Profit Centre Hierarchy Change and Profit Centre Budget
Hello Friends
For better view of Profit Centre Reports we are planing to change the Profit Centre Hierarchy.
I wanted to know that, are there some Specific Points which we have to take care of, before changing the Hierarchy?
Will some other settings get affected in System after changing the Hierarchy?
Also i want to know the TCode for entering Profit Centre Budget in System.
regards
prashant
Hi,
Profit centre planning (there is no budget for profit centres) is entered via 7KE1 transaction. If you change your hierarchy you should think of the effect on your reporting and allocation processes. That is if you use certain group in your cost allocation cylce and now you change it, it might have an effect on costs distribution.
Regards,
Eli
Similar Messages
-
HI to all,
I have created work centre hierarchy with three work centre having 24 hrs capacity each. from this hrchy i have used the superior work centre in the routing.so when i create the production order how i can use the cumulative capacity (72 hrs) of subordinate work centres to reduce the scheduling time.
u r answers will be rewarded,
Regards ,
Daniel.Hi,
Extract from help.sap.com
===========================================================================
Use of Work Center Hierarchies
Work center hierarchies are used in capacity planning to cumulate available capacity and capacity requirements.
You can cumulate available capacities from subordinate work centers to a superior work center level in order to determine the total available capacity for the superior work center.
In your factory you have several lathes. You create a higher-level work center, called "Machine center 3", which you use to cumulate the available capacity of several lathes.
===========================================================================
The below may be useful..
http://help.sap.com/saphelp_erp60_sp/helpdata/en/b1/c037a1439a11d189410000e829fbbd/content.htm
Regards,
Siva -
Profit Center Hierarchy Maintenance
Hello
As part of a project we need to transfer an existing Profit Center Hierarchy (including all Profit Center groups and Profit Centers) to a different Controlling Area. The hierarchy in question contains over 2500 Profit Centers and we would like to avoid doing this manually, to reduce both time and margin for error.
We know that we can use KCH1 to copy the Profit Center Groups to the new Controlling Area, using the original Controlling Area as a reference, but this does not copy across the Profit Centers master data.
Master Data transaction KE55, does not allow Controlling Area to be amended.
Questions:
- Is there a way to transfer/copy the complete hierarchy (including Profit Centers) to a different Controlling Area?
If we use KCH1 - how can we copy/reassign the Profit Centers to the new Controlling Area?
Any ideas for this would be greatly appreciated
ThanksHi
It can not be fully the way you like...
You can go to KCH4 and select your Prof Ctr Hie.. Click on Extras > Export... This would create a text file...
Create Std Hie with same name in new contr area and SAVE.. Then click on Extras > Import.... This would create the Hie Structure and also the profit center names under it.. But, as such the Prof Ctrs wont be created...
You need to create them again using KE51... Ideal way would be to create it using reference of the same profit center (LSMW)
Regards
Ajay M -
Hi experts
I need a help from you all,
Can we assign budgets to profit centres?
Iam having 2 profit centres which has to be tagged to one account code and each profit centre will have a different Budget,
Help me to assign two profit centres into one account code and also need to assign budgets based on the profit centres.
thank you
best regards
vinodh kumarHi,
If just for reporting purposes that you need to have the following reports:
1) Budget vs Actual for Profit Center A
2) Budget vs Actual for Profit Center B
3) Budget vs Actual for both profit centers.
Then my suggestion is that you create 3 different budget scenarios. Means in Budget 1, you create budget figures that apply to Profit Center A only, then Budget 2 is for Profit Center B and then Budget 3 to have combination of Profit Center A&B's figures.
At the Budget P&L, you will be able to select profit center under 'Expanded' button. Then to compare budget vs actual for Profit Center A, first select the scenario Budget 1 and then go to 'Expanded' button to select Profit Center A only.
Thus you will be able to achieve budget P&L for report 1 above. -
Relation between Prod. Hierarchy and Profit Centre
Dearest all,
does anybody know what the relation between prod. hierarchies and profit centre?
actually, i am trying to display total of actual line items (table GPCPT, if i am not wrong). The total value grouped by Profit Centre?
