Problem issueing material from one WBS element to another

Hi Guys,   This is my first post so be kind.
Our projects during their life cycle change their WBS element sub number.   Example New project starts with WBS element # E.7029.00.010  at some point in the project it moves on to the next level and the WBS element changes to E.7029.00.020  later in the project it will again change to E.7029.00.030.  Ok you get the idea.
Now the problem.   When the project is at the .020 level we purchase inventory and recieve it into project inventory under the WBS elemement E.7029.00.020.
Now the project has moved on to E.7029.00.030 and we want to create a production order to make a prototype.  The WBS element for the production order is E.7029.00.030  but the inventory is still under WBS element E.7029.00.020.  When we go to issue the material to the job it says there is none in inventory under WBS E.7029.00.030. Which is right it is all under E.7029.00.020. 
Is there a way that we can store the inventory under E.7029.00 and be able to issue it to any sub group of E.7029.00 so that it would not matter if the current WBS is E.7029.00.020 , E.7029.00.030 or E.7029.00.050?
Since our BOM's can be quite extensive and often contain a large number of new components this would be of great assistance.
Thanks for your time and consideration.

The project moves on to another stage.   During the development of new products the project goes through several stages before the new product is released for production and sales.   For example:
Stage 10 - concept
Stage 20 - initial design
Stage 30 - design refinement
Stage 40 - Bata testing
Stage 50 - Final design
Stage 60 - Production process design
At each of stages 20 - 50 changes to the BOM can occur.  Material would be purchased at stage 20 and could continue to be used through the rest of the stages including after release to production.   But if the material is purchased during stage 20 then it sits in inventory under the WBS element ending in 020 but when the project moves on to the next stage the material will  be used to produce prototypes for stages 30 - 60 as long as the material is included in the BOM at that time.

Similar Messages

  • Transfer material from one storage location to another storage location

    Is there any bapi  to transfer material from one storage location to another storage location

    Hi,
    You need to use the below BAPI
    BAPI_GOODSMVT_CREATE
    Regards
    Sudheer

  • Sending material from one subcontracting vendor to another vendor

    Hi Experts
    we have a scenario we have more than one subcontracting vendors.so the unused raw material should be send to one vendor to another.so how can we configure it.please give me feedback.
    Thanks in advance...

    Hi Madhu ,
    What do u mean sending unused material from one vendor to another ?
    In subcontracting u can send material to only one vendor at a time.
    Regards
    Ramesh Ch

  • How to transfer material from One HU strorage location another HU location

    Hi Guys
    Is there any procedure to transfer material Box from one HU storage location to another HU storage location
    thanks in advancve

    Hello,
    No you are wrong Vishal. We can use HUMO for HU movement. In the detaili of report screen of HUMO t-code, select the data and go to header tab "edit". You will get multiple option to do the transaction related to HU movement.
    Thanks
    Milind

  • Time machine problem. Switching from one external drive to another. Problem started when upgrading to Mavrics, and changing to a WD drive

    I am a long time Mac user, running my business on an apple  platform since 1984. I currently use a 17" MacBook Pro as my primary computer for work. when it is at work it is plugged in via thunderbolt to my monitor and a one tb back up drive. I use time machine to back up the laptop to the one tb drive. When I go home, I take the laptop with me and use another drive at home as a back up. This way I have redundant back ups, in two separate locations. I have been doing this for years, and Time machine has worked flawlessly, automaticity switching from one drive to another.
    I recently switched to Maverics, and got a new drive for home. Now whether I am at home or at work, time machine fails to automatically back up. It will alert me every hour that backups cannot be completed, and I  must go to the time machine control panel and manually select a drive and click, "back up now". I also see an alert that says "waiting to complete first back up" even though each backup has been completed.
    This is quite annoying, and sometimes embarrassing. When giving lectures in large venues, the backup failure alert appears and shuts down my keynote presentation (again, something new since switching to Maverics and the new WD drive.
    I have reformatted the WD drive, and also spent time trying to change parameters in the time machine control panel, but so far no luck.
    Any advice out there?

