Process chain creation: error:
Hi,
i am creating process chain for the data upload of three info packages!
Two are master data IPs and one is transactional data IP. ( Requirement is to make single process chain for the master data and transactional data ).
Before transactional data upload, i had included the process delete indexes.
When i check the process chain, it says:
"process DROPCUBE variant is referenced but not in the chain "
May i know what is wrong with this process flow? i had actually done similarly in dev system it was not giving any error:
Please suggest me
Thanks,
Ravi
Hi Ravi,
Did you go for Meta chain, if not please try that. Be a bit clear on the question.
regards,
ashok.
Similar Messages
-
Error in process chain creation : SET SCREEN not allowed in subscreens
Hello,
We are getting an Error in process chain creation : SET SCREEN not allowed in subscreens SAPRSSM 0100.
Please give a solution. Thanks in advance.
RR.Just do detail view on in the process chain. It will take you to the error. See the message and then display message. You can know why the message is appearing.
-
Process chain creation and which are the module depending
Hi Expert,
I have confusion on process chain creation and triggering the process chain also same of the module are depending other module what those. What are thing we take consideration Please guide me in this regards .
Regards,
Ravi
Edited by: Ravichendra k on Oct 15, 2008 11:48 AMHi,
Here are a few links about process chains. Hope it helps.
http://help.sap.com/saphelp_nw04/Helpdata/EN/67/13843b74f7be0fe10000000a114084/content.htm
https://www.sdn.sap.com/irj/sdn/advancedsearch?query=howtocreateaprocesschain&cat=sdn_all
http://sapbwneelam.blogspot.com/2007/09/how-to-start-process-chain-through.html
Regards,
Gaurav -
Hi,
I am creating a process chain for flat file upload..in this i have created the following processes..
1.generate index
2.load data
I have manually ran the infopackge, the data is loaded upto PSA.
Could anyone let me know what is the other process type that can be added to load the data from PSA to Data target and please give the steps to do....
Thanks in advance
-ManjulaIt is always advisable to transport the process chain from DEV to Production. You can just do this by simply gather all the necessary objects for process chain into your transport.
During the support phase, you have to monitor the data load through process chain. That can be done via transaction code rspcm. In case there is any error in the process chain ( various errors can be there, data loading error, delta error). In that case you have to go to the step of the process chain when the error occurs (it will be marked as red) , rectify the error and process the step manually at the point so that the following process finishes.
Hope this is clear now. -
Error in Process chain creation
Hi All,
My dataflow is:
R/3---ODS--Cube.
R/3 to ODS is Daily Load
ODS to cube is Monthly Load.
I am planning to create 2 process chains.
One I did from R/3 to ODS with following Processes.( This Chain Is OK)
Start----Execute ODS Infopackage--
ODS Activation.
Second One with (Error)
Start-----Further Processing--Delete IndexLoad Data--Create Index.
When I click on Checking View I am getting Red mark on Load data Process.
WHen I take Further Process as variant It proposed Activation of DSO process Again, I removed that process.
Details of the eRROR IS: Infopackage ZPAK_**is generated, Not able to be used as Loading variant.
Can ANy body help me on this and what could be the best way to create chain for this flow.
Regards,
MadhuHi Friend,
Q. Second One with (Error)
Start-----Further Processing--Delete IndexLoad Data--Create Index.
A. The Flow should be :
Start - > Delete Index for Cube - > Load Data (IP to load from ODS to Cube) - > Create Index for Cube.
Hope this helps.
Regards
Hemant Khemani -
Process chain scheduling error( Job BI_PROCESS_DROPINDEX could not schedule
Hi,
I am scheduling the process chain but it was throwing an error.
Job BI_PROCESS_DROPINDEX could not be scheduled. Termination with returncode 8
Message no. RSPC065
Diagnosis
Program RSPROCESS is to be scheduled as job BI_PROCESS_DROPINDEX under user ALEREMOTE.
System Response
Scheduling terminated with return code 8. The meanings of the return codes are as follows:
SY-SUBRC = 4:
Scheduling terminated by user
SY-SUBRC = 8:
Error when scheduling job (JOB_SUBMIT)
SY-SUBRC = 12:
Error in internal number assignment
Procedure
Check the system log for more detailed information.
Execute Function
for this i have already checked
in RSPC menu tab
Process Chain >> Attributes >> Execution User
Choose "BW Background User" which should be ALEREMOTE.
above settings i have done.
even though when i am scheduling the process chain i am getting the same error
thanks
sumanSuman,
You are not able to schedule it b'coz it is getting scheduled from user RFCUSER whereas the background user should be ALEREMOTE.