But I want to display them per Product hierarchies...
Question:
1. More than 1 product hierarchies could be assigned to 1 profit center, right ? (I checked in the matl master, checking all matl)
2. Could I find other way to do this ? any suggestion ?
thanks in advance,
meHi Barry,
I have tried MCSI, it displayed "no data found", what does it mean ?
Thanks in advance,
me -
Cost centre and Profit centre in one query - Authorisations not working!
Hiya,
I have another problem related to Analysis Authorisations.
I have created an AA with Cost Centre and Profit centre access restricted to a certain node of a hierarchy (type 1 - this node and below). For example, the User can only run a query at Cost Centres level of Country Belgium - the query works fine. Now, the user wants to drill down by the relevant Profit centres. According to the log, the system checks for Profit centres like * and says the user is not authorised. All this, despite the fact that all Profit centres belong to country Belgium and user has been given access to see these profit centres.
What do I need to do to enable drilldown by Profit centre? I can't make a "*" access to Profit centre as the user will be able to run other queries at global level, which is not what I can allow.
Any suggestions?Hello,
I don't know if it is relevant, but I had a similar problem when I had two characteristic each with hierarchy restrictions in one authorization object.
I "solved" it by separting each characteristic into its own authorization object.
BR
Ondrej -
Intercompany elimination at legal entity and profit centre level
All,
I have a question regarding intercompany elimination. As far as I understand, BPC can only hold one Interco dimension per application. If you want to perform an intercompany elimination for two dimensions which do not roll up into each other, two separate applications are needed. Please see example below to clarify:
Data is reported the following way:
Legal entity Profit Centre Account Interco Value
The problem is that the profit centre hierarchy does not roll up into the legal entity hierarchy mainly because there are profit centres set up as legal entities. Consequently, the legal entity hierarchy and the profit centre hierarchy are two independent hierarchies.
The business requirement is to have an intercompany elimination at profit centre and legal entity level at the same time (hence requiring two Intercos at the same time). This is needed as some of the profit centres are set up as legal entities.
Can someone advise me as to how to resolve this issue? Did anyone come across a similar problem?
Please let me know if you require any further clarifications.
MarcHi
Try to use 2 application for the interco elimination
for the 1st appls ur entity will be the entity dimension and use intco as intco dimension
for the 2nd one use the profit center as entity and build a new intco
As per interco logic this is using the Intco property in the Entity dimension and Entity property in intco dimension
it is very impossible to do this in one application
Thanks
CSD -
MIRO User - Exit to Change the Profit Centre..?
I need to change the Profit Centre in the Accounting document(for Vendor Line Item) and Profit Centre Accounting Document(For Payable Line Item) Created by MIRO Transaction.Can any one let me know if there is anyuser-exit or badi to achieve the same
Thanks a lot for your help .
Regards,
Gopi.Khi
These are all the user exits avalilable for MIRO transaction.
LMR1M001 User exits in Logistics Invoice Verification
LMR1M002 Account grouping for GR/IR account maintenance
LMR1M003 Number assignment in Logistics Invoice Verification
LMR1M004 Logistics Invoice Verification: item text for follow-on docs
LMR1M005 Logistics Inv. Verification: Release Parked Doc. for Posting
LMR1M006 Logistics Invoice Verification: Process XML Invoice
MRMH0001 Logistics Invoice Verification: ERS procedure
MRMH0002 Logistics Invoice Verification: EDI inbound
MRMH0003 Logistics Invoice Verification: Revaluation/RAP
MRMN0001 Message output and creation: Logistics Invoice Verification
I think you can use this exit.
LMR1M002
Regards.
Lavanya. -
Profit centre hierarchy table!!!
hello SDN,
Could somebody please help me to find this information i need the table name i think where the standard profit centre hierarchy information is stored??
Name of the node of the next level in the structure above the Pofit centre, name of the node of the next level in the structure above the node in first level, name of the node of the next level in the structure above the node in second level.
Its a bit urgent!!
