and the purchase price will keep changing as and when the price changes. This moving average price will be used as selling price.
    The same price needs to be updated in the Sales Order automatically from the Loan Material Master when selling the Loan Material.
    Now, the problem we are facing is, if we create a new Loan Material by copying Raw Material master with ROH material type, how will the price update in New Loan Material since, we will not purchase the Loan Material. We are purchasing the original item as raw material. Hence, this will not update the Loan Material Price automatically and the price will remain unchanged.
    Please suggest a work around?

    Hi,
    Let me explain to you how I am proceeding.
    Step 1:
    Create new material master by copying existing Raw Material with Issue on Loan material type. I am assigning a new Valuation Class in this material master. Also, we keep the pricing
    Step 2:
    Transfer stock from old material to new material in MB1B with movement type 309.
    Step 3: Issue of Loan Material to Customer on loan basis.
    Creating Sales Order, PGI and Billing
    Step 4: Receipt of Item back from Customer
    Sales Return process.
    Step 5: In case Customer does not return goods, then we will collect payment from them
    In the entire process we need to maintain the selling price at purchase price of the original material. Can you suggest any work around, in case this process is not advisable.

Maybe you are looking for

  • NWDI setup, problem while deploying .sca files on SAP PI 7.1 server

    Hi I have a SAP PI 7.1 server. I want to setup DTR on it. From service market place i downloaded the required .sca files Location: Support Packages and Patches --> Browse our Download Catalog --> SAP NetWeaver and complementary products --> SAP NETWE

  • Cannot upgrade CC suite

    need help with CC update installs receive errors when attempting update through CC app, through the update option within individual applications and when logged in on my Adobe account

  • Automotatic Message Determination:Consignment Settlement

    Friends, I need some help in after doing the consignment settlement process: After I run MRKO and settle the consignment once a month, I need to send a form to the vendor detailing the settlements done over the period of one month. My questions speci

  • Installation Difficulty

    I am a High School Library Media specialist who is trying to install Adobe Flash Player on several desktops within a classroom. The computers OS is Windows 98. When I visit the website that students need to use, I am provided with the information tha

  • Create workflow for parking document

    hiiii all can any one tell me in detail, what is the function of  creation of work flow for parking document? and how do i configure? and how do i assign with user? please help menu path :- financial accounting global settings - document - document p