There is an option somewhere in the Menu bar in RSPC to change the Execution user. Please change that to ALEREMOTE,
Please check whether your BW user has enough authorization to run this job. The above post tell you how to do it. -
Process chain Transport error in BI7
Hello All,
We are facing an error while importing a transport request in the BI7 system. The objects collected in the transport request are
InfoPackage
Process chain
Process variants
Table Contents
The error which we are facing is as follows,
Start of the after-import method RS_RSPC_AFTER_IMPORT for object type(s) RSPC (Activation Mode)
Version 'M' of chain LAP_ROM_CS_LOAD_DAILY was saved without checking
Results of check for process in chain :
Results of check for process in chain :
Results of check for process LOADING ZPAK_3GBB2YPFIQL01BW1IDLUNON45 in chain LAP_ROM_CS_LOAD_DAILY:
Kindly let us know if you had faced similar problem before.
regards,
ChandranHi Chandran,
I think that if you expand the transport/import log further there will be a more detailed error message. Can you
check this? If yes can you let us know what the error message text and error code is? It might be the case that
the note 659160 is relevant for the problem.
Best Regards,
Des. -
Send process chain in error by abap
Hi all,
I want to send in error my process chain by abap code, because i've a routine in transfer structure and on the particular conditions this code must stop the load.
How to send in error my process chain by abap?
The following code send in error the infopackage but not the routine in trasfer roule.
l_s_errorlog-msgid = 'Z_my_message_class'.
l_s_errorlog-msgty = 'E'.
l_s_errorlog-msgno = '001'.
APPEND l_s_errorlog TO g_t_errorlog.
thanks,
AlessandroAlessandro
Check this link. It may give some info.
Thnaks
Sat
https://www.sdn.sap.com/irj/sdn/docs?rid=/webcontent/uuid/ee14e25d-0501-0010-11ad-8eb2861a7ec0 [original link is broken] -
Process chain - After error ABAP - trigger a metachain start does not work.
Hi,
I have a process chain, where after an ABAP runs into red (ERROR MESSAGE triggered), another process type, like start a new meta-chain, or start an infopackage starts.... But is does not work. After i go to logs, it asks me whether i want to trigger the following jobs, if i choose yes, it works. But i need to start it automatically, when the ABAP Routine has an error message (RED) in the chain.
Any idea, because I tried to solve it all the day, but i did not manage to get itwork...
Many Thanks,
L.Hi,
the problem is not the ABAP Program.
I have the following situation:
A Metachain contains as second step a call of local chain. After the local chain, according to the status of it (green o red), we have other different steps. So we have two different link (red and green) starting from the local process chain step.
Inside the local process chain there is the ABAP program that check several parameters and if something is not as expected fails with status red. if this situation happens, the local process chain becomes red and in SM37 inside the job i see the error that i forced, but the status is not triggered to the first metachain , so the corresponding following steps are not triggered.
This issue happens only if fails the ABAP program because, for example, a Infopackages loading fails every thing works and the corresponding steps in the metachain are executed.
In the ABAP program in order to force the status red we have the following code:
MESSAGE e162(00) WITH 'Status' 'Red'.
Any idea?
Thanks,
Veronica -
Process chain activation error in BI7...
hi gurus,
we are creating process chain for master data for
0PROMOTION_ATTR
0PROMOTION_TEXT
0SALESORG_ATTR
0SALESORG_TEXT
0CUSTOMER_ATTR
0CUSTOMER_TEXT
0VTYPE_TEXT
0DIVISION_TEXT
0SALES_GRP_TEXT
0DISTR_CHAN_TEXT
0CUST_GROUP_TEXT
0SALES_OFF_TEXT
0MATL_GROUP_TEXT.
we have created 1 start process and then execute info packages and DTP'S and used 'OR' conditions to connect to Attribute change run.
while i try to save my process chain its giving warning that 'Add at least one process to the chain before saving' and when i try to activate the chain its giving below error
Chain has no starter. Add a starter.
Message no. RSPC020
Diagnosis
The process chain has no start-process. A process chain always requires exactly one general starter.
System Response
The system is unable to activate the process chain.
Procedure
Add a general starter to the chain, and schedule it as the first process in the chain.
please suggest me how to rectify the problem.
regardsHi Harish,
Will you please goto process chain start varint and give the new varint for that and try to execute it once again..it will work for you...
If you could check once the check button all will be green and you can able to activate the process chain...I hope you are maintained the infoobjects in attr bute change run...problem might be with the start varint ionly...change the start varint and if you could not able to activate please let me know....
Regards
Srini -
First DTP in Process chain giving Error "CX_RSB_WRITE_ERROR"
Hi All,
I am facing a problem when I execute a process chain.