MAny thanks
Pankajhello thanx for your reply.
But this is not what i was looking for. Actually i am writing a interface program to download Profit centre master data and this profit centre hierarchy information to CRM program.
That is why i need the table name where i can see all the information related to hierarchy if possible.
Please provide your views / suggestions.
Thanks
pankaj
thanks Raymond i will look into these tables.
Message was edited by:
PANKAJ ARORA -
Change the profit centre in the cost centre master after a year
Hi All,
Could you'll please let me know whether it was possible to change the profit centre in the cost centre master and if i did what will be the implications.
Thanks and Regards,
VandanaRefer transaction code OKEG.
You can maintain master data for cost centers, cost elements, activity
types, and business processes with time dependencies. You can make
changes at any time for any given time interval. Data storage also takes
place with a time reference. In this way, a master data record can have
multiple database records storing different information.
The smallest interval is one day. To ensure data consistency, you cannot
change each field daily. The timeframes in which you can change a field
depend on the field functions, which are fixed by the system and cannot
be changed. Master data maintenance includes an automatic check for each
field's time-based consistency, resulting in individual time-based
maintenance for each field.
The following dependencies are supported:
o Not time-based
o Day-based
o Period-based
o (Fiscal) year-based
This function provides an overview of the time dependencies of
individual master data fields during master data maintenance, along with
checks and storage of consistency timeframes. You find this information
in the "Time dependency" column.
If you use fields requiring characteristics greater than one day and
which are changed for the system lifetime of the object, the system
automatically creates a new database record for this processing
interval, and changes the time-based validity of existing records. The
change is logged in the master data record with the time reference.
However, a great number of changes in multiple timeframes will result in
a correspondingly great number of data records.
Fields which you can change freely (indicated in the DAY column) can
possess different time dependencies only if you mark them additionally
as historically relevant. This activates the time-based updating for the
records.
Object 1000 has one master data record created with a fiscal year of 12
periods and the cost center name AAAAAAAAAA. During master data
maintenance, you change the cost center name in period 5 to BBBBBBBBBB.
The system reacts with one of two options.
o "Name" is marked as historically relevant. The existing master data
record for periods 1 - 12 must now become three records:
1000 01-04 AAAAAAAAAA
1000 05 BBBBBBBBBB
1000 06-12 AAAAAAAAAA
o "Name" is not marked as historically relevant. The existing master
data record remains intact, with the name changed for the entire
existence of the record:
1000 01-12 BBBBBBBBBB
Edited by: Ravi Sankar Venna on May 19, 2009 4:03 PM -
IW32 Auto update of profit centre when work centre is changed
Hi... we have some difficulties with PM exits. Basically, if the work centre for an order is changed in IW32, SAP does not automatically re-populate the profit centre and cost centre associated with the changed work centre. To try to achieve this I have implemented the Sap suggested exits EXIT_SAPLCOIH_005/IWO10005 (for profit centre) and EXIT_SAPLCOIH_025/IWO10025 (for cost centre). The cost centre exit works. For the profit centre exit to work (invoke EXIT_SAPLCOIH_005) it needs profit centre to be blank. Being change mode (IW32) this field is populated already and asking the users to blank the profit centre field beforehand is not practical. Tried to see if auto blanking the profit centre field as soon as the work centre field is changed is possible... but there is no exit triggered at that point to do this. It appears that EXIT_SAPLCOIH_005 is triggered before anything else. Any ideas on how Profit Centre can be updated? (I have tried previous exit suggestions here). Thanks...
Profit Centres are generally applicable only for Revenue & Expense accounts.
When you load the opening balances, it affect the Inventory Account which is an Account Account and that is why there is no Profit Centre marked in the JE. -
How to change the Profit centre in goods receipt before posting
Hi All,
when we are doing MB01, material master and Purchase order are having different profit centres, since legacy has multiple profit centre for the same material.
My requirement is to change the profit centre before posting a Goods receip with the Purchase order Profit centre.