    Time machine requires a GUID partion scheme, as well as a Mac OS X extended, journaled Volume.
    It needs these to correctly:
    1) copy the files
    2) run a modified spotlight index pass on the files
    Both are required to complete a abckup, and most new drives do not conme this way from the factory.

  • Problem with SMTP from one computer but not another

    I have an iMac connected directly to my network via Ethernet and a MacBook Pro which connects via wireless. I have a program installed on my iMac that sends me alerts via e-mail, and it works just fine. When I try and use Mail, however, on my MBP with the exact same settings and credentials, it fails. To make this even more perplexing, Mail works fine from my office on a different network.
    To work around this, I use Comcast's SMTP server on my laptop, but why would my regular e-mail provider's SMTP work on one machine and not another on the same network? The only difference is one is connected via Ethernet and the other by wireless.
    I use a Time Capsule as my router and wireless access point. Has anyone got an idea about what's causing this?

    Please report the relationship, if any, of the "regular e-mail provider's SMTP" and your ISP? If Comcast is your ISP, they regularly block use of Port 25, but if you have selected Use Default Port in Mail Preferences/Accounts/Account Information for the Outgoing Server, then it may be making the wrong choice to work with Comcast. Regardless of the ISP, for this regular account click on the arrows beside the name of the SMTP, choose Edit Server List, then click on the Advanced Tab that will then be seen and choose Use Custom Port, then enter the proper port directly -- that port is probably Port 587, but that could depend on the advisory of the email provider for using their SMTP.
    Ernie

  • Movement of material from one S.Loc to another S.Loc (both are WM managed)

    Hi,
    When i transfer the material between s.locations (both are WM managed) TR itself is not getting created and i checked all the necessary configs and everything seems to be correct. But the strange thing is if i check in LS24 the stock is placed in interim storage type where as TO is not created also TR is not created as our process is TO will be converted automatically from TR.
    Any light on this issue will be much appreciated.
    Regards
    Sudhakar

    Hi Sudhakar,
    Check if Auto TR is enabled for the Movement type, if you need to have the TR information - disable this setting in  OMLR. Else Goto LT10 and move the Goods from Interim location to the final bins.
    Let me know if this helps.
    Thanks

  • Problem passing parameter from one interactive report to another

    Hi.
    I'm going slightly mad over this simple problem.
    Apex 4.0.2 installed. Created one interactive report with 4 columns, one is linked to a custom target which is another interactive report where the column is used in the WHERE clause through a hidden field value.
    This works fine in other applications on same Apex install, but not in this one.... Writing the hidden field to the screen shows that it gets the correct value from the first report, but the SQL-query returns no rows when querying on the :<parameter_name> value (there are rows in database - query runs fine when hard coding a value).
    Tried link column both directly from the column value link definition, and from the report definition - both pass value ok to hidden field, but SQL-query doesn't pick it up.
    Tried deleteing and recreating second report page, same problem.
    Anyone else had this problem? Are there any properties on the pages/fields that I've forgot to set, that may cause the session value not to be set when the query is running? I've got it working in other apps, and can't find anything done differently there....
    Regards,
    -Haakon-

    Yes, it shows the correct value. Also creating a second text field and assigning it the Source value of the hidden field shows the correct value in the textbox on page load.
    It's only the report's sql query that doesn't seem to get the value. Hard coding a document number (without hyphens etc) works fine, I get the expected records - so the rest of the query is correct.
    Tried '=' and LIKE - but still nothing...
    It's just the sql variable substitution of :P21_DOCNO that under no circumstance will work.... also tried a simple pl/sql block with the variable - nothing.... using the V('P21_DOCNO') - nothing....
    It seems like the sql query is parsed and run before the hidden field gets it's value or something....
    This is very strange - as it works in another application on same Apex installation.