I have a master process chain and 3 sub process chains. Each of these sub process chains are having some DTP in it in a sequential order. These DTP's are Independent of each other, so even if the first one gives you errors, the remaining ones will get executed.
These DTP's are used to put some files in to the Open Hub Destination, which is the application server, using logical files names.
now the problem is that, when i execute the master Process Chain, the first DTP in each of the sub Process chains are getting failed by giving an error. the error is as follows.
Error : Uncaught_exception.
Exception : CX_RSB_WRITE_ERROR
Any idea in how to correct this? Any help in this regard will be highly appreciated.
Thanks
AjithYou might have missed some parameters in the FILE transaction.
Check the below links so that u may get idea wht u missed out.
Re: Can any one tell me how to write open hubs to application server?
http://help.sap.com/saphelp_nw2004s/helpdata/en/8d/3e4ec2462a11d189000000e8323d3a/content.htm
This might not be an security or authorization issue if u did not face such issue earlier. if so check with BASIS and add security roles to the generic user. -
Process Chain Authorisation Error.
Hi All,
While i am executing process chain i am getting error message " You don't have the authorization for infosource...........".
Can anybody tell ,what i have to do to resolve this issue.
Thanks in Advance...
Points assigned.hi,
Looks like an authorization issue.Please check if you have authorizations for all the objects used in the process chains like execute infopackages, infosources and data targets where you are trying to load data.
hope it helps,
regards,
Parth. -
Process Chain : Communication error
Hi, i have DataSource from UDConnect and working good loading data, but when use the InfoPackage in Process Chain then have the Error :
<b>Communication error: Incoming call is not authorized</b>
Any idea for help me in detect the problem ?Hi any can help in tris problem, only happen in data from UDConnect, the user is BWREMOTE, i test using user by SAP_ALL and not working.
Any idea the Autorization for UDConnect when using Process Chain ? -
Process Chain Activation Error
Hi Experts,
We are Transferring Data from Flat file to Infocube using PROCESS CHAIN..
Process chain Formation:
Start -
>> Infopackage----->>Delete Index--->>DTP--
>>Create Index
While Connecting START Variant with Infopackage i am getting following Error....
Access via 'NULL' object reference not possible.
A Short Dumb Created Contains Following Messages
Error in the ABAP Application Program
The current ABAP program "CL_RSPC_FRONTEND==============CP" had to be terminated because it has come across a statement that unfortunately cannot be executed.
Note :
1. we are also try to drag the start variant with Infopackage it is not connected .
2. Datasource and Infopackage are Delta Enabled.
Need Solution?
ThanksHi ,
We are allready give our file in Transaction Code : AL11 ==> DIR_HOME , But Same Error Coming ?
What is the Problem?
Thanks -
URGENT-Process Chain - transport error
Hi
I am facing a problem in process chains
when I tranport to quality system my chains are not activated after importing it is raising the error as
Error in remote call of destination ABAP Connection
Message no. RSPC051
Diagnosis
The following error occurred during the remote function call for destination ABAP Connection:
Name or password is incorrect (repeat logon)
System Response
A short dump has probably been written in the other system.
Procedure
Look at the short-dump overview in the other system.
I am unable to get the solution!!!!! how to activate the chains in Quality.........It sreally urgenthi,
chk the start variant of ur process chain whether an start immediate is choosen, if so change it to some date in future and try to transport.
Ramesh
Maybe you are looking for
-
I used to have iPod shuffle connected to a PC, I now want to use it on my Mac - I cannot get iTunes to see the shuffle at all - trid the 5 sec fix - no go. How can I now assign iPod to Mac?
-
Audio driver is installed but sound is not come
I recently formatted my compaq presario sr1530IL then i noticed that i had lost the motherboard cd, so i went to compaq site and downloaded drivers, now the trouble is that all other drivers r working except audio, i tried all drivers frm realtek sit
-
Want to test OSD in Vmware Workstation SCCm 2012
Which Drivers needed and where to get VMware scsi controller drivers ,I got .flp file but don't know how to extract that can any one provide link from where I can get Drivers needed for OSD in VMware workstation with SCCM 2012 for windows 7.
-
Hi Guys Prosperous 2014 to all . I am stuck with a Huge issue that I am unable to resolve. I did a PWA Administrative restore the other day to try to recover some fields that was deleted. After the restore I got a queue error and since then my report
-
How to make Grid command or save grid preferences
Hi there, long time user of macromedia / adobe suite with high use of fireworks Have finally got around to installing CS4, and its all very nice, but having trouble setting up the grid as a command. Previously in CS3, one could set the grid size via