Is thre any user-exit, Badi or Substitutions for this requirement. I have implimented the below code in the Badi
MB_DOCUMENT_UPDATE.
data : ls_xmseg type mseg.
ls_xmseg-Profit Centre = .....
ls_xmseg-prctr = '0020077170'.
modify XMSEG from ls_xmseg transporting prctr .
But i'm getting Data base update terminated message. Please help me in this.
thanks,
Ram.Dear Sir,
But is T-code not working ....
have you other code/ process so, pls. give me ....
Pls sir
Regards
Jayesh Kanungo -
Reading the description of Sales document type and Profit centre from table
Hi
I want to print the description of Sales document type and Profit center on output
I have checked in table TVAK and CEPC but i am unable to pick description against the code
Can anyone please suggest from where can i capture the description of sales document type and profit centre
Thanks and Regards
Sunil SrinivasanHi
If you have the sales document number VBELN then pass this VBELN in to table VBAK and you can get the sales document type VBAK-AUART.
Now pass the same VBELN to VBAP table here you can get the Profit Center VBAP-PRCTR
For sales Document type description you pass the VBAK-AUART values into table TVAKT table and get the values for TVAKT-BEZEI is you sales document type description
For Profit center description goto table CEPCT and enter the profit center you will get the
KTEXT
LTEXT
MCTXT
regards
Prashanth
Edited by: Prashanth@SD on Oct 25, 2010 12:29 PM -
Project Systems: Profit and Cost Centres
Hi
When maintaining a WBS element through transaction CJ02 or CJ20N for example; it is poossible to link a profit centre, ressponsible cost centre and requesting cost centre to each WBS element.
My question is: When cost gets incurred against a WBS element the profit centre gets updated with the cost as well. However, the cost centres (responsible and requesting) do not get updated. Is there any automatic effect on these cost centres (such as is the case with profit centres)?
I know that the requesting cost centre will be the cost centre allocated to AUC's assigned (if applicable) and that to get cost onto the cost centre a settlement rule must be maintained. What therefore is the use of having responsible and requesting cost centres assigned to a WBS apart from this?Hi
Cost center and WBS elements are both cost objects hence at a time real posting can happen to only one of them. Since WBS elements are getting debited , it will not simultaneously debit a cost center. However profit center it is not the case , hence the data flow to the profit center happens as an when a posting is done to WBS element and also when WBS is settled to cost center then also there will be a posting to profit center.
Anand -
Profit Centre and Cost centre not updated
Hi,
I have posted expenses through FB60 and assigned cost centre to the expenses account and not for vendor item. Entry passed was posted.
But when i checked the document, i saw that the cost centre and profit centre is appearing in one line item (i.e. expense line item) only.
Afterwards i made payment through F-53. In this entry also there was no cost centre and profit centre in vendor line item. But the same was appearing in "outgoing bank" line itemHello,
If you are on classical GL, your vendor line items or customer line item will not be updated automatically.
If you are on New GL functionality and document splitting, you will have profit center updated on customer and vendor line items.
Regards,
Ravi
Maybe you are looking for
-
One button click call function more than once
I have a function I call from a button (onClick) which inserts a record in mySQL via a PHP page. For some odd reason it tends to insert more than 1 record. The extra records tend to be duplicates of previous records. I do not know of SPRY is calling
-
Indesign Files just won't open
Hi, I try to open some Indesign files in CS6 & when I attempt to open them nothing appears. The program doesnt even give me an error it just doesnt open the file. If I open the file without Indesign open, it will open the Indesign program but no docu
-
First off thank you for anyone that reads this, I am very new at LabVIEW, and I think this maybe a trival question but I am not sure. I am building a test bench to measure the torque vs angle of clutch disc to find the hystersis. I am confedient tha
-
A sad or unhappy iPod icon appears on the screen
I have had my ipod mini f0r 2 month A sad or unhappy iPod icon appears on the screen and the hard drive is making sounds when turn on
-
Hi all, what is orderid in FBV1 transaction? what is the relation ship between cost center , profit center and order id? while parking the document i have given only orderid for a particular line item with out giving the cost center and profi