  • Transfer stock vaule of material from one profit center to another one

    Hello All experts,
    in our system (SAP 470) there're some materials which need to change the profit center in their master data. these materials still have stock values. after change the profict center, we want transfer the stock of old profit center to the new profit center.
    is there any way to do that?
    Thanks you very much
    mavis

    Hi,
    i still have some concerns about the creating new materials solution because we have to create the following relevant things:
    SD: condition record
    MM: infor record
    PP: new BoM
    we have 25 materials which will change profit center, there're a lot extra works we need to do.
    Is there any other way we can try?
    Regards

  • Daresbury purchase price will be variable for a given material from one sal

    HI
    This is the Issue came from my client
    Daresbury purchase price will be variable for a given material from one sales order to another. System currently allows manual enter prices on purchase req in relation to selling price. Price in Pur Info Req has price of 0.01, Purchase order takes price of

    I probably have at least over 2000 songs in my iTunes, plus a couple of videos. Though since I can always still use my desktop for anything else, maybe it is better I take the 256 over the 128. I had read a lot of other topics on this with a lot of people saying it is better to go with the 8GB memory and I would buy that also if I could, but I can't and of course I want this laptop to last me a while.
    Thanks for your help I think I'll go for the 256 + 4 instead, and I presume I can always get other external drives to store anything if I really need to down the road.

  • Level One WBS Element as Acct Assignment Element

    Dear Friend's
    My user have created one project, In that there are various levels WBS Elements.
    Normally we never tick Level One WBS Element as a Acct Assignment Element.But User have made Level One WBS Element as Acct Assg Element and then Project is Released.So now I can't remove that tick because that field is Grayed out or Freezed.
    Now i wanted to Remove or Undo Release status and then I have to remove Acct Assg Element Tick.
    Pls guide me on this issue.
    Thanks in Advance.
    Regards,
    Sandeep N.Theurkar

    Hello,
             I had not seen this problem before. So i checked it in my system. But i didn't see this
    happening for me.
             I think once system status is in REL (released) status you cannot reverse it. According to me Acct.
    assignment field become gray only when posting is made against that WBS and not after release.
    Pls check it and inform.
    Regards,
    Ashish Kulkarni

  • COPA - Multiple Sales Order with one wbs element.  COPA does not reference

    COPA - Multiple Sales Order with one wbs element.  COPA does not reference of reference of sales order.
    Hi All
    Currently we are in process of implementation of project related to Club Service for one of the client.
    Concept of this project is - there is "X" company engaged in supporting the different shared services for their client e.g. Client IBM - Shared Support Services of IBM is
    u2022     IDM
    u2022     Software Installation
    u2022     Help Desk
    u2022     Maintenance
    Co.. "X' is performing these services for IBM.    So for Co. "X" - IBM is one engagement. Like this way Co. X is performing such activities for many companies e.g. microsoft, HP, ABN AMRO etc.
    Objective - Get the consolidate report from COPA (Customer wise/services wise/sales order wise e.g. IBM/HelpDesk/10002/10).
    We propose a solution to create a project for each engagement and with WBS element. Each WBS element of different services e.g.
    Project IBM Inc.  100.100
    WBS Element    100.100.IDM 
    WBS Element    100.100.SoftIns
    WBS Element    100.100.HelpDesk
    WBS Element    100.100.Maintainance
    For this engagement (IBM), we are creating a sales order with line items (for services) and account assignment is WBS element.  In a sales order, there may be two lines for one services.   In a particular period, there are many such sales orders for this engagement... Milestone billing/period billing is used depending upon the services rendered.
    Now Cost Object will be WBS Element. So cost and revenue will posted to WBS and from this it goes to COPA.  In a month of May 2009 two - sales order is booked with three different line items with account assignment is WBS element.
    Sales Order Line Item No.....Item                  Account Assignment                      Revenue
    10000          100     IDM      100.100.IDM              1000
    10000          200     HELPDESK      100.100.HelpDesk              2000
    10000          100     Maintenance      100.100.Maintainance         3000
    Another Sales order booked with two different line items
    10000          100      IDM     100.100.IDM          3000
    10000          200      HELPDESK     100.100.HelpDesk          4000
    Cost will be booked directly against WBS element.
    In sales order level, there is no profitability segment, as cost object is WBS element.
    Billing, revenue will be posted directly to wbs element, from this revenue and cost of sales goes to COPA.
    Now in COPA,
    1.There is only one line for WBS element ex. 100.100.IDM with revenue 4000 (combing both the sales order)
    2.There is only one line for WBS element ex. 100.100.HelpDesk with revenue 6000 (combing both the sales order)
    3.There is only one line for WBS element ex. 100.100.Maintainance with revenue 4000
    In above case 1 & 2 we will not have reference of sales order and sales order line item in COPA table. There is only one line for this.  So we can not have reporting to sales order level.
    Is there any way by this the reference of sales order and sales order line will come in COPA for case 1 & 2.
    Please help in this issue.
    Regards
    Abhay Dev
    Ph:- 91-22-67782229
    Cell:- 91-9819175185

    Hi,
    For these case (multiple materials with different characteristics); have you consider going to next level of WBS Elements. Meaning; lets say currently you are assigning WBS "Engineering (which is a level 2 WBS)" to all the items in SO. Instead under "Engineering" create 2 or 3 level 3 WBS Elements as E1, E2 etc and assign them 1:1 to your sales order line items. This would eliminate the exit as welll as complex development option. And also will let you get all the data in COPA and in turn you can pull to BW as well for reporting. Just a thought.
    Regards
    Sreekanth

  • Moving NWA from one WBS to another and consolidated costs under WBS

    HI,
    I'm restructuring the project by moving released NWA from one WBS to another to aling actual costs with new budget categories.
    After moving these NWA I run the report and found out that WBS element summarize costs even if there is no NWA under this specific WBS.
    What field should I enable to allow WBS elements recalculate costs according to new NWA under these WBS.
    Thanks,
    Minsk2000

    Hi,
    Run CJEN to reconstruct project database.
    Rgds
    Abhinay

  • How to transfer costs from one WBS to another WBS?

    Hi,
    I want to transfer costs from one WBS to another. Remember two currencies are maintained viz. local and group.
    So how can i transfer the balance such that both the local currency and group currency balance gets transferred.
    Please ensure that the transfer should show 0 balance outstanding in CJI3 report.
    I need to transfer because WBS is holding some value which was not settled in the previous year.

    Hi
    You can transfer the Amount from One WBS to Another through KB11N. In this you Choose the Screen Variant as "_WBS/Network_" and do necessary steps.
    Hope it helps.
    Regards
    Babu

  • ABAB programm to copy material sales text from one sales org to another?

    Hi all,
    i'm searching for a ABAP programm to copy a material sales text from one sales org to another.
    Has anybody seen something like that before or has anybody an idea how to do this?
    Greetings & TIA
    strobbel

    @Narin
    I've tried to execute both code now over a new programm in the se38 and i get a error message from the first code (http://www.sap-img.com/abap/bapi-to-copy-materials-from-one-plant-to-another.htm).
    It's called:
    "BAPI_MARC1" cannot be converted to a character-type field.
    Could you help me to solve this?
    Sorry but i'm an absolutely newbie in things like ABAP and so on ...

Maybe you are looking for

  • Embed a video on file server in SharePoint

    I have video file on file server, they are very large. I cannot upload those videos in SharePoint Library. Is it possible to embed videos on file server in SharePoint Media Web Part? If yes how can I do it?

  • NTLM Authentication with a domain controller/active directory

    Hi, I have a requirement to do an NTLM authentication with the MS active directory. I am aware that JNDI doesn't support this protocol to communicate with the AD. I have looked into couple of online solutions available but that doesn't seem to meet m

  • Sysctl.conf - best way to start at boot?

    Hi all!  My arch box serves as firewall/router to other boxes on my home network. Obviously, I have to use NAT and net.ipv4 forwarding set to 1 (via sysctl.conf file). My question is: what's the best way to start sysctl at boot, so those kernel varia

  • IE Version's Can't Play SWF

    Hey guys, I'm putting an swf on a website and it's working great except for IE. (Although it works great in IE 9). In some versions of IE it will start to play then stop as if the video was never load and in others it will just go white. It works gre

  • CF10 and IIS 7

    Hi All I have a strange problem here and am hoping for a solution. Previous setup CF9 and IIS7.  At a lower level folder I enabled Windows Authentication. All I needed was the auth_user value. This worked well. I have now upgraded to CF10 and the win